Resolution: 49-23
File Number: 2023414
JBZ, INC. D/B/A/ ELLINGSON CONTRACTING:
A RESOLUTION TO APPROVE CHANGE ORDER NO. 6 TO THE CONTRACT WITH JBZ, INC. DB/A
ELLINGSON CONTRACTING IN THE AMOUNT OF $t56,812.00 FOR ADDITIONAL CONSTRUCTION
ASSOCIATED WITH THE WOOLSEY FARMSTEAD RESTORATION PROJECT, AND TO APPROVE A
PROJECT CONTINGENCY IN THE AMOUNT OF $20,000.00
WHEREAS, on November 5, 2019, the City Council passed Resolution 245-19 to approve a contract with JBZ, Inc.
d/b/a Ellingson Contracting for Phase 1 of the restoration and reconstruction of the Woolsey Farmstead; and
WHEREAS, Change Order No. 6 authorizes the restoration of two stone chimneys.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Jordan to sign Change
Order No. 6 to the contract with JBZ, Inc. d/b/a Ellingson Contracting in the amount of $156,812.00 for restoration
work associated with the Woolsey Farmstead Restoration Project, and further approves a project contingency in the
amount of $20,000.00.
PASSED and APPROVED on March 7, 2023
Page 1
Attest:
CITY OF
Pow,
FAYETTEVILLE
ARKANSAS
MEETING OF MARCH 7, 2023
TO: Mayor Jordan and City Council
THRU: Waylon Abernathy, Bond Projects & Construction Dir
Paul Becker, Chief Financial Officer
FROM: Quin Thompson, Facilities & Bldg Maint Manager
DATE:
CITY COUNCIL MEMO
SUBJECT: Approval of Change Order #6 with JBZ, Inc. dba Ellingson Contracting for
Restoration of the Woolsey Historic Farmhouse.
RECOMMENDATION:
2023-414
Staff recommends approval of change order #6 to the contract with JBZ, Inc, DBA Ellingson Contracting in the
amount of $156,812 for restoration of two stone chimneys, and a project contingency of $20,000.
BACKGROUND:
This is an ongoing multi -phased restoration contract started in late 2019. Administration, with City Council
approval, has appropriated Capital Improvement Funds each year through 2024. To date, the house has been
restored to the original 1850's structure, with porch, siding, shingles, doors, and windows. Work is currently
underway on the interior finishes of the house.
DISCUSSION:
The scope of this change order will allow restoration of two dressed stone chimneys. Future improvements will
include pathways, gravel parking, and restoration of the Potato House.
BUDGET/STAFF IMPACT:
This change order is funded through 4470 Sales Tax Capital Improvement Fund previously approved by
Council in the 2023 Budget.
ATTACHMENTS: C06 Woolsey Restoration, 2023-414 SRF Woolsey C06
Mailing address:
113 W. Mountain Street www.fayetteville-ar.gov
Fayetteville, AR 72701
City of Fayetteville, Arkansas 113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
- Legislation Text
File #: 2023-414
Approval of Change Order #6 with JBZ, Inc. dba Ellingson Contracting for Restoration of the
Woolsey Historic Farmhouse.
A RESOLUTION TO APPROVE CHANGE ORDER NO. 6 TO THE CONTRACT WITH JBZ, INC.
DB/A ELLINGSON CONTRACTING IN THE AMOUNT OF $156,812.00 FOR ADDITIONAL
CONSTRUCTION ASSOCIATED WITH THE WOOLSEY FARMSTEAD RESTORATION
PROJECT, AND TO APPROVE A PROJECT CONTINGENCY IN THE AMOUNT OF $20,000.00
WHEREAS, on November 5, 2019, the City Council passed Resolution 245-19 to approve a
contract with JBZ, Inc. d/b/a Ellingson Contracting for Phase 1 of the restoration and reconstruction of
the Woolsey Farmstead; and
WHEREAS, Change Order No. 6 authorizes the restoration of two stone chimneys.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Jordan
to sign Change Order No. 6 to the contract with JBZ, Inc. d/b/a Ellingson Contracting in the amount of
$156,812.00 for restoration work associated with the Woolsey Farmstead Restoration Project, and
further approves a project contingency in the amount of $20,000.00.
Page 1
PROJECT:
A Restoration of the Historic
Woolsey Farmstead
OWNER:
City of Fayetteville
113 W. Mountain St.
Fayetteville, AR 72701
REVIVAL
ARCHITECTURE
P.O. Box 400 Scorn AR 72142
501.951.3316
wgw.r wmlarch.com
CHANGE ORDER
FROM ARCHITECT:
Revival Architecture, Inc.
301 Main St. Suite 203
N. Uttle Rock, AR 72114
TO CONTRACTOR:
Ellingson Contracting
108 E. University St.
Siloam Springs, AR 72761
CHANGE ORDER NO: 5
ISSUE DATE: July 26, 2022
CONTRACT DATE: Oct. 16, 2019
This Change Order is not valid until signed by the Architect, Contractor & Owner
DESCRIPTION: The Contract is changed asfollows:
1. ADD to contract the construction of two stone chimneys (as detailed and described on PRp4 dated
2/11/22), Including necessary project management and coordination. Custamfit siding andflooring as
necessary to accommodate integration into existing construction.
The original Contract Sum was
$ 329,299.00
The net change by previously authorized Change Orders
$ 415.182.00
The Contract Sum prior to this Change Order was
$ 744,481.00
The Contract Sum will be Increased/ Oeereased.hy this Change Order in the amount of
$156,812.00
The new Contract Sum including this Change Order will be
$ 901,293.00
The Contract Time will be Increased rDEEFeased WREhanged by 365 day_
The date of Substantial Completion as of the date of this Change Order therefore is: May 1, 2024
ATTACHMENTS: Change Order Request #6 dated 1/11/23
Revival Architecture, Inc Ellingson Contracting City of Fayetteville
ARCHITECT (firm name) CONTRACTOR ffirm name) OWNER (firm name)
PO Box 400
Scott, AR 72142
SBY
)o
Aaron C. Rub IA Owner
PO Box 7202
51learn Springs AR 72761
(signature)
Mr. David Ellingson Owner
CEllingson contracting
CHANGE ORDER REQUEST k6-PR#4
To: Quin Thompson RE: Woolsey Historic Farmhouse Renovation
City of Fayetteville 535 S. Broyles Ave
Fayetteville, AR 72701
c/o'. Aamn Ruby
Revival Architecture
Chimney Scope of Work Included in PR #4
1/11/2023
General Conditions: Two weeks of project managment, four weeks of supervision, and equipment. Two months of temporary
electric, toilet, and water. One week of skid steer and trailer rental for cleanup. One 30 Cy dumpster pull.
Chimneys: Rebuild 2 Fireplaces reusing onsste stone and supplying new stone approved by Owner. Install cast iron dampers in each fireplace.
Provide and install 13" x 13" clay Rue the wrapped with concrete block. Provide any lashings needed to provide a waterproof installation.
- Siding and Flooring: Custom fit existing siding and Flooring to new stone chimneys and stone hearth. Includes manlift rental.
Subcontractors: Bids were recieved from two qualified masons. Strong Masonry can start immediately, but will require a price increase of
$2,940.00 IT he is not under contract by February 19. Square One masonry can start on April 19 but is requesting a deposit of $32,595.00
due 14 days prior to commencement of work.
Schedule: 8 to 10 weeks after materials are approved and on site.
Contract time to be increased by 365 days for continuation of contract to May 15t, 2024.
Exclusions:
- ADA parking or paths
Line Item Breakout
Daxriptlon
Material
labor
Equipment
Subrwmractor
Tetzl
General Conditions
$ 800
$ 14,960
$
5,340
$
$
21,ion
Chimneys
$
$
$
$ 108,650
5
308'650
Siding and Flooring
$ 440
$ 6,656
$
1,890
$
$
8,986
Subtotal
$ 1,240
$ 23b16
$
7,230
S
138,736
Sales Tax(9.75%)
$ 121.00
$
705.110
5
116
General Liability Insurance(1.5%)
Performance and Payment Bonds (2.5%)
$
3,541
Fee (8%)
$
11,616
lump Sum Total
$
356,813
Summary
The original contract sum was
$ 329,299
The net change by previously authorized change orders
$ 415,182
Contract sum prior to this change, request
$ ]44pe1
Proposed new contract sum Including Mks Nang ender request
$ g01,293
Upon your approval, we intend to make this change/addition immediately. If you have any questions please feel free to contact me.
Siinnjcere�ly,� Acceptance of Change
m/
Nae L I aal&U
Chris Hobby VVV Signature
Ellingson Contracting
Director of Preconstruction Date • J L
Ellingson Contracting I PO Box 7202 1 Siloam Springs I AR 172761
City of Fayetteville Staff Review Form
2023-414
Item ID
2/21/2023
City Council Meeting Date - Agenda Item Only
N/A for Non -Agenda Item
Quin Thompson 2/3/2023 FACILITIES MANAGEMENT (140)
Submitted By Submitted Date Division / Department
Action Recommendation:
Staff recommends approval of Change Order No. 6 to the Contract with JBZ, Inc D/B/A Ellingson Contracting in the
amount of $156,812.00 for additional construction associated with the Woolsey Farmstead Restoration Project,
and a project contingency of $20,000.
4470.090.8900-5315.00
Account Number
15008.1
Project Number
Budgeted Item? Yes
Does item have a direct cost? Yes
Is a Budget Adjustment attached? No
Budget Impact:
4470-Sales Tax Capital
Fund
Woolsey Homestead Historic Restoration
Total Amended Budget
Expenses (Actual+Encum)
Available Budget
Item Cost
Budget Adjustment
Remaining Budget
Project Title
$ 430,514.00
$ 159,881.41
r-
270,632.59
$ 156,812.00
113,820.59
V20221130
Purchase Order Number: 2019-782 Previous Ordinance or Resolution # 184-22
Change Order Number:
Original Contract Number
Comments:
31
2019-52
Approval Date:
8/16/2022