HomeMy WebLinkAbout41-23 RESOLUTION113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
Resolution: 41-23
File Number: 2023-411
KIM PETRONE WATER DAMAGE CLAIM:
A RESOLUTION PURSUANT TO §39.10(C)(4) OF THE FAYETTEVILLE CITY CODE TO AUTHORIZE THE
MAYOR TO PAY THE AMOUNT OF $50,000.00 TO KIM PETRONE, PRIVACY FENCE, INC., AND JDE
FOUNDATIONS, INC. FOR A WATER DAMAGE CLAIM ARISING AT 3263 NORTH MAKEIG COURT
WHEREAS, pursuant to §39.10(C)(4) of the City Code, the City Council may in an extraordinary case, upon the
Mayor's recommendation and by two-thirds majority, approve the payment of water or sewer damage claims exceeding
$25,000.00 up to $50,000.00.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas, pursuant to § 39.10(C)(4) of the Fayetteville City
Code, authorizes Mayor Jordan to pay the amount of $32,241.27 to Kim Petrone for hotel expenses, painting, flooring
and trim, and plumbing expenses related to the water main break damage at 3263 North Makeig Court.
Section 2: That the City Council of the City of Fayetteville, Arkansas, pursuant to § 39.10(C)(4) of the Fayetteville City
Code, authorizes Mayor Jordan to pay the amount of $2,580.00 to Kim Petrone and Privacy Fence, Inc. for fence repair
related to the water main break damage at 3263 North Makeig Court.
Section 3: That the City Council of the City of Fayetteville, Arkansas, pursuant to § 39.10(C)(4) of the Fayetteville City
Code, authorizes Mayor Jordan to pay the amount of $15,178.73 to Kim Petrone and JDE Foundations, Inc. for
foundation repairs related to the water main break damage at 3263 North Makeig Court.
PASSED and APPROVED on February 21, 2023
Page 1
CITY OF
Pow,
FAYETTEVILLE
ARKANSAS
MEETING OF FEBRUARY 21, 2023
CITY COUNCIL MEMO
TO:
Mayor Jordan and City Council
THRU:
Susan Norton, Chief of Staff
FROM:
Timothy Nyander, Utilities Director
DATE:
SUBJECT:
Kim Petrone - Water Damage Claim at 3263 N. Makeig Ct.
RECOMMENDATION:
2023-411
Staff recommends approval of a damage claim payment to Kim Petrone in the amount of $32,241.27, a joint
payment to Privacy Fence, Inc. & Kim Petrone in the amount of $2,580.00, and joint payment to JDE
Foundations, Inc. & Kim Petrone in the amount of $15,178.73 for water damage remediation at 3263 N. Makeig
Ct. after a City water main break caused damage to the property.
BACKGROUND:
On September 20, 2021, the City of Fayetteville experienced a large 36-inch diameter water main break on N.
Makeig Ct. Kim Petrone owns the home located at 3263 N. Makeig Ct. This large water main break caused
substantial amounts of flooding and damage to the neighborhood and to the Petrone's residence. Kim
Petrone's insurance company denied her claim, so she immediately filed a damage claim with the City after the
incident.
DISCUSSION:
Per City Code Section 39.10 — Water and Wastewater Damage Claims, "The Utilities Department Director may
not authorize any payment greater than $10,000.00 for any claim pursuant to this section. The Mayor may
request the City Council to authorize an amount greater than $10,000.00 by resolution, but in no case shall the
city pay more than $25,000.00 pursuant to this claims procedure for a damage claim related to a water or
wastewater utility infrastructure occurrence unless in an extraordinary case the Mayor recommends and the
City Council by two-thirds (%) majority approves an exemption from the $25,000.00 damage cap and approves
a payment up to $50,000.00."
When the large water main broke, the rush of water flooded the Petrone's home destroying flooring, walls, trim,
and cabinetry. Foundation damage also occurred to the residence. The foundation repairs will include
excavating around the perimeter of the home and installing 18 steel piers to lift the foundation and stabilize the
home. The Petrone's 6-foot wooden fence and gate were also damaged and need to be repaired.
The reimbursements and payments to remediate the water damage would include:
• Reimbursement to Kim Petrone in the amount of $32,241.27 for hotel expenses, painting, flooring and trim,
and plumbing expenses
• Joint payment to Privacy Fence, Inc. & Kim Petrone in the amount of $2,580.00 to repair the 6-foot wooden
Mailing address:
113 W. Mountain Street www.fayetteville-ar.gov
Fayetteville, AR 72701
fence and gate
• Joint payment to JDE Foundations, Inc. & Kim Petrone in the amount of $15,178.73 for foundation repair to
the residence to permanently stabilize the foundation after erosion caused damage after the water main break
and subsequent flooding
Staff requests approval to reimburse Kim Petrone and pay for the foundation and fence repairs needed for
$50,000.00, which is the maximum amount allowed by Section 39.10 of the Fayetteville City Code.
BUDGET/STAFF IMPACT:
Funds are available in the Insurance Self (Non -Vehicle Damage) account within the Water & Sewer fund.
ATTACHMENTS: SRF Kim Petrone Water Damage Claim, 3263 Makeig Final Costs
Mailing address:
113 W. Mountain Street www.fayetteville-ar.gov
Fayetteville, AR 72701
City of Fayetteville, Arkansas 113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
- Legislation Text
File #: 2023-411
Kim Petrone - Water Damage Claim at 3263 N. Makeig Ct.
A RESOLUTION PURSUANT TO §39.10(C)(4) OF THE FAYETTEVILLE CITY CODE TO
AUTHORIZE THE MAYOR TO PAY THE AMOUNT OF $50,000.00 TO KIM PETRONE,
PRIVACY FENCE, INC., AND JDE FOUNDATIONS, INC. FOR A WATER DAMAGE CLAIM
ARISING AT 3263 NORTH MAKEIG COURT
WHEREAS, pursuant to §39.10(C)(4) of the City Code, the City Council may in an extraordinary case,
upon the Mayor's recommendation and by two-thirds majority, approve the payment of water or sewer
damage claims exceeding $25,000.00 up to $50,000.00.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas, pursuant to § 39.10(C)(4) of the
Fayetteville City Code, authorizes Mayor Jordan to pay the amount of $32,241.27 to Kim Petrone for
hotel expenses, painting, flooring and trim, and plumbing expenses related to the water main break
damage at 3263 North Makeig Court.
Section 2: That the City Council of the City of Fayetteville, Arkansas, pursuant to § 39.10(C)(4) of the
Fayetteville City Code, authorizes Mayor Jordan to pay the amount of $2,580.00 to Kim Petrone and
Privacy Fence, Inc. for fence repair related to the water main break damage at 3263 North Makeig
Court.
Section 3: That the City Council of the City of Fayetteville, Arkansas, pursuant to § 39.10(C)(4) of the
Fayetteville City Code, authorizes Mayor Jordan to pay the amount of $15,178.73 to Kim Petrone and
JDE Foundations, Inc. for foundation repairs related to the water main break damage at 3263 North
Makeig Court.
Page 1
Tim Nyander
Submitted By
City of Fayetteville Staff Review Form
2023-411
Item ID
2/21/2023
City Council Meeting Date - Agenda Item Only
N/A for Non -Agenda Item
2/2/2023 WATER SEWER (720)
Submitted Date Division / Department
Action Recommendation:
Staff recommends approval of a damage claim payment to Kim Petrone in the amount of $32,241.27, a joint
payment to Privacy Fence, Inc. & Kim Petrone in the amount of $2,580.00, and joint payment to JDE Foundations,
Inc. & Kim Petrone in the amount of $15,178.73 for water damage remediation at 3263 N. Makeig Ct. after a City
water main break caused damage to the property.
5400.720.4310-5311.04
Account Number
Project Number
Budgeted Item? Yes
Does item have a direct cost? Yes
Is a Budget Adjustment attached? No
Purchase Order Number:
Change Order Number:
Original Contract Number:
Comments:
Budget Impact:
Total Amended Budget
Expenses (Actual+Encum)
Available Budget
Item Cost
Budget Adjustment
Remaining Budget
Water and Sewer
Fund
Project Title
$ 103,838.88
103,838.88
$ 50,000.00
53,838.88
Previous Ordinance or Resolution #
Approval Date:
V20221130
Details of 3263 N. Makeig Ct. claim - Kim Petrone
Reimbursement
Hotel Expense (Hampton)
$
300.31
Painting (Adrian's Painting)
$
17,800.00
Flooring and trim (Encore)
$
5,340.96
Plumbing (Trenchless Leak Detection)
$
8,800.00
'TOTAL
$
32,241.27
Joint Payable
Foundation repairs (JDE Foundations Inc)
$
18,000.00
Fence repairs (Privacy Fence Inc)
$
2,580.00
TOTAL - $20,580.00 (up to $50,000 claim limit)
$
17,758.73
$32,241.27 Check payable to Lou & Kim Petrone
$2,580.00 Check jointly payable to Privacy Fence Inc. & Kim Petrone
$15,178.73 Check jointly payable to JDE Foundations Inc. & Kim Petrone
Claim Totals
$
52,821.27
Reimbursement
$
32,241.27
Joint Reimbursement
$
17,758.73
Not Reimbured
$
2,821.27
TOTAL ($32,241.27 + $17,758.73)
$
50,000.00
(WAi 1 state.,ALL. S X660636
� ,in�nw�,b.
1111'1'Illl'111111'11i1'Illllll'�'1"�l�ll'I"l�'lll'll"1"111�1
LOUIS PETRONE KIMBERLY PETRONE
2769 E BOARDWALK CT
FAYETTEVILLE AR 727012703
&cprvmhcr 24. 2021
fR'3UREL): KIMBERLY PETRONE
1>4'P£ OF LOSS: Seprcmhrr 21, 2021
CLAlM NumBER: 0642441 1 17 TJB
POLICY NUMBER: 0008212974S4
Re: Your Claim Status
Dear LOUIS PETRONE KIMBERLY PETRONE,
PHONE NUMBER: 800-347-551 1
FAX NUMBER: 866447-4293
OFFICE HOURS:
We appreciate the time you've spent assisting us with your claim. We have carefully reviewed the information about your
loss that was reported to us, as well as the policy provisions that apply to this claim. Based on this review, we are unable to
provide coverage for floodwater into the interior of home. Please refer to losses we do not cover, paragraph A I page 6 of
your Landlords Package policy which states: Losses We Cover Under Coverages A and B:
We will cover sudden and accidental direct physical loss to property
described in Dwelling Protection -Coverage A and Other Structures
Protection -Coverage B except as limited or excluded in this policy.
Losses
We Do Not Cover Under Coverages A and B:
A. We do not cover loss to the property described in Dwelling
Protection-Coveragr A or Other Structures Protection -Coverage B
consisting of or calmed b}:
1. Flood, including, but not limited to, surface water, waves, tidal
wateror overflow of any body or water, or spray From any of these,
whetherorgotdriven by wind).
We're Here to Help You
Plea,ecall .+ts as the number below and refer to your claim number should you wish to discuss any aspect of this case,
including this letter.
Sincerely,
Jl"1:�►J BIMCK
JAMES BITTICK
800-347-5511 Ext. 1988556
Allstate Indemnity Company
PRODotig
06424-41117 zie
Watkins, Aaron
From: Kim Petrone <kkpetrone@yahoo.com>
Sent: Monday, December 12, 2022 11:54 AM
To: Watkins, Aaron
Subject: First receipt
CAUTION: This email originated from outside of the City of Fayetteville. Do not click links or open attachments unless you recognize
the sender and know the content is safe.
Renter hotel bills
cpuk+r ABC APT
! HY��atr•
r�. r.r�..rw�yrr.rr
t1.17�
dtr.�
itTr. w..wsnY..yr
ttnh: 1
AR'r'r• �
WIr i or J{KRr.
fxe R7..7R :SAY .rrwr.r�V w...r e...�
VArpffr1[
•p^'0Pd
�� wrw r�srwwti7f+�
17 C. F.M�f•rT.Nr
ram. / � •.F. nn.r
Cr
� rr ryrn.y w _
V.
farrr�
,
r+rli4:77 17675<
�170+M
1ArL5
+i tisrt
1��:
�4JAF��
i...,
•1 sty r{.
lSrrR r:r i4 Mpiv r ay�yytT - - 1't 1 € _
}}
R% 77
7k>r� yq'n'i
�
xS71Lr
1
-• .:C..� •iiiri
-- :x-
• r.. r.r M
rim' S •,� ..i: _ ....
•- i�ifrlc►r�
KtcL711p,
s Ys►a
•3mwrow.v-r .
+opt Rcx�Rr
40MOftyAUQW5SEMOWAk"krEM IlaS16A
NQr10.SRR)OAC rAcr. rtr AND SwaV4 is sVft srW ar
NAMDARE"*)I'MOAar hwsoRUpToLW4At
u ►C U SMOT IN-W YOUR ROW on Pone ftft C
rrw
Sent from Yahoo Mail for iPhone
cot
'U �Czcun Rrilf1A 11il
4WD
Receipt
Traveiocity itinerary: 724314432
Purchase date: Nov 16.2022
Booking details
Hampton Inn Fayette ill
915 Krupa. FayettevOle. AR. 727
Check -in. Nov 16, 2022
Check-out: Nov 17. 2022
1 roam x 1 night
Room, 2 Queen Beds
Booked for ROBERT MION
ayment details
Roars price
�N�ed. Nov 16
faxes & Fig
Sent from Yahoo Maii for iPhone
SI35.0Q
518.56 AW
S1S3.56 -
Paint
(V�Sd 657$]
4r�
2
Adrian's Painting
176 Niagara St
Springdale, Ar 72762
(479)659-2402
Adnansp nl;n mafl corn
K , m ee;V,0r\-s—
32 c,,3 /V10,�--C-;
�-
j�:�rllnc.{ Vani�
P�� n
5,�
C/e.,.n;�Iq I I
-',.csh
QUOTE
DATE -2
QUOTE #
CUSTOMER ID
VALID UNTIL
300
Ca260
5 `} 5 0
y z. o O
9C9b
950
Subtotal
f �
T01AL
If you have any questions about this price quote, please contact
[Adrian Orozco,(479)659-2402,Adrian'spainting@gmail.com]
Thank You For Your Business!
ENCORE
Building Products
RECEIVED FROM
Lou Petrone
3263 Makeig Ct.
Fayetteville, AR 72703
Encore Building Products
3905 S. Thompson St.
Springdale AR 72764
479-361-8900
Received On Account
Deposit on Order
Current Order Balances
Order Total
Deposit
Balance Due
COD Payment On Invoice
2112-021996
X Current Invoice Balances
Invoice Total
5,340.96
Original COD Amt
1,335.24
Paid To Date
5,340.96
Balance Due
0.00
Miscellaneous Payment
Installed Sale
Previously Paid
Payment Today
Balance Due
Payment Methods
American Express 1,335.24
SALE: 1335.24
Entry Mode: MANUAL
COD (2112-021996) ##1004 246668
IIIIII IIIII IIIII IIIII IIII IIIIII IIIII IIIII IIIII IIIII IIIII IIII IIII
PAYMENT RECEIPT
2201-029163
ACCOUNT JOB
CASH 0 T�
PAID ON 1/18/2022 8:14:34AM
BRANCH 1000
STATION S17
CASHIER 204
Amount
1,335.24
Total 1,335.24
Received
Signature
TRENCHLESS
LEAK
DETECTION
2814 Zion Place
Van Buren, AR 72956
(479) 651-6022 / (479) 414-5744
service@tldpro.com
BILL TO
Kim Petrone
Kim Petrone
3263 North Makeig Court
Fayetteville, AR 72703
JOB# DATE PO/REF#
1008181978 11/15/2022
Job Charges
NU Drain Install
Install
Job Subtotal
7w1. T..4..1
CUSTOMER MESSAGE
Add 3% for Credit Card payment.
Invoice
DATE
11 /28/2022
INVOICE#
636158
TERMS
Due Upon Receipt
DUE DATE
11/28/2022
SERVICE LOCATION
3263 North Makeig Court
Fayetteville, AR 72703
DESCRIPTION
Descaled and Structurally Lined 30'.
Qty Rate
1.00 $8,800.00
Invoice Total:
Deposits (-):
Payments (-):
Total Due:
Total
$8,800.00
$8,800.00
$8,800.00
$8,800.00
$0.00
$0.00
$8,800.00
Mayes Plumbing and Heating, Inc.
mayesp lumbingandheating. com
3730 S Carley Road
Springdale, AR 72762
Phone:479-751-8839 Fax: 479-872-1080
Email: mayesplumbing@gmail.com
November 7th, 2022
Kim Petrone
3263 N Makeig Ct
Fayetteville, AR
Mayes Plumbing and Heating, Inc. proposes to re -line approximately 30' of 30" cast iron pipe. 30'
from upstream main to downstream exterior clean out, covering rot & broken sections of pipe. Customer
will be given a video recording of liner once installed.
Mayes to provide all equipment, labor, and materials necessary to complete this scope of work.
Projected cost for this scope of work: $10,800.00
Exclusions: Unforeseen issues that may arise during given scope of work
We appreciate your consideration of this quotation and would like to thank you for your interest in Mayes
Plumbing & Heating's services. If you have any questions, please call our office. Payment is due within
30 days of work unless other arrangements have been made.
Thank you,
Nathan Mayes
Note: This proposal may be withdrawn by us if not accepted within 30 days.
Accepted by:
Date: _
CONTRACT AGREEMENT
JOE Foundations Inc. hereinafter referred to as the "CONTRACTOR" and John & Kim Petrone
"OWNER. Witnesseth:On this 1 8th day of
January 2022
hereinafter referred to as
in consideration of the mutual agreements and provisions set forth below in
this Contract by and between •" CONTRACTOR" and "OWNER" who warrants that he/she is the owner of the premises at:
3263 Makeig Ct Fayetteville, Ar 72703
for the enumerated work, described below, and do hereby agree as follows:
DESCRIPTION OF WORK TO BE PERFORMED BY CONTRACTOR:
88Exterior Pier _Interior Pier _Support Pier
Wall Membrane __Sump Pump _Trench Drain
and he/she has the right and authority to contract
_Interior Floor Drain —Surface Drain
_Concrete Yards _Exterior Deep Drain
warranty: Lifetime Transferable Warranty on DynaPierS.
Extent of Work to be : done includes excavation along perimeter of home as provided graph shows for pier
locations. Post excavation, installation of eighteen 18 hydraulically driven steel D naPiers in locations
shown, to slightly lift foundation and permanently stablize home. All broken bricks will be replaced, regrouted
and acid washed. sealant will be api2lied to windows to prevent water intrusion.
All excess material hauled off by JDE.
Mailing Address: 3263 Makeig Ct Fayetteville, Ar 72703
kkpetrone@yahoo.com 479-713-0851
Email Addfe se Phan Number AIL Phone Number
Work shall be completed in approximately_ days. Contractor shall remove and haul away all construction and/or installation debris and/or trash from the premises. Contractor
shall furnish all necessary equipment, material and supplies and perform and complete all labor and services in a good workmanlike manner Contractor warrants that the
Company is insured, and qualified to perform and complete the above -described work. All the above -described construction, installation, and work is presumed to improve and
enhance the value of the property and all labors and materials, furnished by Contractor shall become part of the Owner's real property.
II. PRICE AND PAYMENT SCHEDULE: Total cost to the owner for the above described work is S18,1710 of which S2 500s due upon acceptance of this
contract, S when work begins, S at 60% completion (determined by A7 Enterprise), and 5rarkp on completion. Any and all building permits, license fees,
ye
inspection fees by governmental agency including, but not limited to the City;State of Fattemm ll.e —II be paid by Contractor. In the event of the Owners failure
to promptly pay Contractor Pursuant to this payment schedule, Owner shall be liable for any and all collection fees including attorney's fees, for the filing and enforcement of a
mechanics lien and/or other legal remedies available to Contractor to enforce this Contract also leaving contracts warrantyVoid A 3% processing fee will be applied to all credit
card transactions When you provide a check as a payment, you authorize us either to use the information from your check to make a one-time electronic funds transfer from
your account or to process the payment as a check transaction,
III. MODIFICATIONS AND CHANGES: Any changes or variations from the above descriptions and specifications in this Contract involving extra costs will be
invoiced. promptly and due within 30 days to avert a null and void warranty.
IV. DISCLAIMERS:
1. Contractor wl11 take grn Lt cars for plant: 4rid:111u bs It In patad ly removed for wnfk to be performed. All pia nu will be replanted by Caniractar but will not be
respo risible for life or Ion gevi ly.
2. Co rtractor will. attempt to stop any watet intruslon 4auid 4 wort performed, but will not be responw1ile for any water damages to used to any item: or objects/ /y
inside of 11te fou nd3 don tyStem t►`�/
3. Any damage to the structure or ut bties causer) Irf the Cmt ractor as a result of nog llgence nr accident w•11f be repo lfed by the Contractor Liftmgg a snuc lure Carl rt ,
cause :rime Cosmedc damage. such as cracks inr.heelt ve k- cvncmte and other rigidmate rlaE. Thamfu re, damage msulth ng from lifting the w1 ructare as tailed for in
the Agreement Will not be the r4-pam ibility of the Contractor
4. The wartantles cover the perfarmance of &§steno Installed by the Contractor. Prrrrnp.5ys[ems cover stabifiiadon only Contractor will achieve lift roco•eafy as the
,ttuctum allows
5 This Contract is contingent upon there not being any "unavoidable" delays that shall be construed to mean delays due to strikes, lockouts, acts of God, inability to
obtain Labor or materials, governmental restrictions, enemy or terrorist action, civil condition, fire, unavoidable casualty or similar causes beyond the control of
tDntr. ctor.
V. NOTICE TO OWNER: I UNDERSTAND THAT EACH CONTRACTOR, sue CONTRACTOR, LABORER, SUPPLIER, ARCFHTECT, ENGINEER, SURVEYOR.
APPRAISER, LANDSCAPEfC ABSTRACTOR, OR TITLE INSURANCE AGENT SUPPLYING LABOR, SERVICES, MATERIAL. OR FIXTURES IS ENTITLf:D
TO A LIEN AGAINST THE PROPERTY IF NOT PAID IN FULL FOR THE LABOR, SERVICES, ATATERIALS, OR FtXTUR£S USED Ttl Ni
CONSTRUCT, OR INSURE OR EXAMINE TITLE TO THE PROPERTY EVEN THOUGH 731E FULL CONTRACT PRICE MAY HAVE BEEN PAID TO 1HE
CONTRACTOR. t REALIZE THAT THIS LJ EN CAN BE ENFORCED BY THE SALE OF THE PROPERTY IF NECESSARY. I AM ALSO AWARE THAT
PAYMENT MAY SE WITH HELL) TO THE CONTRACTOR JN THE ANICU NT OF THE COST OF ANY SERVICES FIXTURES, MATERIALS, OR LABOR
NOT PAID FOR, I KNOW THAT IT IS ADVISABLE TO. AND I MAY, REQUIRE THE CONTRACTOR TO FURNISH fo ME A TRUE AND CORRECT FULL
LIST OF ALL SUPPLIERS AND SERVICE PROVIDERS UNDER THE CONTRACT, AND I MAY CHECK WITH THEM TO DETERMINE IF ALL
MATERIALS, LABOR, FIXTURES, AND SERVICES FURNISHED FOR THE PROPERTY HAVE BEEN PAID FOR, I MAY ALSO REQUIRE THE
CONTRACTOR TO PRESENT LIEN WAIVERS BY ALL SU P PLIERS AND SERVICE PROVIDERS, STATING THAT THEY HAVE BEEN PAID IN FULL
FOR SUPPLIES AND SERVICES PROVIDED UNDER THE CONTRACT, BEFORE I PAY THE CONTRACTOR IN FULL, IF A SUPPLIER OR OTHER
SERVICE PROVIDER HAS NOT BEEN PAID. I MAY PAY THE SUPPLIER OR OTHER SERVICE PROVIDER AND CONTRACTOR WITH A CHECK
MADE PAYABLE TO THEM .JOINTLY.
VI. COUNTERPARTS: This Contract may be executed in counterpart, each of which shall be deemed an original but all of which together shall constitute one and the
same Lontr:i ct.
VIL ENTIRE AGREEMENT: This cone i:t ephstitutes the entire understanding and agreement between the Contractor and Owner with regard to all matters herein. There
are no other agreements. conditl.vhs, or rCilresentations, oral or written, expressed or implied, with regard thereto. The Contract may Be amended only in writing, and
signed by both Contractor apd Owner-
VIII. BINDING EFFECT: The provisions of this Contract shall be binding upon and inure to the benefit of the Contractor and Owner and their respective successors and
assigns.
IX. GOVERNING LAW: This contract shall be construed and enforced in accordance with the laws of the State of Arkansas.
X. ACCEPTANCE: We have read and agree to the terms and conditions of this Contract as set forth above. Note- This Contract Agreement "BID" may be withdrawn by
us if not accepted within 30 days.
XI. FAILURE OF PAYMENT: Failure to ppayy the contract in full upon Completion will result in prosecution immediately under Arkansas law Ark, Code Ann
§16-56-111(a) Ark. Code Ann. § 4-2-725(1), Warranty Voided.
Owner
Owner
Contractor
JDE11�t
P.O. Box 8704 Springdale, AR 72766
AVESTA
Foundation Solutions
Project Summary
Lift and Level
Stabilize & Protect: 2-Part
Permanently Stabilize Foundation
Prepared by:
Fitz Coleman
fcoleman@vestafs.com
VESTA Foundation Solutions
www.vestaofarkansas.com
TF 479-424-1188
O Arkansas Ad min2021
Prepared on:
1-27-22
Prepared for:
Kim Petrone
kkpetrone@yahoo.com
P (479) 713-0851
Job location:
3263 N Makeig Court
Fayetteville, AR 72703
Total Investment ................................ $44,428.87
Total Contract Price ....................................... ........................ $44,428.87
Deposit Required -15% .............................................. $6,664.33
Deposit Paid ................................... ........... $0.00
Amount Due Upon Installation ........ ............ ........................ :............ :......._....-.......................... $44,428.87
Customer Consent
Any alteration from the above specifications and corresponding price adjustment (if necessary) will be made only at the Customer's
request or approval. Completing the work in this Proposal at the time scheduled is contingent upon accidents or delays beyond our
control. This Proposal is based primarily on the Customer's description of the problem. This Proposal may be withdrawn if not accepted
by the Customer within 30 days due to prices being subject to market fluctuations.
Authorized Signature
Date
Acceptance of Contract— I am/we are aware of and agree to the contents of this Proposal, the attached Job Detail sheet(s), and the
attached Limited Warranty, (together, the "Contract"). You are authorized to do the work as specified in the Contract. I/we will make the
payment set forth in this Contract at the time it is due. I/we will pay your service charge of 1-1/3% per month (16% per annum) if my/our
account is 5 days or more past due, plus your attorney's fees and costs to collect and enforce this Contract. NO VERBAL
COMMITMENTS AND PROMISES ARE EXPRESSED OR IMPLIED OUTSIDE OF THIS WRITTEN DOCUMENT.
Customer Signature
Customer understands VFS is not liable for damage caused by lift.
Customer understands original position may not be possible.
Date
Initial
Initial
VESTA Foundation Solutions Job Location Page 1/8
13243 Puppy Creek Road #13 Springdale AR 72762 3263 N Makeig Court Fayetteville AR 72703 1-27-22 (1)
6302 S. Wilkerson St
Fayetteville, Arkancac
72704
Office (479)4-41-9515
19JAN2022
Kim Petrone t Q�
3263 N Makeig Ct
Fayetteville, Arkansas �(J
(479)713-0851 +
RE: 22-01181 Cursory Foundation Survey
Dear Kim,
Thank you for contacting our company to provide a foundation survey for the residence
referenced above. This report shall serve as our opinions as to the current foundation survey
conducted on 18JAN2022 and recommendations for repairs to be done. All references and
recommendations are based the Non -Destructive Test (NDT) Methods and local building code by
visual observations only. The visual assessment was conducted by David Johnston, VP
Operations and our International Code Council Certified Master Special Inspector (#8053368).
The foundation system was observed to be constructed of a standard concrete continuous footing
with concrete slab on grade with an exterior brick veneer. The slope of the plot plat is negative
towards the front of the home from the old cul-de-sac and positive drainage away from the home
on the rear and sides.
Finding(s)
1. Both pictures and live video of the water main break and the amount of water
flowing towards the home;
2. Shear fractures were observed on ALL perimeter foundation walls;
3. The brick veneer has moved on nine (9) window jambs;
4. The soils in the were very saturated and "spongy';
Opinion(s)
1. We are of the opinion that the foundation has moved in the outward and down
directions due to differential soil settlement caused by the flooding of the property;
especially the foundation system, due to the water main that broke in late 2021;
2. We are of the opinion the brick veneer and most of the wall ties that are directly
supporting the system have been over -stressed due to the amount of water received due
to the broken water main;
3. We are of the opinion the house and it's foundation will continue to settle up to five (5)
years after the water flooding event due to the sub -surface soils being supersaturated;
furthermore, causing the internal concrete slab on grade to then settle and fracture along
with an unknown amount of soil erosion below the concrete slab on grade which will
then have to be high pressure injected with a polyurethane lifting foam in order to
stabilize and potentially lift back into its original place. The cost of this is not included in
this survey, but easily reach $25,000.00 additional (depending on the amount of
settlement) on top of the recommended perimeter foundation underpinning cost
analysis.
We are of the opinion that the foundation is not to be considered stable at the time of the survey
due to its continued movement over the last four (4) months as determined by the photographs
and live video observed.
Recommendation(s)
We are under the recommendation that the entire perimeter foundation system be
underpinned by in the installation of the series of up to 27 ASTM A510 steel hydrulic
pressed piers to bedrock or soil bearing strata (whichever occurs first to provide positive
reaction to the foundation system) at a span of not greater than seven (7) between. The
existing brick fractures should be sealed utilized a structural epoxy and the mortar joints
should be filled by point and tuck methods per minimum masonry standards by the
International Residential Code (IRC) 2021
The cost analysis for this extensive repair is based upon each pier being driven up to a depth of
nine (9') based upon current geological surveys as provided by the USGS as well as PFS Inc.
extensive knowledge of the soils in the neighborhood. The estimated cost of this service is
$22,950.00 with a lock down price guaranteed for 30 calendar days from the date of this survey.
Below are some specifications for minimum construction standards that are referenced for our
cursory surveys.
International Residential Code (IRC)
Section R301.1 Design (Comment: The code requires that buildings and structures have adequate
strength to support the loads and forces without exceeding the allowable stresses on any
element)
Section R301.5 Mlnimum Uniform Live Loads (Comment: The code requires that the nurumum
live loads be not less than the minimums established by the code)
Section R301.7 Deflections (Comment: The code establishes standards for the deflection of
members) 1
Section R401.2 Foundation Construction (Comment: The code requires that the foundation
construction be capable of accommodating of all loads. Structural fill can also be utilized with
appropriate engineering design.)
Section R401.3 Drainage (Comment: The code requires that surface drainage shall be diverted to
a storm sewer conveyance or other approved point of collection so as to not create a hazard. Lots
shall be graded to drain surface water away from foundation walls. The grade shall fall a
minimum of 6 inches (152 mm) within the first 10 feet (3048 mm))
Section R403.1.4 Minimum Depth (Comment: The code requires that the bottom of foundations
extend below the frost penetration level, but not less than twelve inches)
Section R403.1.8 Expansive Soils (Comment: The code requires that foundations in expansive
soils be designed for that condition)
ASTM C1754 Standard Test Method for Density and Void Content of Hardened Pervious
Concrete (Comment: The code requires for the concrete to be free of porosity and consolidation
by vibratory screed methods, not hand vibration)
All opinions and references are in accordance with the International Code Council, the
International Residential Code and the Arkansas Fire Prevention Code as it pertained to the
minimum specifications during the original construction.
This professional opinion was based upon a cursory examination of the perineeter walls and foundation materials visible
at the time of examination on this specific day within the given range of emvironunental factors on the date of this report
above. Other opinions could perhaps be developed as the result of a technically exhaustive engineering design by a
licensed professional engineer. Such a study could involve several hours of information gathering at the site, laboratory
testin& research, and engineering analysis by an licensed engineer and would involve a substantially higher fee
(beginning at ($1,500.00). This cursory survey should not be construed as a guarantee or warranty of any kind in the
construction methods utilized.
This professional opinion is for the sole use of the Precision Fouudatiou Specialists Inc's (PFS Inc.) client and is the
intellectual property of PFS Inc. Client will defend indemnify, represent and hold hornless PFS, Inc. four and against
any claim, action or proceeding brought by any party claiming to rely upon inforaation or opinions contained in this
document. No release without having obtained PFS, Inc's. prior written consent. PFS hrc. does not authorize client to
share this information with competing companies. Unauthorized use is will be punished by to the full extent of the law
through all legal avenues. By release of this report all parties promise to in indemnify, represent and defend any and all
claims for any damages claimed by others in the use of this report. Liability is limited to the fees for the services
provided Thank you for calling upon PFS Inc. for this service.
Respectfully submitted,
Precision Foundation Specialists Inc.
By: EGG.
Matt Johnston, ACSE, tSE, CSI
ti'
`* E 9 AUr
PRECISION:_
FOUNDATION
ClAl15i5 INC o
a,RK�AH5A5,.a
Gs C3
PRIVACY FENCE, INC
ESTIMATE: M T 6) T F S PO Box 7582 INV# zi- 0839
Date: /u ,-Z-LJ21 AM!PM Springdale, AR 72766 ARConbaclioiruoettm#
APPROV DATE: �_� zI
Office: 479-751-7894 0>.565
APPROX START: zI!tt�s:Ilwww.Priyat7+FerlceNWA.corn arc awc Ica,. aRRou arr�vnle Sx
/} c-7En Lc ozco coot acr swmco sys
ADVMINIM LNG Proposal / Invoice REF a -
A usr ®RR colvrR GooGLe NO ARKUPS: AM ! PM
NQ RED AEF SIGN SEAL YU
Client: -' Email: -
Add ress: 3,,�6 3 N . ACV, Phone: q7q-1�/3- o�s�
❑ TREES/BRUSH
O HILLSIDE
❑ ROCKY
14,WATER i ,L
AVAILABLE p - v5r jhr
@&'-2" OFF
ZIU
AVAILABLE Lyd
❑ FENCE OFF
GROUND >2"
❑ FINISHED / 7
SIDE OUTSIDE LA'
"I
• FINISHED
SIDE INSIDE
❑ DOGS
**PRESSURE TREATED RAILS AND POSTS USED UNLESS OTHERIIIIISE NOTED ON THIS PROPOSAL**
FENCE TYPE PICKETS HEIGHT FOOTAGE We Propose to furnish material and labor,
l?f BOARD TO BOARD ❑ PRESSURE•TREATEfOPINE 4FT/5E--T16F �S-��� with the included specifications for the sum
❑i:~ y�
❑ SHADOWBOX 1'ASTERNCEDAR, JI�y�_ d;, 4FT/`iFT%6FT CHECK/CASHPRICE:$
r BOARD ON BOARD ❑ WESTERN CEDAR 4FT/ SFT / 6CLLi --
ORNAMENTAL IRON _i N1AGESl-It: (SMGC)TH TOP; CREDIT CARD PRICE: S
2 RAIL ❑ CLASSIC (PINCHED PICKET; JCL f SFT / 6FT ���
3 RAIL GENESIS (EX -I ENDED PII:KETj � .is%ccp,,,, inu fee
CHAIN LINK GAGS T FFM r 111S
GAL :AN;Zt-D TAX:
L�tiE 4FT i SFT !'-FT
'VlNYL'-0A--" !--
BLACK GREEN BROWN TOP FAIL DEPOSIT: _
OTHER: BALANCE DUE_UPON C MO PLET101P,
zz�
DOUBLE GATES:
W
�, I
WOOD FRAME � CI� �%' �r
OOD FRAME Client Signature:
F'
❑ STEEL FRAME -•'TE L� CAME
❑ CHAIN LINK ❑ y AIN LINK,
❑O AIDA�ENTALOHNMAMEN7A1 PFISignature:
EAR OUT DECORATIVE WOOD ORN ROUND STEEL POSTMASTERS
I9�-IAULOF POSTS STARTERS STARTERS POSTS STEEL POSTS aQe; �p71
*RESPONSIBILITY OF CLIENT AND PRIVACY FENCE, INC*
Privacy Fence, Inc. agrees to guarantee tyre abm fence to be free from detects In workmar5nlp for one ill year - (Not Included are; alignment due to warping, splitting, miov,
shrinking, cheddng, or other oranges In the shape of the Wood). All other warranties come from manUratxwer maternal used under this contract it is mmmmended that sealer
be appbed to the wood In appradmately 4o days to help lessen wood warping or Cheddng.
Responsibility for complying with zone regulations and obtalang any required permits shell rest with the dlenL Under no drtumstarwis does Privacy Fence, Inc assume arty
responsibility Concerning property lines. If property pins carVrot be bcarod, It Is recommended that the client have the property slrveyed. The client will defend PrHacy Ferree.,
Im In cmneoon With any doIms made by anyone ]lout. the Iwzc-n or the fence.
Privacy Fence, Inc will assume the responsibility for having underground public utildes looted and marked. However, Privacy Fence, Inc asswnes no resporsulay for umnarkod
sprinkler lines or any other unmarked burled lens or objects. The client will assume all liability for damages caused by dlrecung PrKWY Fence, Inc to dig In the ImmediatavIdnity
of known or unknown utlllttes.
Any adinAws or Changes made by fhe dlent that regulres extra labor and material will be added to the pike establdned an tl%Chntrad drid will Wunird due and pay&* to
prnraCy Fence, ire. Right of amess and removal x grantM to Pnvacy Fer", Try- In the
of nori-PaYment
a debt under the terms rf the contract The r9entagreesta pay all
lrrtelest and costs Incurred co
35.00 Returned Check Fee