MUD CREEK BRIDGE ASSESSMENT FUNDS-SAIN STREET:
A RESOLUTION TO APPROVE A BUDGET ADJUSTMENT IN THE AMOUNT OF
$23,996.00 RECOGNIZING REVENUE FROM THE MUD CREEK BRIDGE ASSESSMENT
FUNDS FOR THE SAIN STREET PROJECT
THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1. That the City Council of the City of Fayetteville, Arkansas hereby approves the attached
budget adjustment in the amount of $23,996.00 recognizing revenue from the Mud Creek Bridge
Assessment Funds for the Sain Street Project.
PASSED and APPROVED on 9/6/2022
���►{1llIIIJFl
Appro .ed: Attest: �E �rrf'
FAYF-TTEVELLE.
Lioneld Jord i, Mayor Kara Paxton, City Clerk Treasurer ►�Y-,,: P:`A
Page 1 Printed on 917122
City of Fayetteville, Arkansas 113 West Mountain Street
Fayetteville, AR 72701
(479)575-8323
Text File
File Number: 2022-0763
Agenda Date: 9/6/2022 Version: 1 Status: Passed
In Control: City Council Meetinq File Type: Resolution
Agenda Number: A.4
MUD CREEK BRIDGE ASSESSMENT FUNDS-SAIN STREET:
A RESOLUTION TO APPROVE A BUDGET ADJUSTMENT IN THE AMOUNT OF $23,996.00
RECOGNIZING REVENUE FROM THE MUD CREEK BRIDGE ASSESSMENT FUNDS FOR THE
SAIN STREET PROJECT
THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section 1. That the City Council of the City of Fayetteville, Arkansas hereby approves the attached budget
adjustment in the amount of $23,996.00 recognizing revenue from the Mud Creek Bridge Assessment Funds
for the Sain Street Project.
City of Fayetteville, Arkansas Page 1 Printed on 91712022
Paul Libertini
Submitted By
City of Fayetteville Staff Review Form
2022-0763
Legistar File ID
9/6/2022
City Council Meeting Date - Agenda Item Only
N/A for Non -Agenda Item
8/16/2022 ENGINEERING (621)
Submitted Date Division / Department
Action Recommendation:
A Resolution to recognize revenue in the amount of $23,996 from the Mud Creek Bridge Assessment funds for the
Sain Street project which has constructed a new bridge over Mud Creek and to approve a Budget Adjustment.
Budget Impact:
4470.800.8835-5809.00
Sales Tax Capital Improvement
Account Number Fund
06035.7213 Sain Street Extension (2019 Bond Project)
Project Number
Budgeted Item? Yes
Does item have a cost? No
Budget Adjustment Attached? Yes
Purchase Order Number:
Change Order Number:
Original Contract Number:
Comments:
2020-00000784
2020-00000085
Current Budget
Funds Obligated
Current Balance
Item Cost
Budget Adjustment
Remaining Budget
Project Title
$ 2,515,228.00
$ 2,227,989.00
$ 287,239.00
$ 23,996.00
311,235.00
V20210527
Previous Ordinance or Resolution # 05-22
Approval Date:
�W'
MEETING OF SEPTEMBER 6, 2022
TO: Mayor and City Council
THRU: Susan Norton, Chief of Staff
Chris Brown, Public Works DCity Engineer
FROM: Paul Libertini, Staff Engineer
DATE: August 16, 2022
SUBJECT: Sain Street Construction Project — Recognize Mud Creek Bridge
Assessment Funds.
RECOMMENDATION:
Staff recommends approval of a Resolution to recognize revenue in the amount of $23,996 from
the Mud Creek Bridge Assessment funds for the Sain Street project which has constructed a
new bridge over Mud Creek and to approve a Budget Adjustment.
BACKGROUND:
Mud Creek Bridge Assessment funds have been collected since 2006. On December 1, 2020,
City Council recognized $268,466 which were collected for bridge improvements and allocated
the funds to the Sain Street Construction project which is approximately 70% complete. As part
of this project, a new 320 ft. two lane bridge has been constructed over Mud Creek which is
approximately 95% complete.
DISCUSSION:
Subsequent to recognizing the bridge assessment funds referred to above, an additional
development near Mud Creek was approved in late 2021 by the City and was assessed
$23,961.60 for bridge improvements. With interest, this escrow amount is now $23,996.00.
BUDGET/STAFF IMPACT:
The construction budget for this project will be increased by $23,996.00.
Attachments:
Bridge Assessment Staff Memo dated 9/28/2021
Budget Adjustment
CITY OF
f FAYETTEVILLE
ARKANSAS
TO: Gretchen Harrison, Planner
FROM: Josh Boccaccio, Staff Engineer
DATE: September 28, 2021
SUBJECT: LSD 2021-000038 Bridge Assessment
STAFF MEMO
The Engineering Division requires that this development be assessed for a percentage of the
construction costs for a bridge over Mud Creek. The following is a rational nexus calculation
for this offsite improvement:
Projected Traffic from development — 435 vpd
Assume 50% of vehicle trips will turn east onto Joyce — 218 vpd
Assume 33% of vehicle trips will turn south and use the Mud Creek Bridge — 72 vpd
Neighborhood Link (Collector) traffic capacity = 6,000 vpd
% Traffic from development = 1.2%
Estimated Mud Creek Bridge Costs:
15,360 sf x $130/sf = $1,996,800.
Hedberg Allergy Percentage of Costs:
0.012($1,996,800) = $23,961.60
Therefore, the Engineering Division concludes the Joyce St. Office Building development be
assessed for the Mud Creek Bridge.
Joyce Boulevard Investments LLC 1003
4200 N Gabel Dr 81-088510829
Fayetteville, AR 72703
DATE
A ,
PAY TO THE
ORDER OF-
�f�
.4Ui t
P.O. Box 6490
Springdale AR 72766
L E CY �. ar.corn
Hati�o,na�lliank MYBenk.MY�Y �
MEMO. i'U ZL ()DCD 36
AQ Si+cufliy Ilerur9e
DOLLARS I *Jnormun beck
u°00 L00 3u° i:08 29088 SB1: 900464000
City of Fayetteville, Arkansas - Budget Adjustment Form (Legistar)
Budget Year Division Adjustment Number
/Org2 ENGINEERING (621)
2022
Requestor: Paul Libertini
BUDGET ADJUSTMENT DESCRIPTION / JUSTIFICATION:
Move the remaining Mud Creek Bridge Assessment funds into the Sain Street Construction project which has
constructed a new bridge over Mud Creek.
RESOLUTION/ORDINANCE
COUNCIL DATE: 9/6/2022
LEGISTAR FILE ID#: 2022-0763
Hovy 3lack�
811712022 2:20 PM
Budget Director Date
TYPE: D - (City Council)
JOURNAL #:
GLDATE:
CHKD/POSTED:
TOTAL 23,996 23,996
Increase / (Decrease)
Account Number Expense Revenue
v.20220718
Proiect.Sub#
Project Sub.Detl AT Account Name
4470.800.8835-4420.00 - 23,996
06035 7213 RE Payments by Property Owners - base
4470.800.8835-5809.00 23,996 -
06035 7213 EX Improvements - Street
H:\Budget Adjustments\2022_Budget\CITY COUNCIL\09-06-22\2022-0763
BA Mud Creek Bridge revenue (Sain St) 1 of 1