HomeMy WebLinkAbout185-22 RESOLUTION113 West Mountain Street
Fayetteville, AR 72701
(479)575-8323
Resolution: 185-22
File Number: 2022-0683
NABHOLZ CONSTRUCTION CHANGE ORDER 11, CULTURAL ARTS CORRIDOR:
A RESOLUTION TO APPROVE CHANGE ORDER NO. 11 TO THE CONTRACT WITH
NABHOLZ CONSTRUCTION CORPORATION IN THE AMOUNT OF $4,984,952.00 FOR
WEST AVENUE IMPROVEMENTS AND THE GREENWAY TRAIL IMPROVEMENTS
RELATED TO THE CULTURAL ARTS CORRIDOR PROJECT, AND TO APPROVE A
BUDGET ADJUSTMENT - 2022 CULTURAL ARTS CORRIDOR BOND PROJECT
WHEREAS, on October 2, 2018, the City Council passed Resolution 217-18 to approve a
Construction Manager at Risk Services Contract with Nabholz Construction Corporation for services
related to Phase 1 of the Cultural Arts Corridor Project; and
WHEREAS, Change Order No. 11 will include work on West Avenue from Meadow Street to
Dickson Street and the Greenway Trail Improvements from Meadow Street to Spring Street.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE. CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves Change Order
No. 11 to the Construction Manager at Risk Services Contract with Nabholz Construction
Corporation, a copy of which is attached to this Resolution, in the amount of $4,984,952.00 for the
work on West Avenue from Meadow Street to Dickson Street and the Greenway Trail Improvements
from Meadow Street to Spring Street, related to Phase 1 of the Cultural Arts Corridor Project.
Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget
adjustment, a copy of which is attached to this Resolution.
Page 1 Printed on 8118122
Resolution: 185-22
File Number: 2022-0683
PASSED and APPROVED on 8/16/2022
Awroved:
Attest: � �gK �' R�//z
I AYETTEVILLL;'�w
Kara Paxton, City Clerk Treasur'.'9.Q p�,�
■.,sy, ,
kA Nc.
Page 2 Printed on 8118122
City of Fayetteville, Arkansas 113 West Mountain Street
Fayetteville, AR 72701
(479)575-8323
Text File
File Number: 2022-0683
Agenda Date: 8/16/2022 Version: 1 Status: Passed
In Control: City Council Meetinq File Type: Resolution
Agenda Number: A. 11
NABHOLZ CONSTRUCTION CHANGE ORDER 11, CULTURAL ARTS CORRIDOR:
A RESOLUTION TO APPROVE CHANGE ORDER NO. 11 TO THE CONTRACT WITH NABHOLZ
CONSTRUCTION CORPORATION IN THE AMOUNT OF $4,984,952.00 FOR WEST AVENUE
IMPROVEMENTS AND THE GREENWAY TRAIL IMPROVEMENTS RELATED TO THE
CULTURAL ARTS CORRIDOR PROJECT, AND TO APPROVE A BUDGET ADJUSTMENT - 2022
CULTURAL ARTS CORRIDOR BOND PROJECT
WHEREAS, on October 2, 2018, the City Council passed Resolution 217-18 to approve a Construction
Manager at Risk Services Contract with Nabholz Construction Corporation for services related to Phase 1 of
the Cultural Arts Corridor Project; and
WHEREAS, Change Order No. 11 will include work on West Avenue from Meadow Street to Dickson
Street and the Greenway Trail Improvements from Meadow Street to Spring Street.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves Change Order No. 11
to the Construction Manager at Risk Services Contract with Nabholz Construction Corporation, a copy of
which is attached to this Resolution, in the amount of $4,984,952.00 for the work on West Avenue from
Meadow Street to Dickson Street and the Greenway Trail Improvements from Meadow Street to Spring
Street, related to Phase 1 of the Cultural Arts Corridor Project.
Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget adjustment, a
copy of which is attached to this Resolution.
City of Fayetteville, Arkansas Page 1 Printed on 811812022
Wade Abernathy
Submitted By
City of Fayetteville Staff Review Form
2022-0683
Legistar File ID
8/16/2022
City Council Meeting Date - Agenda Item Only
N/A for Non -Agenda Item
7/27/2022
Submitted Date
Action Recommendation:
FACILITIES MANAGEMENT (140)
Division / Department
Approval of Change Order #11 to RFQ 18-11 with Nabholz Construction for the Arts Corridor project in the amount
of $4,984,952.00 for West Avenue improvements from Meadow Street to Dickson Street and the Greenway Trail
improvements from Meadow Street to Spring Street, and approval of a budget adjustment.
Budget Impact:
4708.860.7800-5809.00 Arts Corridor Bond Projects
4470.170.8170-5315.00 Sales Tax Capital Improvements
Account Number
46080.7800
09028.1
Project Number
Budgeted Item? Yes
Does item have a cost? Yes
Budget Adjustment Attached? Yes
Fund
Arts Corridor Improvements
Fiber Optic Cable
Current Budget
Funds Obligated
Current Balance
Item Cost
Budget Adjustment
Remaining Budget
Project Title
$ 4,194,708.00
$ 3,706,480.84
$ 488,227.16
$ 4,984,952.00
$ 4,949,772.00
453,047.16
V20210527
Purchase Order Number: Previous Ordinance or Resolution # 309-321
Change Order Number: 11 Approval Date:
Original Contract Number: 2018-00000042
Comments: A new Purchase Order will be established for Phase 11 Bond Projects.
CITY OF
FAYETTEVILLE
ARKANSAS
MEETING OF AUGUST 16, 2022
TO: Mayor and City Council
THRU: Susan Norton, Chief of Staff
Paul Becker, Chief Financial Officer
CITY COUNCIL MEMO
FROM: Wade Abernathy, Director Bond and Construction Projects
DATE: 7/27/2022
SUBJECT: Approval of change order #11 to RFQ 18-11 with Nabholz Construction for
the Arts Corridor project and approve a budget adjustment.
RECOMMENDATION:
Staff recommends approval of change order #11 with Nabholz Construction on the Arts Corridor
project in the amount of $4,984,952.00 for the West Avenue Street Improvements from Meadow
Street to Dickson Street and Greenway Trail Improvements from Meadow Street to Spring
Street.
BACKGROUND:
With the Phase 1 Arts Corridor Bond Project nearing completion, staff recommends moving
forward with this portion of the project to avoid any remobilization charges and future
escalations as we await the completion of the replacement parking deck. Allowing the early start
of this phase will also help maintain the completion schedule of the overall Arts Corridor project.
DISCUSSION:
This change order includes West Avenue Improvements from Meadow Street to Dickson Street
and Greenway Trail Improvements from Meadow Street to Spring Street.
BUDGET/STAFF IMPACT:
Unallocated Bond funds will be used for this change order. This BA will also reverse the General
Fund loan approved on 05/17/22 with resolution 123-22.
Purchase Order Detail
GLACCOUNT
PROJECT
AMOUNT
4708.860.7800-5809.00
46080.7800
$ 4,949,772
4470.170.8170-5315.00
09028.1
$ 35,180
TOTAL
$ 4,984,952
Attachments:
Change Order #11
Mailing Address:
113 W. Mountain Street www.fayetteville-ar.gov
Fayetteville, AR 72701
�NTE6BIrY
1�
City of Fayetteville
Upper Ramble Phase
Fayetteville, AR
Exhibit A: Guaranteed Maximum Price
July 27, 2022
Executive Summary
Pricing
Nabholz presents this Guaranteed Maximum Price dated July 27, 2022 for the Upper
Ramble Phase 1. Based on the Construction Documents provided by Nelson Byrd Woltz,
we propose a Guaranteed Maximum Price of $4,984,952. A more detailed estimate is
enclosed for your review.
Scope of Work
The following allowances have been included in the GMP:
1. An allowance of $10,000 for unsuitable soils.
2. An allowance of $25,500 for restoration of the laydown area to the south of the
library.
The following are the accepted alternates that were requested and have been incorporated
into the GMP:
1. DEDUCT - $229,886 to eliminate the streets work from the intersection of Spring
St. to Meadow St.
2. DEDUCT - $293,921 to remove relocating the overhead lines to underground.
The following are items which have been excluded from the GMP:
1. A Building Permit has not been included.
Bid Documents
The Guaranteed Maximum Price is based upon the following Construction Bid
Documents.
Drawings and specifications provided by Nelson Byrd Woltz, dated April 22,
2022.
0 Addendum #1 issued July 14, 2022.
111S�17ilr
� I
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
GMP
PROJECT NAME
Upper Ramble Phase 1
PROJECT LOCATION
Fayetteville , AR
REVIEW DATE
7/27/2022
ARCHITECT
Nelson Byrd Woltz
ESTIMATED DURATION
10 Mo
ob Phase
Nabholz
Description
Grand Total
Amount
01
Upper Ramble Phase 1
01-7423
Final Cleaning
Speedy Cleaners
3,638
01-7423 Final Cleaning
3,638
05-1205
Metal Fabrications (Supply & Install)
STI
19,509
STI Street Deductive Alt.
(1,219)
05-1205 Metal Fabrications (Supply & Install)
18,289
06-2000
Carpentry
Nabholz Carpentry
9,908
06-2000 Carpentry
9,908
07-1000
Joint Sealants
Crum & Marshall
3,493
Crum & Marshall Street Deductive Alt.
(182)
07-1000 Joint Sealants
3,311
26-1000
Electrical
Original scope allownace
1,237,394
Laydown Area Restoration Electrical Allowance
5,080
Street Deductive Alt.
(46,231)
OH Electric Line Deductive Alt.
(30,482)
Conduit for IT Connectivity Project
35,180
26-1000 Electrical Allowance: contractor to be selected
1,200,941
31-0000
Earthwork, Storm Drainage and Asphalt
Oelke
1,409,724
Unsuitable Soils Allowance
10,161
Oelke Street Deductive Alt.
(98,559)
Oelke Asphalt Scope VE
(215,407)
31-0000 Earthwork, Storm Drainage and Asphalt
1,105,918
32-1723
Pavement Markings and Signage
Marking Systems
21,222
Marking Systems Street Deductive Alt.
(652)
32-1723 Pavement Markings and Signage
20,569
32-4750
Site Concrete
Nabholz Concrete
615,190
Nabholz Concrete Street Deductive Alt.
(58,735)
32-4750 Site Concrete
556,455
32-9323
Landscaping & Irrigation
Sharum
164,952
Laydown Area Restoration Sod Allowance
18,289
Laydown Area Restoration Irrigation Allowance
2,540
Sharum Street Deductive Alt.
(10,669)
Permeable Pavers VE
(90,540)
32-9323 Landscaping & Irrigation
84,573
01 Upper Ramble Phase 1
3,003,602
GMP
PROJECT NAME Upper Ramble Phase 1
NACT LOCATION Fayetteville , AR
22 001Z
PROJ REVIEW ARCHI ECT Nelson Byrd Woltz
ESTIMATED DURATION 10 Mo
Estimate Totals
Cost of Work
3,003,602
3,003,602
Building Permit Fee NIC
Building Permit NIC
3,003,602
General Liability
35,997
Builder's Risk
4,235
Performance Payment Bond
21,175
Insurance & Bonds
61,407
3,065,009
GCs & GRs
959,899
Entenrity Sustainability, Consulting
5,660
GCs & GRs
965,559
4,030,568
Preconstruction Services Fee
10,000
Proiect Fee
194,384
Contractors Fee
204,384
4,234,952
Owner Contingency
750.000
Construction Contingency
750,000
4,984,952
Total
4,984,952
4.590
PROJECT CONFIDENTIAL
Property of Nabholz Construction Corporation Not for Duplication or Distribution
This document includes data that is deemed trade secret or proprietary to Nabholz and prepared in
conjunction with the Project. This document is shared with the Project team solely for use on this Project
consistent with the responsibilities of the Project team. The Recipients shall not duplicate, use, or disclose,
in whole or in part, to any person, entity, or party outside the Project team without Nabholz' prior written authorization.
FCAC Phase II
NA01Z Early Streetscape Package
Activity ID
Activity Name
Original
Duration
Start
Finish
2023
Q3 Q4
Q1 Q2
Q3
A1000
A1010
A1020
A1030
A1040
A1050
A1150
. ,
Gose West Ave. from Meadow St. to Dickson St.
• .
•�.
Od
10d
• .
• .
9-6-22*
9-6-22
9-19-22
5-29-23, FCAC Phase III —Civic Plaza
5-29-23, West Ave. from Meadow St. to Dickson
♦ Gose West Ave. from Meadow St. to Dickson St.
01ma Install SWPPP BMPs
1 Install Temp. Traffic Control Signage
. .........
Demo Asphalt, Sidewalk, and Curb & Gutter
Demo Existing Storm Drainage
Install Storm Drainage Pipes and Structures
Install Water Line
Install Underground Electrical'
Rough Grading
Install Curb & Gutter
Adjust SS Manholes
InstallApproaches
O Install Storm Drainage Box Tops
......... ......... __.....
O Install Paverdrain System
Install Driveways
Install Sidewalks
Final Grading
O Adjust Existing Storm Drainage Grates to Grade
O Install Furnishings
0 Install Light Pole Bases
E� Tree Wells and Top Soil
0 Asphalt: Binder Course
IMI Asphalt Paving
..........
Install Landscaping
O Install Light Poles
O Install Pavement Markings & Signage
M Remove SWPPP BMPs
0 Remove Temp. Traffic Control Signage
♦ Open West Ave. from Meadow St. to Dickson St.
11-25-22, Greenway from Center St. to Meadow St.
♦ Gose Greenway from Center St. to Spring St.
1 Install SWPPP BMPs
I Install Temp. Traffic Control Signage
......... :.......
I Install Tree Protection
1 Protect Existing Block Retaining Walls to Remain
1 Demo Existing Block Retaining Walls to be Demolished
■ Demo Trail
Install Underground Electrical
IMI Install Concrete Retaining Walls
O Install Handrail
Install SWPPP BMPs
Install Temp. Traffic Control Signage
2d
9-6-22
9-7-22
Demo Asphalt, Sidewalk, and Curb & Gutter
10d
9-20-22
10-3-22
Demo Existing Storm Drainage
10d
10-4-22
10-17-22
Install Storm Drainage Pipes and Structures
30d
10-18-22
11-28-22
Install Water Line
30d
11-1-22
12-12-22
A1170
A1060
A1070
A1240
A1080
A1210
A1280
A1090
A1100
A1110
A1260
A1220
A1180
A1160
A1120
A1130
A1230
A1270
A1140
A1410
A1420
A1430
A1440
A1450
A1460
A1470
A1480
A1490
A1510
A1540
A1560
A1570
Install Underground Electrical
30d
11-15-22
12-26-22
Rough Grading
10d
12-20-22
1-2-23
Install Curb & Gutter
25d
1-3-23
2-6-23
Adjust SS Manholes
15d
1-17-23
2-6-23
Install Approaches
10d
131-23
2-13-23
Install Storm Drainage Box Tops
25d
2-7-23
3-13-23
Install Paverdrain System
15d
2-7-23
2-27-23
Install Driveways
10d
2-14-23
2-27-23
Install Sidewalks
20d
2-28-23
3-27-23
Final Grading
15d
2-28-23
3-20-23
Adjust Existing Storm Drainage Grates to Grade
15d
3-14-23
4-3-23
Install Furnishings
5d
3-21-23
3-27-23
Install Light Pole Bases
15d
3-28-23
4-17-23
Tree Wells and Top Soil
10d
3-28-23
4-10-23
Asphalt Binder Course
5d
4-4-23
4-10-23
Asphalt Paving
5d
4-11-23
4-17-23
Install Landscaping
30d
4-11-23
5-22-23
Install Light Poles
5d
4-11-23
4-17-23
Install Pavement Markings &Signage
5d
4-18-23
4-24-23
Remove SWPPP BMPs
5d
5-23-23
5-29 23
Remove Temp. Traffic Control Signage
2d
5-23-23
5-24-23
Open West Ave. from Meadow St. to Dickson St.
Gose Greenway from Center St. to Spring St.
Od
10-3-22*
5-29-23
Od
Install SWPPP BMPs
1d
10-3-22
10-3-22
Install Temp. Traffic Control Signage
1 d
10-3-22
10-3-22
Install Tree Protection
1d
10-3-22
10-3-22
Protect Existing Block Retaining Walls to Remain
2d
10-4-22
10-5-22
Demo Existing Block Retaining Walls to be Demolished
2d
10-6-22
10-7-22
Demo Trail
4d
10-10-22
10-13-22
Install Underground Electrical
10d
10-14-22
10-27-22
Install Concrete Retaining Walls
7d
10-14-22
10-24-22
Install Handrail
5d
10-25-22
10-31-22
Actual Work Critical Remaining Work VmmmmmI Summary Printed 7-26-22
0 Remaining Work ♦ ♦ Milestone Page 1 of 2
Activity ID
Activity Name
Original
Duration
Start
Finish
A1520
Grade Trail
2d 10-28-22
10d 11-1-22
10-31-22
A1580
Install Concrete Trail
11-14-22
A1530
Install Light Pole Bases
3d
11-11-22
11-15-22
A1650
Install Landscaping
5d
11-16-22
11-22-22
A1670
Install Light Poles
5d
11-16-22
11-22-22
A1630
Install Pavement Markings
1d
11-23-22
11-23-22
A1640
Install Passive Detection Bollards
2d
11-23-22
11-24-22
A1680
Remove SWPPP BMPs
1d
11-25-22
11-25-22
A2340
Remove Temp. Traffic Control Signage
1d
11-25-22
11-25-22
A1610
I Open Greenway from Center St. to Spring St.
Od
11-25-22
Actual Work Critical Remaining Work VmmmmmI Summary Printed 7-26-22
O Remaining Work ♦ ♦ Milestone Page 2 of 2
City of Fayetteville, Arkansas - Budget Adjustment Form (Legistar)
Budget Year Division Adjustment Number
/Org2 FACILITIES MANAGEMENT (140)
2022
Requestor: Wade Abernathy
BUDGET ADJUSTMENT DESCRIPTION / JUSTIFICATION:
Approval of Change Order #11 to RFQ 18-11 with Nabholz Construction for the Arts Corridor project in the amount of
$4,984,952.00 for West Avenue improvements from Meadow Street to Dickson Street and the Greenway Trail
improvements from Meadow Street to Spring Street
RESOLUTION/ORDINANCE
COUNCIL DATE: 8/1 6/2022
LEGISTAR FILE ID#: 2022-0683
}f o-ll y 31ac1�
712812022 10:13 AM
Budget Director Date
TYPE: D - (City Council)
JOURNAL #:
GLDATE: 8/16/2022
CHKD/POSTED:
TOTAL
Account Number
(988,070) (988,070)
Increase / (Decrease)
Expense Revenue
Proiect.Sub#
Project Sub.Detl AT
v.20220718
Account Name
4708.860.7800-5809.00
4,949,772 -
46080 7800 EX
Improvements - Street
4708.860.7999-5899.00
(4,949,772) -
46080 7999 EX
Unallocated - Budget
4708.860.7999-5899.00
4708.860.7000-4999.99
(988,070) -
- (988,070)
46080 7999 EX
RE
Unallocated - Budget
Use Fund Balance - Current
H:\Budget Adjustments\2022_Budget\CITY COUNCIL\08-16-22\2022-0683 BA C01 1 Nabholz CAC 1 of 1