HomeMy WebLinkAbout167-22 RESOLUTIONi 1 113 West Mountain Street Fayetteville, AR 72701 (479) 575-8323 Resolution: 167-22 File Number: 2022-0621 NABHOLZ CONSTRUCTION CORPORATION CHANGE ORDER NO. 10: A RESOLUTION TO APPROVE CHANGE ORDER NO. 10 TO THE CONTRACT WITH NABHOLZ CONSTRUCTION CORPORATION IN THE AMOUNT OF $505,652.42 FOR PAVING ON GREGG AVENUE AND WEST AVENUE, STREET WORK ON WEST AVENUE AND RECONCILIATION OF CONTINGENCY FOR ADDITIONAL ITEMS RELATED TO THE CULTURAL ARTS CORRIDOR PROJECT, AND TO APPROVE A BUDGET ADJUSTMENT - 2019 CULTURAL ARTS CORRIDOR BOND PROJECT WHEREAS, on October 2, 2018, the City Council passed Resolution 217-18 to approve a Construction Manager at Risk Services Contract with Nabholz Construction Corporation for services related to Phase 1 of the Cultural Arts Corridor Project; and WHEREAS, Change Order No. 10 will include work on West Avenue at Hillcrest Towers, West Avenue paving, Gregg Avenue paving, as well as bioswale materials testing and reconciliation of items added to the contract that were not included in contingency. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS: Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves Change Order No. 10 to the Construction Manager at Risk Services Contract with Nabholz Construction Corporation, a copy of which is attached to this Resolution, in the amount of $505,652.42 for the work on West Avenue at Hillcrest Towers, West Avenue paving, Gregg Avenue paving, as well as bioswale materials testing and reconciliation of items added to the contract that were not previously included in contingency related to Phase 1 of the Cultural Arts Corridor Project. Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget Page t Printed on 813122 Resolution: 167-22 File Number: 2022-0621 adjustment, a copy of which is attached to this Resolution. PASSED and APPROVED on 8/2/2022 Attest: ►►►nn i �r►lrrr RK • G fAYETTEVIL6 ;S Kara Paxton, City Clerk Treasurer �;.�,� r �a • A... h4rl.��••�a •�` fNG Tp N •CC iN Nr t1 t i 110%■. Page 2 Printed on 813122 City of Fayetteville, Arkansas 113 West Mountain Street Fayetteville, AR 72701 (479)575-8323 Text File File Number: 2022-0621 Agenda Date: 8/2/2022 Version: 1 Status: Passed In Control: City Council Meetinq File Type: Resolution Agenda Number: A.3 NABHOLZ CONSTRUCTION CORPORATION CHANGE ORDER NO. 10: A RESOLUTION TO APPROVE CHANGE ORDER NO. 10 TO THE CONTRACT WITH NABHOLZ CONSTRUCTION CORPORATION IN THE AMOUNT OF $505,652.42 FOR PAVING ON GREGG AVENUE AND WEST AVENUE, STREET WORK ON WEST AVENUE AND RECONCILIATION OF CONTINGENCY FOR ADDITIONAL ITEMS RELATED TO THE CULTURAL ARTS CORRIDOR PROJECT, AND TO APPROVE A BUDGET ADJUSTMENT - 2019 CULTURAL ARTS CORRIDOR BOND PROJECT WHEREAS, on October 2, 2018, the City Council passed Resolution 217-18 to approve a Construction Manager at Risk Services Contract with Nabholz Construction Corporation for services related to Phase 1 of the Cultural Arts Corridor Project; and WHEREAS, Change Order No. 10 will include work on West Avenue at Hillcrest Towers, West Avenue paving, Gregg Avenue paving, as well as bioswale materials testing and reconciliation of items added to the contract that were not included in contingency. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS: Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves Change Order No. 10 to the Construction Manager at Risk Services Contract with Nabholz Construction Corporation, a copy of which is attached to this Resolution, in the amount of $505,652.42 for the work on West Avenue at Hillcrest Towers, West Avenue paving, Gregg Avenue paving, as well as bioswale materials testing and reconciliation of items added to the contract that were not previously included in contingency related to Phase 1 of the Cultural Arts Corridor Project. Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget adjustment, a copy of which is attached to this Resolution. City of Fayetteville, Arkansas Page 1 Printed on 81312022 Wade Abernathy City of Fayetteville Staff Review Form 2022-0621 Legistar File ID 8/2/2022 City Council Meeting Date - Agenda Item Only N/A for Non -Agenda Item FACILITIES MANAGEMENT (140) Submitted By Submitted Date Division / Department Action Recommendation: 7/13/2022 Staff recommends approval of change order #10 with Nabholz Construction on the Arts Corridor Project in the amount of $505,652.42 for paving on Gregg and West Avenues, reconciliation of contingency for additional items, and street work on West Avenue at Hillcrest Towers, and approval of a budget adjustment. Budget Impact: Various Accounts (See Budget Impact on Memo) Various Account Number Fund 46080.7800 Arts Corridor (2019 Bonds) - Arts Corridor Impr. 46020.7800 Streets Projects (2019 Bonds) - Arts Corridor Impr. Project Number Budgeted Item? Yes Does item have a cost? Yes Budget Adjustment Attached? Yes Current Budget Funds Obligated Current Balance Item Cost Budget Adjustment Remaining Budget Project Title $ 3,713,557.00 $ 3,690,169.52 $ 23,387.48 $ 505,652.42 $ 505,653.00 $ 23,388.06 Purchase Order Number: 2020-00000689 Previous Ordinance or Resolution # 309-21 Change Order Number: Original Contract Number: Comments: 10 2018-00000042 Approval Date: V20210527 CITY OF FAYETTEVILLE ARKANSAS MEETING OF AUGUST 2, 2022 TO: Mayor and City Council THRU: Susan Norton, Chief of Staff Paul Becker, Chief Financial Officer CITY COUNCIL MEMO FROM: Wade Abernathy, Director Bond & Construction Projects DATE: July 13, 2022 SUBJECT: Change Order #10 in the amount of $505,652.42 to RFQ 18-11 with Nabholz Construction for the Arts Corridor Project and approval of a budget adjustment. RECOMMENDATION: Staff recommends approval of change order #10 with Nabholz Construction on the Arts Corridor Project in the amount of $505,652.42 for paving on Gregg and West Avenues, reconciliation of contingency for additional items, and street work on West Avenue at Hillcrest Towers, and approval of a budget adjustment. BACKGROUND: The original contract with Nabholz did not include the scope of paving. For cost saving measures, that scope was to be completed internally. Due to the Arts Corridor completion schedule and conflicts with the Transportation division's workload, it was determined to add the paving to the Nabholz contract. Street work along West Avenue at Hillcrest Towers was deferred as we awaited Hillcrest Towers' future developments. Since the certainty of those developments are indefinite, we going to proceed with that portion of work. As we are nearing completion, this change order also will reconcile some items added to the contract that were not included in contingency. DISCUSSION: This change order includes work on West Avenue at Hillcrest Towers, West Avenue paving from South Street to East Avenue, Gregg Avenue paving at the new park and south towards Prairie Street, as well as bioswale materials testing. Mailing Address: 113 W. Mountain Street www.fayetteville-ar.gov Fayetteville, AR 72701 BUDGET/STAFF IMPACT: This change order will use unallocated Arts Corridor bond funds, remaining balances from other Arts Corridor bond and Sales Tax fund accounts, and recognize unbudgeted interest revenue from the Transportation bond fund. PURCHASE ORDER DETAIL: FUNDING SOURCE ACCOUNT PROJECT AMOUNT Sales Tax 4470.140.8900-5804.00 46080.7800 $ 10,562.00 Arts Corridor Bonds 4608.860.7800-5804.00 46080.7800 $ 237,438.00 Street Bonds 4602.860.7800-5809.00 46020.7800 $ 257,652.42 TOTAL $ 505,652.42 Attachments: Change Order #10 and documents. 4iE6R1ty A '• I Prime Contract Change Order Fayetteville Cultural Arts Corridor Project # 02-19-2526 113 W. Mountain St. Tel: Fax: Fayetteville, AR 72701 Nabholz Construction Corporation Date: 7/13/2022 To Contractor: Architect's Project No: Nabholz Construction Corporation Contract Date: 4/18/2018 3301 N 2nd St (72756), PO Box 277 Contract Number: 02-19-2526 Rogers, AR 72757 Change Order Number: 10 The Contract is hereby revised by the following items: CORs #49-80 (less CORs included in prior PCCOs or not yet approved) PCO Description Amount 069 North Crosswalk Curb & Gutter Rework $ 0.00 080 Additional Crane Costs $ 0.00 098 Gregg Ave. Demo, Grading, and Paving $ 72,287.76 079 Tenon Mount Modifications $ 0.00 081 Additional Dry Stack Wall $ 0.00 053 Oelke - RFI 61, 62, 63 demo concrete $ 0.00 083 West Ave. Asphalt Remediation $ 126,861.63 084 Regrade 200' of Greenway $ 0.00 085 PCCO #9 Correction $ 0.00 086 Light Pole Spread Footing $ 0.00 087 Rock and RCP Demo at Headwall $ 0.00 088 Replace Concrete Ramp $ 0.00 076 Bioswale Medium Testing $ 0.00 094 RFI #83 Handrail $ 0.00 099 RFI #77 Trail Camera Provisions $ 0.00 100 RFI #84 Concrete Service Trail Tie In $ 0.00 101 RFI #82 Plantings between Overlook Entrances $ 0.00 102 West Ave. Paving Damage and Overrun $ 0.00 103 Fence Changes $ 0.00 096 RFI #86 Gregg Ave. Park Changes $ 0.00 104 Gregg Ave. Sidewalk Termination $ 0.00 092 Perch Deck Guardrail $ 0.00 107 12 West Ave. Additional Items $ 0.00 108 Contingency for Additional Gregg Ave. Paving $ 58,503.03 109 Increase to Contingency $ 248,000.00 Contract updated days requested for additional work. Additional GCs will be coordinated in conjunction with other work with City of Fayetteville representative. COR #49 - Concrete contractor installed ribbon curbs on each side of the north raised crosswalk per sheet C1.03 and supplemental spot elevations provided by Olsson. However, when further design direction was received, the initially installed ribbon curb needed to be removed and replaced. COR #54 - In an effort to expedite the approval of a bioswale medium, Nabholz took over the sample submission and testing process. PROJECT CONFIDENTIAL Property of Nabholz Construction Corporation Not for Duplication or Distribution This document includes data prepared in conjunction with the Project that is deemed trade secret or proprietary to Nabholz. This document is shared with the Project team solely for use on this Project consistent with the responsibilities of the Project team. The Recipients shall not duplicate, use, or disclose, in whole or in part, to any person, entity, or party outside the Project team without Nabholz' prior written authorization. Prolog Manager Printed on: 7/13/2022 Nabholz Page 1 1NTE6g1T� 1 � Prime Contract Change Order Private Confidential COR #56 - The cost of the crane required to place the large boulders from Ibison Stone was higher than expected. The proposed cost is the delta between the actual total from Nabholz Cranes and Rigging and the estimated total previously charged to the City via CDR #28. COR #57 - As received, the tenon mounts for the curved light poles do not fit the light poles as they should. Either the length of the arm to which the bracket mounts is too long, or the location of the mounting cyliner is too close to the pole with respect to the rest of the bracket. The result is that the bracket is not allowed to sit flush with the main tube of the pole as shown in the attached photo. Brackets were designed and approved by Tillett specifically for these light poles. Manufacturer (WE-EF) directed Arnold & Blevins to modify the brackets in-house. COR #58 - Cost to install additional dry -stack retaining wall along trail. COR #60 - Cost to demo six (6) sidewalk panels and box lid adjacent to the south crosswalk was not included in COR #32. Sidewalk panels and box lid had to be demo'd and repoured due to grades changed in RFIs #61, #62, and #63. COR #61 - COR for paving installation on behalf of City of Fayetteville Transportation Department. COR #62 - In order to minimize the longitudinal slope of the Greenway of a 200 If section, the section had to be regraded to a slope of less than or equal to 5%. This directive was given by Matt Mihalevich. COR #63 - PCCO #9 inlcuded a credit for the amount of $8,863.74 to pay for the grading and boardform retaining wall at the South St./West Ave. Intersection. This credit was meant to undo a charge of an equal amount in PCCO #7, but it was not included/approved with PCCO #7. As such, the credit was unnecessary as was discovered after execution of PCCO #9. In order to rectify this mistake, a charge of $8,863.74 should be issued to undo the credit of the same amount. This COR will undo the credit of $8,863.74 mistakenly included in PCCO #9. COR #64 - Cost to install two spread footing light pole bases in Ieiu of the standard 18" light pole bases. Two light pole bases had to be converted to spread footings in order to clear rock and utilities below. COR #65 - While digging the footing for the headwall in the upper tributary, the concrete crew encountered rock and an abandoned RCP. A 25k excavator and breaker were utilized to demo the rock and pipe -after a jackhammer failed to break them in a timely manner. COR #66 - Cost to replace a concrete ramp with truncated domes at the Greenway trail crossing at Center St.. Existing ramp is 2" thick, and it broke when equipment was driven over it. COR #67 - Cost is for misc. steel components (including SS mesh), thermalized ash posts, and locust grab rail. COR #68 - Cost to install a tube -steel handrail with stainless steel mesh between the Overlook and West Ave. in accordance with the response to RFI #83. COR #69 - Cost to install six (6) paint -matched NEMA enclosures according to the response to RFI #77. All NEMA enclosures are to be provided by the City of Fayetteville IT department. Arnold & Blevins will be painting the NEMA enclosures to match the light poles. COR #71 - Due to the substantial elevation difference between the Greenway and the sewer service road below, the concrete access trail was omitted in favor of a compacted earth footpath and gravel turnaround area. COR #72 - In response to RFI #82, the design team called for ten new shrubs to be planted between the entrances of the overlook. These shrubs will discourage pedestrians from approaching the edge. COR #73 - West Ave. paving damage and overrun. Value of overrun will be charged to the owner. Value of damage will be credited back to the owner. COR #74 - Cost to extend bounds of paving replacement to include the entire width of Gregg Ave. south to Prairie St.. COR #75 - The fence at 419 W Center St. would block vehicular access to the garage as drawn. Fencing from the garage, up the east side of the property, and joining with the house has been omitted per the property owner's request. The split rail fence at 101 S West Ave. was missed. COR #76 - Cost to shift an area drain (previously installed) in the Gregg Ave. park area, and cost to replace the resin -bound crushed stone paving at the top terrace with plantings. COR #77 - Cost to provide and install signage at the Gregg Ave. sidewalk termination. COR #79 - Cost for the additional work requested at 12 West Avenue. COR #80 - Increase to Contingency. The original Contract Value was ........................ .................................. :....:...:...:._......:..:....::.:..,.._............... ...... $ 80,000.00 Sum of changes by prior Prime Contract Change Orders ................................... ..........., ............ .................. I— $ 10,654,116.95 The Contract Value priorto this Prime Contract Change Order was................................................................ $ 10,734,116.95 The Contract Value will be changed by this Prime Contract Change Order in the amount of ........................., $ 505,652.42 The new Contract Value including this Prime Contract Change Order will be...... ............................................ $ 11,239,769.37 The Contract duration will be changed by................... ................................ ......................... ............................. 195 Days The revised Substantial Completion date as of this Prime Contract Change Order is........................f........ 1 12/2/2023 Nabholz Construction Corporation CONTRACTOR 3301 N 2nd St (72756), PO Box 277 Rogers, AR 72757 Address PROJECT CONFIDENTIAL 11RAUTA Address 72701 Property of Nabbolz Construction Corporation Not for Duplication or Distribution This document includes data prepared in conjunction with the Project that is deemed trade secret or proprietary to Nabholz. This document is shared with the Project team solely for use on this Project consistent with the responsibilities of the Project team. The Recipients shall not duplicate, use, or disclose, in whole or in part, to any person, entity, or party outside the Project team without Nabbolz' prior written authorization. Prolog Manager Printed on: 7/13/2022 Nabholz Page 2 r� 1NiE6gti� 1 Prime Contract Change Order Private Confidential Vr PROJECT CONFIDENTIAL By Lioneld Jar SIGNATUR ',' DATE ll Property of Nabholz Construction Corporation Not for Duplication or Distribution This document includes data prepared in conjunction with the Project that is deemed trade secret or proprietary to Nabholz. This document is shared with the Project team solely for use on this Project consistent with the responsibilities of the Project team. The Recipients shall not duplicate, use, or disclose, in whole or in part, to any person, entity, or party outside the Project team without Nabholz' prior written authorization. Prolog Manager Printed on: 7/13/2022 Nabholz Page 3 City of Fayetteville, Arkansas - Budget Adjustment Form (Legistar) Budget Year Division Adjustment Number /Org2 FACILITIES MANAGEMENT (140) 2022 Requestor: Wade Abernathy BUDGET ADJUSTMENT DESCRIPTION / JUSTIFICATION: Approval of change order #10 with Nabholz Construction on the Arts Corridor Project in the amount of $505,652.42 for paving on Gregg and West Avenues, reconciliation of contingency for additional items, and street work on West Avenue at Hillcrest Towers. In addition, we are recognizing $302,120 in interest proceeds on the Phase I Street Bonds. RESOLUTION/ORDINANCE COUNCIL DATE: $/2/2022 LEGISTAR FILE ID#: 2022-0621 Hovy 3lack� 711412022 7:14 AM Budget Director Date TYPE: D - (City Council) JOURNAL #: GLDATE: 8/2/2022 CHKD/POSTED: TOTAL 302,120 302,120 v.20220616 Increase / (Decrease) Proiect.Sub# Account Number Expense Revenue Project Sub.Detl AT Account Name 4602.860.7800-5809.00 257,653 - 46020 7800 EX Improvements - Street 4608.860.7800-5804.00 237,438 - 46080 7800 EX Building Costs 4470.140.8900-5804.00 10,562 46080 7800 EX Building Costs 4608.860.7800-5805.00 (9,364) - 46080 7800 EX Land - Acquisition 4608.860.7800-5804.00 4608.860.7999-5899.00 (12,485) (215,589) - 46080 - 46080 7800 7999 EX EX Building Costs Unallocated - Budget 4470.140.8900-5805.00 4602.860.7999-5899.00 (10,562) 44,467 - 46080 - 46020 7830 7999 EX EX Land - Acquisition Unallocated - Budget 4602.860.7000-4707.46 - 302,120 46020 7000 RE Interest - 2019 Project Funds H:\Budget Adjustments\2022_Budget\CITY COUNC I L\08-02-22\2022-0621 BA Nabholz CO 10 Arts Corridor 1 of 1