Ordinance: 6549
File Number: 2022-0235
JACK TYLER ENGINEERING, INC.:
AN ORDINANCE TO WAIVE COMPETITIVE BIDDING AND ACCEPT A QUOTE IN THE
AMOUNT OF $266,250.00 PLUS APPLICABLE TAXES AND FREIGHT CHARGES FROM
JACK TYLER ENGINEERING, INC. FOR THE PURCHASE OF SIX ANOXIC MIXERS FOR
THE NOLAND WATER RESOURCE RECOVERY FACILITY, AND TO APPROVE A
PROJECT CONTINGENCY IN THE AMOUNT OF $26,625.00
WHEREAS, the Utilities Department determined that the anoxic mixers in both the East and West
Basins at the Noland Water Resource Recovery Facility required replacement but, because one basin
must remain open, the mixers can only be replaced in one basin at a time; and
WHEREAS, on October 5, 2021, the City Council awarded Bid #21-63 and authorized the
purchase of six replacement anoxic mixers for the East Basin from Jack Tyler Engineering; and
WHEREAS, Jack Tyler Engineering is the sole authorized dealer of this type of anoxic mixer for our
area and mixers for the West Basin must match those in the East Basin.
NOW, THEREFORE, BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby determines an
exceptional situation exists in which competitive bidding is deemed not feasible or practical and
therefore waives the requirements of formal competitive bidding and authorizes the purchase of six
anoxic mixers for the Noland Water Resource Recovery Facility for the amount of $266,250.00 (plus
any applicable taxes and freight charges) from Jack Tyler Engineering, Inc., and further approves a
project contingency in the amount of $26,625.00.
Page 1 Printed on 416122
Ordinance: 6549
File Number: 2022-0235
PASSED and APPROVED on 4/5/2022
Attest:
t • ti
Kara Paxton, City Clerk Treasurer
1� L7N G0� ';,'i`�
riImli
Page 2 Printed on 416122
City of Fayetteville, Arkansas 113 West Mountain Street
Fayetteville, AR 72701
(479)575-8323
Text File
File Number: 2022-0235
Agenda Date: 4/5/2022 Version: 1 Status: Passed
In Control: City Council Meetinq File Type: Ordinance
Agenda Number: DA
JACK TYLER ENGINEERING, INC.:
AN ORDINANCE TO WAIVE COMPETITIVE BIDDING AND ACCEPT A QUOTE IN THE
AMOUNT OF $266,250.00 PLUS APPLICABLE TAXES AND FREIGHT CHARGES FROM JACK
TYLER ENGINEERING, INC. FOR THE PURCHASE OF SIX ANOXIC MIXERS FOR THE
NOLAND WATER RESOURCE RECOVERY FACILITY, AND TO APPROVE A PROJECT
CONTINGENCY IN THE AMOUNT OF $26,625.00
WHEREAS, the Utilities Department determined that the anoxic mixers in both the East and West Basins at
the Noland Water Resource Recovery Facility required replacement but, because one basin must remain open,
the mixers can only be replaced in one basin at a time; and
WHEREAS, on October 5, 2021, the City Council awarded Bid #21-63 and authorized the purchase of six
replacement anoxic mixers for the East Basin from Jack Tyler Engineering; and
WHEREAS, Jack Tyler Engineering is the sole authorized dealer of this type of anoxic mixer for our area and
mixers for the West Basin must match those in the East Basin.
NOW, THEREFORE, BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby determines an exceptional
situation exists in which competitive bidding is deemed not feasible or practical and therefore waives the
requirements of formal competitive bidding and authorizes the purchase of six anoxic mixers for the Noland
Water Resource Recovery Facility for the amount of $266,250.00 (plus any applicable taxes and freight
charges) from Jack Tyler Engineering, Inc., and further approves a project contingency in the amount of
$26,625.00.
City of Fayetteville, Arkansas Page 1 Printed on 41612022
City of Fayetteville Staff Review Form
2022-0235
Legistar File ID
4/5/2022
City Council Meeting Date - Agenda Item Only
N/A for Non -Agenda Item
Tim Nyander 3/18/2022 WASTEWATER TREATMENT (730)
Submitted By Submitted Date Division / Department
Action Recommendation:
Staff recommends approval of the purchase of six (6) anoxic mixers for the Noland Water Resource Recovery
Facility from Jack Tyler Engineering, Inc. in the amount of $266,250.00 including applicable taxes and freight
charges, and approval of a contingency in the amount of $26,625.00.
Budget Impact:
5400.730.5800-5801.00
Water and Sewer
Account Number
Fund
02069.1
Plant Pumps and Equipment
- WWTP
Project Number
Project Title
Budgeted Item? Yes
Current Budget
$
1,459,141.00
Funds Obligated
$
571,499.44
Current Balance
$ 887,641.56
Does item have a cost? Yes
Item Cost
$
292,875.00
Budget Adjustment Attached? No
Budget Adjustment
$
-
Remaining Budget
594,766.56
V20210527
Purchase Order Number: Previous Ordinance or Resolution #
Change Order Number:
Original Contract Number:
Approval Date:
Comments: The total estimated cost including freight and taxes is $266,250.00. Staff also requests a 10%
contingency in the amount of $26,625.00.
CITY OF
FAYETTEVILLE
ARKANSAS
MEETING OF APRIL 5, 2022
TO: Mayor and City Council
THRU: Susan Norton, Chief of Staff
Water & Sewer Committee
FROM: Tim Nyander, Utilities Director
DATE: March 18, 2022
CITY COUNCIL MEMO
SUBJECT: Jack Tyler Engineering, Inc. — Six Anoxic Mixers for Noland WRRF
RECOMMENDATION:
Staff recommends approval of the purchase of six (6) anoxic mixers for the Noland Water
Resource Recovery Facility from Jack Tyler Engineering, Inc. in the amount of $266,250.00
including applicable taxes and freight charges, and approval of a contingency in the amount of
$26,625.00.
BACKGROUND:
Bid #21-63 was conducted for the replacement of the anoxic mixers for the East Basin at
Noland WRRF. The project was intended to replace all the mixers in both the West and East
Basins. Jack Tyler was the lowest responsive bidder and was selected to provide the equipment
because the only other bidder did not meet specifications. The bid specifications required
engineering to match the mixers with the process design for wastewater treatment. The East
and West Basins are symmetrical and require the same mixer configuration to operate in the
same manner.
DISCUSSION:
It was not possible to bid 12 mixers and replace them at the same time. During the
fall/winter/early spring, the permit is relaxed allowing the plant to treat with only one basin.
However, one basin must remain in service. We were only able to purchase six mixers because
we could only install one basin in that time period. The remaining mixers will be installed in the
next permit period that allows one basin.
Because Jack Tyler Engineering is the sole provider of the brand of anoxic mixers to match
existing equipment, staff is seeking a bid waiver to complete the rehabilitation of the remaining
basin in 2022. Jack Tyler Engineering has submitted a quote for six anoxic mixers. The total
estimated cost including freight and taxes is $266,250.00. Staff also requests a 10%
contingency in the amount of $26,625.00 due to fluctuations in the current materials market.
Mailing Address:
113 W. Mountain Street www.fayetteville-ar.gov
Fayetteville, AR 72701
BUDGET/STAFF IMPACT:
Funds are available in the Plant Pumps and Equipment account.
Attachments:
Quote from Jack Tyler Engineering
��Net E lg -
JACK TYLER ENGINEERING, INCORPORATED
6112 PATTERSON AVENUE, LITTLE ROCK, ARKANSAS 72209
(501) 562-2296 FAX (501) 562-4273 WATTS 1-800-562-2296
� a
Ooorpove
QUOTATION NUMBER: SJ22422A Rv1 QUOTATION DATE: March 17, 2022 PAGE: 1 OF 2
TO: City of Fayetteville
1400 Fox Hunter Road
Fayetteville, AR 72901
ATTN: Josh Alleman
COPIES: James Spann
Cory Gray
Phone: 479-502-0963
Email: Joshua.alleman@jacobs.com
ITEM 1:
Xylem FLYGT Adaptive Mixer, model 4320 1.5HP with 3 blade 2.0 Meter diameter mixer. 460
volt 3— single speed operation. Includes MinCAS and socket for mixer monitoring.
PRICE EACH.................................................................................................................. $ 35,500
PRICE FOR SIX UNITS................................................................................................$ 213,000
DELIVERY: 14-16 Weeks, ARO
FOB POINT: Shipping Point; Standard Freight and Fayetteville (9.75%) Sales Taxes Included
ITEM 2:
Xylem FLYGT Mixer Tripod with 20 foot tall 4" square mast. Constructed of 304 stainless steel.
PRICE EACH....................................................................................................................$ 8,875
PRICE FOR SIX UNITS..................................................................................................$ 53,250
DELIVERY: 14-16 Weeks, ARO
FOB POINT: Shipping Point; Standard Freight and Fayetteville (9.75%) Sales Taxes Included
'NOTE: FREIGHT CHARGES AND ANY APPLICABLE SALES TAXES ARE NOT INCLUDED
IN QUOTED PRICE.
Thank you for the opportunity to quote on your requirements. If we may be of further assistance,
please do not hesitate to contact me at scott(a_jteng.com or 479-806-8970.
Very truly yours,
JACK TYLER ENGINEERING, INCORPORATED
Scott Jones
Senior Sales Representative
�,\ler Eqo,�
JACK TYLER ENGINEERING, INCORPORATED
6301 S UNIVERSITY AVE, LITTLE ROCK, ARKANSAS 72209
iy ea (501) 562-2296 • FAX (501) 562-4273 • ARKANSAS WATS 1-800-562-2296
rorporat
STATEMENT OF TERMS AND CONDITIONS
TERMS/PAYMENTS: Our terms of payment are net cash 15 days from date of the invoice subject to
Seller's prior credit approval. If the Buyer shall fail to make any payments in
accordance with the terms and conditions of sale, the Seller, in addition to its other
rights and remedies, but not in limitation thereof, may, at its option, without prior
notice, cancel this order as to any undelivered products or defer shipments or
deliveries hereunder, or under any other agreement between Buyer and Seller,
except upon Seller's receipt of cash before shipment or such security as Seller
considers satisfactory. Seller reserves the right to impose an interest charge of 16%
on the balance of each invoice not paid on its due date for the period from the due
date to the date of receipt of payment by Seller. In the event Buyer's failure to make
timely payments to Seller results in Seller incurring additional costs, including but not
limited to collection expenses and attorneys' fees, said costs shall be added to the
amount due Seller from Buyer. Buyer shall have no right to any discount or
retainage and shall not withhold payment as a set-off on Seller's invoice in any
amount. Visa, MasterCard, Discover, and American Express credit card purchases
are accepted.
SHIPMENT: The date of shipment is subject to our receiving your order with complete information
at our office, final approval of any prints or drawings as may be required, credit
approval, and the acceptance of your order by the company. Freight Charges are
not included in the quoted price.
EXPIRATION: Quotation expires 30 days from the date of proposal and, in the interim, is subject to
change without notice.
TAXES: Unless otherwise stated in the proposal, the prices quoted herein are exclusive of
all sales, use and similar taxes and, wherever applicable, such taxes will be added
to the invoice as separate items.
SPECIAL NOTE:
THIS PROPOSAL IS BASED ON CURRENT PRICES. EQUIPMENT IS SUBJECT TO THE SAME
PERCENTAGE INCREASE AS MADE BY OUR SUPPLIERS AND THE INVOICE WILL REFLECT PRICE
IN EFFECT AT TIME OF SHIPMENT UNLESS SPECIFICALLY EXCEPTED. WE WILL NOT ACCEPT
RETAINAGE ON ANY OF OUR INVOICES!
***** A $50.00 minimum order charge will apply *****
WARRANTY:
"The products sold by Jack Tyler Engineering, Inc. hereunder are manufactured by others, and the only
warranties that apply to these products are those of the manufacturer of the products which can be passed
on by Jack Tyler Engineering, Inc. to its customers. No other warranty of any kind is given in connection with
the sale of any of the above products, and JACK TYLER ENGINEERING, INC. MAKES NO WARRANTY OF
ANY KIND, EXPRESS OR IMPLIED, AS TO MERCHANTABILITY, FITNESS FOR A PARTICULAR
PURPOSE, OR AS TO ANY OTHER MATTER RESPECTING THESE PRODUCTS. Jack Tyler Engineering,
Inc. shall not be liable in connection with the sale of the above products for any incidental or consequential
damages of any kind."