Resolution: 06-22
File Number: 2021-1030
BLACK HILLS ENERGY ARKANSAS, INC. MIDTOWN CORRIDOR PROJECT
UTILITY WORK - 2019 STREET IMPROVEMENT BOND PROJECT:
A RESOLUTION TO APPROVE A UTILITY WORK AGREEMLNT WITH BLACK HILLS
ENERGY ARKANSAS. INC. IN THE AMOUNT OF $93.765.40 FOR UTILITY
RELOCATIONS ASSOCIATED WITH THE MIDTOWN CORRIDOR PROJECT ALONG
PORTER ROAD AND DEANE STREET, AND TO APPROVE A BUDGET ADJUSTMENT-
2019 STREET IMPROVEMENT BOND PROJECT
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section I: That the City Council of the City of Fayetteville. Arkansas hereby approves a utility work
agreement, a copy of which is attached to this Resolution. with Black Hills Energy Arkansas Inc. in the
amount of $93,765.40 for utility relocations associated with the Midtown Corridor Project along
Porter Road and Deane Street at the Police Headquarters and authorizes Mayor Jordan to sign the
agreement.
Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget
adjustment. a copy of which is attached to this Resolution.
PASSED and APPROVED on 1/4/2022
Page 1 Primed on 115122
Resolution: 06-22
File Number: 2021-1030
Attest:
`����ittrrrr��D
% GOER K
.�A,�.•'
Kara Paxton, City Clerk Treasury
i lz • •
Page 2 Printed on 115122
City of Fayetteville, Arkansas 113 West Mountain Street
Fayetteville, AR 72701
(479)575-8323
Text File
File Number: 2021-1030
Agenda Date: 1/4/2022 Version: 1 Status: Passed
In Control: City Council Meetinq File Type: Resolution
Agenda Number: A.7
BLACK HILLS ENERGY ARKANSAS, INC. MIDTOWN CORRIDOR PROJECT UTILITY
WORK - 2019 STREET IMPROVEMENT BOND PROJECT:
A RESOLUTION TO APPROVE A UTILITY WORK AGREEMENT WITH BLACK HILLS ENERGY
ARKANSAS, INC. IN THE AMOUNT OF $93,765.40 FOR UTILITY RELOCATIONS ASSOCIATED
WITH THE MIDTOWN CORRIDOR PROJECT ALONG PORTER ROAD AND DEANE STREET,
AND TO APPROVE A BUDGET ADJUSTMENT- 2019 STREET IMPROVEMENT BOND PROJECT
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves a utility work
agreement, a copy of which is attached to this Resolution, with Black Hills Energy Arkansas Inc. in the amount
of $93,765.40 for utility relocations associated with the Midtown Corridor Project along Porter Road and
Deane Street at the Police Headquarters and authorizes Mayor Jordan to sign the agreement.
Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget adjustment, a
copy of which is attached to this Resolution.
City of Fayetteville, Arkansas Page 1 Printed on 11512022
Matt Casey
Submitted By
City of Fayetteville Staff Review Form
2021-1030
Legistar File ID
1/4/2022
City Council Meeting Date - Agenda Item Only
N/A for Non -Agenda Item
12/16/2021 ENGINEERING (621)
Submitted Date Division / Department
Action Recommendation:
Staff recommends approval of an agreement with Black Hills Energy Arkansas, Inc. in the amount of $93,765.40 for
utility relocations associated with the Midtown Corridor Project along Porter Road and Deane Street at the Police
Headquarters site and approval of a budget adjustment.
4602.860.7218-5809.00
Account Number
46020.7218.1000
Budget Impact:
4602 - Street Projects 2019 Bonds
Fund
Streets Projects - Midtown Corridor
Project Number
Budgeted Item? Yes Current Budget
Funds Obligated
Current Balance
Does item have a cost? Yes Item Cost
Budget Adjustment Attached? Yes Budget Adjustment
Remaining Budget
Purchase Order Number:
Change Order Number:
Original Contract Number:
Comments:
Project Title
$ 632,172.00
$ 592,128.46
40,043.54
$ 93,765.40
$ 93,766.00
40,044.14
V20210527
Previous Ordinance or Resolution #
Approval Date:
—� CITY OF
FAYETTEVILLE
ARKANSAS
MEETING OF JANUARY 4, 2022
TO: Mayor and City Council
THRU: Susan Norton, Chief of Staff
Chris Brown, Public Works Director
FROM: Matt Casey, Engineering Design Manager
DATE: December 14, 2021
CITY COUNCIL MEMO
SUBJECT: Black Hills Energy Agreement for Utility Relocations for the Midtown Corridor
project at Porter and Deane
RECOMMENDATION:
Staff recommends approval of an agreement with Black Hills Energy Arkansas, Inc. in the
amount of $93,765.40 for utility relocations associated with the Midtown Corridor Project along
Porter Road and Deane Street at the Police Headquarters site.
BACKGROUND:
The Midtown Corridor is a project in the 2019 Bond Program and includes several different
components. Along Porter Road and Deane Street from the interstate to Garland Avenue the
project includes street improvements with a new roundabout at the intersection of Porter Road
and Deane Street, drainage improvements and separated pedestrian and bicycle facilities. The
street, drainage pedestrian, and bicycle improvements will continue along Sycamore Street from
Garland Avenue to the Razorback Greenway. From the Greenway to Woodland Jr. High, the
project will include multi -use trail construction along the Poplar Street alignment. Finally, a
connection to the south from Poplar Street to Gregory Park will be designed as part of this
contract. The City Council approved a design contract with Olsson Associates, Inc. in
November of 2019.
DISCUSSION:
The portion of the project along the frontage of the Police Headquarters and new Fire Station
(Porter and Deane) will be constructed as the first phase of this project. During the
development of the construction plans, Black Hills Energy identified portions of their natural gas
system outside of the city right of way that will need to be relocated in order to construct this
project. Black Hills Energy has provided a proposal of $93,765.40 for this relocation.
BUDGET/STAFF IMPACT:
These utility relocations are funded by the 2019 Transportation Bond Program. This portion of
the Midtown Corridor Project is currently estimated at $4,300,000.
Attachments:
Black Hills Agreement
Black Hills Cost Estimate
Mailing Address:
113 W. Mountain Street www.fayetteville-ar.gov
Fayetteville, AR 72701
AMAMW
Black Hills Energy
UTILITY WORK AGREEMENT
(DEVELOPER)
Developer: City of Fayetteville
Developer's Address: 113 West Mountain St. Fayetteville, AR 72701
Job Location: Intersection of Porter Rd and Deane St, Fayetteville, AR
This Utility Work Agreement ("Agreement") is made and entered into this 8th day
of December 2021, by and between City of Fayetteville (hereinafter referred to as
"Developer"), and Black_ Hills Energy Arkansas, Inc. d/h/al Black Hills Energy
(hereinafter referred to as "Black Hills").
WHEREAS Developer proposes to make certain improvements at the location
designated above, and as a result of such improvements, Black Hills must adjust,
enhance, locate, observe, and/or relocate certain of its existing facilities, or construct
additional facilities; and
WHEREAS, in connection with Developer's proposed improvements, Developer
wishes Black Hills to do the following. -
The proiect to begin at GPS 36.086361,-94.190483. Where Black Hills will tie onto
the existing 4" steel pipeline. From that tie-in point, Black Hills will extend 4" steel
pipe West for approx. 1500'. staying within the designated utility easement. The
newly installed 4" steel will tie back into existing 4" steel at GPS 36.088498,
-94.192726. The existing 4" steel pipeline will be abandoned in place.
-(hereinafter referred to as the "Work"); and
WHEREAS, such Work is shown in detail in Black Hills' plans, sketches, estimate
of cost, and specifications (when applicable), which are attached to this Agreement and
made a part hereof; and
WHEREAS, Developer agrees to pay for the cost of such Work to the extent
herein agreed upon.
Imprr wv ql fe with energy
www.blackhillsenergy.com
HAK* Hills Energy
NOW, THEREFORE, IN CONSIDERATION OF THE PROMISES AND OTHER
VALUABLE CONSIDERATION HEREIN ACKNOWLEDGED, DEVELOPER AND
BLACK HILLS AGREE AS FOLLOWS:
1. Where applicable hereunder by reason of new utility occupancy or
crossing of Developer's property, Developer hereby grants to Black Hills an easement
or license to install and operate utility facilities on or across Developer's property as
shown on the approved plans or sketch maps attached hereto and made a part hereof.
Prior to Black Hills beginning the Work, Developer will, at no cost to Black Hills, furnish
Black Hills with all necessary easements, rights of way and permits. Those easements,
rights of way and permits shall release Black Hills from any and all claims for damage
done to streets, land, fences, and crops arising out of the performance of the Work.
2. Where applicable hereunder by reason of new construction on existing
utility rights of way, Black Hills hereby grants to Developer the right to use for
Developer's purposes the lands within the limits of the improvement project limits on or
across which Black Hills holds a valid property interest antedating Developer's rights
which were subsequently acquired in the same lands, and which property rights Black
Hills shall retain so long as Black Hills, its successors or assigns continues such use
and occupancy and does not abandon, and thereby release, such property interest to
Developer through removal of facilities in performing the Work or by subsequent
removal of facilities for Black Hills' convenience; and Developer hereby agrees that
Black Hills, by granting said right and by said continued joint use and occupancy, does
not waive any future claim for reimbursement for any costs as may be eligible for
reimbursement by reason of such prior property interest, nor does Black Hills waive any
other legal or property right held under the laws or Constitution of the State of Arkansas
or the United States.
3. In the event that future construction, reconstruction, expansion, relocation,
rehabilitation, betterment, maintenance, or other work on the facilities owned and
operated by either Developer or Black Hills in the area jointly occupied or used under
either or both Paragraphs 1 or 2 of this Agreement will disturb, detrimentally affect,
interfere, or be inconvenient to the facilities or responsibilities of either party, the parties
hereto shall reach agreement in writing as to locations, extent, and methods of such
work before the work is undertaken. In a case of emergency, and where immediate
action is necessary for the protection of the public and to minimize damage to or loss of
investment in the property of Developer or of Black Hills, either party hereto may, at its
own responsibility and risk, make any necessary emergency repairs, and shall notify the
other party hereto of such action as soon as practicable.
2
Black Hills Energy
4. The estimated cost of the Work is $93,765.40. After it has completed the
Work, Black Hills will bill Developer for the actual cost of the Work. Developer shall pay
such invoice within 30 days of Developer's receipt of the invoice. .
5. Black Hills will perform the Work, as described on the first page of this
Agreement. Black Hills will endeavor to perform the Work within a reasonable time
period, subject to applicable laws, rules and regulations of governmental authorities,
and subject to any delay occasioned by lack of right of way, availability of materials and
supplies, force majeure or events or conditions of whatsoever nature reasonably
beyond Black Hills' control, and further conditioned upon the receipt of all required
approvals and consents in form and substance acceptable to Black Hills. Black Hills
shall not be obligated to commence the Work unless and until, at no cost to Black Hills,
all necessary easements and rights of way have been executed, acknowledged and
delivered to Black Hills in a form acceptable to Black Hills.
6. Title to and ownership of facilities which are the subject of the Work shall
forever be and remain exclusively and unconditionally vested in Black Hills. Developer
understands, acknowledges and agrees that Developer shall have no title to, interest in,
or ownership of those facilities.
7. It is mutually agreed by the parties hereto that the provisions of this
Agreement pertaining to property rights, right of way occupancy permission, access for
servicing when applicable, and joint use of rights of way shall continue in full force and
effect from the date of this Agreement, and shall be perpetually binding upon each
party, and its representatives, successors and assigns.
8. Developer and Black Hills acknowledge that there are no agreements or
understandings, either written or oral, between the parties related to the Work, other
than as set forth in this Agreement, and that this Agreement (including any attachments
hereto) contains the entire agreement between the parties regarding the Work.
9. This Agreement shall be governed in accordance with the laws of the
State of Arkansas, the rules and regulations of the Arkansas Public Service
Commission, and the Tariff of Black Hills. In the event of a conflict between this
Agreement and any such laws, rules, regulations or Tariff, such laws, rules, regulations
or Tariff shall control.
10. In the event either party is required to initiate litigation to enforce the terms
and conditions of this Agreement, then the initiating party shall have the right to recover
itscosts and expenses of such litigation, including reasonable attorney fees, from the
other party.
3
Swrvy
11. Developer acknowledges that it has been afforded an opportunity to have
its attorney review and explain the terms of this Agreement.
IN WITNESS WHEREOF, the parties hereto have caused this Agreement to be
executed in duplicate by their duly authorized representatives on the date stated above.
BLACK HILLS ENERGY ARKANSAS INC.
By:
Its:
Federal Tax I.D. No.:I IW1 !Z'*2
M
City of Fayetteville, Arkansas - Budget Adjustment Form (Legistar)
Budget Year Division Adjustment Number
/Org2 ENGINEERING (621)
2021
Requestor: Matt Casey
BUDGET ADJUSTMENT DESCRIPTION / JUSTIFICATION:
Staff recommends approval of an agreement with Black Hills Energy Arkansas, Inc. in the amount of $93,765.40 for
utility relocations associated with the Midtown Corridor Project along Porter Road and Deane Street at the Police
Headquarters site and approval of a budget adjustment.
RESOLUTION/ORDINANCE
COUNCIL DATE: 1 /4/2022
LEGISTAR FILE ID#: 2021-1030
}f o-ll y 31ac1�
12/16/2021 8:53 AM
Budget Director Date
TYPE: D - (City Council)
JOURNAL #:
GLDATE: 1/4/2022
CHKD/POSTED:
TOTAL
Account Number
- -
Increase / (Decrease)
Expense Revenue
Proiect.Sub#
Project Sub.Detl AT
v.20211122
Account Name
4602.860.7218-5809.00
93,766 -
46020 7218.1000 EX
Improvements - Street
4602.860.7999-5899.00
(93,766)
46020 7999 EX
Unallocated - Budget
H:\Budget Adjustments\2022_Budget\CITY COUNCIL\01-04-22\2021-1030 BA Black Hills Midtownxlsm 1 of 1