HomeMy WebLinkAbout253-21 RESOLUTIONWOOLSEY HOMESTEAD
RESTORATION CHANGE ORDER
#4
City of Fayetteville Staff Review Form
2022-0337
Legistar File ID
N/A
City Council Meeting Date - Agenda Item Only
N/A for Non -Agenda Item
MATTHEW CABE 4/11/2022 FACILITIES MANAGEMENT (140)
Submitted By Submitted Date Division / Department
Action Recommendation:
Approval of Change Order #4 to the contract with Ellingson Contracting in the amount of $13,725 for restoration
of the Woolsey family cemetery plot. This change order includes cleaning and resetting the family marker and
restoration of the decorative iron fence. This scope of work is funded by a grant from the Arkansas Historic
Preservation Program (including City match) and project contingency.
1010.090.6600-5315.00
4470.090.8900-5315.00
Account Number
32103
15008.1
Project Number
Budgeted Item? Yes
Does item have a cost? Yes
Budget Adjustment Attached? No
Purchase Order Number: 2019-782
Change Order Number:
Original Contract Number: 2019-52
Comments:
Budget Impact:
GENERAL FUND
SALES TAX CAPITAL
Fund
AR Historic Preservation Woolsey
Woolsey Homestead Historic Restoration
Current Budget
Funds Obligated
Current Balance
Item Cost
Budget Adjustment
Remaining Budget
Project Title
$ 323,091.00
$ 140,694.80
$ - 182,396.20
$ 13,725.00
$ 168,671.20
Previous Ordinance or Resolution # 253-21
Approval Date:
4-13-22
V20210527
CITY OF
FAYETTEVILLE
ARKANSAS
TO: Mayor Lioneld Jordan
THRU: Paul Becker, Chief Financial Officer
Wade Abernathy, Director of Bond Projects and Facilities
FROM: 'Matthew Cabe, Facilities and Building Maintenance Manager
DATE: April 7, 2022
SUBJECT: Woolsey Homestead Restoration Change Order #4
STAFF MEMO
RECOMMENDATION:
Staff recommends approval of Change Order #4 to the contract with Ellingson Contracting for
restoration of the Woolsey family cemetery plot.
BACKGROUND:
This change order includes cleaning and resetting the family marker and restoration of the
decorative iron fence around the plot. This scope of work is funded by a grant from the
Arkansas Historic Preservation Program, City matching funds, and project contingency.
BUDGET/STAFF IMPACT:
A Certified Local Government (CLG) grant plus City match is budgeted at $12,488 for this
project. The remaining cost will be paid for from project contingency.
Account
Project
Amount
1010.090.6600-5315.00 — Contract Services
32103
12,488
4470.090.8900-5315.00 — Contract Services
15008.1
1,237
TOTAL 13,726
Attachments:
Change Order #4
Mailing Address:
113 W. Mountain Street www.fayetteville-ar.gov
Fayetteville, AR 72701
PROJECT:
A Restoration of the Historic
Woolsey Farmstead
OWNER:
City of Fayetteville
113 W. Mountain St.
Fayetteville, AR 72701
REVIVAL
ARCHITECTURE
P.O. Box 400 Scott, AR 72I42
50I.95I.33I6
www.revivalarch.com
CHANGE ORDER
FROM ARCHITECT:
Revival Architecture, Inc.
PO Box 400, Scott, AR 72142
TO CONTRACTOR:
Ellingson Contracting
108 E. University St.
Siloam Springs, AR 72761
CHANGE ORDER NO: 4
ISSUE DATE: March 9, 2022
CONTRACT DATE: Oct. 16, 2019
This Change Order is not valid until signed by the Architect, Contractor & Owner
DESCRIPTION: The Contract is changed as follows:
1. ADD to contract restoration of the Cemetery, consisting of the fence and headstones, as described in
Proposal Request ##3 dated 12121121, attached.
The original Contract Sum was $ 329,299.00
The net change by previously authorized Change Orders $ 253,419.00
The Contract Sum prior to this Change Order was $ 582,718.00
The Contract Sum will be Increased / Per -reared by this Change Order in the amount of $13,725.00
The new Contract Sum including this Change Order will be $ 596,443.00
The Contract Time will be Increased /vkec'rea&ec/ wed by 60 days.
The date of Substantial Completion as of the date of this Change Order therefore is: June 30, 2022
ATTACHMENTS: 1.) "Change Order Request #5, Revision 3 dated 8/31/21(1 page); 2.) Email from Chris Hobby
dated 8/17/21(1 page)
Revival Architecture, Inc. Ellingson Contracting City of Fayetteville
ARCHITECT (firm name) CONTRACTOR (firm name) OWNER (firm name)
PO Box 400 PO Box 7202
Scott, AR 72142 Siloam 5p4qgs, AR 72761
000,
BY (signature)
Mr. David Ellingson, Owner
BY
REVIVAL
ARCHITECTURE
P.O. Box 400 Scott, AR 72142
50I.95I.33I6
www.revivalarch.com
Date: September 22, 202I
Project: A Restoration of the Historic Woolsey Farmstead
Subject: Cemetery Scope of Work
To: Matthew Cabe, City of Fayetteville
Cc
From: Aaron C. Ruby, AIA, LEED AP
Existing chain link fence shall remain in place until further notice. Keep locked at all times.
Wrought Iron Fence & Gate
a. All existing, original fence material shall remain. Discard none. Where possible,
re -heat existing members to allow for some minor straightening out where severe
bending or gaps are present. A perfectly square fence is not expected. Re -heating
of existing members is expected to be minimal.
i. Attempt re -heating on one select piece to determine the metal's capability
in being bent in this manner. Relative brittleness of existing members is
not known, but it is highly preferable to retain existing members to
greatest extent possible and NOT replace with new.
b. Fabricate new gate using new components matching existing (horizontal channels,
vertical pickets). Assume a brace will be necessary. Use pintel type hinges that set
into receiver pockets on hinge side.
c. Replace missing pickets with new to match existing.
d. Re -set existing braces
e. No painting is anticipated.
2. Headstones
a. Take note of locations of markers --do not move nor disturb.
b. Reset headstone A by placing back onto base the toppled sections. Use type O
mortar, lime based only, no cement.
C. Headstones A, F, G, H are to be cleaned using Dawn detergent, potable water and
soft brushes. Apply by hand and gently scrub. Rinse thoroughly. Pressure
waters are not permitted. Harsher chemicals and cleaners may be permitted if
difficult stains are present, but only accepted on case by case basis as permitted by
the Architect. Remaining headstones -no work.
3. Grounds
a. Remove/demo small trees and stumps shown in drawing to be removed. Take
care not to damage adjacent materials.
C
ellingson contracting
To
CITY OF FAYETTEVILLE
113 W MOUNTAIN ST
FAYETTEVILLE, AR 72701
Project:
Woolsey Historic Renovation
535 E BROYLES RD
FAYETTEVILLE, AR 72704
Change Order Request:
Date:
From:
Ellingson Contracting
PO Box 7202
Siloam Springs, AR 72761
Description of Proposed Change: Amount: $13,725.00
Cemetery Restoration
Scope to include the following:
1. Repairs to existing iron fence.
2. Clean all existing headstones using D2 biological cleaner.
3. Resetting and leveling of large family marker stones.
4. Raking leaves and debris from trees inside chain link fence.
Exclusions:
- No new gate or finishing on iron fence.
- No resetting of small marker stones.
- No tree removal or stump removal.
- No work to existing chain link fence.
*** Work to be complete by May 13, 2022*""
If you have any other questions, please do not hesitate to contact me.
Sincerely, Acce
Ellingson Contracting By:
A
Title
Dat(
SHAWN ALEXANDER, Asst. Project Manager
C 003
03/09/22
Page 1 of 1
i�
N
M
EXISTING LARGE TREES AVE
GROWN UP INTO IRON FENCING.
TREES ARE TO REMAIN.
� Sr
rn
F
n
ORIG. WROUGHT IRON
FENCE IS SHOWN SQUARE FOR EASE OF DRAWING
CEMETERY PLAN
I SCALE: I/4"
Sept. 22, 202I
36'-4" t
r
h °
DEMO TREES &
STUMPS SHOWN
WITH DASHED LINES
r'
r
h I'
i
EXISTING GRAVE MARKERS.
THIS CENTRAL MARKER HAS BEEN
TOPPLED OVER. RESET INTO PLACE
IN MORTAR. CLEAN HEADSTONE
REVIVAL.,
ARCHITECTURE
P.O. Box 400, Scott, Aft 72142
(501) 951-3316 tv-trriralatch.com t
- ORIG. GATE IS MISSING S•_ 1
F'rajra N,vnr:
A Reconstruction of the 1843 Woolsey Farmstead