Resolution: 235-21
File Number: 2021-0735
FLINTCO, LLC CHANGE ORDER NO. 5:
A RESOLUTION TO APPROVE CHANGE ORDER NO. 5 TO THE CONSTRUCTION
MANAGER AT RISK CONTRACT WITH FLINTCO, LLC FOR THE POLICE
HEADQUARTERS PROJECT IN THE AMOUNT OF $3,320,439.00, AND TO APPROVE A
BUDGET ADJUSTMENT - 2019 POLICE HEADQUARTERS BOND PROJECT
WHEREAS, on December 3. 2019. the City Council passed Resolution 282-19 to approve a
Construction Manager at Risk agreement with Flintco. LLC for the Police Headquarters Project; and
WHEREAS. Change Order No. 5 includes railing systems. doors.. frames. hardware, signage.
lockers. pre-engineered buildings. and value engineering items.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves Change Order
No. 5 to the Construction Manager at Risk Contract with Flintco, LLC in the amount of
$3,320,439.00 for railing systems, doors, frames. hardware, signage, lockers, pre-engineered
buildings, and value engineering items at the Police Headquarters site.
Section 2: That the City Council of the City of Fayetteville. Arkansas hereby approves a budget
adjustment, a copy of which is attached to this Resolution.
PASSED and APPROVED on 10/5/2021
Page 1 Printed on 1016121
Resolution: 235-21
File Number: 2021-0735
Attest:
F���NIIAAAAI►��N��
`tQw% %j�RK
`.'�\ . • c,J )Y •.-f1 lo
•.�
rn
Kara Paxton. City Clerk Treasu&r F'4YE7-rE�f�<<E ��
•
Page 2 Printed on 101W1
City of Fayetteville, Arkansas 113 West Mountain Street
Fayetteville, AR 72701
(479)575-8323
Text File
File Number: 2021-0735
Agenda Date: 10/5/2021 Version: 1 Status: Passed
In Control: City Council Meetinq File Type: Resolution
Agenda Number: A.3
FLINTCO, LLC CHANGE ORDER NO. 5:
A RESOLUTION TO APPROVE CHANGE ORDER NO. 5 TO THE CONSTRUCTION MANAGER
AT RISK CONTRACT WITH FLINTCO, LLC FOR THE POLICE HEADQUARTERS PROJECT IN
THE AMOUNT OF $3,320,439.00, AND TO APPROVE A BUDGET ADJUSTMENT - 2019 POLICE
HEADQUARTERS BOND PROJECT
WHEREAS, on December 3, 2019, the City Council passed Resolution 282-19 to approve a Construction
Manager at Risk agreement with Flintco, LLC for the Police Headquarters Project; and
WHEREAS, Change Order No. 5 includes railing systems, doors, frames, hardware, signage, lockers,
pre-engineered buildings, and value engineering items.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves Change Order No. 5 to
the Construction Manager at Risk Contract with Flintco, LLC in the amount of $3,320,439.00 for railing
systems, doors, frames, hardware, signage, lockers, pre-engineered buildings, and value engineering items at
the Police Headquarters site.
Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget adjustment, a
copy of which is attached to this Resolution.
City of Fayetteville, Arkansas Page 1 Printed on 101612021
Wade Abernathy
City of Fayetteville Staff Review Form
2021-0735
Legistar File ID
10/5/2021
City Council Meeting Date - Agenda Item Only
N/A for Non -Agenda Item
FACILITIES MANAGEMENT (140)
Submitted By Submitted Date Division / Department
Action Recommendation:
9/17/2021
Approval of Change Order #5 with Flintco, LLC, to RFQ#19-05 Contract for the police Headquarters Facilities
Project in the amount of $3,320,439.00 and approve a Budget Adjustment.
Budget Impact:
4609.860.7900-5804.00 4609-Police Projects 2019 Bond
Account Number Fund
46090.7900.8040 Police Headquarters Building Construction
Project Number
Budgeted Item? Yes
Does item have a cost? Yes
Budget Adjustment Attached? Yes
Current Budget
Funds Obligated
Current Balance
Item Cost
Budget Adjustment
Remaining Budget
Project Title
$ 35,240,705.00
$ 26,858,232.90
$ 8,382,472.10
$ 3,320,439.00
$ 5,062,033.10
V20210527
Purchase Order Number: 2019-00000839 Previous Ordinance or Resolution # 175-21
Change Order Number:
Original Contract Number:
Comments:
5
2019-00000062
Approval Date:
CITY OF
FAYETTEVILLE
ARKANSAS
MEETING OF OCTOBER 5, 2021
TO: Mayor and City Council
THRU: Susan Norton, Chief of Staff
Paul A. Becker, Chief Financial Officer
Police Chief, Mike Reynolds
CITY COUNCIL MEMO
FROM: Wade Abernathy, Director Bond and Building Construction Projects
DATE: September 17,2021
SUBJECT: Change Order #5 to RFQ #19-05 Contract with Flintco, LLC for the Police
Headquarters Facilities Project
RECOMMENDATION:
Staff recommends approval of Change Order #5 to the RFQ # 19-05 contract with Flintco, LLC
for the Police Headquarters Facilities Project in the amount of $3,320,439.00 and approve a
Budget Adjustment.
BACKGROUND:
• In April 2019, Fayetteville voters approved the public safety bond question 9 in the
2019 bond initiative, which included a new police headquarters, and identified
$38,801,126 for the new facilities.
• In September 2019, Resolution 202-19 authorized the approval of the Land Sale
Agreement with the University of Arkansas System Division of Agriculture in the
amount of $2,590,000 for 11.50 acres with PD utilizing 10 acres and Fire utilizing 1.5
acres. The Close of the Land is ongoing.
• In September 2019, The City of Fayetteville Purchasing Division managed the RFQ
process of selecting a construction manager at risk for the Police Headquarters
Facilities. The request for statement of qualifications (RFQ) was advertised on 9-3-19
with a deadline of 9-26-19. Ten responses were received. Three construction
management firms were short listed for interview. The selection committee chose
Flintco to negotiate a CMAR contract for the Police Headquarters.
• In December 2019, Resolution 282-19 authorized the approval of a Construction
Manager at Risk contract with Flintco Construction and included pre -construction
services.
• In January of this year, resolution 37-21 was approved for the Earthwork package for
the police headquarters and Fire Station 8.
• In January of 2021, Resolution 37-21 authorized Change Order #1 for earthwork and
grading.
Mailing Address:
113 W. Mountain Street www.fayetteville-ar.gov
Fayetteville, AR 72701
• In April 6cn of 2021, Resolution 116-21 authorized Change Order #2 including
Foundations, Masonry, Structural Steel, and the Elevator
In May 181" of 2021, Resolution 146-21 authorized Change Order #3 including Site Utilities, Fire
Sprinkler, Mechanical, Ventilation, Electrical, Plumbing and Equipment.
• In June of 2021, Resolution 175-21 approved Change Order #4 for Masonry, Metal
Studs, Drywall, Ceilings and Metal Panels.
DISCUSSION:
The scope of work in this change order includes Railing systems, Hollow Metal Doors, Frames,
Hardware, Wood Doors, Signage, Lockers, Pre-engineered Buildings, and many value
engineering items.
BUDGET/STAFF IMPACT:
Funding for this Change order is allocated from the 2019 Police Bond Funds.
Attachments:
Change Order #5
DocuSign Envelope ID: 541=B4F97-EB9B-453D-AAD5-292D7CF9F350
Change Order
PROJECT: (Name and address)
Fayetteville Police Headquarters
1800 N. Porter Rd
Fayetteville Arkansas 72703
OWNER: (Name and address)
City of Fayetteville
113 West Mountian Street
Fayettevill, AR 72701
Document G701 - 2017
CONTRACT INFORMATION:
Contract For: General Construction
Date: December 03, 2019
ARCHITECT: (Name and address)
BRINKLEY SARGENT WIGINTON
ARCHITECT
5000 Quorum, Suite 600
Dallas, Texas 74254
CHANGE ORDER INFORMATION:
Change Order Number: 5
Date: September 1611, 2021
CONTRACTOR: (Name and address)
Flintco, LLC
184 E. Fanitnel Dr.
Springdale, AR 72762
THE CONTRACT IS CHANGED AS FOLLOWS:
(Insert a detailed description of the change and, if applicable, attach or reference specific exhibits. Also include agreed upon adjustments
attributable to executed Construction Change Directives.)
Incudes additional scopes of work as shown in Exhib B as it pertains to WP#4A on the Fayetteville Police Headquarters Project. The
following attached documents shall be incorporated into this change order.
Date Description
9/16/21 Exhibit A - GMP Itemization
9/16/21 Exhibit B - Clarificaitons & Assumptions
9/16/21 Exhibit C - Enumeration of Documents
The original Guaranteed Maximum Price was $ 82,500.00
The net change by previously authorized Change Orders $ 26,413,101.00
The Guaranteed Maximum Price prior to this Change Order was $ 26,495,601.00
The Guaranteed Maximum Price will be increased by this Change Order in the amount of $ 3,320,439.00
The new Guaranteed Maximum Price including this Change Order will be $ 29,816,040.00
The Contract Time will be increased by Zero (0) days.
The new date of Substantial Completion will be TBD in WP#4B
NOTE: This Change Order does not include adjustments to the Contract Sum or Guaranteed Maximum Price, or the Contract
Time, that have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the
Owner and Contractor, in which case a Change Order is executed to supersede the Construction Change Directive.
NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACTOR AND OWNER.
BSW Architects
ARCHITECT (Firm name)
SIGNATURE
PRINTED NAME AND TITLE
DATE
Flintco, LLC
City o a et eville
CONTRACTOR (Firm name)
W
OW (Fi n me)
SIGNATURE
Brent Farmer/ Vice President
IGNATU
(1
h
PRINTED NAME AND TITLE
PRINTED NAME AND TITLE
9/16/2021 1 5:44 PM CDT
L o — , -2i
DATE
DATE
AIA Document G701'" — 2017. Copyright C 1979, 1987, 2000 , 2001 and 2017 by The American Institute of Architects. All rights reserved. The "American
Institute of Architects "AIA. the AIA Logo. and "AIA Contract Documents' are registered trademarks and may not be used without permission. This document .�
was produced by AIA software at 18:06:19 ET on 09/16/2021 under Order No.2513164306 which expires on 09/17/2022, is not for resale, is licensed for one-time
use only, and may only be used in accordance with the AIA Contract Documentse Terms of Service. To report copyright violations, e-mail copyright@aia.org.
User Notes: (3B9ADA4E)
Doeu9rfrA Enrdope ' Stf 6sF 97 FTl9B-s4:ll'�wAos r>Znn
�ATA Document G701 - 2017
Change Order
f — 'Ar'rrft OWFw .IRad1"llou-I
fnn Pane Rd
i •,. , rAllc AAkslw .' bi
�. � k�r �-+ .a6►r
City at) areas r-Ik
t A:qa %La-aMlaw AAA!
f *c*Lvd1. AR mrl
caMTRACT fI'df111tTgfr
(-aMcat Tar
nwe f7a . c rt. OT
ARCHMT ' rAke..
ORIW, FYSAR(4tNT•ltdhl(Air
W1(11tt '
soon QWM*W saae eM
Dallas Ttaw ►4:34
CI{VM DIM1lJt NOCWAAMN
now ()Eft ko wbo i
Dw �.. ..
CllfT�ACTOR '" . oa/ afJ'
4vAit r.762
TM COUTRACT M CRAM= All lOLLUM
llamas • *wmAw ,-- 0 boasa dr a -=n and " A-VrR ,+ wtpai o✓ Rhona r V" M saMiaa /6.+ ,+ .. d .�.eatd �� UrwllarAAl.
"rea6M s.+rrMdlisrrwrw•. �yAjrrir.Y-AA+' r
FanAdee sdd'uvAYl Rnpes aAf wadl as slao�o i FwAib Y a s � Ao TYh(A aal M1.a FaIyACA�t fbliuc FtaebfefltAsa � THs
Td[-e�IsK wltaefiM MQFwew1A idl' x aArnffrpArd t dab dAW rdcr
thds Ota.Aq-tlwl
111f✓21 Fab" N - CIW4 wa+a A Amomaphnu
M1drl1 C F MUM r,•'l'ii ' oftdwena
Tlr -wW (wm arced Mmtawm tune was 1 _ e: 'We fW
lc a drr/s ep iwWarFl rAlliati se/ Rbae fe des f 2641 101.40
The i-assaasAi Msawwwf flf9ut pAw w 'Mee Cbm fe OMm was f T_+a+y jyj tj
TLAr t'—U wcAd Mretaea m Pdoe" be nrnelAed bb a" cbmw (4dh - dK mo me - f _ ) j.119 00
TIAr — r—we "eaf Ma— "- -rcMmd"*m om fe tpdw .al be f "%xa lA.w0 w
TIw roo Fn Tim —:1 4W aoaad by ?AM fft &V.
T►c — #- of S-d AU -d C'a-AA0AeAi--iw rill %a Ten m 1Mr4N
IFDTE Tia CI-W Order d m — -du&.lyww mt+ o. dw ( owma Srw or to� Mowwlwm bite: or dAe (•sascl
Ttma *ml N-9 brat wsi-A -W by t ,lnw md— t mW Muctrve wMI dw ona wad fllfe have bam armed epos ' ' be& dw
(j•nAz wed CaOfrautm in u'IAidt COC w ( lA w (ltdte is -:a --ow w wpo u'k de Cametme ok", (%ow/f Dmm"c
NOT VriM UM r OY W AAC1[W. COt( RK TOR AMD OVOW
k%i A,.1 IIc. -
�i
D KAFI[ AID S�l�*
L.(-t _
vqfflR Whv AtaANI
11 Arl row
umm
lFam" 1 ix, ■AW A R
v/1fi2 l S:s'( ftA CDT
sm—
ara O'etseA.eM tHe1 -1RA'f--eOMVA leNt N JM � '+r M-sA� aAa�� d AiOMeti N ri�� �.� 1�. rw�.
rat-. Lags J.V. .�a F rrr,.�� .� - ' .*r.w 1ledAt1y ,+e .�.y eelM R• +i-. r•�cr '*'g sYawre�
• mossw.ad oo Allift tirt a r of ' iT - - '+ 'a y" Omw No 3losm Is* • *mom o-..aw ' ' -GG 11—'r -awm r wtarrul tar aas�+
,•. - b aad ero M/ r Y- ' sca maw- O- mA tAwww lLr..n.sr Tw of sov— r ...m mpr wm ,eawdsr ..W
an. laege
DocuSign Envelope ID: 54FB4F97-EB9B-453D-AAD5-292D7CF9F350
r LI NTCO Exhibit
UPDATED: 9/16/2021
Spreadsheet Report
FAY PDHQ WP#4 (FINISHES) with PR#3
Project Name: Fayetteville Police Headquarters WP #4A
Description
Total Amount
STEEL RAILING SYSTEM
$
167,000
Rail Allowance in WP #3
$
(100,000)
VE- ICON Railing System
$
(10,800)
VE - Change All Stainless Steel To Powder Coat
$
(22,500)
Railing Full Size Mockup
$
2,500
BID PACKAGE #8A H.M. DOORS, FRAMES, HARDWARE, WOOD DOORS
$
468,971
VE - Hollow Metal Frames From 5-7/8" to 5-3/4"
$
(894)
VE - Change Finish Hardware To Falcon As Equal Hardware
$
(34,022)
BID PACKAGE 10B EXTERIOR SIGNAGE
$
19,983
BID PACKAGE 10F LOCKERS
$
410,450
BID PACKAGE #13A PRE-ENGINEERED METAL BUILDING & ERECTION
$
360,244
Work Package #4 Changes To Previous Contracts
NWA / GSG
STEEL DESIGN COMPLETION & PR #3
$
178,222
HIGHLANDS
METAL PANEL DESIGN COMPLETION
$
225,350
ROOF SCREEN
PANEL COLOR SELECTION
$
13,750
MOUNTAIN
ASSET1,2, DESIGN COMPLETION & PR #3
$
406,100
VE - Stand Alone Controls At Asset Buildings 1 And 2
$
(2,999)
VE - Deduct Controls UPS System.
$
(3,500)
BEI
ASSET1,2, DESIGN COMPLETION & PR #3
$
847,657
VE - Delete NETA Testing
$
(1,500)
VE - Decrease Light Fixtures
$
(52,000)
VE - Change Linear Fixtures to 2x4 in 1008 & 1401, Delete Decorative Dispatch Fixture
$
(11,952)
VE - Daisy Chain Light Fixtures
$
(10,600)
VE - Use 3/4" Conduit at Site Work
$
(7,400)
VE - Delete Starline Bussway System at Asset 1 and 2
$
(80,000)
VE - Delete Receptacle Control System
$
(23,905)
VE - Delete DAS Phone System
$
(61,567)
VE - Cameras Per WP#3 Design, Rough in & Cable Only for WP #4 Cameras
$
(62,000)
VE - Delete Branch Circuit Monitoring
$
(35,175)
BEI PR#4
PR#4
$
3,815
SUBTOTAL: $ 2,583,228
General Conditions $ 326,757
Project Requirements $ 219,679
General Insurance $ 15,499
Builder's Risk Insurance $ -
Subcontractor Default Insurance $ 32,290
CM CONTINGENCY: $ -
FEES: $ 142,985
Work Package #4A Total $ 3,320,439
WP #1,2,3 TOTAL: $ 26,495,601
PROJECT GRAND TOTAL: $ 29,816,040
DocuSign Envelope ID: 54FB4F97-EB9B-453D-AAD5-292D7CF9F350
Clarifications and Assumptions
Exhibit 'B"
Work Package #4A: September 16, 2021
Fayetteville Police Headquarters
?FL INTCO 9.16.21 Fayetteville Police Headquarters WP#4A 11 Page
DocuSign Envelope ID: 54FB4F97-EB9B-453D-AAD5-292D7CF9F350
PACKAGE #4A FAYETTEVILLE POLICE HEADQUARTERS
CLARIFICATIONS, ASSUMPTIONS, INCLUSIONS AND EXCLUSIONS
Scope of Work
Work Package #4A/ Change Order #5 is a partial scope of work which includes labor, material, equipment,
tools, and supervision required to perform the scopes of work specifically listed below.
• Bid Package 08A - Doors, Frames & Hardware Supply
• Bid Package 10B - Exterior Signage
• Bid Package 10F - Lockers
• Bid Package 13A - Pre-engineered Metal Building Supply and Erection
• Steel Railing System
• Design Changes to Structural Steel Supply
• Design Changes to Exterior Metal Panels & Roof Screen Metal Panels
• Design Changes to HVAC and Plumbing
• Design Changes to Electrical
All work to be performed in accordance with the Work Package #4 plans issued by BSW Architects dated
May 26, 2021, Specification Manual dated May 26, 2021, Addendum #1 dated July 19, 2021, and the
Construction Managers Bid Manual dated July 8, 2021.
Design Criteria
Where possible, items and systems specified by these C&A's are defined and specific to material, finish and
intended use. Where materials, finishes and/or quantities are not clearly defined, this proposal assumes the
most practical and economical solution consistent with the design concepts and scope. Where scope is
unclear, suggested allowances have been provided.
Any work referred to as "By Owner", "By Others", "OFCI" (owner furnished contractor installed), or "N.I.C." (not
in contract) is not part of the scope of this proposal unless installation is specified.
Code Requirements
We exclude any liability regarding errors and omissions from the bid documents. In addition, we have
assumed that the Architect/Engineer has incorporated into the bid documents all code requirements, ADA
requirements and has taken all seismic design into consideration.
General Conditions & Project Requirements
Three (3) months of General Conditions are included in this work package.
Three (3) months of Project Requirements are included in this work package.
Bonds & Insurance
General Insurance (0.6%), and Subcontractor Default Insurance (1.25%) have been included.
Quality Control Services
Costs for testing and special inspection services shall be provided by Owner and are excluded. Flintco will
provide coordination and scheduling of said services. These services include, but are not limited to
engineering testing services, engineering observation, and LEED consultation and testing.
Schedule
This proposal is based on a continuing construction schedule with anticipated activity from February 5, 2021
through April, 2022. The date of substantial completion will be determined with Work Package #413 after all
documents have been issued, and WP #4B change order has been executed.
l LINTCO 9.16.21 Fayetteville Police Headquarters WP#4A 2 1 Page
DocuSign Envelope ID: 54FB4F97-EB9B-453D-AAD5-292D7CF9F350
Delays
If the Contractor is delayed at any time in the progress of the work by labor disputes, unavoidable
casualties, material shortages or delay, changes in the work, or any other causes beyond Contractor's
control, the time of completion shall be extended. Claims for extension of time and/or adjustments to the
Contract Sum shall be made within a reasonable time after the occurrence of the delay.
This proposal excludes any time delays and cost increases arising from or related to the COVID-19 virus
and any government or other third -party action in response thereto.
Permits and Fees
The Architect/Engineer is responsible for permit submission and acceptance by the City of Fayetteville and
other Authorities Having Jurisdiction (AHJ).
The Owner is responsible for the cost of the building permits, tap fees, impact fees, and meters.
General Inclusions/Exclusions
1. Typical hours of construction operations are 7 am through 7 pm.
2. Certain construction procedures such as concrete placement and material deliveries require work
outside of normal hours. Work will be scheduled with onsite personnel.
3. Excludes all work associated with the Asset Building #1 and Asset Building #2 other that the costs
associated with the supply and install of the Pre-engineered metal buildings and all associated
Plumbing, HVAC and Electrical requirements.
4. All work shown within the Fire Station 8 boundary is excluded.
5. Dean & Porter Road improvements along with parking, sidewalks, greenway trail and utility
improvements and repairs are excluded. Only temporary gravel road patch is included for new water
and sanitary sewer utility construction crossings.
6. This package is not all inclusive for all work associated with Work Package #4.
Division 1 — Final Clean
There is no Final Clean cost included in the change order.
Division 3 — Concrete
There is no concrete cost included in the change order.
Division 3 — Polished Concrete
There is no Polished Concrete cost included in the change order.
Division 4 — Masonry
There is no Masonry or Stone cost included in the change order.
Division 5 — Metal Stairs and Railings
Includes all Stair and second floor railings located at ST-03, and Balcony rails located at 2108 and 2322.
The VE option of changing the railing system from stainless steel to a powder coated finish has been
accepted and the cost saving has been reflected in this package. The railing system included is a Livers
Bronze "ICON" railing system with mesh panels.
Division 5 — Structural Steel Supply
Includes all Structural Steel detailing and fabrication associated with all changes per Work Package #4 and
PR #03 documents.
Division 5 — Structural Steel Erect
There is no Structural Steel Erect cost included in the change order.
Division 6 — Millwork. Finish Carpentry
There is no Millwork, Finish Carpentry cost included in the change order.
l LINTCO 9.16.21 Fayetteville Police Headquarters WP#4A 3 1 Page
DocuSign Envelope ID: 54FB4F97-EB9B-453D-AAD5-292D7CF9F350
Division 7 - Fluid Applied Membrane Weather Barrier
There is no Fluid Applied Membrane Weather Barrier cost included in the change order.
Division 7 — Composite Metal Wall Panels
Includes all Exterior Metal Panel and Roof Screen Panel changes between Work Package #3 and Work
Package #4 including PR #03 changes. This pricing includes the premium finish color chosen by the owner.
Division 8 — Overhead Sectional & Coiling Doors
There is no Overhead Sectional & Coiling Doors cost included in the change order.
Division 8 — Doors. Hardware & Specialties Installation
There is no Doors, Hardware & Specialties Installation cost included in the change order.
Division 8 — Entrances. Storefronts and Glazin;3
There is no Entrances, Storefronts and Glazing cost included in the change order.
Division 8 — Doors. Frames & Hardware Supply
Includes the supply of all hollow metal and wood doors, frames, and hardware per work package #4
documents. The following VE has been accepted and is included in this work package:
a. Substitute Falcon hardware ILO the specified door hardware.
b. Fabrication of frames at 5-3/4" width in lieu of 5-7/8".
Division 9 — Framing. Drywall & Acoustical
There is no Framing, Drywall and Acoustical cost included in the change order.
Division 9 — Floorin>�
There is no Flooring cost included in the change order.
Division 9 — Paint, Finish and Wallcoverft
There is no Paint, Finish and Wallcovering cost included in the change order.
Division 9 — Access Floaft
There is no Access Flooring cost included in the change order.
Division 10 — Wall and Floor Pads
There is no Wall and Floor Pads cost included in the change order.
Division 10 - Canopies
There is no Canopies cost included in the change order.
Division 10 — Interior Signage and Plaque
There is no Interior Signage and Plaque cost included in the change order.
Division 10 — Specialty Supply
There is no Specialty Supply cost included in the change order.
Division 10 — Visual Display Boards
There is no Visual Display Boards cost included in the change order.
Division 10 — Ordinance Equipment
There is no Ordinance Equipment cost included in the change order.
Division 10 — Appliance Equipment
There is no Appliance Equipment cost included in the change order.
l LINTCO 9.16.21 Fayetteville Police Headquarters WP#4A 4 1 Page
DocuSign Envelope ID: 54FB4F97-EB9B-453D-AAD5-292D7CF9F350
Division 10 - Evidence Equipment
There is no Evidence Equipment cost included in the change order.
Division 10 — Exterior Signs
Includes all exterior building letters and signs per work package #4.
Division 10 — Lockers
Includes all Personnel, Gear Bag, Evidence, Refrigerated Evidence, Phenolic and Metal lockers including
integral benches. Storage of fabricated lockers until the date of installation will be at an additional charge.
Division 12 — Roller Shades
There is no Roller Shades cost included in the change order.
Division 13 — Pre-engineered Metal Buildings
Includes all supply, fabrication, and erection of the two pre-engineered metal buildings (Asset Buildings #1
and #2).
Division 21 — Fire Suppression
There is no Fire Suppression cost included in the change order.
Division 22 - Plumbin>�
Includes all Plumbing associated with all changes per Work Package #4 and PR #03 documents.
Division 23 - HVAC
Includes all HVAC associated with all changes per Work Package #4 and PR #03 documents. The VE option
of providing stand alone controls systems at Asset Buildings 1 and 2 has been accepted and the cost
saving has been reflected in this package. The VE option of deducting the UPS system for the controls has
been accepted and the cost saving has been reflected in this package.
Division 26. 27. 28 — Electrical. Communications. Electronic Safetv. and Securitv Svstems
Includes all Electrical, Communications, Electronic Safety and Security Systems work associated with all
changes per Work Package #4, PR #03 and PR #4 documents. The VE options listed below have been
accepted and the cost saving has been reflected in this package.
1. Delete NETA Testing
2. Decrease Light Fixtures
3. Change Linear Fixtures to 2X4 Fixtures in rooms 1008 and 1401 and delete decorative dispatch
fixtu re.
4. Daisy Chain Light Fixtures
5. Use 3/4" Conduit at site work
6. Delete Starline Bussway System at Asset Buildings 1 and 2
7. Delete Receptacle Control System
8. Delete DAS Phone System
9. Cameras per Work Package #3 Design, Rough in and Cable Only for Work Package #4 Added Cameras
10. Delete Branch Circuit Monitoring
Division 32 — Landscape and Irrigation
There is no Landscape and Irrigation cost included in the change order.
Division 32 — Fence
There is no Fence cost included in the change order.
Division 33 - Utilities
There is no Utilities cost included in the change order.
END OF DOCUMENT
l LINTCO 9.16.21 Fayetteville Police Headquarters WP#4A 5 1 Page
DocuSign Envelope ID: 54FB4F97-EB9B-453D-AAD5-292D7CF9F350
�LINTCO Exhibit C - Enumeration of Documents
Current Drawings
Drawing N..
CVR
Drawing Title
COVER SHEET
Revision
GENERAL
6
Drawing Date
07/19/2021
Received Date
07/19/2021
S.t
WP#04-Addendum 1(07/19/21)
T1.0
TITLE SHEET
1
05/12/2021
05/12/2021
Permit Set (05/12/21)
00.0
GENERAL NOTES
1
05/12/2021
05/12/2021
Permit Set (05/12/21)
C1.0
OVERALL SITE PLAN
5
07/09/2021
07/09/2021
PR #03 (07/09/21)
C1.1
SITE PLAN
5
07/09/2021
07/09/2021
PR #03 (07/09/21)
C1.2
SITE PLAN
3
06/08/2021
06/08/2021
WP#04 - Supplemental Sheets (06/ 08/21)
C1.3
SITE PLAN
2
07/09/2021
07/09/2021
PR #03 (07/09/21)
CIA
SITE PLAN
1
05/12/2021
05/12/2021
Permit Set (05/12/21)
C2.0
OVERALL GRADING & STORM PLAN
1
05/12/2021
05/12/2021
Permit Set (05/12/21)
C2.1
GRADING PLAN
2
06/08/2021
06/08/2021
WP#04 - Supplemental Sheets (06/ 08/21)
C2.2
GRADING PLAN
2
06/08/2021
06/08/2021
WP#04 - Supplemental Sheets (06/ 08/21)
C2.3
GRADING PLAN
3
07/09/2021
07/09/2021
PR #03 (07/09/21)
C2.4
GRADING PLAN
3
07/09/2021
07/09/2021
PR #03 (07/09/21)
C3.0
STORM PLAN AND PROFILE
1
05/12/2021
05/12/2021
Permit Set (05/12/21)
C3.1
STORM PLAN AND PROFILE
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
C3.2
STORM PLAN AND PROFILE
1
05/12/2021
05/12/2021
Permit Set (05/12/21)
C3.3
STORM PLAN AND PROFILE
1
05/12/2021
05/12/2021
Permit Set (05/12/21)
C3.4
POND PROFILE
1
05/12/2021
05/12/2021
Permit Set (05/12/21)
C4.0
OVERALL UTILITY PLAN
1
05/12/2021
05/12/2021
Permit Set (05/12/21)
C4.1
WATER LINE PLAN AND PROFILE
2
06/08/2021
06/08/2021
WP#04 - Supplemental Sheets (06/ 08/21)
C4.2
WATER LINE PLAN AND PROFILE
2
06/08/2021
06/08/2021
WP#04 - Supplemental Sheets (06/ 08/21)
C4.3
SANITARY SEWER PLAN AND PROFILE LINE A
2
06/08/2021
06/08/2021
WP#04 - Supplemental Sheets (06/ 08/21)
C4.4
SANITARY SEWER PLAN AND PROFILE LINE A & B
2
06/08/2021
06/08/2021
WP#04 - Supplemental Sheets (06/ 08/21)
C4.5
SANITARY SEWER PLAN AND PROFILE LINE A & B
0
05/12/2021
05/12/2021
Permit Set (05/12/21)
C5.0
EROSION CONTROL PLAN
0
03/08/2021
03/09/2021
WP#03 (03/08/21)
C5.1
EROSION CONTROL PLAN PHASE 1
1
06/08/2021
06/08/2021
WP#04 - Supplemental Sheets (06/ 08/21)
C5.2
EROSION CONTROL PLAN PHASE 2
1
06/08/2021
06/08/2021
WP#04 - Supplemental Sheets (06/ 08/21)
C6.0
CIVIL SITE DETAIL
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
C6.1
CIVIL SITE DETAIL
1
05/12/2021
05/12/2021
Permit Set (05/12/21)
C6.2
DRAINAGE DETAIL
3
06/08/2021
06/08/2021
WP#04 - Supplemental Sheets (06/ 08/21)
C6.3
EROSION CONTROL DETAILS
1
05/12/2021
05/12/2021
Permit Set (05/12/21)
C6.4
SANITARY SEWER DETAIL
1
05/12/2021
05/12/2021
Permit Set (05/12/21)
C6.5
WATER DETAIL
LANDSCAPE
1
05/12/2021
05/12/2021
Permit Set (05/12/21)
1-1.0
TREE PRESERVATION PLAN
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
1-1.1
LANDSCAPE PLAN
2
06/08/2021
06/08/2021
WP#04 - Supplemental Sheets (06/ 08/21)
L1.2
Landscape Details (I)
2
06/08/2021
06/08/2021
WP#04 - Supplemental Sheets (06/ 08/21)
L1.3
LANDSCAPE DETAILS 2
STRUCTURAL
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
S001
STRUCTURAL GENERAL NOTES
1
05/26/2021
05/27/2021
WP#04(05/26/21)
S002
GENERAL NOTES
3
05/26/2021
05/27/2021
WP#04 (05/26/21)
S003
LOADING DIAGRAMS
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
SO10
AXONOMETRIC VIEW
5
07/09/2021
07/09/2021
PR #03 (07/09/21)
S011
AXONOMETRIC VIEW
4
05/26/2021
05/27/2021
WP#04 (05/26/21)
S101
OVERALL SITE PLAN
6
07/09/2021
07/09/2021
PR #03 (07/09/21)
S102
SITE PLANS AND DETAILS
4
07/09/2021
07/09/2021
PR #03 (07/09/21)
S103
SITE PLANS AND DETAILS
3
07/09/2021
07/09/2021
PR #03 (07/09/21)
S104
SITE PLANS AND DETAILS
1
05/26/2021
05/27/2021
WP#04 (05/26/21)
S201
OVERALL LEVEL 1 PLAN
6
07/09/2021
07/09/2021
PR #03 (07/09/21)
S202
OVERALL LEVEL 2 FRAMING PLAN
5
05/26/2021
05/27/2021
WP#04 (05/26/21)
S203
OVERALL ROOF FRAMING PLAN
6
07/09/2021
07/09/2021
PR #03 (07/09/21)
S210
LEVEL 1 - POLICE - WEST
6
07/09/2021
07/09/2021
PR #03 (07/09/21)
S211
LEVEL 1- POLICE- EAST
5
05/26/2021
05/27/2021
WP#04 (05/26/21)
S220
LEVEL 2 - POLICE - WEST
4
05/26/2021
05/27/2021
WP#04 (05/26/21)
S221
LEVEL 2- POLICE- EAST
5
07/09/2021
07/09/2021
PR #03 (07/09/21)
S230
ROOF - POLICE -WEST
4
05/26/2021
05/27/2021
WP#04 (05/26/21)
DocuSign Envelope ID: 54FB4F97-EB9B-453D-AAD5-292D7CF9F350
�LINTCO
Drawing No.
Drawing Tifl,
R—m—
Drawing D
R—i—d Dar,
S�t
S231
ROOF - POLICE - EAST
5
07/09/2021
07/09/2021
PR #03 (07/09/21)
S240
LEVEL I - RANGE
5
07/09/2521
07/09/2021
PR #03 (07/09/21)
S241
ROOF -RANGE
4
07/09/2021
07/09/2021
PR #03 (07/09/21)
S250
LEVEL 1 & ROOF - ASSET BLDG 1
1
05/26/2021
05/27/2021
WP#04 (05/26/21)
S260
LEVEL 1 & ROOF - ASSET BLDG 2
1
05/26/2021
05/27/2021
WP#04 (05/26/21)
S301
TYPICAL CONCRETE DETAILS
5
05/26/2021
05/27/2021
WP#04 (05/26/21)
S310
CONCRETE DETAILS
0
11/09/2020
12/10/2020
DO Budget Set 11-9 (11/09/20)
S401
TYPICAL STRUCTURAL MASONRY DETAILS
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
S410
STRUCTURAL MASONRY DETAILS
0
11/09/2020
12/10/2020
DO Budget Set 11-9 (11/09/20)
S501
TYPICAL STEEL DETAILS
3
05/12/2021
05/12/2021
Permit Set (05/12/21)
S502
TYPICAL STEEL DETAILS
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
S503
TYPICAL STEEL DETAILS
1
05/12/2021
05/12/2021
Permit Set (05/12/21)
S505
VERTICAL BRACE ELEVATIONS AND DETAILS
4
05/12/2021
05/12/2021
Permit Set (05/12/21)
S510
STEEL DETAILS
0
11/09/2020
12/10/2020
DD Budget Set 11-9 (11/09/20)
S520
STEEL DETAILS
0
11/09/2020
12/10/2020
DO Budget Set 11-9 (11/09/20)
S601
STRUCTURAL DETAILS
4
07/09/2021
07/09/2021
PR #03 (07/09/21)
S602
STRUCTURAL DETAILS
3
07/09/2021
07/09/2021
PR #03 (07/09/21)
S603
STRUCTURAL DETAILS
1
07/09/2021
07/09/2021
PR #03 (07/09/21)
S610
STRUCTURAL DETAILS
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
S611
STRUCTURAL DETAILS
1
05/12/2021
05/12/2021
Permit Set (05/12/21)
S620
STRUCTURAL DETAILS
2
05/26/2021
05/27/2021
WP#04 (05/26/21)
S621
STRUCTURAL DETAILS
1
05/12/2021
05/12/2021
Permit Set (05/12/21)
S622
STRUCTURAL DETAILS
4
05/26/2021
05/27/2021
WP#04 (05/26/21)
S623
STRUCTURAL DETAILS
ARCHITECTURAL
0
05/26/2021
05/27/2021
WP#04 (05/26/21)
A000
ACCESSIBILITY STANDARDS (TAS)
1
05/26/2021
05/27/2021
WP#04 (05/26/21)
A021
CODE PLAN -POLICE LEVEL 1
1
05/26/2021
05/27/2021
WP#04 (05/26/21)
A022
CODE PLAN - POLICE LEVEL 2
2
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
A023
CODE PLAN - RANGE
2
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
A024
CODE PLAN -ASSET BLDG 1
0
05/12/2021
05/12/2021
Permit Set (05/12/21)
A025
CODE PLAN -ASSET BLDG 2
0
05/12/2021
05/12/2021
Permit Set (05/12/21)
A101
SITE PLAN
5
07/09/2021
07/09/2021
PR #03 (07/09/21)
A102
SITE SLIDING GATE DETAILS
4
07/09/2021
07/09/2021
PR #03 (07/09/21)
A103
MONUMENT SIGN AND MEMORIAL WALL
3
05/12/2021
05/12/2021
Permit Set (05/12/21)
A104
SITE DETAILS AND ENLARGED PLANS
3
05/12/2021
05/12/2021
Permit Set (05/12/21)
A105
ENLARGED SITE PLANS
3
05/12/2021
05/12/2021
Permit Set (05/12/21)
A106
ENLARGED SITE PLANS AND ELEVATIONS
3
05/26/2021
05/27/2021
WP#04 (05/26/21)
A107
SITE - SIGNAGE AND WALL ELEVATIONS
4
07/09/2021
07/09/2021
PR #03 (07/09/21)
A201
SLAB EDGE PLAN - POLICE -LEVEL 1
5
08/25/2021
08/25/2021
S.I. #02 (08/25/21)
A202
SLAB EDGE PLAN - POLICE -LEVEL 2
3
05/26/2021
05/27/2021
WP#04 (05/26/21)
A203
SLAB EDGE PLAN - RANGE
5
08/25/2021
08/25/2021
S.I. #02 (08/25/21)
A210
REFERENCE PLAN - POLICE - LEVEL 1
4
07/09/2021
07/09/2021
PR #03 (07/09/21)
A211
PLAN - WALL TAGS, DIMENSIONS - WEST - POLICE - LEVEL 1
5
06/08/2021
06/08/2021
WP#04 - Supplemental Sheets (06/
08/21)
A212
PLAN - WALL TAGS, DIMENSIONS - EAST - POLICE - LEVEL 1
4
07/09/2021
07/09/2021
PR #03 (07/09/21)
A213
PLAN - EQUIPMENT, INT. ELEVS. -WEST- POLICE -LEVEL 1
3
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
A214
PLAN - EQUIPMENT, INT. ELEVS. - EAST - POLICE - LEVEL 1
1
05/26/2021
05/27/2021
WP#04 (05/26/21)
A220
REFERENCE PLAN - POLICE -LEVEL 2
3
05/12/2021
05/12/2021
Permit Set (05/12/21)
A221
PLAN -WALL TAGS, DIMENSIONS - WEST -POLICE-LEVEL 2
5
09/03/2021
09/03/2021
RFI #70 (09/03/21)
A222
PLAN -WALL TAGS, DIMENSIONS - EAST -POLICE-LEVEL 2
2
05/26/2021
05/27/2021
WP#04 (05/26/21)
A223
PLAN - EQUIPMENT, INT. ELEVS. -WEST- POLICE -LEVEL 2
3
09/03/2021
09/03/2021
RFI #70 (09/03/21)
A224
PLAN - EQUIPMENT, INT. ELEVS. - EAST - POLICE - LEVEL 2
2
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
A230
REFERENCE PLAN - RANGE
3
07/09/2021
07/09/2021
PR #03 (07/09/21)
A231
PLAN -WALL TAGS, DIMENSIONS - RANGE
3
07/09/2021
07/09/2021
PR #03 (07/09/21)
A232
PLAN - EQUIPMENT &SCHED, INT. ELEVS, DOORS & SCHED-RANGE
2
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
A233
PLAN - MECHANICAL YARD - RANGE
3
07/09/2021
07/09/2021
PR #03 (07/09/21)
A240
PLANS & SCHEDULES -ASSET BLDG1
2
07/19/2021
07/19/2021
WP#04 - Addendum 1(07/19/21)
A241
BUILDING ELEVATIONS, SECTIONS & AXONS - ASSET BLDG 1
1
05/26/2021
05/27/2021
WP#04 (05/26/21)
A250
PLANS & SCHEDULES -ASSET BLDG 2
2
07/19/2021
07/19/2021
WP#04 - Addendum 1(07/19/21)
A251
BUILDING ELEVS, SECTIONS & AXONS - ASSET BLDG 2
1
05/26/2021
05/27/2021
WP#04 (05/26/21)
A270
ENLARGED FLOOR PLANS - POLICE
6
09/03/2021
09/03/2021
RFI #70 (09/03/21)
A272
ENLARGED FLOOR PLANS - RANGE
3
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
A280
STAIR PLANS & SECTIONS - POLICE (ST-01 & ST-02)
4
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
A281
STAIR PLANS & SECTIONS - POLICE (ST-03)
5
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/11)
A282
STAIR & RAILING DETAILS
2
07/19/2021
07/19/2021
WP#04 - Addendum 1(07/19/21)
A290
ROOF PLAN - POLICE
3
05/26/2021
05/27/2021
WP#04 (05/26/21)
A291
ROOF PLAN -RANGE
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
DocuSign Envelope ID: 54FB4F97-EB9B-453D-AAD5-292D7CF9F350
�LINTCO
A292
ROOF DETAILS - POLICE
2
05/12/2021
05/12/2021
Permit Set(05/12/21)
A293
ROOF DETAILS - RANGE
1
05/12/2021
05/12/2021
Permit Set(05/12/21)
A311
REFLECTED CEILING PLAN -WEST- POLICE -LEVEL 1
6
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
A312
REFLECTED CEILING PLAN -EAST- POLICE -LEVEL 1
3
05/26/2021
05/27/2021
WP#04 (05/26/21)
A321
REFLECTED CEILING PLAN -WEST- POLICE -LEVEL 2
6
09/09/2021
09/09/2021
RFI #74 (09/09/21)
A322
REFLECTED CEILING PLAN -EAST- POLICE -LEVEL 2
3
05/26/2021
05/27/2021
WP#04 (05/26/21)
A331
REFLECTED CEILING PLAN - RANGE
3
07/09/2021
07/09/2021
PR #03 (07/09/21)
A341
CEILING DETAILS - POLICE
1
05/26/2021
05/27/2021
WP#04 (05/26/21)
A342
CEILING DETAILS - POLICE
0
05/26/2021
05/27/2021
WP#04 (05/26/21)
A401
BUILDING ELEVATIONS - POLICE
5
07/09/2021
07/09/2021
PR #03 (07/09/21)
A402
BUILDING ELEVATIONS - RANGE
3
07/09/2021
07/09/2021
PR #03 (07/09/21)
A411
AXONOMETRIC VIEWS - POLICE & RANGE BUILDING
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
A412
3D VIEWS
2
05/12/2021
05/12/2021
Permit Set(05/12/21)
A501
BUILDING SECTIONS -POLICE
2
05/12/2021
05/12/2021
Permit Set(05/12/21)
A502
BUILDING SECTIONS - POLICE
2
05/26/2021
05/27/2021
WP#04 (05/26/21)
A503
BUILDING SECTIONS - POLICE
2
05/12/2021
05/12/2021
Permit Set(05/12/21)
A504
BUILDING SECTIONS -POLICE
2
05/12/2021
05/12/2021
Permit Set(05/12/21)
A505
BUILDING SECTIONS -POLICE
2
05/12/2021
05/12/2021
Permit Set(05/12/21)
A506
BUILDING SECTIONS -POLICE
2
05/12/2021
05/12/2021
Permit Set(05/12/21)
A507
BUILDING SECTIONS -RANGE
3
07/09/2021
07/09/2021
PR #03 (07/09/21)
A511
WALL SECTIONS - POLICE
3
07/09/2021
07/09/2021
PR #03 (07/09/21)
A512
WALL SECTIONS - POLICE
2
07/09/2021
07/09/2021
PR #03 (07/09/21)
A513
WALL SECTIONS - POLICE
3
07/09/2021
07/09/2021
PR #03 (07/09/21)
A514
WALL SECTIONS - POLICE
3
07/09/2021
07/09/2021
PR #03 (07/09/21)
A515
WALL SECTIONS - RANGE
2
07/09/2021
07/09/2021
PR #03 (07/09/21)
A521
SECTION DETAILS - POLICE
3
07/09/2021
07/09/2021
PR #03 (07/09/21)
A522
SECTION DETAILS - POLICE
2
07/09/2021
07/09/2021
PR #03 (07/09/21)
A523
SECTION DETAILS - POLICE
2
07/09/2021
07/09/2021
PR #03 (07/09/21)
A524
SECTION DETAILS - POLICE
4
07/09/2021
07/09/2021
PR #03 (07/09/21)
A531
SECTION DETAILS - RANGE
2
07/09/2021
07/09/2021
PR #03 (07/09/21)
A601
PLAN DETAILS - POLICE
2
07/19/2021
07/19/2021
WP#04 - Addendum 1(07/19/21)
A701
PARTITION TYPES
2
05/26/2021
05/27/2021
WP#04 (05/26/21)
A702
DOOR SCHEDULE- POLICE, DOOR TYPES
3
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
A703
DOOR DETAILS - INTERIOR -POLICE
1
05/26/2021
05/27/2021
WP#04 (05/26/21)
A704
DOOR DETAILS - EXTERIOR - POLICE
2
07/09/2021
07/09/2021
PR #03 (07/09/21)
A705
DOOR & FENCE DETAILS - EXTERIOR -POLICE
3
07/09/2021
07/09/2021
PR #03 (07/09/21)
A711
EQUIPMENT SCHEDULE - POLICE
2
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
A801
FINISH SCHEDULE, NOTES & LEGEND - POLICE - LEVEL 1
2
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
A802
FINISH SCHEDULE, NOTES & LEGEND - POLICE - LEVEL 2
2
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
A803
FINISH SCHEDULE, NOTES & LEGEND - RANGE
2
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
A811
FINISH PLAN - POLICE - LEVEL 1
3
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
A812
FINISH PLAN - EAST - POLICE - LEVEL 1
1
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
A821
FINISH PLAN - POLICE - LEVEL 2
3
09/03/2021
09/03/2021
RFI #70 (09/03/21)
A822
FINISH PLAN - EAST - POLICE - LEVEL 2
1
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
A831
FINISH PLAN - RANGE
1
05/26/2021
05/27/2021
WP#04 (05/26/21)
A841
FINISH DETAILS - POLICE
0
05/26/2021
05/27/2021
WP#04 (05/26/21)
A842
FINISH DETAILS - POLICE
0
07/19/2021
07/19/2021
WP#04 - Addendum 1(07/19/21)
A901
INTERIOR ELEVATIONS - POLICE
3
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
A902
INTERIOR ELEVATIONS - POLICE
3
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
A903
INTERIOR ELEVATIONS - POLICE
3
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
A904
INTERIOR ELEVATIONS - POLICE
3
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
A905
INTERIOR ELEVATIONS - POLICE
3
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
A906
INTERIOR ELEVATIONS - POLICE
3
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
A907
INTERIOR ELEVATIONS - POLICE
3
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
A921
INTERIOR ELEVATIONS - RANGE
2
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
A922
MILLWORK SECTIONS - POLICE
1
06/08/2021
06/08/2021
WP#04 - Supplemental Sheets (06/ 08/21)
A923
MILLWORK SECTIONS -POLICE
MECHANICAL
1
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
M001
MECHANICAL LEGEND
2
05/12/2021
05/12/2021
Permit Set(05/12/21)
M002
MECHANICAL GENERAL NOTES
2
05/12/2021
05/12/2021
Permit Set(05/12/21)
M003
MECHANICAL SCHEDULES
2
05/26/2021
05/27/2021
WP#04 (05/26/21)
M004
MECHANICAL SCHEDULES
3
09/09/2021
09/09/2021
RFI #74 (09/09/21)
M005
MECHANICAL SCHEDULES
2
05/26/2021
05/27/2021
WP#04 (05/26/21)
M006
MECHANICAL SCHEDULES
0
05/26/2021
05/27/2021
WP#04 (05/26/21)
M210
LEVEL 1 - POLICE MECHANICAL OVERALL PLAN
3
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
M211
LEVEL I - POLICE MECHANICAL PLAN - WEST
3
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
DocuSign Envelope ID: 54FB4F97-EB9B-453D-AAD5-292D7CF9F350
�LINTCO
M212
LEVEL 1 - POLICE MECHANICAL PLAN - EAST
3
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
M220
LEVEL 2 - POLICE MECHANICAL OVERALL PLAN
3
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
M221
LEVEL 2 - POLICE MECHANICAL PLAN - WEST
4
09/09/2021
09/09/2021
RFI #74 (09/09/21)
M222
LEVEL 2 - POLICE MECHANICAL PLAN - EAST
4
09/09/2021
09/09/2021
RFI #74 (09/09/21)
M230
LEVEL I - RANGE MECHANICAL PLAN
3
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
M240
LEVEL I - ASSET BUILDINGS MECHANICAL PLAN
2
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
M250
LEVEL I - ASSET BUILDING 2 MECHANICAL PLAN
0
11/09/2020
12/10/2020
DO Budget Set I1-9 (11/09/20)
M290
ROOF - POLICE MECHANICAL OVERALL PLAN
3
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
M291
ROOF - POLICE MECHANICAL PLAN - WEST
3
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
M292
ROOF - POLICE MECHANICAL PLAN -EAST
4
09/09/2021
09/09/2021
RFI #74 (09/09/21)
M293
ROOF -RANGE MECHANICAL PLAN
3
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
M294
ROOF - ASSET BUILDING 1 MECHANICAL PLAN
0
11/09/2020
12/10/2020
DO Budget Set 11-9 (11/09/20)
M295
ROOF - ASSET BUILDING 2 MECHANICAL PLAN
0
11/09/2020
12/10/2020
DO Budget Set 11-9 (11/09/20)
M301
MECHANICAL ENLARGED PLAN
1
05/12/2021
05/12/2021
Permit Set(05/12/21)
M401
CONTROLS
2
05/26/2021
05/27/2021
WP#04 (05/26/21)
M402
MECHANICAL CONTROLS
2
05/26/2021
05/27/2021
WP#04 (05/26/21)
M501
MECHANICAL DETAILS
2
05/26/2021
05/27/2021
WP#04 (05/26/21)
M502
MECHANICAL DETAILS
2
05/26/2021
05/27/2021
WP#04 (05/26/21)
M503
MECHANICAL DETAILS
ELECTRICAL
2
05/12/2021
05/12/2021
Permit Set(05/12/21)
E001
ELECTRICAL LEGEND AND NOTES
3
05/12/2021
05/12/2021
Permit Set(05/12/21)
E002
ELECTRICAL ONE LINE
6
07/09/2021
07/09/2021
PR #03 (07/09/21)
E003
ELECTRICAL ONE LINE
5
07/09/2021
07/09/2021
PR #03 (07/09/21)
E010
ELECTRICAL SCHEDULES
3
05/26/2021
05/27/2021
WP#04 (05/26/21)
E011
ELECTRICAL SCHEDULES
2
05/26/2021
05/27/2021
WP#04 (05/26/21)
E012
ELECTRICAL SCHEDULES
2
05/26/2021
05/27/2021
WP#04 (05/26/21)
E013
ELECTRICAL SCHEDULES
2
05/26/2021
05/27/2021
WP#04 (05/26/21)
E014
ELECTRICAL SCHEDULES
2
05/26/2021
05/27/2021
WP#04 (05/26/21)
E015
ELECTRICAL SCHEDULES
2
05/26/2021
05/27/2021
WP#04 (05/26/21)
E016
ELECTRICAL SCHEDULES
2
07/19/2021
07/19/2021
WP#04 - Addendum 1(07/19/21)
E020
ELECTRICAL EQUIPMENT CONNECTION SCHEDULE
0
05/26/2021
05/27/2021
WP#04(05/26/21)
E030
LIGHT FIXTURE SCHEDULES
4
08/05/2021
08/05/2021
PR #04 (08/05/21)
E031
LIGHTING CONTROL
2
05/26/2021
05/27/2021
WP#04 (05/26/21)
E100
SITE- UNDERGROUND ELECTRICAL PLAN
4
07/09/2021
07/09/2021
PR #03 (07/09/21)
E101
SITE- ELECTRICAL PLAN
4
08/05/2021
08/05/2021
PR #04 (08/05/21)
E102
SITE- PHOTOMETRIC PLAN
0
08/05/2021
08/05/2021
PR #04 (08/05/21)
E103
SITE - ELECTRICAL ENLARGED PLAN
3
08/05/2021
08/05/2021
PR #04 (08/05/21)
E210
LEVEL 1 - POLICE ELECTRICAL OVERALL PLAN
2
05/26/2021
05/27/2021
WP#04 (05/26/21)
E211
LEVEL 1- POLICE ELECTRICAL PLAN - WEST
4
07/09/2021
07/09/2021
PR #03 (07/09/21)
E212
LEVEL 1 - POLICE ELECTRICAL PLAN -EAST
4
07/09/2021
07/09/2021
PR #03 (07/09/21)
E220
LEVEL 2 - POLICE ELECTRICAL OVERALL PLAN
2
05/26/2021
05/27/2021
WP#04 (05/26/21)
E221
LEVEL 2- POLICE ELECTRICAL PLAN - WEST
3
07/09/2021
07/09/2021
PR #03 (07/09/21)
E222
LEVEL 2- POLICE ELECTRICAL PLAN - EAST
3
07/09/2021
07/09/2021
PR #03 (07/09/21)
E223
ROOF - POLICE ELECTRICAL PLAN
2
05/26/2021
05/27/2021
WP#04 (05/26/21)
E230
LEVEL 1 - RANGE ELECTRICAL PLAN
3
07/09/2021
07/09/2021
PR #03 (07/09/21)
E240
LEVEL 1 - ASSET BUILDING 1 ELECTRICAL PLAN
1
05/26/2021
05/27/2021
WP#04 (05/26/21)
E250
LEVEL 1 - ASSET BUILDING 2 ELECTRICAL PLAN
0
11/09/2020
12/10/2020
DO Budget Set 11-9 (11/09/20)
E260
ELECTRICAL ENLARGED PLAN
1
05/26/2021
05/27/2021
WP#04 (05/26/21)
E261
ELECTRICAL ENLARGED PLAN
1
05/26/2021
05/27/2021
WP#04 (05/26/21)
E262
DISPATCH
3
07/09/2021
07/09/2021
PR #03 (07/09/21)
E263
ELECTRICAL ENLARGED PLAN
1
05/26/2021
05/27/2021
WP#04 (05/26/21)
E310
LEVEL 1 - POLICE MECH POWER PLAN
0
11/09/2020
12/10/2020
DO Budget Set 11-9 (11/09/20)
E311
LEVEL 1 - POLICE LIGHTING RCP - WEST
1
05/26/2021
05/27/2021
WP#04 (05/26/21)
E312
LEVEL 1 - POLICE LIGHTING RCP - EAST
1
05/26/2021
05/27/2021
WP#04 (05/26/21)
E320
LEVEL 2 - POLICE MECH POWER PLAN
0
11/09/2020
12/10/2020
DO Budget Set 11-9 (11/09/20)
E321
LEVEL 2 - POLICE LIGHTING RCP - WEST
2
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
E322
LEVEL 2 - POLICE LIGHTING RCP - EAST
1
05/26/2021
05/27/2021
WP#04 (05/26/21)
E330
LEVEL 1 - RANGE LIGHTING RCP
3
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
E360
LIGHTING ENLARGED PLAN - STAFF STAIR
2
05/26/2021
05/27/2021
WP#04 (05/26/21)
E361
LIGHTING ENLARGED PLAN - TRAINING
1
05/26/2021
05/27/2021
WP#04 (05/26/21)
E401
LIGHTING ELEVATIONS
2
08/05/2021
08/05/2021
PR #04 (08/05/21)
E402
LIGHTING ELEVATIONS
3
08/05/2021
08/05/2021
PR #04 (08/05/21)
E410
LIGHTING SECTIONS
1
05/26/2021
05/27/2021
WP#04 (05/26/21)
E411
LEVEL 1 - POLICE LIGHTING RCP -WEST
0
11/09/2020
12/10/2020
DO Budget Set 11-9 (11/09/20)
E412
LEVEL 1 - POLICE LIGHTING RCP - EAST
0
11/09/2020
12/10/2020
DO Budget Set 11-9 (11/09/20)
E421
LEVEL 2 - POLICE LIGHTING RCP - WEST
0
11/09/2020
12/10/2020
DO Budget Set 11-9 (11/09/20)
E422
LEVEL 2 - POLICE LIGHTING RCP - EAST
0
11/09/2020
12/10/2020
DO Budget Set 11-9 (11/09/20)
DocuSign Envelope ID: 54FB4F97-EB9B-453D-AAD5-292D7CF9F350
�LINTCO
Drawing No.
Drawing Tifl,
R—m—
Drawing Dat,
R,,,i,,d Dar,
S�t
E430
LEVEL 1 - RANGE LIGHTING RCP
0
11/09/2020
12/10/2020
DO Budget Set 11-9 (11/09/20)
E440
LEVEL 1- ASSET BUILDING 1 LIGHTING RCP
0
11/09/2020
12/10/2020
DO Budget Set 11-9 (11/09/20)
E450
LEVEL 1- ASSET BUILDING 2 LIGHTING RCP
0
11/09/2020
12/10/2020
DO Budget Set 11-9 (11/09/20)
E501
ELECTRICAL ENLARGED PLAN
0
11/09/2020
12/10/2020
DO Budget Set 11-9 (11/09/20)
E502
ELECTRICAL ENLARGED PLAN
0
11/09/2020
12/10/2020
DO Budget Set 11-9 (11/09/20)
E510
LEVEL 1 - POLICE MECH POWER PLAN
1
05/26/2021
05/27/2021
WP#04 (05/26/21)
E520
LEVEL 2 - POLICE MECH POWER PLAN
1
05/26/2021
05/27/2021
WP#04 (05/26/21)
E530
LEVEL 1 - RANGE MECH POWER PLAN
3
07/09/2021
07/09/2021
PR #03 (07/09/21)
E601
ELECTRICAL DETAILS
1
01/25/2021
01/25/2021
WP#02 (01/25/21)
E602
ELECTRICAL DETAILS
1
01/25/2021
01/25/2021
WP#02 (01/25/21)
E603
ELECTRICAL DETAILS
1
01/25/2021
01/25/2021
WP#02 (01/25/21)
E610
LEVEL 1- FIRE ALARM PLAN
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
E620
LEVEL 2- FIRE ALARM PLAN
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
E630
LEVEL 1 - RANGE FIRE ALARM PLAN
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
E701
ELECTRICAL DETAILS
1
05/12/2021
05/12/2021
Permit Set (05/12/21)
E702
ELECTRICAL DETAILS
1
05/12/2021
05/12/2021
Permit Set (05/12/21)
E703
ELECTRICAL DETAILS
1
05/12/2021
05/12/2021
Permit Set (05/12/21)
E704
ELECTRICAL DETAILS
1
05/26/2021
05/27/2021
WP#04 (05/26/21)
E710
LEVEL 1 -FIRE ALARM PLAN
0
11/09/2020
12/10/2020
DO Budget Set 11-9 (11/09/20)
E720
LEVEL 2 -FIRE ALARM PLAN
0
11/09/2020
12/10/2020
DO Budget Set 11-9 (11/09/20)
E730
LEVEL 1 - RANGE FIRE ALARM PLAN
0
11/09/2020
12/10/2020
DO Budget Set I1-9 (11/09/20)
E740
LEVEL 1- ASSET BUILDING 1 FIRE ALARM PLAN
0
11/09/2020
12/10/2020
DD Budget Set I1-9 (11/09/20)
E750
LEVEL 1- ASSET BUILDING 2 FIRE ALARM PLAN
0
PLUMBING
11/09/2020
12/10/2020
DO Budget Set 11-9 (11/09/20)
P001
PLUMBING LEGEND AND NOTES
3
05/12/2021
05/12/2021
Permit Set (05/12/21)
P002
PLUMBING SCHEDULES
4
07/09/2021
07/09/2021
PR #03 (07/09/21)
P003
PLUMBING SCHEDULES
3
05/26/2021
05/27/2021
WP#04 (05/26/21)
P101
SITE - PLUMBING PLAN
3
05/26/2021
05/27/2021
WP#04 (05/26/21)
P210
LEVEL 1 - POLICE PLUMBING OVERALL PLAN
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
P21OU
LEVEL 1 - POLICE PLUMBING UNDERGROUND OVERALL PLAN
3
05/12/2021
05/12/2021
Permit Set (05/12/21)
P211
LEVEL 1 - POLICE PLUMBING PLAN - WEST
4
07/09/2021
07/09/2021
PR #03 (07/09/21)
P211U
LEVEL 1 - POLICE PLUMBING UNDERGROUND PLAN - WEST
5
07/09/2021
07/09/2021
PR #03 (07/09/21)
P212
LEVEL 1 - POLICE PLUMBING PLAN - EAST
3
07/09/2021
07/09/2021
PR #03 (07/09/21)
P212U
LEVEL 1 - POLICE PLUMBING UNDERGROUND PLAN - EAST
3
05/26/2021
05/27/2021
WP#04 (05/26/21)
P220
LEVEL 2- POLICE PLUMBING OVERALL PLAN
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
P221
LEVEL 2 - POLICE PLUMBING PLAN - WEST
3
07/09/2021
07/09/2021
PR #03 (07/09/21)
P222
LEVEL 2 - POLICE PLUMBING PLAN - EAST
3
07/09/2021
07/09/2021
PR #03 (07/09/21)
P230
LEVEL 1 - RANGE PLUMBING PLAN
3
07/09/2021
07/09/2021
PR #03 (07/09/21)
P230U
LEVEL 1 - RANGE PLUMBING UNDERGROUND PLAN
4
07/09/2021
07/09/2021
PR #03 (07/09/21)
P240
ASSET BUILDINGS 1&2 PLUMBING PLANS
3
07/19/2021
07/19/2021
WP#04 - Addendum 1(07/19/21)
P240U
LEVEL 1 - ASSET BUILDING 1 PLUMBING UNDERGROUND PLAN
0
11/09/2020
12/10/2020
DO Budget Set 11-9 (11/09/20)
P250
LEVEL 1 - ASSET BUILDING 2 PLUMBING PLAN
0
11/09/2020
12/10/2020
DO Budget Set 11-9 (11/09/20)
P250U
LEVEL 1 - ASSET BUILDING 2 PLUMBING UNDERGROUND PLAN
0
11/09/2020
12/10/2020
DO Budget Set 11-9 (11/09/20)
P290
ROOF - POLICE PLUMBING OVERALL PLAN
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
P291
ROOF - POLICE PLUMBING PLAN - WEST
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
P292
ROOF - POLICE PLUMBING PLAN - EAST
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
P293
ROOF - RANGE PLUMBING PLAN
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
P294
ROOF -ASSET BUILDING 1 PLUMBING PLAN
0
11/09/2020
12/10/2020
DO Budget Set 11-9 (11/09/20)
P295
ROOF -ASSET BUILDING 2 PLUMBING PLAN
0
11/09/2020
12/10/2020
DO Budget Set 11-9 (11/09/20)
P301
PLUMBING ENLARGED PLANS
2
05/26/2021
05/27/2021
WP#04 (05/26/21)
P302
PLUMBING ENLARGED PLANS
3
07/09/2021
07/09/2021
PR #03 (07/09/21)
P303
PLUMBING ENLARGED PLANS
3
07/09/2021
07/09/2021
PR #03 (07/09/21)
P304
PLUMBING ENLARGED PLANS
3
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
P401
SANITARY ISOMETRICS
1
05/26/2021
05/27/2021
WP#04 (05/26/21)
P402
SANITARY ISOMETRICS
2
07/09/2021
07/09/2021
PR #03 (07/09/21)
P403
SANITARY ISOMETRICS
2
07/09/2021
07/09/2021
PR #03 (07/09/21)
P404
SANITARY ISOMETRICS
2
07/09/2021
07/09/2021
PR #03 (07/09/21)
P405
GAS ISOMETRICS
1
05/12/2021
05/12/2021
Permit Set (05/12/21)
P406
GAS ISOMETRICS
1
05/12/2021
05/12/2021
Permit Set (05/12/21)
P407
GAS ISOMETRICS
1
05/12/2021
05/12/2021
Permit Set (05/12/21)
P501
PLUMBING DETAILS
3
05/12/2021
05/12/2021
Permit Set (05/12/21)
P502
PLUMBING DETAILS
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
P503
PLUMBING DETAILS
FIRE
1
PROTECTION
05/12/2021
05/12/2021
Permit Set (05/12/21)
FP001
FIRE PROTECTION LEGEND AND NOTES
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
FP210
LEVEL 1- POLICE FIRE PROTECTION OVERALL PLAN
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
FP220
LEVEL 2- POLICE FIRE PROTECTION OVERALL PLAN
3
05/12/2021
05/12/2021
Permit Set (05/12/21)
FP230
LEVEL 1 - RANGE & ASSET FIRE PROTECTION PLANS
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
DocuSign Envelope ID: 54FB4F97-EB9B-453D-AAD5-292D7CF9F350
�LINTCO
Dr-ving No.
AV001
D—ing Title
AUDIOVISUAL LEGEND
Revision
2
D—ing Date
06/08/2021
Received Date
06/08/2021
Set
77704 -Supplemental Sheets (06/
08/21)
AV002
AUDIOVISUAL ONE LINE
1
05/12/2021
05/12/2021
Permit Set (05/12/21)
AV003
AUDIOVISUAL ONE LINE
1
05/12/2021
05/12/2021
Permit Set (05/12/21)
AV004
AUDIOVISUAL ONE LINE
1
05/12/2021
05/12/2021
Permit Set (05/12/21)
AV005
AUDIOVISUAL ONE LINE
1
05/12/2021
05/12/2021
Permit Set (05/12/21)
AV006
AUDIOVISUAL ONE LINE
1
05/12/2021
05/12/2021
Permit Set (05/12/21)
AV007
AUDIOVISUAL ONE LINE
1
06/08/2021
06/08/2021
WP#04 - Supplemental Sheets (06/ 08/21)
AV008
AUDIOVISUAL SCHEDULES
1
05/12/2021
05/12/2021
Permit Set (05/12/21)
AV210
LEVEL 1 - POLICE AUDIOVISUAL OVERALL PLAN
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
AV211
LEVEL 1 - POLICE AUDIOVISUAL PLAN - EAST
2
06/08/2021
06/08/2021
WP#04 - Supplemental Sheets (06/ 08/21)
AV212
LEVEL 1 - POLICE AUDIO/VISUAL PLAN - WEST
2
06/08/2021
06/08/2021
WP#04 - Supplemental Sheets (06/ 08/21)
AV220
LEVEL 2 - POLICE TECHNOLOGY OVERALL PLAN
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
AV221
LEVEL 2 - POLICE TECHNOLOGY PLAN - WEST
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
AV222
LEVEL 2 - POLICE TECHNOLOGY PLAN - EAST
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
AV230
LEVEL 1 - RANGE TECHNOLOGY PLAN
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
AV301
AUDIOVISUAL ENLARGED PLAN
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
AV302
AUDIOVISUAL ENLARGED PLAN
1
06/08/2021
06/08/2021
WP#04 - Supplemental Sheets (06/ 08/21)
AV303
AUDIOVISUAL ENLARGED PLAN
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
AV304
AUDIOVISUAL ENLARGED PLAN
0
11/09/2020
12/10/2020
DID Budget Set 11-9 (11/09/20)
AV401
AUDIOVISUAL DETAILS
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
AV402
AUDIOVISUAL DETAILS
TELECOMMUNICATIONS
1 0
1 11/09/2020
12/10/2020
DO Budget Set 11-9 (11/09/20)
T001
TECHNOLOGY LEGEND AND NOTES
4
07/09/2021
07/09/2021
PR #03 (07/09/21)
T002
TECHNOLOGY LEGEND AND NOTES
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
T003
TECHNOLOGY ONE LINE
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
T004
TECHNOLOGY SCHEDULES
3
07/19/2021
07/19/2021
WP#04-Addendum 1(07/19/21)
TI01
SITE - TECHNOLOGY PLAN
2
06/08/2021
06/08/2021
WP#04 - Supplemental Sheets (06/ 08/21)
T210
LEVEL 1 - POLICE TECHNOLOGY OVERALL PLAN
2
06/08/2021
06/08/2021
WP#04 - Supplemental Sheets (06/ 08/21)
T211
LEVEL 1 - POLICE TECHNOLOGY PLAN - WEST
3
07/09/2021
07/09/2021
PR #03 (07/09/21)
T212
LEVEL I - POLICE TECHNOLOGY PLAN - EAST
3
07/09/2021
07/09/2021
PR #03 (07/09/21)
T220
LEVEL 2 - POLICE TECHNOLOGY OVERALL PLAN
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
T221
LEVEL 2 - POLICE TECHNOLOGY PLAN - WEST
2
06/08/2021
06/08/2021
WP#04 - Supplemental Sheets (06/ 08/21)
T222
LEVEL 2 - POLICE TECHNOLOGY PLAN - EAST
2
06/08/2021
06/08/2021
WP#04 - Supplemental Sheets (06/
08/21)
T230
LEVEL 1-RANGE TECHNOLOGY PLAN
3
07/09/2021
07/09/2021
PR #03 (07/09/21)
T240
LEVEL 1 - ASSET BUILDING 1 TECHNOLOGY PLAN
0
11/09/2020
12/10/2020
DID Budget Set 11-9 (11/09/20)
T250
LEVEL 1 - ASSET BUILDING 2 TECHNOLOGY PLAN
1
06/08/2021
06/08/2021
WP#04 - Supplemental Sheets (06/ 08/21)
T301
TECHNOLOGY ENLARGED PLAN
0
11/09/2020
12/10/2020
DID Budget Set I1-9 (11/09/20)
T302
TECHNOLOGY ENLARGED PLAN
0
11/09/2020
12/10/2020
DID Budget Set 11-9 (11/09/20)
T311
LEVEL 1 - POLICE SECURITY PLAN - WEST
2
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
T312
LEVEL I - POLICE SECURITY PLAN - EAST
1
06/08/2021
06/08/2021
WP#04 - Supplemental Sheets (06/ 08/21)
T321
LEVEL 2 - POLICE SECURITY PLAN - WEST
2
07/19/2021
07/19/2021
WP#04 - Addendum 1 (07/19/21)
T322
LEVEL 2 -POLICE SECURITY PLAN -EAST
1
06/08/2021
06/08/2021
WP#04 - Supplemental Sheets (06/ 08/21)
T330
LEVEL 1 - RANGE SECURITY PLAN
1
06/08/2021
06/08/2021
WP#04 - Supplemental Sheets (06/ 08/21)
T350
LEVEL 1 - ASSET BUILDING 2 SECURITY PLAN
0
06/08/2021
06/08/2021
WP#04 - Supplemental Sheets (06/ 08/21)
T401
TECHNOLOGY ENLARGED PLAN
3
05/12/2021
05/12/2021
Permit Set (05/12/21)
T402
TECHNOLOGY ENLARGED PLAN
2
05/12/2021
05/12/2021
Permit Set (05/12/21)
T403
TECHNOLOGY DETAILS
0
11/09/2020
12/10/2020
DO Budget Set 11-9 (11/09/20)
T404
TECHNOLOGY DETAILS
0
11/09/2020
12/10/2020
DID Budget Set 11-9 (11/09/20)
T501
TECHNOLOGY DETAILS
1
05/12/2021
05/12/2021
Permit Set (05/12/21)
T502
TECHNOLOGY DETAILS
1
05/12/2021
05/12/2021
Permit Set (05/12/21)
T503
TECHNOLOGY DETAILS
1
05/12/2021
05/12/2021
Permit Set (05/12/21)
T504
TECHNOLOGY DETAILS
1
05/12/2021
05/12/2021
Permit Set (05/12/21)
DocuSign Envelope ID: 54FB4F97-EB9B-453D-AAD5-292D7CF9F350
�LINTCO Exhibit C - Enumeration of Documents
Current Specifications
Number Description Revision Issued Date Received Date Set
00 - Procurement and Contracting Requirements
0001 10 Table of Contents 5 1 06/08/21 1 06/08/21 WP#04 - Supplemental Sheets
01 - General Requirements
01 00 00
GENREAL REQUIREMENTS
1
06/08/21
06/08/21
WP#04 - Supplemental Sheets
01 01 00
Summary of Work
4
06/08/21
06/08/21
WP#04 - Supplemental Sheets
01 02 00
Allowances
2
06/08/21
06/08/21
WP#04 - Supplemental Sheets
01 02 50
MEASUREMENT AND PAYMENT
4
06/08/21
06/08/21
WP#04 - Supplemental Sheets
01 03 00
Alternates
3
06/08/21
06/08/21
WP#04 - Supplemental Sheets
01 04 00
COORDINATION
4
06/08/21
06/08/21
WP#04 - Supplemental Sheets
01 04 50
CUTTING AND PATCHING
4
06/08/21
06/08/21
WP#04 - Supplemental Sheets
01 05 00
FIELD ENGINEERING
4
06/08/21
06/08/21
WP#04 - Supplemental Sheets
01 06 00
REGULATORY REQUIREMENTS
4
06/08/21
06/08/21
WP#04 - Supplemental Sheets
01 20 00
Project Meetings
3
06/08/21
06/08/21
WP#04 - Supplemental Sheets
01 31 00
Project Management and Coordination
3
06/08/21
06/08/21
WP#04 - Supplemental Sheets
01 32 00
Construction Progress Documentation
3
06/08/21
06/08/21
WP#04 - Supplemental Sheets
01 33 00
Submittal Procedures
3
06/08/21
06/08/21
WP#04 - Supplemental Sheets
01 40 00
QUALITY REQUIREMENTS
4
06/08/21
06/08/21
WP#04 - Supplemental Sheets
01 42 00
References
3
06/08/21
06/08/21
WP#04 - Supplemental Sheets
01 43 00
Mock -Up Procedures
2
06/08/21
06/08/21
WP#04 - Supplemental Sheets
01 45 23
Code Required Special Inspections and Procedures
2
06/08/21
06/08/21
WP#04 - Supplemental Sheets
01 50 00
CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
4
06/08/21
06/08/21
WP#04 - Supplemental Sheets
01 60 00
Materials and Equipment
3
06/08/21
06/08/21
WP#04 - Supplemental Sheets
01 70 00
CONTRACT CLOSEOUT
4
06/08/21
06/08/21
WP#04 - Supplemental Sheets
01 71 00
Cleaning
3
06/08/21
06/08/21
WP#04 - Supplemental Sheets
01 72 00
Project Record Documents
3
06/08/21
06/08/21
WP#04 - Supplemental Sheets
01 73 00
operation and Maintenance Data
2
06/08/21
06/08/21
WP#04 - Supplemental Sheets
01 74 00
WARRANTIES AND BONDS
3
06/08/21
06/08/21
WP#04 - Supplemental Sheets
01 74 19
Construction Waste Management
3
06/08/21
06/08/21
WP#04 - Supplemental Sheets
01 78 00
Closeout Submittals
0
05/26/21
05/27/21
WP#04
01 79 00
Minimum Owner Training requirements
2
06/08/21
06/08/21
WP#04 - Supplemental Sheets
01 81 13
LEED Certification Requirements
3
06/08/21
06/08/21
WP#04 - Supplemental Sheets
01 81 19
ENVIROMENTAL COMPLIANCE
2
06/08/21
06/08/21
WP#04 - Supplemental Sheets
01 82 00
Demonstration and Traininc
2
06/08/21
1 06/08/21
WP#04 - Supplemental Sheets
01 91 13
General Commissioning Requiremets
2
06/08/21
06/08/21
WP#04 - Supplemental Sheets
03 - Concrete
03 00 00
DIVISION 3 CONCRETE
1
05/26/21
05/27/21
WP#04
03 11 13
Structural Concrete Forming
2
05/26/21
05/27/21
WP#04
03 11 15
Expanded Polystyrene Foam Block Formwork
2
05/26/21
05/27/21
WP#04
03 15 00
Cast -In Anchors and Embeds
2
05/26/21
05/27/21
WP#04
03 20 00
Concrete Reinforcing
2
05/26/21
05/27/21
WP#04
03 30 00
Cast -in -Place Concrete
0
05/26/21
05/27/21
WP#04
03 30 13
Conrete Footings
2
05/26/21
05/27/21
WP#04
03 30 53
Civil Site Concrete
1
05/26/21
05/27/21
WP#04
03 31 00
Structural Concrete
2
05/26/21
05/27/21
WP#04
033150
Grouts
1
05/26/21
05/27/21
WP#04
03 35 43
Bonded Abrasive Polished Concrete
1
05/26/21
05/27/21
WP#04
03 36 60
Concrete Floor Sealer
1
05/26/21
05/27/21
WP#04
03 62 14
Grouting Steel Base Plates
2
05/26/21
05/27/21
WP#04
04 - Masonry
04 00 00
DIVISION 4 MASONRY
2
06/08/21
06/08/21
WP#04 - Supplemental Sheets
04 05 13
Masonry Mortar
3
06/08/21
06/08/21
WP#04 - Supplemental Sheets
04 22 00
Concrete Unit Masonry
4
06/08/21
06/08/21
WP#04 - Supplemental Sheets
04 40 00
Stone
3
06/08/21
06/08/21
WP#04 - Supplemental Sheets
04 72 00
Cast Stone
2
06/08/21
06/08/21
WP#04 - Supplemental Sheets
04 73 23
Calcium Silicate Manufactured Building Stone Masonry
2
06/08/21
06/08/21
WP#04 - Supplemental Sheets
05 - Metals
05 00 00
DIVISION 5 METALS
1
05/26/21
05/27/21
WP#04
05 01 00
Miscellaneous Metals
1
05/26/21
05/27/21
WP#04
05 1200
Structural Steel Framing
2
05/26/21
05/27/21
WP#04
05 21 00
Steel Joists
2
05/26/21
05/27/21
WP#04
0531 14
Steel Composite Floor Decking
2
05/26/21
05/27/21
WP#04
05 31 23
Steel Roof Decking
2
05/26/21
05/27/21
WP#04
05 40 00
Cold -Formed Metal Stud Framing
j 1
j 05/26/21
j 05/27/21
WP#04
05 51 13
Metal Stairs and Railings
1
05/26/21
05/27/21
WP#04
05 73 50
Perforated Metal
1
05/26/21
05/27/21
WP#04
DocuSign Envelope ID: 54FB4F97-EB9B-453D-AAD5-292D7CF9F350
'CF"LINTC0
Number Description Revision Issued Date Received Date Set
06 - Wood, Plastics, and Composites
06 00 00
DIVISION 6 - WOOD AND PLASTICS
0
05/26/21
05/27/21
WP#04
06 10 00
Rough Carpentry
0
05/26/21
05/27/21
WP#04
061653
Sheathing
1
05/26/21
05/27/21
WP#04
06 20 00
Finish Carpentry
0
05/26/21
05/27/21
WP#04
064000
Architectural Woodwork
0
05/26/21
05/27/21
WP#04
07 - Thermal and Moisture Protection
07 13 26
Blindside Waterproofing
1
05/26/21
05/27/21
WP#04
07 19 50
Vapor Barrier
1
05/26/21
05/27/21
WP#04
07 20 00
Insulation
1
05/26/21
05/27/21
WP#04
07 24 13
Exterior Insulation and Finish System (EIFS)
1
05/26/21
05/27/21
WP#04
07 24 23
Direct Applied Exterior Finish System (DEFS)
1
05/26/21
05/27/21
WP#04
07 27 20
Fluid -Applied Membrane Weather Barrier
1
05/26/21
05/27/21
WP#04
07 42 14
METAL ROOF SCREEN PANELS AND SITE WALL LOUVER PANELS
0
05/26/21
05/27/21
WP#04
074217
Metal Panels
2
07/19/21
07/19/21
WP#04- Addendum l
07 42 44
Composite Metal Panels (Aluminum -Faced)
2
05/26/21
05/27/21
WP#04
07 54 23
Thermoplastic Roof System (TPO
1
05/26/21
05/27/21
WP#04
07 60 00
Flashing and Sheet Metal
1
05/26/21
05/27/21
WP#04
07 72 00
Roof Hatches
1
05/26/21
05/27/21
WP#04
07 84 00
Firestopping
1
05/26/21
05/27/21
WP#04
07 92 00
Sealants & Caulking
1
05/26/21
05/27/21
WP#04
08 - Openings
08 00 00
DIVISION 8 OPENINGS
0
05/26/21
05/27/21
WP#04
0811 13
Hollow Metal Doors and Frames
1
05/26/21
05/27/21
WP#04
08 14 16
WOOD DOORS
0
05/26/21
05/27/21
WP#04
08 29 00
ACCESS DOORS
0
05/26/21
05/27/21
WP#04
08 33 23
Overhead Coiling Doors
1
05/26/21
05/27/21
WP#04
08 36 00
Sectional Overhead Doors
1
05/26/21
05/27/21
WP#04
08 40 00
Entrances and Storefronts
1
05/26/21
05/27/21
WP#04
08 56 00
LAMINATED POLYCARBONATE GLAZING
0
05/26/21
05/27/21
WP#04
08 70 00
Hardware
3
07/19/21
07/19/21
WP#04 - Addendum 1
08 70 01
HARDWARE AT ALUMINUM DOORS
2
07/19/21
07/19/21
WP#04 - Addendum 1
08 80 00
Glazing
1
05/26/21
05/27/21
WP#04
09 - Finishes
09 00 00
DIVISION 9 FINISHES
0
06/08/21
06/08/21
WP#04 - Supplemental Sheets
09 24 23
Plaster
2
06/08/21
06/08/21
WP#04 - Supplemental Sheets
09 29 00
Gypsum Board Systems
2
06/08/21
06/08/21
WP#04 - Supplemental Sheets
09 30 10
TILE
1
06/08/21
06/08/21
WP#04 - Supplemental Sheets
09 5123
Acoustical Tile Ceilings
0
03/23/21
03/23/21
WP#03 - Addendum 1
09 5151
Cube Ceiling Systems
2
06/08/21
06/08/21
WP#04 - Supplemental Sheets
09 52 00
ACOUSTICAL PANELS
1
06/08/21
06/08/21
WP#04 - Supplemental Sheets
09 54 50
SECURITY PLANK METAL CEILINGS
0
05/26/21
05/27/21
WP#04
09 5533
WOOD LOOK SUSPENDED SOFFIT
1
06/08/21
06/08/21
WP#04 - Supplemental Sheets
09 65 00
Resilient Flooring
2
07/19/21
07/19/21
WP#04 - Addendum 1
09 65 50
RESILIENT ATHLETIC FLOORING
1
06/08/21
06/08/21
WP#04 - Supplemental Sheets
09 68 00
Carpeting
1
06/08/21
06/08/21
WP#04 - Supplemental Sheets
09 69 00
Access Flooring
j 1
j 06/08/21
j 06/08/21
WP#04 - Supplemental Sheets
09 90 00
Painting
1
06/08/21
06/08/21
WP#04 - Supplemental Sheets
09 95 00
WALLCOVERING
1
06/08/21
06/08/21
WP#04 - Supplemental Sheets
10 - Specialties
10 00 00
Specialties
0
06/08/21
06/08/21
WP#04 - Supplemental Sheets
10 00 00.0
DIVISION 10 - SPECIALTIES
1
06/08/21
06/08/21
WP#04 - Supplemental Sheets
10 00 01
Miscellaneous Specialites
1
06/08/21
06/08/21
WP#04 - Supplemental Sheets
10 1550
TOILET COMPARTMENTS
1
06/08/21
06/08/21
WP#04 - Supplemental Sheets
10 42 00
Plaque
2
06/08/21
06/08/21
WP#04 - Supplemental Sheets
10 43 00
Exterior Signs
2
06/08/21
06/08/21
WP#04 - Supplemental Sheets
10 44 00
INTERIOR SIGNAGE
1
06/08/21
06/08/21
WP#04 - Supplemental Sheets
10 50 00
LOCKERS
1
06/08/21
06/08/21
WP#04 - Supplemental Sheets
10 50 10
PERSONNEL LOCKERS
1
06/08/21
06/08/21
WP#04 - Supplemental Sheets
10 51 13
Metal Lockers
0
06/08/21
06/08/21
WP#04 - Supplemental Sheets
1051 14
EVIDENCE LOCKERS
1
06/08/21
06/08/21
WP#04 - Supplemental Sheets
10 5121
GEAR BAG LOCKERS
1
06/08/21
06/08/21
WP#04 - Supplemental Sheets
10 73 00
Protective Covers
j 2
j 06/08/21
j 06/08/21
WP#04 - Supplemental Sheets
10 75 16
Flagpoles
3
06/08/21
06/08/21
WP#04 - Supplemental Sheets
10 80 00
TOILET AND BATH ACCESSORIES
1
06/08/21
06/08/21
WP#04 - Supplemental Sheets
DocuSign Envelope ID: 54FB4F97-EB9B-453D-AAD5-292D7CF9F350
�LINTCO
Number Description Revision Issued Date Received Date Set
10 82 13 Roof Screens 2 06/08/21 06/08/21 WP#04 - Supplemental Sheets
11 - Equipment
11 00 00
DIVISION 11 - EQUIPMENT
1
06/08/21
06/08/21
WP#04 - Supplemental Sheets
11 1230
Exterior Gate Operators
2
06/08/21
06/08/21
WP#04 - Supplemental Sheetr
11 45 00
Equipment
1
06/08/21
06/08/21
WP#04 - Supplemental Sheets
11 60 00
EVIDENCE PROCESSING EQUIPMENT
1
06/08/21
06/08/21
WP#04 - Supplemental Sheets
14 - Conveying Equipment
14 00 00
DIVISION 14 - CONVEYING SYSTEMS
0
05/26/21
05/27/21
WP#04
14 24 46
MACHINE ROOMLESS HYDRAULIC ELEVATORS
1
05/26/21
05/27/21
WP#04
21 - Fire Suppression
21 00 00
DMSION 21 FIRE SUPPRESSION
1
05/26/21
05/27/21
WP#04
21 05 00
COMMON WORK RESULTS FOR FIRE SUPPRESSION
2
05/26/21
05/27/21
WP#04
21 09 00
Fire Suppression System Automation and Automatic Control System
1
05/26/21
05/27/21
WP#04
21 1300
Fire Suppression Sprinkler Systems
2
05/26/21
05/27/21
WP#04
21 1319
Preaction Suppression Systems
1
05/26/21
05/27/21
WP#04
21 22 00
Clean -Agent Fire Extinguishing Systems
1
05/26/21
05/27/21
WP#04
21 90 00
Fire Suppression System Project Closeout
1
05/26/21
05/27/21
WP#04
22 - Plumbing
22 00 00
DIVISION 22 PLUMBING
1
05/26/21
05/27/21
WP#04
22 05 00
COMMON WORK RESULTS FOR PLUMBING
2
05/26/21
05/27/21
WP#04
22 05 50
Plumbing Seismic Restraints
1
05/26/21
05/27/21
WP#04
22 07 00
Plumbing Insulation
1
05/26/21
05/27/21
WP#04
22 08 00
Commissioning of Plumbing Systems
1
05/26/21
05/27/21
WP#04
22 09 00
Plumbing Automation and Automatic Temperature Control System
1
05/26/21
05/27/21
WP#04
22 1000
Plumbing Piping
2
05/26/21
05/27/21
WP#04
22 1500
Compressed Air System
1
05/26/21
05/27/21
WP#04
22 21 23
Natural Gas Systems
2
05/26/21
05/27/21
WP#04
22 30 00
Plumbing Equipment
2
05/26/21
05/27/21
WP#04
22 40 00
Plumbing Fixtures
2
05/26/21
05/27/21
WP#04
22 90 00
Plumbing Project Closeout
1
05/26/21
05/27/21
WP#04
23 - Heating, Ventilating, and Air Conditioning (HVAC)
23 00 00
DIVISION 23 HVAC
1
05/26/21
05/27/21
WP#04
23 05 01
Mechanical and Electrical Coordination
2
05/26/21
05/27/21
WP#04
23 05 02
Basic Mechanical Requirements
2
05/26/21
05/27/21
WP#04
23 05 03
Basic Mechanical Materials and Methods
2
05/26/21
05/27/21
WP#04
23 05 13
Motors and Starters
1
05/26/21
05/27/21
WP#04
23 05 21
Pipe and Pipe Fittings
2
05/26/21
05/27/21
WP#04
23 05 22
Piping Accessories
2
05/26/21
05/27/21
WP#04
23 05 23
Valves
2
05/26/21
05/27/21
WP#04
23 05 29
Pipe Supports and Anchors
2
05/26/21
05/27/21
WP#04
23 05 30
Electronic Speed Controllers
1
05/26/21
05/27/21
WP#04
23 05 48
Vibration Control
1
05/26/21
05/27/21
WP#04
23 05 49
Seismic Restraints
1
05/26/21
05/27/21
WP#04
23 05 53
Mechanical Identification
1
05/26/21
05/27/21
WP#04
23 05 93
Test -Adjust -Balance
1
05/26/21
05/27/21
WP#04
23 07 00
Mechanical Insulation
1
05/26/21
05/27/21
WP#04
23 08 00
Commissioning of HVAC Systems
1
05/26/21
05/27/21
WP#04
23 09 00
Building Automation and Automatic Temp Control System
1
05/26/21
05/27/21
WP#04
23 23 00
Refrigerant Piping
1
05/26/21
05/27/21
WP#04
2331 13
Ductwork
1
05/26/21
05/27/21
WP#04
23 33 00
Ductwork Accessories
1
05/26/21
05/27/21
WP#04
23 34 00
HVAC Fans
1
05/26/21
05/27/21
WP#04
23 36 00
Air Terminals Units
1
05/26/21
05/27/21
WP#04
23 37 00
Air Inlets and Outlets
1
05/26/21
05/27/21
WP#04
23 40 00
Air Cleaning
1
05/26/21
05/27/21
WP#04
23 51 00
Flue Systems
1
05/26/21
05/27/21
WP#04
23 74 00
Packaged Rooftop Air Conditioning Units
1
05/26/21
05/27/21
WP#04
2381 19
PACKAGED TERMINAL AIR CONDITIONING UNITS
1
05/26/21
05/27/21
WP#04
23 81 23
Electronic Room Air Conditions Unit
1
05/26/21
05/27/21
WP#04
23 81 26
Split System Air Conditioners
1
05/26/21
05/27/21
WP#04
23 82 39
Heating Terminal Units
1
05/26/21
05/27/21
WP#04
23 90 00
Project Closeout
1
05/26/21
05/27/21
WP#04
26 - Electrical
26 00 00
DIVISION 26 ELECTRICAL
1
05/26/21
05/27/21
WP#04
260500
Electrical Requirements
2
05/26/21
05/27/21
WP#04
DocuSign Envelope ID: 54FB4F97-EB9B-453D-AAD5-292D7CF9F350
'CF"LINTC0
Number
Description
Revision
Issued Date
Received Date
Set
26 05 01
MECHANICAL AND ELECTRICAL COORDINATION
0
05/26/21
05/27/21
WP#04
26 05 02
BASIC MATERAILS AND METHODS
2
05/26/21
05/27/21
WP#04
26 05 03
Manufacturers
1
05/26/21
05/27/21
WP#04
260510
Testing
1
05/26/21
05/27/21
WP#04
26 05 19
Electrical Power Conductors and Cables
1
05/26/21
05/27/21
WP#04
26 05 26
Grounding and Bonding
2
05/26/21
05/27/21
WP#04
26 05 29
Hangers and Supports
1
05/26/21
05/27/21
WP#04
26 05 33
RACEWAYS AND BOXES
2
05/26/21
05/27/21
WP#04
26 05 39
Undernoor Manufactured Wiring Systems
1
05/26/21
05/27/21
WP#04
26 05 43
Underground Ducts, Raceways and Manholes
2
05/26/21
05/27/21
WP#04
26 05 48
Vibration and Seismic Controls
1
05/26/21
05/27/21
WP#04
26 05 53
Identification
2
05/26/21
05/27/21
WP#04
26 08 00
Commissioning of Electrical Systems
1
05/26/21
05/27/21
WP#04
26 09 13
Electrical Power Monitoring -Tenant Submetering
1
05/26/21
05/27/21
WP#04
26 09 43
Lighting Control System
1
05/26/21
05/27/21
WP#04
26 09 44
Wireless Network Lighting Control
1
05/26/21
05/27/21
WP#04
26 22 13
Low -Voltage Distribution Transformers
1
05/26/21
05/27/21
WP#04
26 23 00
Low -Voltage Switchgear
1
05/26/21
05/27/21
WP#04
262413
Distribution Switchboards
1
05/26/21
05/27/21
WP#04
26 24 16
Panelboards
1
05/26/21
05/27/21
WP#04
262726
Wiring Devices
1
05/26/21
05/27/21
WP#04
2628 16
Enclosed Switches, Fuses and Circuit Breakers
1
05/26/21
05/27/21
WP#04
26 32 14
Gas -Engine Driven Generator Sets
1
05/26/21
05/27/21
WP#04
26 33 53
Static Uninterruptable Power Supply
1
05/26/21
05/27/21
WP#04
26 36 23
Automatic Transfer Switches
1
05/26/21
05/27/21
WP#04
2641 13
Lightning Protection for Structures
2
05/26/21
05/27/21
WP#04
26 43 13
Surge Protective Device (SPD) Selenium Enhanced
1
05/26/21
05/27/21
WP#04
26 43 14
Surge Protective Device (SPD
2
05/26/21
05/27/21
WP#04
26 50 00
Lighting
1
05/26/21
05/27/21
WP#04
26 56 13
Poles and Standards
1
05/26/21
05/27/21
WP#04
26 90 00
Project Closeout
1
05/26/21
05/27/21
WP#04
27 - Communications
27 00 00
DIVISION 27 COMMUNICATIONS
1
05/26/21
05/27/21
WP#04
27 05 00
Common Work Results for Communications
2
05/26/21
05/27/21
WP#04
27 05 26
Telecommunications Grounding and Bonding
1
05/26/21
05/27/21
WP#04
27 05 33
Telecommunications Raceways and Boxes
1
05/26/21
05/27/21
WP#04
27 05 36
Cable Tray
1
05/26/21
05/27/21
WP#04
27 05 43
Underground Ducts, Raceways and Manholes
2
05/26/21
05/27/21
WP#04
27 11 00
Communications Equipment Room Fit -Out
1
05/26/21
05/27/21
WP#04
27 13 13
Communications Copper Backbone Cabling
1
05/26/21
05/27/21
WP#04
27 13 23
Communications Optical Fiber Backbone Cabling
1
05/26/21
05/27/21
WP#04
27 15 00
Communications Horizontal Cabling
1
05/26/21
05/27/21
WP#04
27 41 00
Audio Visual Systems
1
05/26/21
05/27/21
WP#04
27 41 40
CAN Distribution System
1
05/26/21
05/27/21
WP#04
28 - Electronic Safety and Security
28 00 00
Security Systems - General
1
05/26/21
05/27/21
WP#04
28 00 01
SECURITY SYSTEMS MONITORING AND CONTROLS
1
05/26/21
05/27/21
WP#04
28 13 00
Access Control
1
05/26/21
05/27/21
WP#04
28 23 00
Video Surveillance System
1
05/26/21
05/27/21
WP#04
28 46 00
ADDRESSABLE FIRE ALARM SYSTEM
1
05/26/21
05/27/21
WP#04
28 50 10
AREA OF RESUCE ASSISTANCE SYSTEM
0
05/26/21
05/27/21
WP#04
28 50 20
EMERGENCY RESPONDER RADIO SYSTEM
0
05/26/21
05/27/21
WP#04
31 - Earthwork
31 00 00
DIVISION 31 - EARTHWORK
0
05/26/21
05/27/21
WP#04
31 1000
Site Clearing and Demolition
1
05/26/21
05/27/21
WP#04
31 20 00
EARTHWORK
0
WP#01
312319
Dewatering
1
05/26/21
05/27/21
WP#04
313116
Termite Control
1
05/26/21
05/27/21
WP#04
32 - Exterior Improvements
32 00 00
EXTERIOR IMPROVEMENTS
0
05/26/21
05/27/21
WP#04
321216
Hot -Mix Asphalt Paving
1
05/26/21
05/27/21
WP#04
32 13 13
Concrete Paving
0
03/08/21
03/09/21
WP#3
32 1823
Synthetic Turf
1
05/26/21
05/27/21
WP#04
3231 13
Chain Link Fencing
1
05/26/21
05/27/21
WP#04
3231 19
Metal Fencing
1
05/26/21
05/27/21
WP#04
DocuSign Envelope ID: 54FB4F97-EB9B-453D-AAD5-292D7CF9F350
�LINTCO
Number
Description Revision
Issued Date
Received Date
Set
32 31 20
Metal Screen Fencing 1
05/26/21
05/27/21
WP#04
32 84 00
Planting Irrigation 1
05/26/21
05/27/21
WP#04
32 92 10
Turf Sodding 1
05/26/21
05/27/21
WP#04
32 92 20
Turf Seeding 1
05/26/21
05/27/21
WP#04
32 93 00
Trees, Shrubs and Groundcover 1
05/26/21
05/27/21
WP#04
33 - Utilities
33 00 00
DIVISION 33 SITE UTILITIES
0
05/26/21
05/27/21
WP#04
33 05 00
Common Work Results for Utilities
1
05/26/21
05/27/21
WP#04
33 20 00
Standard Specification for Design and Construction of Water Lines and Sewer Lines
1
05/26/21
05/27/21
WP#04
33 41 00
Storm Drainage
1
05/26/21
05/27/21
WP#04
33 44 43
STORM WATER TREATMENT DEVICE
0
05/26/21
05/27/21
WP#04
City of Fayetteville, Arkansas - Budget Adjustment Form (Legistar)
Budget Year Division Adjustment Number
/Org2 FACILITIES MANAGEMENT (140)
2021
Requestor: Wade Abernathy
BUDGET ADJUSTMENT DESCRIPTION / JUSTIFICATION:
Approval of Change Order #5 with Flintco, LLC, to RFQ#19-05 Contract for the police Headquarters Facilities Project
in the amount of $3,320,439.00 and approve a Budget Adjustment.
RESOLUTION/ORDINANCE
COUNCIL DATE: 10/5/2021
LEGISTAR FILE ID#: 2021-0735
KP,vLwSpr �
911712021 10:08 AM
Budget Director Date
TYPE: D - (City Council)
JOURNAL #:
GLDATE:
CHKD/POSTED:
TOTAL
Account Number
- -
Increase / (Decrease)
Expense Revenue
Proiect.Sub#
Project Sub.Detl AT
v.20210831
Account Name
4609.860.7900-5804.00
3,320,439 -
46090 7900.8040 EX
Building Costs
4609.860.7999-5899.00
(3,320,439) -
46090 7999 EX
Unallocated - Budget
H:\Budget Adjustments\2021_Budget\City Council\10-05-2021\2021-0735 BA Police CO 5 Flintco.xlsm 1 of 1