Resolution: 130-21
File Number: 2021-0284
J.R. STEWART PUMP & EQUIPMENT, INC.:
A RESOLUTION TO ACCEPT A QUOTE IN THE AMOUNT OF $32,942.89 PLUS
APPLICABLE TAXES AND FREIGHT CHARGES FROM J.R. STEWART PUMP &
EQUIPMENT, INC. FOR THE REPAIR OF A PUMP AT THE GREGG AVENUE LIFT
STATION
WHEREAS, a submersible pump used at the Gregg Avenue Lift Station was recently shipped to J.R.
Stewart Pump & Equipment to disassemble, inspect, and provide a quote for repair of the pump; and
WHEREAS, pursuant to Ark. Code Ann. §19-1 1-203(14)(DD), formal competitive bidding is not
necessary for the repair of "hidden or unknown damages."
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby determines that because
of Ark. Code Ann. § 19-1 1-203(14)(DD), repair of "hidden or unknown damages," the repair of the
pump does not require formal competitive bidding and, therefore, accepts the quote in the amount of
$32,942.89 (plus any applicable taxes and freight charges) from J.R. Stewart Pump & Equipment for
the repair of a submersible pump used at the Gregg Avenue Lift Station.
PASSED and APPROVED on 5/4/2021
Page 1 Printed on 515/21
Resolution: 130-21
File Number: 2021-0284
Attest:
'VR')'16111
Kara Paxton, City Clerk Tre r`���
�ti• .tea
��FAYE�E`�ILLE:
Page 2 Printed on 5/5/21
City of Fayetteville, Arkansas 113 West Mountain Street
Fayetteville, AR 72701
j (479) 575-8323
Text File
File Number: 2021-0284
Agenda Date: 5/4/2021 Version: 1 Status: Passed
In Control: City Council Meeting File Type: Resolution
Agenda Number: A.10
J.R. STEWART PUMP & EQUIPMENT, INC.:
A RESOLUTION TO ACCEPT A QUOTE IN THE AMOUNT OF $32,942.89 PLUS APPLICABLE
TAXES AND FREIGHT CHARGES FROM J.R. STEWART PUMP & EQUIPMENT, INC. FOR THE -
REPAIR OF A PUMP AT THE GREGG AVENUE LIFT STATION
WHEREAS, a submersible pump used at the Gregg Avenue Lift Station was recently shipped to J.R. Stewart
Pump & Equipment to disassemble, inspect, and provide a quote for repair of the pump; and
WHEREAS, pursuant to Ark. Code Ann. §19-1 1-203(14)(DD), formal competitive bidding is not necessary
for the repair of "hidden or unknown damages."
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby determines that because of Ark.
Code Ann. § 19-1 1-203(14)(DD), repair of "hidden or unknown damages," the repair of the pump does not
require formal competitive bidding and, therefore, accepts the quote in the amount of$32,942.89 (plus any
applicable taxes and freight charges) from J.R. Stewart Pump & Equipment for the repair of a submersible
pump used at the Gregg Avenue Lift Station.
City of Fayetteville, Arkansas Page 1 Printed on 5/5/2021
Tim Nyander
Submitted By
City of Fayetteville Staff Review Form
2021-0284
Legistar File ID
5/4/2021
City Council Meeting Date - Agenda Item Only
N/A for Non -Agenda Item
4/15/2021
Submitted Date
Action Recommendation:
WASTEWATER TREATMENT (730)
Division / Department
Staff recommends approval of the repair of a submersible pump for the Gregg Avenue Lift Station by J.R. Stewart
Pump & Equipment in the amount of $32,942.89 plus applicable taxes and freight charges.
5400.730.5800-5414.00
Account Number
02069.1
Project Number
Budget Impact:
Water and Sewer
Fund
Plant Pumps and Equipment - WWTP
Project Title
Budgeted Item? Yes Current Budget
$ 1,317,743.00
Funds Obligated
$ 162,039.97
Current Balance
$ 1,155,703.03
Does item have a cost? Yes Item Cost
$ 37,997.18
Budget Adjustment Attached? No Budget Adjustment
$ -
Remaining Budget I $ 1,117,705.85
V20180321
Purchase Order Number: Previous Ordinance or Resolution #
Change Order Number:
Original Contract Number:
Approval Date:
Comments: Freight charges are estimated at $1,600 and taxes are estimated at $3,454.29 for an estimated total cost
of $37,997.18.
QCITY OF
FAYETTEVILLE
ARKANSAS
MEETING OF MAY 4, 2021
TO: Mayor Lioneld Jordan
THRU: Susan Norton, Chief of Staff
Tim Nyander, Utilities Director
FROM: Monty Sedlak, Project Manager
DATE: April 15, 2021
CITY COUNCIL MEMO
SUBJECT: J.R. Stewart Pump & Equipment — Submersible Pump Repair for the Gregg
Avenue Sewer Lift Station
RECOMMENDATION:
Staff recommends approval of the repair of a submersible pump for the Gregg Avenue Lift
Station by J.R. Stewart Pump & Equipment in the amount of $32,942.89 plus applicable taxes
and freight charges.
BACKGROUND:
The Gregg Avenue Lift Station uses four submersible KSB pumps to move sewage through the
collection system. It feeds directly into the Hamestring Lift Station which delivers over 85% of
the West Side WRRF's average 7+ MGD of wastewater influent.
In late 2020, pump No. 4 began experiencing longer than normal run times. Jacob's
maintenance staff inspected the pump and found that a 200 amp fuse was blown and that
phases A and B on the motor were shorted to the ground. They promptly pulled pump No. 4 and
sent it to J.R. Stewart Pump & Equipment out of West Memphis, Arkansas for an inspection.
DISCUSSION:
J.R. Stewart Pump & Equipment has submitted a quote for the repair of Pump No. 4 in the
amount of $32,942.89, plus applicable taxes and freight charges for a total estimated cost of
$37,997.18.
Because it was necessary to have the repair facility disassemble the units to determine the
extent of hidden and unknown damage to equipment already purchased, a bid waiver and/or
formal sealed bidding is not necessary according to Ark. Code Ann. §19-11-203(14)(DD).
BUDGET/STAFF IMPACT:
Funds are available in the Plant Pumps and Equipment account within the Water & Sewer Fund.
Attachments:
Quote from J.R. Stewart Pump & Equipment
Mailing Address:
113 W. Mountain Street www.fayetteville-ar.gov
Fayetteville, AR 72701
J.R. STEWART PUMP & EQUIP INC,
313 S.Second St West MEMPHIS AR
Office (870)-735-2484 Fax (870)-735-0765
Josh Alleman
Jacobs Engineering
The following will consist of the following;
Labor and material to dismantle, clean, and inspect motor.
Electrically test windings (grounded/shorted) rewind, dip,
and bake stator.
Hypot and surge test stator windings, Mic and record all
mechanical fits. Dynamically balance all rotating parts.
Install new SKF bearings. Assemble. Test run and record
all date. Balance impeller on arbor, final assembly, prime
and paint.
Total price $32,942.89
Monday, April 12, 2021
Tax Not Included
Freight 1,600.00 adder
2 to 3 Weeks
Lead times may be impacted due to COVID 19
Patrick Hughey
Outside sales
WWW.JRSPUMP.COM
Office; 870-735-2484
Cell; 901-461-7603