RFQ 20-01 SELECTION #16 ENGINEERING ELEMENTS, PLLC:
A RESOLUTION TO AUTHORIZE A CONTRACT WITH ENGINEERING ELEMENTS, PLLC,
IN THE AMOUNT OF $4,500.00, PURSUANT TO RFQ 20-01 SELECTION #16, TO
PROVIDE DESIGN SERVICES, BID DOCUMENTS AND CONSTRUCTION
ADMINISTRATION FOR THE INSTALLATION OF LIGHTING AT THE WALKER PARK
SKATEBOARD AREA, TO APPROVE A PROJECT CONTINGENCY IN THE AMOUNT OF
$500.00, AND TO APPROVE A BUDGET ADJUSTMENT
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby authorizes the Mayor to
sign a contract with Engineering Elements, PLLC in the amount of $4,500.00, pursuant to RFQ 20-01
Selection #16, for design services, bid documents and construction administration for installing LED
lighting at the Walker Park Skateboard Area and further approves a project contingency in the amount
of $500.00.
Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget
adjustment, a copy of which is attached to this Resolution.
PASSED and APPROVED on 9/l/2020
Page 1 Printed on 912120
Resolution: 218-20
File Number: 2020-0671
Attest:
c_ERK !
Kara Paxton, City Clerk Treasur8t- FAYrIT ��'
=c� �V144E
;ON COO
Page 2 Printed on 912120
City of Fayetteville, Arkansas 113 West Mountain Street
Fayetteville, AR 72701
i` (479) 575-8323
Text File
—l' File Number: 2020-0671
Agenda Date: 9/1/2020 Version: 1 Status: Passed
In Control: City Council Meeting File Type: Resolution
Agenda Number: A. 4
RFQ 20-01 SELECTION #16 ENGINEERING ELEMENTS, PLLC:
A RESOLUTION TO AUTHORIZE A CONTRACT WITH ENGINEERING ELEMENTS, PLLC, IN
THE AMOUNT OF $4,500.00, PURSUANT TO RFQ 20-01 SELECTION #16, TO PROVIDE DESIGN
SERVICES, BID DOCUMENTS AND CONSTRUCTION ADMINISTRATION FOR THE
INSTALLATION OF LIGHTING AT THE WALKER PARK SKATEBOARD AREA, TO APPROVE A
PROJECT CONTINGENCY IN THE AMOUNT OF $500.00, AND TO APPROVE A BUDGET
ADJUSTMENT
BE IT RESOLVED BV THE CITY COUNCIL OF THE CITY OF FAVETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby authorizes the Mayor to sign a
contract with Engineering Elements, PLLC in the amount of $4,500.00, pursuant to RFQ 20-01 Selection # 16,
for design services, bid documents and construction administration for installing LED lighting at the Walker Park
Skateboard Area and further approves a project contingency in the amount of $500.00.
Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget adjustment, a
copy of which is attached to this Resolution.
City of Fayetteville, Arkansas Page 1 Printed on 9/2/2020
Ted Jack
Submitted By
City of Fayetteville Staff Review Form
2020-0671
Legistar File ID
9/1/2020
City Council Meeting Date - Agenda Item Only
N/A for Non -Agenda Item
8/6/2020 PARKS & RECREATION (520)
Submitted Date Division / Department
Action Recommendation:
Approval of a contract with Engineering Elements, PLLC for $4500.00 for design, bid documents, and construction
administration for installing LED lighting at the Skateboard Area at Walker Park, and a $500.00 design
contingency and approval of a budget adjustment.
2250.520.9255-5806.00
Account Number
13001.2001
Project Number
Budgeted Item? Yes
Does item have a cost? Yes
Budget Adjustment Attached? Yes
Budget Impact:
Parks Development
Fund
Walker Park Skateboard Park Lights
Current Budget
Funds Obligated
Current Balance
Item Cost
Budget Adjustment
Remaining Budget
Project Title
$ -
$ 5,000.00
$ 98,000.00
$ 93,000.00
V20180321
Purchase Order Number: Previous Ordinance or Resolution #
Change Order Number: Approval Date:
Original Contract Number:
Comments:
CITY OF
FAYETTEVILLE
ARKANSAS
MEETING OF SEPTEMBER 1, 2020
TO: Mayor and City Council
CITY COUNCIL MEMO
THRU: Susan Norton, Chief of Staff
Connie Edmonston, Parks and Recreation Director
FROM: Ted Jack, Park Planning Superintendent
DATE: August 7, 2020
SUBJECT: Approval of a contract with Engineering Elements, PLLC for $4500.00 for design,
bid documents, and construction administration for installing LED lighting at the Skateboard
Area at Walker Park, and a $500.00 design contingency and approval of a budget adjustment.
RECOMMENDATION:
Approval of a contract with Engineering Elements, PLLC for $4500.00 for design, bid
documents, and construction administration for installing LED lighting at the Skateboard Area
at Walker Park, and a $500 design contingency and approval of a budget adjustment.
BACKGROUND:
The popular skateboard park has been used primarily by area youth who have frequently
requested lighting. This project is in the five-year CIP plan for implementation in 2020 and will
add LED lighting increasing the usability of this amenity, particularly in winter months.
DISCUSSION:
Engineering Elements PLLC, of Fayetteville, was selected from RFQ 20-01, Selection #16, to
prepare the design, bid documents, and to provide construction administration for this project.
BUDGET/STAFF IMPACT:
Total project funding for this project in the CIP is $98,000. Engineering Elements fixed fee is
$4500. A design contingency of $500 is included in the $5,000.00 item costs. Additionally, $500
will be allocated for bid advertisement, with the remainder allocated to construction and
construction contingency. Long-term budget/staff impacts are minimal. The LED lighting will
cause a minor increase to electrical usage at Walker Park.
Attachments:
Staff Review Form
Engineering Elements Proposal
Mailing Address:
113 W. Mountain Street www.fayetteville-ar.gov
Fayetteville, AR 72701
E c
August 6, 2020
Mr. Ted Jack
City of Fayetteville
113 West Mountain Street
Fayetteville, AR 72701
Engineering Elements, PLLC
i458 F:..loycti Bled.. Suitc I FaNettevllle. Arkxisas 72703
Plxmc (479) 695-1333 Fax: (479) 251-7982
Re: Walker Skatepark Lighting Upgrade
Fayetteville, Arkansas
Mr. Jack,
I am pleased to propose electrical engineering services to you for the above referenced project.
This proposal is based on the preliminary information I received from Mr. Theodore Jack and
from a site visit made on July 30, 2020. It is my understanding that this project will consist of
new lighting at the Skatepark with pushbutton "ON" controls as well as time clock and wireless
app controls.
Our services will include standard basic engineering services consisting of preliminary design
and design development, contract documents, bidding assistance, submittal review and
construction observation. This level of services will pertain to the following systems as our part
of the work.
Engineering Design Services:
Our services include the following standard engineering services:
a. Preliminary Design and Design Development. Two design review meetings are
planned to evaluate design and light fixture selections.
b. Contract Documents
c. Bidding Assistance
d. Value Engineering Process
e. Submittal Review and Construction Observation.
2. Scope of Systems Designed:
The above -listed services will apply to the electrical systems listed below.
Electrical:
Exterior site lighting systems including "sports" type pole light fixtures and
controls. Specific care will be given to the selection of fixture characteristics
such as lamp color temperature, aesthetics, camera mounting options and
control systems. All new lighting shall feature LED lamp technology.
New lighting controls. Options will be explored and considered prior to final
specification such as pushbuttons, astronomical clock timers and wireless
apps. Controls will include a hand -off -auto switch for manual override of
lighting systems.
iii. Electrical power distribution system for all new fixtures including conduit,
wiring and overcurrent protection.
iv. Additional electrical service capacity for future park lighting expansion.
V. Empty conduit system for Owner furnished equipment where necessary. This
includes new security and/or data provided under a separate contract.
3. Fee:
The fee for the above described services is proposed as a Fixed Fee of Four Thousand Five
Hundred Dollars ($4,500) for our portion of the work. Additional services that you may request
will be provided on an hourly basis utilizing the following hourly rates:
Principal Engineer
$165
Project Engineer
$135
Designer
$80
Administration
$50
If this proposal is acceptable please sign in the space provided and return a copy for my files. If
you have any questions or need additional information, please contact me.
Sincerely,
Shane R. Lanning, P
Engineering Eleme s, PLLC
K
9-1-,qp
Date
City of Fayetteville, Arkansas - Budget Adjustment Form (Legistar)
Budget Year Division PARKS & RECREATION (520) Adjustment Number
2020 /Org2
Requestor: Alan Bearden
BUDGET ADJUSTMENT DESCRIPTION / JUSTIFICATION:
BUDGET ADJUSTMENT DESCRIPTION / JUSTIFICATION: To transfer funds within the Community Park Improvements
project (13001) designated in 2020 CIP for Walker Park Skateboard Area lighting improvements to a new sub -project
(13002.2001) specifically for this planned project work.
COUNCIL DATE: 9/1 /2020
LEGISTAR FILE ID#: 2020-0671
Holly Buck.
811212020 9:25 AM
Budget Director Date
TYPE: D - (City Council)
JOURNAL #:
9/1/2020
GLDATE:
RESOLUTION/ORDINANCE
CHKD/POSTED:
TOTAL
- -
v.20200528
Increase / (Decrease)
Proiect.Sub#
Account Number
Expense Revenue
Project Sub.Detl AT
Account Name
2250.520.9255-5806.00
(98,000)
13001 1 EX
Improvements - Park
2250.520.9255-5301.00
500
13001 2001 EX
Public Notification
2250.520.9255-5806.00
97,500
13001 2001 EX
Improvements - Park
HABudget Adjustments\2020_Budget\City Council\09-01-2020\2020-0671 BA Walker Park