HomeMy WebLinkAbout215-20 RESOLUTION113 West Mountain Street Fayetteville, AR 72701 (479) 575-8323 Resolution: 215-20 File Number: 2020-0680 HAYNES PUMP AND PROCESS, LLC: A RESOLUTION TO APPROVE CHANGE ORDER NO. 1 TO THE CONTRACT WITH HAYNES PUMP AND PROCESS, LLC FOR AERATION BASIN GATES AT THE NOLAND WATER RESOURCE RECOVERY FACILITY IN THE AMOUNT OF $5,761.88 WHEREAS, on February 4, 2020, the City Council passed Resolution 42-20 to approve a contract with Haynes Pump and Process, LLC for the purchase of two sealing slide gates for the aeration basin at the Noland Water Resource Recovery Facility; and WHEREAS, during the detailed fabrication drawings it was determined the gates needed to increase by 8 inches in length and 4 inches in height to ensure adequate clearance; and WHEREAS, the change order represents the increased cost of the larger dimensions. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS: Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves Change Order No. 1 to the Contract with Haynes Pump and Process, LLC for aeration basin gates at the Noland Water Resource Recovery Facility, in the amount of $5,761.88. A copy of Change Order No. 1 is attached to this Resolution and made a part hereof. PASSED and APPROVED on 9/1/2020 Page 1 Printed on 912120 Resolution: 215-20 File Number: 2020-0680 Attest: ````���rtrt►ri�rr / R K v • ;••U �Ala'4 I'A Kara Paxton, City Clerk Treasurer' •;�ANSAS �y i�ON i COO 0 Page 2 Printed on 9/2/20 W City of Fayetteville, Arkansas 113 West Mountain Street Fayetteville, AR 72701 (479) 575-8323 i Text File File Number: 2020-0680 Agenda Date: 9/1/2020 Version: 1 Status: Passed In Control: City Council Meeting File Type: Resolution Agenda Number: A. 1 HAYNES PUMP AND PROCESS, LLC: A RESOLUTION TO APPROVE CHANGE ORDER NO. I TO THE CONTRACT WITH HAYNES PUMP AND PROCESS, LLC FOR AERATION BASIN GATES AT THE NOLAND WATER RESOURCE RECOVERY FACILITY IN THE AMOUNT OF $5,761.88 WHEREAS, on February 4, 2020, the City Council passed Resolution 42-20 to approve a contract with Haynes Pump and Process, LLC for the purchase of two sealing slide gates for the aeration basin at the Noland Water Resource Recovery Facility; and WHEREAS, during the detailed fabrication drawings it was determined the gates needed to increase by 8 inches in length and 4 inches in height to ensure adequate clearance; and WHEREAS, the change order represents the increased cost of the larger dimensions. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS: Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves Change Order No. 1 to the Contract with Haynes Pump and Process, LLC for aeration basin gates at the Noland Water Resource Recovery Facility, in the amount of $5,761.88. A copy of Change Order No. 1 is attached to this Resolution and made a part hereof. City of Fayetteville, Arkansas Page 1 Pdnted on 2=020 City of Fayetteville Staff Review Form 2020-0680 Legistar File ID 9/1/2020 City Council Meeting Date - Agenda Item Only N/A for Non -Agenda Item Tim Nyander 8/12/2020 WASTEWATER TREATMENT (730) Submitted By Submitted Date Division / Department Action Recommendation: Staff recommends approval of Change Order No. 1 with Haynes Pump and Process, LLC to increase the contract amount by $5,761.88 for the Noland aeration basin gate fabrication. Budget Impact: 5400.730.5800-5801.00 Water and Sewer Account Number Fund 02032.1 WWTP - Building Improvements Project Number Project Title Budgeted Item? Yes Current Budget $ 3,887,656.00 Funds Obligated $ 2,786,539.60 Current Balance $ 1,101,116.40 Does item have a cost? Yes Item Cost $ 5,761.88 Budget Adjustment Attached? No Budget Adjustment $ - Remaining Budget $ 1,095,354.52 V20180321 Purchase Order Number: 2020-246 Previous Ordinance or Resolution # -12 20 Change Order Number: Original Contract Number: Comments: 1 Approval Date: CITY OF FAYETTEVILLE %PF ARKANSAS MEETING OF SEPTEMBER 1, 2020 TO: Mayor and City Council THRU: Susan Norton, Chief of Staff Tim Nyander, Utilities Director FROM: Corey Granderson, Utilities Engineer CITY COUNCIL MEMO DATE: August 12, 2020 SUBJECT: Approval of Change Order No. 1 to the purchase of two (2) sealing slide gates for the aeration basin at the Noland Water Resource Recovery Facility RECOMMENDATION: Staff recommends approval of Change Order No. 1 with Haynes Pump and Process, LLC to increase the contract amount 5 761.88. BACKGROUND: On June 181h, 2019, Fayetteville City Council approved Resolution 142-19, an engineering services contract with Jacobs Engineering to design the replacement of two large aeration -basin gates located under a reinforced concrete slab at the Noland WRRF. These gates are original to the aeration facility, are inaccessible, and are leaking. Replacement is necessary so that the plant may remain fully operational and have the ability to isolate each of the two aeration basin treatment trains. Resolution 42-20, passed on February 4, 2020, awarded Bid #19-61 to Haynes Pump and Process, LLC in the amount of $32,150.00 plus tax for the purchase of two sealing slide gates for the aeration basin at the Noland Water Resource Recovery Facility. DISCUSSION: The labor for installation will be publicly bid at a later date, to coincide with lower -flow operations at the WRRF. The gates require a long fabrication lead-time and will be purchased directly by the city in advance and stored onsite. Bids for the gate fabrication were opened on December 17th, 2019 with Haynes Pump and Process, LLC submitting a low -bid of $35,284.63 after taxes. As the design progressed and Haynes provided detailed fabrication shop drawings, it was determined that the gates needed to increase by 8-inches in length and 4-inches in height to ensure adequate clearance from the existing gates' mounting hardware. The costs associated with the larger fabrication dimensions is $5,761.88 as represented by this change order, including taxes. This increases the overall gate cost to $41,046.50. Mailing Address: 113 W. Mountain Street www.fayetteville-ar.gov Fayetteville, AR 72701 BUDGET/STAFF IMPACT: Funds are available in the Wastewater Treatment Plant — Building Improvements project. Attachments: Change Order No. 1 Haynes' Change Order Quote CHANGE ORDER _CITY OF FAYETTEVILLE A R K A N S A S Contract Title. Bid 19-61, Aeration Basin Gate Fabrication Change Order No. I Date of Issuance: August 3, 2020 To Contractor Haynes Pump and Process, LLC The Contract is changed as follows: ORDINANCErR ESOLLITION: 4 2-20 Effective: February 4.2020 Bid Bid Previous Knit Contract Revised Revised Original Revised Item Item Estimated of Unit Estimated Unit Estimated Estimated No. Description Quantity Measure Price Quantity Price Cost Cost I Basin Gate 2 FA S 16,07500 2 S 18,700.00 S32,150.00 $37,400 00 Taxes S3,134 63 $3,646 50 Summation of Cost $35,284.63 $41,046.50 Net Cost for this Change Order S5,761.88 Not valid until signed by the Owner The original Contract Price was S35,284.63 Net change by previously authorized change ordersThe Contract Price prior to this Change Order was S 35,284.63 The Contract Price will [increase by] ] _ -- --� $ 5,761.88 The new Contract Price including this Change Order will be S 41,046.50 The Contract Time(s) will jinefeased hylideeFensed hyl(remain unchanged) n/a calendar days Required dates of Completion as of the date of this Change Order therefore are: Substantial Completion _ _ _ nJa Final Completion ah NOTE: This summary does not reflect changes in the Contract Price or Time(s) which have,been aulhorized� Work Change Dire \�es not incorporated in this or previous Change Orders. // Haynes Pump and Pro, , L Cl Ati �2 Y DATE Y Page 1 of 1 DATE Haynes Pump and Process, LLC. Equipment for New and Used Water 417 Main Street, 400-3 Little Rock, AR 72201 Phone 800-832-1580 Date: Bill To: City of Fayetteville Job Number: 113 W Maintain Street Job Name: Fayetteville, AR 72701 HPP PM: Customer PO #: Change Order Form 7/20/2020 420-0006 Fayetteville/Noland Gates Wes Ivory/Lisa Mills 2020-00000246 CO NUMBER CO Date DESCRIPTION CO Amount 1 7/20/20 Increasing width by 8' and height by 4" - Additional Cost $5,250.00 2 7/20/20 Additional Taxes $4-2489- Miscalculated @8% 9.75% Tax = $511.88 ,Reviewed by Corey Granderson Utilities Engineer j cgranderson@fayetteville-ar.gov 479-444-3452 Change Order Sub -Total 1$5.761.8c 5 0_710.111C ORIGINAL CONTRACT AMOUNT $35,284.63 PREVIOUS CHANGE ORDERS $0.00 AMOUNT THIS CHANGE ORDER !$5,761.88 $&,&70.go REVISED CONTRACT AMOUNT $41,046.50 $4863 O� fpYFrTF' r 4Rkd NS pS 113 West Mountain Street Fayetteville, AR 72701 (479) 575-W23 Resolution: 42-20 File Number: 2020-0058 BID #19-61 HAYNES PUMP AND PROCESS, LLC: A RESOLUTION TO AWARD BID 19-61 AND AUTHORIZE THE PURCHASE OF TWO SEALING SLIDE GATES FOR THE AERATION BASIN AT THE NOLAND WATER RESOURCE RECOVERY FACILITY FROM HAYNES PUMP AND PROCESS, LLC IN THE AMOUNT OF $32,150.00 PLUS APPLICABLE TAXES AND FREIGHT CHARGES BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS: Section 1: That the City Council of the City of Fayetteville, Arkansas hereby awards Bid # 19-61 and authorizes the purchase of two sealing slide gates for the Noland Water Resource Recovery Facility from Haynes Pump and Process, LLC in the amount of $32,150.00 plus applicable taxes and freight charges. PASSED and APPROVED on 2/4/2020 Attest: ``mA1LItrr1►11" RK .`�•. • G17 Y o;..`rG�. •rn— Kara Paxton, City Clerk Treasu#r�*- "YETTEVILLE:x_ IiO N i1liki"o Page 1 Printed on 2/6/20