Resolution: 139-20
File Number: 2020-0360
CRAFTON, TULL AND ASSOCIATES, INC. AMENDMENT NO. 1- 2019
TRANSPORTATION BOND PROGRAM:
A RESOLUTION TO APPROVE AMENDMENT NO. 1 TO THE CONTRACT WITH CRAFTON, TULL
AND ASSOCIATES, INC. FOR THE RUPPLE ROAD EXTENSION PROJECT IN THE AMOUNT OF
$9,500.00, AND TO APPROVE A BUDGET ADJUSTMENT
- 2019 TRANSPORTATION BOND PROGRAM
WHEREAS, on July 16, 2019, the City Council passed Resolution 167-19 to approve a Contract with
Crafton, Tull and Associates, Inc. for the design of Rupple Road; and
WHEREAS, the contract did not include construction phase services.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves Amendment No. 1
to the Contract with Craft, Tull and Associates, Inc. for construction phase services related to the Rupple
Road Project, in the amount of $9,500.00. A copy of Amendment No. 1 is attached to this Resolution
and made a part hereof.
Section 2: That the City Council of the City of Fayetteville, Arkansas herby approves a budget
adjustment, a copy of which is attached to this Resolution.
PASSED and APPROVED on 5/19/2020
Page 1 Printed on 5119120
Resolution. 139-20
File Number 2020-0360
Attest: ��t� I I I I rrrr����
61 Y ox" •sG'%
FAYETTEVILLE
Kara Paxton, City Clerk TreasureP
NS
NGTONw�`���`�.
Page 2 Printed on 5119120
City of Fayetteville, Arkansas 113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
Text File
-� File Number: 2020-0360
Agenda Date: 5/19/2020 Version: 1 Status: Agenda Ready
In Control: City Council Meeting
Agenda Number: A 4
File Type: Resolution
CRAFTON, TULL AND ASSOCIATES, INC. AMENDMENT NO. 1- 2019 TRANSPORTATION
BOND PROGRAM:
A RESOLUTION TO APPROVE AMENDMENT NO. 1 TO THE CONTRACT WITH CRAFTON,
TULL AND ASSOCIATES, INC. FOR THE RUPPLE ROAD EXTENSION PROJECT IN THE
AMOUNT OF $9,500.00, AND TO APPROVE A BUDGET ADJUSTMENT - 2019
TRANSPORTATION BOND PROGRAM
WHEREAS, on July 16, 2019, the City Council passed Resolution 167-19 to approve a Contract with
Crafton, Tull and Associates, Inc. for the design of Rupple Road; and
WHEREAS, the contract did not include construction phase services.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves Amendment No. 1 to
the Contract with Craft, Tull and Associates, Inc. for construction phase services related to the Rupple Road
Project, in the amount of $9,500.00. A copy of Amendment No. 1 is attached to this Resolution and made a
part hereof.
Section 2: That the City Council of the City of Fayetteville, Arkansas herby approves a budget adjustment, a
copy of which is attached to this Resolution.
City of Fayetteville, Arkansas Page 1 Printed on 511912020
Matt Casey
Submitted By
City of Fayetteville Staff Review Form
2020 0360
5/19/2020
City Council Meeting Date - Agenda Item Only
N/A for Non -Agenda Item
4/22/2020 ENGINEERING (621)
Submitted Date Division / Department
Action Recommendation:
Approval of a contract amendment for construction phase services in the amount of $9,500 with Crafton, Tull and
Associates, Inc. for the Rupple Rd. Extension (Tanyard to Weir) and approval of a budget adjustment
4602.860.7210-5860.02
Account Number
46020.7210.2000
Project Number
Budgeted Item? Yes
Does item have a cost? Yes
Budget Adjustment Attached? Yes
Purchase Order Number:
Change Order Number:
Original Contract Number:
Comments:
2019-00000610
2019-00000030
Budget Impact:
4602 - Street Projects (2019 Bonds)
Fund
Rupple Rd Extension - Tanyard to Weir Rd - North
Current Budget
Funds Obligated
Current Balance
Item Cost
Budget Adjustment
Remaining Budget
Project Title
$
1,307,340.00
$
69,617.88
$
1,237,722.12
$
9,500.00
$
9,500.00
I $
1,237,722.12
Previous Ordinance or Resolution #
Approval Date:
V20180321
167 19
CITY OF
FAYETTEVILLE
ARKANSAS
MEETING OF MAY 19, 2020
TO: Mayor and City Council
THRU: Susan Norton, Chief of Staff
Garner Stoll, Development Services Director
Chris Brown, City Engineer
FROM: Matt Casey, Engineering Design Manager
DATE: April 22, 2020
CITY COUNCIL MEMO
SUBJECT: Approval of a contract amendment for construction phase services in the
amount of $9,500 with Crafton, Tull and Associates, Inc. for the Rupple Rd.
Extension (Tanyard to Weir) and approval of a budget adjustment.
RECOMMENDATION:
Staff recommends approval of a contract amendment for construction phase services in the
amount of $9,500 with Crafton, Tull and Associates, Inc. for the Rupple Rd. Extension (Tanyard
to Weir) and approval of a budget adjustment.
BACKGROUND:
On July 16, 2019, the City Council approved a contract with Crafton, Tull and Associates, Inc.
for the design of Rupple Road. The project continues the roadway from the north end of the
construction of Rupple Road that is part of the Magnolia Park Subdivision. The City has a cost
share agreement with the developer of that subdivision for the construction through their
development north of Tanyard Drive. The City's design contract with Crafton, Tull and
Associates continues the roadway north from the development and connects to both portions of
Weir Road to complete the Rupple Road connection from MLK Blvd. to Howard Nickel Drive.
On April 7, 2020, the City Council awarded the construction contract to Emery Sapp and Sons,
Inc. The contractor will begin construction by June of 2020.
DISCUSSION:
The approved contract with Crafton, Tull and Associates does not include construction phase
services. Staff has worked with Crafton, Tull and Associates to develop a scope that will include
support for the contractor and city staff as needed through the construction of this project In
addition, they will provide as -built plans at the end of the job documenting any field changes
made during construction. Crafton, Tull and Associates. has provided a fee in the amount of
$9,500.00 for this additional work. The contract will be paid based on hourly rates for work
completed, up to the total contract amount.
BUDGET/STAFF IMPACT:
The construction of the roadway improvements and this contract amendment are funded by the
2019 Transportation Bond Program.
Mailing Address:
113 W. Mountain Street www.fayetteville-ar.gov
Fayetteville, AR 72701
Attachments:
CTA Proposal
Vicinity Map
Ar
Scale: 1" = 300'
PROPOSED -
DESIGN
-- _
_—__----- _. AREA
It
i
[ '1 &UEG ASS Puct
�i E•: � � t a e
6 r
8 - PROJECT
A + LOCATION
i
North Rupple Road North Rupple Road
CD
CD A10
4 t.}
o a
o
.,, _ ... North Salem Road ♦ eu
F O
CL
AMENDMENT NO. 1 TO OWNER -ENGINEER AGREEMENT
Subject of Amendment: Additional Services
1. Background Data:
a. Effective Date of OWNER -ENGINEER Agreement: 7/16/2019
b. OWNER: City of Fayetteville, Arkansas
C. ENGINEER: Crafton. Tull & Associates, Inc.
d. Project: Rupple Road Extension
2. Nature of Amendment
■ Additional Services to be performed by ENGINEER:
• Construction phase support: provide on -call support to the City of Fayetteville as requested
throughout the construction phase. May include site meetings and production of plan modifications.
Does not include day to day construction observation/inspection. Fee based on 210 calendar day
construction duration.
• As -built survey: obtain field measurements for storm sewer and water appurtenances as required by
the City of Fayetteville.
• As -built drawings: Prepare and deliver modifications to the construction drawings based on field
notes and as -built survey data of storm structures and at -grade water appurtenances.
■ Modifications to Payment to ENGINEER
3. Description of Modifications
See Attachment I, "Modifications"
OWNER and ENGINEER hereby agree to modify the above -referenced Agreement as set forth in this Amendment. All
provisions of the Agreement not modified by this or previous Amendments remain in effect. The Effective Date of this
Amendment is O 5 / 1 a / 9-
OWNER:
C
B
T
Date Signed: 5 / ot / 3_0
EJCDC No. E-501
1999 Edition
ENGINEER:
CRAFTON, TULL & ASSOCIATES, INC.
By: A
Bill Burnett, P.E.
Title: Vice President
Date Signed: 4/14/20
Page I of 2
ATTACHMENT I
MODIFICATIONS
Additional Services to be performed by ENGINEER:
1. On -Call construction support
2. As-Built/Record Drawings
Modifications to Payment to ENGINEER:
The OWNER shall pay ENGINEER for the Additional Services set forth above an amount equal to the
cumulative hours charged to the Project by each class of the ENGINEER's employees times Standard Hourly Rates for
each applicable billing class for all services performed on the Project, plus Reimbursable Expenses charged at cost times
a 1.15 multiplier and ENGINEER's consultants charged at cost times a 1.05 multiplier, if any consultants are included.
Standard Hourly Rates shall be those shown in the attached Exhibit "B". The compensation for the Additional Services
described herein is estimated to be $ 9,500 . Following is the total estimated distribution of compensation:
Basic Services $ 110,400
Additional Services, Item 1 $ 6,000
Additional Services, Item 2 $ 3,500
Total Estimated Compensation $ 119,900
EJCDC No. E-501
1999 Edition
Page 2 of 2
City of Fayetteville, Arkansas - Budget Adjustment Form (Legistar)
Budget Year Division Adjustment Number
/Org2 ENGINEERING (621)
2020
Requestor: Matt Casey
BUDGET ADJUSTMENT DESCRIPTION / JUSTIFICATION:
Approval of a contract amendment for construction phase services in the amount of $9,500 with Crafton, Tull and
Associates, Inc. for the Rupple Rd. Extension (Tanyard to Weir) and approval of a budget adjustment.
Contract: 2019-00000030
RESOLUTION/ORDINANCE
COUNCIL DATE: 5/19/2020
LEGISTAR FILE ID#: 2020-0360
xeAspYbnw-*-
412212020 10:10 AM
Budget Director
TYPE:
JOURNAL #:
Date
D - (City Council)
GLDATE: 5/19/2020
CHKD/POSTED: /
TOTAL - -
v.20200324
Increase / (Decrease) Project.Sub#
Account Number Expense Revenue Project Sub.Detl AT Account Name
4602.860.7210-5860.02 9,500 46020 7210.2000 EX Capital Prof Svcs - Engineering
4602.860.7999-5899.00 (9,500) 46020 7999 EX Unallocated - Budget
H:\Budget Adjustments\2020_Budget\City Council\05-19-2020\BA 2020-0360 Rupple Rd. Extension Contract Amendment 1 of 1