Resolution: 142-20
File Number: 2020-0385
WATERSHED CONSERVATION RESOURCE CENTER TASK ORDER NO. 5:
A RESOLUTION TO APPROVE TASK ORDER NO. 5 WITH THE WATERSHED CONSERVATION
RESOURCE CENTER IN THE AMOUNT OF $60,000.00 FOR STREAMBANK RESTORATION
PROJECTS ON THE WHITE RIVER AND NIOKASKA CREEK, AND TO APPROVE A PROJECT
CONTINGENCY IN THE AMOUNT OF $9,000.00
WHEREAS, on January 3, 2019, the City Council approved Ordinance No. 6141 waiving competitive
bidding and approving a Memorandum of Understanding with the Watershed Conservation Resource Center
for a tern of five years to establish a general framework of cooperation to seek funding, conduct
stream restoration projects, and to work together on nonpoint source related issues.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Jordan
to sign Task Order No. 5 with the Watershed Conservation Resource Center in the amount of
$60,000.00 for streambank restoration projects on the White River and Niokaska Creek, and further
approves a project contingency in the amount of $9,000.00.
PASSED and APPROVED on 5/19/2020
Page 1 Printed on 5119120
Resolution: 142-20
File Number 2020-0385
Attest:
�� •' GAS Y 0' .G;,p
YETTEVILLE
Kara Paxton, City Clerk Treasufpr
.,�'ZYGION11
Page 2 Printed on 5119120
City of Fayetteville, Arkansas 113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
i
\ Text File
\ File Number: 2020-0385
Agenda Date: 5/19/2020 Version: 1 Status: Agenda Ready
In Control: City Council Meeting File Type: Resolution
Agenda Number: A. 7
WATERSHED CONSERVATION RESOURCE CENTER TASK ORDER NO. 5:
A RESOLUTION TO APPROVE TASK ORDER NO. 5 WITH THE WATERSHED CONSERVATION
RESOURCE CENTER IN THE AMOUNT OF $60,000.00 FOR STREAMBANK RESTORATION
PROJECTS ON THE WHITE RIVER AND NIOKASKA CREEK, AND TO APPROVE A PROJECT
CONTINGENCY IN THE AMOUNT OF $9,000.00
WHEREAS, on January 3, 2019, the City Council approved Ordinance No. 6141 waiving competitive
bidding and approving a Memorandum of Understanding with the Watershed Conservation Resource Center
for a term of five years to establish a general framework of cooperation to seek funding, conduct stream
restoration projects, and to work together on nonpoint source related issues.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Jordan to sign
Task Order No. 5 with the Watershed Conservation Resource Center in the amount of $60,000.00 for
streambank restoration projects on the White River and Niokaska Creek, and further approves a project
contingency in the amount of $9,000.00.
City of Fayetteville, Arkansas Page 1 Primed on 511912020
Tim Nyander
Submitted By
City of Fayetteville Staff Review Form
2020-0385
Legistar File ID
5/19/2020
City Council Meeting Date - Agenda Item Only
N/A for Non -Agenda Item
5/1/2020
Submitted Date
Action Recommendation:
WASTEWATER TREATMENT (730)
Division / Department
Staff recommends the approval of a maintenance agreement with the Watershed Conservation Resource Center
(WCRC) for streambank restoration projects on the White River and Niokaska Creek in an amount not to exceed
$60,000.00, and approval of a project contingency in the amount of $9,000.00.
Budget Impact:
5400.730.5800-5818.00
Water and Sewer
Account Number Fund
13018.1 Wastewater Treatment/Water Quality
Improvements
Project Number
Budgeted Item? Yes
Does item have a cost? Yes
Budget Adjustment Attached? No
Current Budget
Funds Obligated
Current Balance
Item Cost
Budget Adjustment
Remaining Budget
Project Title
$
914,641.00
$
60,321.95
$
854,319.05
$
69,000.00
$ 785,319.05
V20180321
Purchase Order Number: Previous Ordinance or Resolution #
Change Order Number:
Original Contract Number:
Comments:
Approval Date:
CITY OF
FAYETTEVILLE
ARKANSAS
MEETING OF MAY 19, 2020
TO: Mayor and City Council
THRU: Susan Norton, Chief of Staff
FROM: Tim Nyander, Utilities Director
DATE: May 1, 2020
CITY COUNCIL MEMO
SUBJECT: Annual Maintenance Task Order for Streambank Restoration
RECOMMENDATION:
Staff recommends the approval of a maintenance agreement with the Watershed Conservation
Resource Center (WCRC) for streambank restoration projects on the White River and Niokaska
Creek in an amount not to exceed $60,000.00, and approval of a project contingency in the
amount of $9,000.00.
BACKGROUND:
The WCRC performed four riverbank restoration projects for the Utility. Two are located on the
White River, one is located on Niokaska Creek, and one is located on the West Fork of the White
River.
DISCUSSION:
The WCRC will perform ongoing maintenance on three of these sites, targeted to maintain and
improve the long-term functionality of the riverbank restoration projects that were implemented
utilizing Utilities Department funding. These services include two major components:
(1) Riverbank restoration maintenance activities that help to create long-term stability:
✓ Minor hand repairs of structural components of the restoration
✓ Removal of unintended gravel deposition within the project site
✓ Repair of soil mattresses.
(2) Vegetation Management:
✓ Irrigation of vegetation during summer months
✓ Removal of invasive vegetation
✓ Planting additional native plants to enhance vegetation density and increase riverbank
roughness
Repair of damage to the projects resulting from large infrequent flood events are generally not
covered under this agreement and will be addressed under supplemental agreements.
Mailing Address:
113 W. Mountain Street www.fayetteville-ar.gov
Fayetteville, AR 72701
The City also intends on removing the Pump Station Dam in the future. Pre -implementation
planning and coordination will be required in order to develop a comprehensive plan for
removing the dam and restoring the river both upstream and downstream of the dam. This
agreement will provide funding to allow the WCRC to utilize their expertise to assist with the
planning process, which include coordination and planning for backwater sediment sampling
and developing a bid request package for biological sampling of the pre -restoration conditions
above and below the dam site.
BUDGET/STAFF IMPACT:
Funds are available in the Wastewater Treatment/Water Quality Improvements account within
the Water and Sewer Fund.
Attachments:
Task Order No. 5
THE CITY OF FAYETTEVILLE, ARKANSAS
TASK ORDER NO. 5
VEGETATION AND CHANNEL STABILITY ESTABLISHMENT AT
FAYETTEVILLE UTILITIES DEPARTMENT FUNDED STREAM AND
RIVER RESTORATION PROJECT SITES
STATE OF ARKANSAS
COUNTY OF WASHINGTON
This Task Order is written pursuant to the Memorandum of Understanding (MOU) as
described in Ordinance No. 6141 executed on January 3, 2019- The referenced MOU
pertains to stream restoration projects and associated services with the Watershed
Conservation Resource Center (WCRC). This Task Order entered into and executed on the
date indicated below the signature block by and between the City of Fayetteville (City) and
WCRC sets forth the project description, schedule and associated fees for services related
to maintaining and tending to stream and river restoration projects that were implemented
using a combination of Utilities Department and grant -based funds and provide assistance
for planning future restoration projects.
Section I - Project Description
This project consists of ongoing maintenance of two riverbank restorations and one stream
restoration whose original implementation was funded, in -part, with the City's Utilities
Department or the site provides protection of critical civil infrastructure. This Task Order will
establish a framework to provide continued project establishment funds to support the work
performed on riverbanks on the White River at the Noland Wastewater Treatment Plant and
a former bio-solids application site. A restoration site at Sweetbriar Park that protects a
high-pressure main and park property from erosion will also be maintained through this task
order. To date, implementation of the two projects on the White River have resulted in the
prevention of 34,000 lb of Total Phosphorus from entering the regions drinking water supply
source. Establishing and fostering a high -density riparian zone consisting of native
vegetation is critical in creating riverbank restoration projects that will, upon maturity of the
vegetation, be able to withstand the power of future flood events. Also, minor repairs need
to be occasionally conducted to prevent cumulative degradation of the restoration projects.
This agreement will provide funding to the WCRC to conduct activities that help to continue
to establish healthy, native vegetation and riverbank stability in order to protect the
investment that the City has made to improve water quality, habitat, and recreational value
of these sites. The City also intends on removing the Pump Station Dam in the future. Pre -
implementation planning and coordination will be required in order to develop a
comprehensive plan for removing the dam and restoring the river both upstream and
downstream of the dam. This agreement will provide funding to allow the WCRC to utilize
their expertise to assist with the planning process.
Section II - Project Timeframe
The WCRC will conduct the work from May 20, 2020 to May 19, 2021.
THE CITY OF FAYETTEVILLE, ARKANSAS
Section III - Scope of Services
The WCRC will perform services to maintain and improve the long-term functionality of the
riverbank restoration projects on the White River that were implemented utilizing Utilities
Department Funding. These services include two major components: 1) maintenance
activities that help to create long-term stability and 2) vegetation management. Riverbank
restoration maintenance activities include but will not be limited to a) minor hand repairs of
structural components of the restoration b) removal of unintended gravel deposition within
the project site and c) repair of soil mattresses. Vegetation management activities include
but are not limited to a) irrigation of vegetation during summer months b) removal of
invasive vegetation and c) planting additional native plants to enhance vegetation density
and increase riverbank roughness. These funds are intended to cover costs associated
with minor and routine maintenance of the sites. Repair of damage to the projects resulting
from large infrequent flood events are generally not covered under this agreement and will
be addressed under supplemental agreements. But, if necessary, these funds can be used
towards major repairs. In addition to the activities listed above, this task order also allows
the WCRC to provide professional services related to planning and assistance in executing
various tasks associated with the Pump Station Dam removal pre -implementation phase of
work. Example activities include coordination and planning for backwater sediment
sampling and developing a bid request package for biological sampling of the pre -
restoration conditions above and below the dam site.
Section IV - Fees and Payments
WCRC will perform the above -referenced Scope of Services amounts not to exceed
$60,000.
Section V - Memorandum of Understanding in Effect
Except as amended specifically herein, the Memorandum of Understanding Fayetteville
shall remain in full force as originally approved.
IN WITNESS WHEREOF, the parties hereto have caused this TASK ORDER to be duly
executed as of the date and year first herein written.
FOR THkCITY qF F�YETTfVILLE
LaWAaW..tid Jordan
Date:
G . Y
Attest: Z1121= FAYETTEVILLE :
Kara Paxton, City Clerk
NGTON0,G�
FOR W TERSHED CONSERVATION RESOUCE CENTER
By: Attest:
Sandi Formica
Date: nR Ai 1 2y�p
Tim Nyander
Submitted By
WATERSHED CONSERVATION RESOURCE CENTER
CHANGE ORDER NO. 1
TASK ORDER NO. S
City of Fayetteville Staff Review Form
2021-0763
Legistar File ID
N/A
City Council Meeting Date - Agenda Item Only
N/A for Non -Agenda Item
9/29/2021 WASTEWATER TREATMENT (730)
Submitted Date Division / Department
Action Recommendation:
Staff recommends approval of Change Order No. 1 to Task Order No. 5 with the Watershed Conservation Resource
Center to extend the contract term until March 31, 2022.
Budget Impact:
N/A
Account Number
N/A
Project Number
N/A
Fund
N/A
Project Title
Budgeted Item? No Current Budget
Funds Obligated
Current Balance
Does item have a cost? No Item Cost
Budget Adjustment Attached? No Budget Adjustment
Remaining Budget
V20210527
Purchase Order Number: Previous Ordinance or Resolution # 142-20
Change Order Number: Approval Date: 10/4/21
Original Contract Number:
Comments:
CITY OF
FAYETTEVILLE
ARKANSAS
TO: Mayor Lioneld Jordan
THRU: Susan Norton, Chief of Staff
FROM: Tim Nyander, Utilities Director
DATE: September 29, 2021
STAFF MEMO
SUBJECT: Watershed Conservation Resource Center — Change Order No. 1 to Task
Order No. 5
RECOMMENDATION:
Staff recommends approval of Change Order No. 1 to Task Order No. 5 with the Watershed
Conservation Resource Center to extend the contract term until March 31, 2022.
BACKGROUND:
Task Order No. 5 was approved on May 19, 2020 by Resolution 142-20 for streambank
restoration projects on the White River and Niokaska Creek. The expiration date of Task Order
No. 5 was May 19, 2021.
DISCUSSION:
The Watershed Conservation Resource Center (WCRC) was not able to complete the work by
this timeframe because the weather conditions and a high White River stage level prevented the
work from being done at this time. Staff requests approval of a contract change order to extend
the contract term until March 31, 2022. This will allow WCRC to accomplish the contract work
for Task Order No. 5.
BUDGET/STAFF IMPACT:
No budget impact for the contract term extension.
Attachments:
Change Order No. 1 to Task Order No. 5
Resolution 142-20
Mailing Address:
113 W. Mountain Street www.fayetteville-ar.gov
Fayetteville, AR 72701
CHANGE ORDER NO. I TO TASK ORDER NO. 5
WHEREAS, on May 19, 2020, as authorized by Resolution No. 142-20, the City of
Fayetteville ("City") and Watershed Conservation Resource Center ("WCRC") entered Task
Order No. 5 for streambank restoration projects on the White River and Niokaska Creek; and
WHEREAS, Task Order No. 5 provides that the work will be conducted from May 20,
2020 to May 19, 2021 and the associated purchase order has an expiration date to match the
contract; and
WHEREAS, weather conditions and a high White River stage level prevented WCRC
from completing the project by the end of the contract term; and
WHEREAS, WCRC has informed the City that the work will be completed by March
31, 2022.
NOW, THEREFORE, BE IT KNOWN TO ALL:
That the City and WCRC, on this day of , 2021, hereby agree to
modify Section II — Project Timeframe of Task Order No. 5 and extend the completion date of
the project to March 31, 2022. No additional costs are associated with this Change Order.
IN WITNESS WHEREOF, the parties hereto have caused their signatures to be set by
their authorized representative effective the date set forth herein above.
WATERSHED CONSERVATION
RESOURCE CENTER
By:
Sandi Formica, Executive Director
CITY OF FAYETTYAqLLE, ARKANSAS
ayor
ATTEST:
K
By:
Kara Paxton, Ci C e" Leasure
r*ti
. FAYcT7'tVILLE
G ,ON"�, ```��
Date: J e pt S, �-, Z-0 Z I
Date: /0 ^ "—/— 21
Date: 10
CHANGE ORDER NO.2 TO TASK ORDER NO.5 WITH
WATERSHED CONSERVATION RESOURCE CENTER
City of Fayetteville Staff Review Form
2022-1074
Legistar File ID
N/A
City Council Meeting Date - Agenda Item Only
N/A for Non -Agenda Item
Tim Nyander 11/16/2022 WASTEWATER TREATMENT(730)
Submitted By Submitted Date Division / Department
Action Recommendation:
Staff recommends approval of Change Order No. 2 to Task Order No. 5 with the Watershed Conservation Resource
Center to extend the contract term until March 31, 2023.
Budget Impact:
N/A N/A
Account Number Fund
N/A N/A
Project Number
Budgeted hem? No
Does item have a cost? No
Budget Adjustment Attached? No
Project Title
Current Budget
$
Funds Obligated
$
Current Balance
Item Cost
$
Budget Adjustment
$
Remaining Budget
V 0210527
Purchase Order Number: Previous Ordinance or Resolution v 142-20
Change Order Number: Approval Date: 11/17/2022
Original Contract Number:
Comments: