HomeMy WebLinkAbout61-20 RESOLUTION113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
Resolution: 61-20
File Number: 2020-0039
DOUBLE SPRINGS DEVELOPMENT, LLC:
A RESOLUTION TO APPROVE A COST SHARE AGREEMENT WITH DOUBLE SPRINGS
DEVELOPMENT, LLC FOR THE UPSIZING OF A SEWER LINE IN THE GOOSE CREEK
VILLAGE SUBDIVISION WITH AN AMOUNT NOT TO EXCEED $72,976.00 TO BE PAID BY THE
CITY OF FAYETTEVILLE, AND TO APPROVE A PROJECT CONTINGENCY IN THE AMOUNT OF
$14,595.20
WHEREAS, Boston Mountain Holdings, LLC is developing the 126 acre Goose Creek Villa, Phase ,1 which
will require the installation of an 8 -inch sewer main to service the development; and
WHEREAS, the Utilities Department recommends upsizing to a 15 -inch diameter sewer main per the
City's Wastewater Collection System Master Plan; and
WHEREAS, § 51.113 of the Fayetteville City Code provides that "the City shall pay the excess material
cost of facilities of a size larger than required to service subdivisions when such excess size is specified
and required by the water and wastewater director for the general benefit of the sewerage system."
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Jordan
to sign a cost share agreement with Double Springs Development, LLC for the upsizing of a sewer line
with an amount not to exceed $72,976.00 to be paid by the City of Fayetteville, and further approves
a project contingency in the amount of $14,595.20.
Page 1 Printed on 2020
File Number.' 2020-0039
Resolution 61-20
PASSED and APPROVED on 2/4/2020
Attest:
`����nrrr►rrr�
...... T����z
Kara Paxton, City Clerk Treasure���y. •CITY'
C F •G=
Page 2 Printed on 216120
City of Fayetteville, Arkansas 113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
<� Text File
File Number: 2020-0039
Agenda Date: 2/4/2020 Version: 1 Status: Passed
In Control: City Council Meeting File Type: Resolution
Agenda Number: C. 1
DOUBLE SPRINGS DEVELOPMENT, LLC:
A RESOLUTION TO APPROVE A COST SHARE AGREEMENT WITH DOUBLE SPRINGS
DEVELOPMENT, LLC FOR THE UPSIZING OF A SEWER LINE IN THE GOOSE CREEK VILLAGE
SUBDIVISION WITH AN AMOUNT NOT TO EXCEED $72,976.00 TO BE PAID BY THE CITY OF
FAYETTEVILLE, AND TO APPROVE A PROJECT CONTINGENCY IN THE AMOUNT OF
$14,595.20
WHEREAS, Boston Mountain Holdings, LLC is developing the 126 acre Goose Creek Villa, Phase 1 which
will require the installation of an 8 -inch sewer main to service the development; and
WHEREAS, the Utilities Department recommends upsizing to a 15 -inch diameter sewer main per the City's
Wastewater Collection System Master Plan; and
WHEREAS, § 51.113 of the Fayetteville City Code provides that "the City shall pay the excess material cost
of facilities of a size larger than required to service subdivisions when such excess size is specified and required
by the water and wastewater director for the general benefit of the sewerage system."
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Jordan to sign a
cost share agreement with Double Springs Development, LLC for the upsizing of a sewer line with an amount
not to exceed $72,976.00 to be paid by the City of Fayetteville, and further approves a project contingency in
the amount of $14,595.20.
City of Fayetteville, Arkansas Page 1 Printed on 2/5/2020
City of Fayetteville Staff Review Form
2020-0039
Legistar File ID
2/4/2020
City Council Meeting Date - Agenda Item Only
N/A for Non -Agenda Item
Tim Nyander 1/14/2020 WATER SEWER (720)
Submitted By Submitted Date Division / Department
Action Recommendation:
Staff recommends the approval of a cost share agreement with Double Springs Development, LLC in an amount not
to exceed $72,976.00 for the upsizing of a sewer line in the Goose Creek Village subdivision, and approval of a
project contingency in the amount of $14,595.20.
5400.720.5700-5815.00
Account Number
04039.1
Project Number
Budget Impact:
Water and Sewer
Fund
Water/Sewer Impact Fee Cost Sharing
Project Title
Budgeted Item? Yes Current Budget
Funds Obligated
Current Balance
Does item have a cost? Yes Item Cost
Budget Adjustment Attached? No Budget Adjustment
Remaining Budget
$ 3,849,049.00
$ 3,849,049.00
$ 87,571.20
$ 3,761,477.80
V20180321
Purchase Order Number: Previous Ordinance or Resolution #
Change Order Number:
Original Contract Number:
Comments:
Approval Date:
0
CITY OF
FAYETTEVILLE
ARKANSAS
MEETING OF FEBRUARY 4, 2020
TO: Mayor and City Council
THRU: Susan Norton, Chief of Staff
FROM: Tim Nyander, Utilities Director
DATE: January 14, 2020
CITY COUNCIL MEMO
SUBJECT: Cost Share Agreement with Double Springs Development, LLC for Upsizing
a Sewer Line in Goose Creek Village Subdivision
RECOMMENDATION:
Staff recommends the approval of a cost share agreement with Double Springs Development,
LLC in an amount not to exceed $72,976.00 for the upsizing of a sewer line in the Goose Creek
Village subdivision, and approval of a project contingency in the amount of $14,595.20.
BACKGROUND:
Double Springs Development, LLC is developing the 126 -acre Goose Creek Village, Phase 1
subdivision on the west side of Double Springs Rd. in Farmington. They are required to install an
8 -inch sanitary sewer main for the development, but the City of Fayetteville's Wastewater
Collection System Master Plan recommends a 15 -inch sanitary sewer main in that location.
DISCUSSION:
The developer received three bids for construction with Gene Nicholas, LLC being the lowest
bidder. Staff recommends approval of a cost share agreement with Goose Creek Development,
LLC in an amount not to exceed $72,976.00 to pay the difference in upsizing the sewer line from
8 -inch to 15 -inch diameter, and approval of a 20% project contingency in the amount of
$14,595.20.
BUDGET/STAFF IMPACT:
Funds are available in the Water/Sewer Impact Fee Cost Sharing account within the Water and
Sewer Fund.
Attachments:
Cost Share Agreement
Exhibit A — Map of Area
Exhibit B — Request Letter and Contractor Estimate
Engineering Plans
Mailing Address:
113 W. Mountain Street www.fayetteville-argov
Fayetteville, AR 72701
CONTRACTUAL AGREEMENT FOR
COST SHARE OF SEWER MAIN INSTALLATION COSTS
This Agreement, made and entered into on this IJ
of February, 2020, by and between
the City of Fayetteville, Arkansas ("City") and Double Springs Development, LLC, witnesseth:
WHEREAS, Double Springs Development, LLC is developing property known as Goose
Creek Village, Phase 1 in the City of Farmington and is required to construct an offsite 8 -inch
sewer line to facilitate the development which will be served by the City of Fayetteville's sewer
system; and
WHEREAS, the City's Wastewater Collection System Master Plan recommends a 15 -inch
sewer line in this area to provide capacity for future development; and
WHEREAS, constructing this segment of sewer main will allow Double Springs
Development, LLC to obtain sewer service to develop the property known as Goose Creek Village,
Phase 1, allow the City to upsize the sewer line from 8 -inch to 15 -inch to follow the
recommendation of the City's Wastewater Collection System Master Plan, and also allow for
ample future capacity which the City recognizes will be necessary for the area that is served by
this sewer main.
NOW, THEREFORE, the City of Fayetteville, Arkansas and Double Springs
Development, LLC agree as follows:
1. The City of Fayetteville, Arkansas agrees to:
A. Reimburse Double Springs Development, LLC for 100% of the cost to upsize the
required 8 -inch sewer main to 15 -inch sewer main in the area identified in Exhibit
"A" up to a maximum -not -to -exceed amount of $72,976.00, as was estimated by
the builder's representatives and shown on Exhibit `B", attached.
B. Payments due to Double Springs Development, LLC, shall be remitted within sixty
(60) days after receipt of valid invoices upon completion of the project.
2. Double Springs Development, LLC agrees to:
A. Provide the necessary and normal project management, inspection, and testing as
necessary for a complete and acceptable sewer main installation, including
submittal of plans and specifications to the City's Engineering Department, per
their standard procedures.
B. Submit all required plans and specifications to the City and receive approval from
the City's Engineering and Utilities Departments prior to commencing work on the
project.
C. Provide a copy of the invoices from the Contractor upon City approval of the sewer
main installation.
D. Pay for the sewer main installation (with reimbursement from the City of
Fayetteville not to exceed $72,976.00).
IN AGREEMENT WITH ALL THE TERMS AND CONDITIONS ABOVE, WE
SIGN BELOW:
DOUBLE SPRINGS DEVELOPMENT,
LLC
By:
D RIGGINS,
anaging Member
By: L I )�
KEVIN GGINS,
Managing Member
ATTEST:
CITY OF FAYETTEVILLE,
ARKANSAS /
ATTEST:
By: / w1a
KARA PAXTON, City Clerk
EXHIBIT A
611
*j
[;uusr t:rA:
PROPOSED SEWER LINE
EXHIBIT B
J O RG E N S E N 124 W Sunbridge Drive, Suite 5
Fayetteville, AR 72703
+ASSOCIATES Fax:4 479.442.9127
Fax: 479.582.4807
t"T) Civil Engineering + Surveying www.jorgensenassoc.com
December 17, 2019
City of Fayetteville
Water & Sewer Operations
2435 S Industrial Drive
Fayetteville, AR 72701
Attn: Corey Granderson, PE
RE: Goose Creek Sewer Cost Share Agreement Proposal
As you know, we have been working on the residential development of 126 acres on the west side of Double
Springs Road owned by Red Canyon LLC. This development, when fully built -out, will provide approximately 335
residential lots. To provide sewer service to this development, an offsite sewer approximately 1220' long will be
constructed to the newer pump station on Double Springs Road. This development only requires an 8" sewer
main to service this development at full build -out. However, this extension was analyzed in a future capacity
study by the City of Fayetteville and shown to require a 15" sewer main to service future development in the
area.
We have created construction documents that have been reviewed by the City of Fayetteville and are in the final
stages of the approval process. We received bids on the extension from three different contractors, who
provided both the 8" extension bids and the alternate 15" extension bids. Those bids are included herewith.
Gene Nicholas LLC was selected to be the contractor on this project. The difference between their 8" and 15"
offsite sewer bids is $72,976.00. We are requesting the City of Fayetteville pay this difference to upsize the
sewer extension to the requested 15" main. The City will not pay anything until the main is installed, tested and
approved. The developer will pay the contractor and the City will reimburse their amount after completion of
the line.
The work on this line will not be started until the construction plans are approved by the City of Fayetteville and
the Health Department.
Your consideration of this cost share is greatly appreciated.
Sincerely,
91
Jared S. Inman, PE
Page 1 of 1
Unit Price Schedule for
Goose Creek Village, Phase 1
8" Sanitary Sewer (Offsite Sewer) Alternate Bid
SELECTED CONTRACTOR
Water & Sewer
SWEETSER
DECCO
Gene Nicholas
Item # Description
Quantity
Unit Unit Price
Amount Quantity
Unit Unit Price
Amount
Juantity
Unit Unit Price
Amount
1
8" Sanitary Sewerline SDR-26 PVC
1287
LF
$54.50
$70,141.50
1287
LF
$48.54
$62,470.98
1287
LF
$42.00
$54,054..00
2
Manhole
9
EA
$3700.00
$33,300.00
9
EA
$7,016.28
$63,146.52
9
EA
$5,100.00
$45,900.00
3
Clean & Test
1
L.S.
$2 400.00
$2,400.00
1
L.S.
$12,251.71
$12,251.71
1
L.S.
$4,500.00
$4,500.00
4
Bond
1
L.S.
$3,700.00
$3,700.00
1
L.S.
$5,649.27
$5,649.2
1
L.S.
$3 SOO.00
$3,500.00
5
Rock Excavation
375
CY
$275.00
$103,125.00
375
CY
$206.39
$77,396.25
375
CY
$200.00
$75,000.00
6
16" Steel Encasement
150
L.F.
$140.00
$21,000.00
150
L.F.
$164.60
$24,690.00
150
L.F.
$150.00
$22,500.00
7
Class 7 Backfill @ Street Crossings)
250 Tons
$24.00
$6,000.00
250 Tons
$59.32
$14,830.00
250 Tons
$17.50
$4,375.00
8
Oen Cut/Repair Double Springs Rd 2 locations
1
L.S.
$28,000.00
$28,000.00
2
EA
$6 652.68
$13,30S.3
1
L.S.
$14,000.00
$14,000.00
9
Traffic Control
1
L.S.
$10,000.00
$10,000.00
1
L.S.
$4,817.32
$4,817.32
1
L.S.
$4,500.00
$4,500.00
10
Temporary Barbwire Fence 3 Strand
900
L.F.
$15.00
$13,500.00
900
L.F.
$16.67
$15,003.00
900
L.F.
$9.00
$8,100.00
11
Construction Entrance 2 locations
1
L.S.
$4 200.00
$4,200.00
1
L.S.
$6,876.84
$6,876.84
1
L.S.
$1440.00
$1,440.00
12
Rip Rap
100 Tons
$75.00
$7,500.00
100 Tons
$121.90
$12,190.00
100 Tons
$45.00
$4 500.00
13
lErosion Control
11
L.S.
$2 500.00
$2,500.00
1
L.S.
$15,747.38
$15,747.38
1
L.S.
$4 500.00
$4,500.00
14
Com tete Site Restoration (includingha /seed
1
L.S.
$4,500.00
$4,50000
1
L5.
$29,232.65
$29,232.65
1
L.S.
$7 500.00
$7,500.00
Total 1
$309,866.50
ITotal I
$357,607.28
Total
$254,369.00
Unit Price Schedule for
Goose Creek Village, Phase 1
15" Sanitary Sewer (Offsite Sewer) Alternate Bid
Water & Sewer
SWEETSER
DECCO
Gene Nichols
Item # Description
Quantity
Unit Unit Price
Amount Quantity
Unit Unit Price
Amount
luantity
Unit Unit Price
Amount
1
15" Sanitary Sewerline SDR-26 PVC
1287
LF
$68.00
$87,516.00
1287
LF
$75.40
$97,039.80
1287
LF
$65.00
$83,655.00
2
Manhole 4' Dia.Epoxy Coat Interior
9
EA
$4,500.00
$40 500.00
9
EA
$9,859.80
$88,738.20
9
EA
$5,100.00
$45,900.00
3
Clean & Test
1
L.S.
$2,400.00
$2,400.00
1
L.S.
$17,152.53
$17,152.53
1
L.S.
$4,500.00
$4,500.00
4
Bond
1
L.S.
$4,800.00
$4,800.00
1
L.S.
$7,920.11
$7,920.11
1
L5.
$3,500.00500.00
5
Rock Excavation
475
CY
$275.00
$130,625.00
475
CY
$207.08
$98363,00
475
CY
$200.0000.00
6
30" Steel Encasement 0.375" thickness
150
L.F.
$400.00
$60,000.00
160
L.F.
$330.31
$52,849.60
150
L.F.
$300.0000.00
7
Class 7 Backfill @ Street Crossings)
300 Tons
$24.00
$7,200.00
300 Tons
$61.03
$18,309.00
300 Tons
$17.5050.00
8
Oen Cut/Re air Double Springs Rd 2 locations
1
L.S.
$28,000.00
$28,000.00
2
EA
$9,410.69
$18,821.38
1
L.S.
$14,000.0000.00
9
Traffic Control
1
L.S.
$10,000.00
$10,000.00
1
L.S.
$6,423.15
$6,423.15
1
L5.
$4,500.0000.00
10
Temporary Barbwire Fence 3 Strand
900
L.F.
$15.00
$13,500.00
900
L.F.
$16.67
$15,003,00
900
L.F.
$9.00100.00
11
Construction Entrance 2 locations
1
L.S.
$4,200.00
$4,200.00
1
L.S.
$6,876.89
$6,876.89
1
L.S.
$1440.0040.00
12
RipRa
100 Tons
$75.00
$7,500.00
100 Tons
$121.90
$12,190.00
100 Tons
$45.0000.00
13
Erosion Control
1
L.S.
$2,500.00
$2,500.00
1
L.S.
$15,747.51
$15,747.51
1
L.S.
$4,500.0000.00
14
Complete Site Restoration (including ha /seed
1
L.S.
$4 500.00
$4,500.00
1
L.S.
$29 232.88
$29 232.88
1
L.S.
$7,500.00500.00
Total
$403,241.00
Total
$484,667.05
Total
45.00
Construc
�ti
"on Plans
/
GOOSE CREEK VILLAGE
SUBDIVISION PHASE 1
FARMINGTON,ARKANSAS
INCLUDING
WATER, SEWER, STREETS,
GRADING, & STORM DRAINAGE
AUGUST 2019
OWNER / DEVELOPER
GOOSE CREEK VILLAGE PHASE 1 DEVELOPMENT LLC
1204 E JOYCE BLVD.
FAYETTEVILLE. AR 72703
PREPARED FIYc
JORGENSEN
}Ml
�
+ASSOCIATES
!Wa En ilrnnM1g • SurveyMp wwrJc
ats
mDn0riMEFi1
Gad Gawp NW
nm awnusaxunnAT
c,m maemrxrnAT
ctm ftm,iuw[Rura
e,d armrz ttrrta ua ww i comae
C,.OS WATERT eEwFA44mmee ran. 1
c,Aa
WATERa sEww IK " nex a more[
C,m WeRRaiPWFRIR gAnimmiE
e,d weTm a sEWtR,sf nwa mane
c,d sTnEfl vux i ramal
n.,s man vw, a mane
aL„ 6TREfl nAxemmae rtpCpEpm
n. naw.+muw manes ormrm
v, a.0 rsAaraimosax mxnoa nAA
esm ttnaea W1rzR a s ft us I
4am TwYxwaTm esEWEa wonus }
esm TmcuwrmasEwEA oe,uas
cxa TYRGL sTR[n i owuaE Daus,
'� ' aJrs TMale s,ssTioRuurt onus} cevse uusr
= MttLLitAfflaaRMUGEaw
C!A) TACLLmO3ANC0!IIRW aflalf
00.00
\�•," iii / �i :v
i �///■� � �//®� :Ido o - _ - --
/11 111 .
G— 1, KAL.e I I €
---_---_---„�.----_--- L_ F c2e
---- _-------.----------
35 T—v—:w
WZ
W E IW79 U;
19 ji..W37..._.j. _7-:7 °— - 0
I - r^
I...... ._.sM._. —.
20 I I I I I ..1 I I i t ,°«11
al
ama°�,w
L. •” ue
@ zu,so
.....:.,v. ....;........
s
49laI
46
191 z7
I°
I I 2s
2e ,a..«. l'x... I �:,.....I. s:
21
I
i W
ns
n
k II
44
ai..... P ,�
I�
/ �. _ - -'L _ yti • _ — _ testi
16
µc11.02
- - ------------ - --
-Eli
wf E WU
s "O
--L—V aw-
oo"
fl/
I
�% N
S
GRAPHIC SCALE
Goose Creek Sewer Cost Share Agreement
City of Fayetteville Staff Review Form
2023-0015
I[N/A
ARCHIVED
N/A
City Council Meeting Date - Agenda Item Only
N/A for Non -Agenda Item
Tim Nyander 1/4/2023
WATER SEWER (720)
Submitted By Submitted Date
Division / Department
Action Recommendation:
Staff recommends approval to use contingency funds in the amount
Share with Double Springs Development, L.I.C.
Goose Creek Sewer Cost
Budget Impact:
5400.720.5700-5815.00
Water and Sewer
Account Number
Fund
04039.1
Water & Sewer Impact Fee Cost Sharing
Project Number
Project Title
Budgeted Item? Yes
Total Amended Budget
$ 1,348,760.00
Expenses (Actual+Encum)
$ 719,196.53
Available Budget
$ 629,563.47
Does item have a direct cost? Yes
Item Cost
$ 14,595.20
Is a Budget Adjustment attached? No
Budget Adjustment
$ -
Remaining Budget
$ 614,968.27
Purchase Order Number: 2020-248
Change Order Number:
Original Contract Number:
Comments:
Previous Ordinance or Resolution # 61-20
Approval Date: 01/05/2023
Pb.CITY OF
FAYETTEVILLE
ARKANSAS
TO:
Mayor Lioneld Jordan
THRU:
Susan Norton, Chief of Staff
FROM:
Tim Nyander, Utilities Director
DATE:
January 4, 2023
SUBJECT: Contingency for Goose Creek Sewer Cost Share
STAFF MEMO
RECOMMENDATION:
Staff recommends approval to use contingency funds in the amount of $14,595.20 for the
Goose Creek Sewer Cost Share with Double Springs Development, LLC.
BACKGROUND:
Resolution 61-20, passed on February 4, 2020, approved a cost share agreement with Double
Springs Development, LLC for a sewer cost share for the development of Goose Creek Villa,
Phase 1. The cost share agreement included a not -to -exceed amount of $72,976.00 for the
upsizing of the planned 8 -inch sewer infrastructure to 15 -inch diameter per the City's
Wastewater Collection System Master Plan. A contingency was also approved by City Council
in the amount of $14,595.20.
DISCUSSION:
During construction, the developer hit large amounts of rock when excavating. The estimated
rock excavation was 475 cubic yards, and the actual amount of rock that had to be excavated
was 1,646 cubic yards. There were also some encasement end seals that were needed that
were not a part of the original construction estimate. Staff recommends approval to utilize
contingency funds in the amount of $14,595.20 to assist the developer in paying for the
additional rock excavation and the encasement end seals.
BUDGETISTAFF IMPACT:
Funds are available in the Water & Sewer Impact Fee Cost Sharing account.
Attachments:
Cost Share Agreement Certification
Change Order No. 1 (for the Mayor's signature)
Resolution 61-20
Mailing Address:
113 W. Mountain Street www.fayettevllle-ar.gov
Fayetteville, AR 72701
CHANGE ORDER
CITY OF
r AKANSA VILLE
ARRKANSAS Contract Title: Goose Creek 15 -inch Sewer Cost Share
Change Order No. I Date of Issuance: December 9, 2022
To Contractor: Double Springs Development, LLC
The Contract is changed as follows:
ORDINANCFJRESOLUTION: 61-20
Effective: February 4, 2020
Bid
Bid
Previous
Unit
Contract
Revised
Revised
Original
Revised
Item
Item
Estimated
of
Unit
Estimated
Unit
Estimated
Estimated
No.
Description
Quantity
Measure
Price
Quantity
Price
Cost
Cost
COI .1
Encasement End Seals
0
EA
$
8
S 1.133.16
$0.00
$9,065.28
COI .2
Rock Excavation
0
LS
$
I
$ 5.529.92
$0.00
$5,529.92
Summation of Cost $0.00 $14.59520
Net Cost for this Change Order $14,595.20
I tie Original Uontract rote was
Net change by previously authorized change orders
The Contract Price prior to this Change Order was
The Contract Price will [increase by] ]
The new Contract Price including this Change Order will be
The Contract Time(s) WillIremain unchanged]
Required dates of Completion as of the date of this Change Order therefore are:
Substantial Completion
Final Completion
NOTE: This sunnily does not reflect changes in the Contract Price or Times) which have been authorized by Work Change Directives not incorporated in this or
previous Change Orders.
Double Spn flvelopment, LLC
4 / member 1211212022
BW DAIL
CIT OF FAME VIL
/I la or 01/05/2023
BY DATE
Page 1 of 1
£,JORGENSEN
+ASSOCIATES
December 19, 2022
City of Fayetteville Utilities Dept.
24355 Industrial Drive
Fayetteville, AR 72701
Attn: Shea Fankhouser
Re: Goose Creek Phase I — Cost Share Agreement for Sanitary Sewer Extension
Dear Shea;
124 W Sunbridge Drive. Suite 5
Fayetteville, AR 72703
Office: 479442.9127
Fax: 4795824807
www orgensenassoccom
Below is the breakdown of costs associated with the Goose Creek Ph I Offsite Sanitary Sewer Extension
that includes engineering fees. The final pay app (Pay App #13) is included as an attachment to this
letter.
Item #
Description
Unit
Unit Price
Qty
Extended Price
1
1555 (SDR-26 PVC)
LF
$ 65.00
1287
$ 83,655.00
2
Manhole (4' Dia. Epoxy Coated)
EA
$ 5,100.00
9
$ 45,900.00
3
Clean & Test
LS
$ 4,500.00
1
$ 4,500.00
4
Bond
IS
$ 3,500.00
1
$ 3,500.00
5
Rock Excavation
a
$ 200.00
1646.47
$ 329,294.00
6
30" Steel Encasement
LF
$ 300.00
150
$ 45,000.00
7
CL -7 Backfill @ Street Crossings
Ton
$ 17.50
300
$ 5,250.00
8
Open Cut/Repair Double Springs Road (2 -Lacs)
IS
$ 14,000.00
1
$ 14,000.00
9
Traffic Control
IS
$ 4,500.00
1
$ 4,500.00
10
Temp Barbed Wire Fence (3 -strand)
LF
$ 9.00
900
$ 8,100.00
11
Construction Entrance (2 -Locations)
IS
$ 1,440.00
1
$ 1,440.00
12
Rip Rap
Ton
$ 45.00
123
$ 5,535.00
13
Erosion Control
IS
$ 4,500.00
1
$ 4,500.00
14
Complete Site Restoration (Hay & Seed)
IS
$ 7,500.00
1
$ 7,500.00
15
Engineering Fees
IS
$ 20,222.00
1
$20,222.00
Total = $ 582,896.00
Please let us know if you have any questions or comments.
Sincerely;
red S. Inm n, P.E.