HomeMy WebLinkAbout09-20 RESOLUTION113 West Mountain Street Fayetteville, AR 72701 (479)575-8323 Resolution: 09-20 File Number: 2019-0931 SWEETSER CONSTRUCTION, INC. CHANGE ORDER NO. 1: A RESOLUTION TO APPROVE CHANGE ORDER NO. 1 TO THE CONTRACT WITH SWEETSER CONSTRUCTION, INC. FOR THE OLD WIRE ROAD PROTECTED BIKE LANE AND SIDEWALK PROJECT IN THE AMOUNT OF $246,488.85, AND TO APPROVE A BUDGET ADJUSTMENT WHEREAS, on March 6, 2018, the City Council passed Resolution 76-18 to approve a Contract with Sweetser Construction, Inc. for construction of the Old Wire Road Protected Bike Lane and Sidewalk Project; and WHEREAS, the change order includes an increase in project cost of $269,018.95 for Schedule 1 which is the 2006 Transportation Bond Fund and a decrease in cost of $22,530.10 for Schedule 2 which is the Water and Sewer Fund. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS: Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves Change Order No. 1 to the contract with Sweetser Construction, Inc. for the construction of the Old Wire Road Protected Bike Lane and Sidewalk Project in the amount of $246,488.85. A copy of Change Order No. 1 is attached to this Resolution and made a part hereof. Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget adjustment, a copy of which is attached to this Resolution. Page 1 Printed on 119120 File Number- 2019-0931 Resolution 09-20 PASSED and APPROVED on 1/7/2020 Attest: O` CLERK Kara Paxton, City Clerk Treasurer ; F-c�•��cn • Ir • %2•. NS AS .• .� Page 2 Printed on 119120 City of Fayetteville, Arkansas 113 West Mountain Street Fayetteville, AR 72701 (479) 575-8323 Text File File Number: 2019-0931 Agenda Date: 1/7/2020 Version: 1 Status: Passed In Control: City Council Meeting File Type: Resolution Agenda Number: A. 10 SWEETSER CONSTRUCTION, INC. CHANGE ORDER NO. 1: A RESOLUTION TO APPROVE CHANGE ORDER NO. 1 TO THE CONTRACT WITH SWEETSER CONSTRUCTION, INC. FOR THE OLD WIRE ROAD PROTECTED BIKE LANE AND SIDEWALK PROJECT IN THE AMOUNT OF $246,488.85, AND TO APPROVE A BUDGET ADJUSTMENT WHEREAS, on March 6, 2018, the City Council passed Resolution 76-18 to approve a Contract with Sweetser Construction, Inc. for construction of the Old Wire Road Protected Bike Lane and Sidewalk Project; and WHEREAS, the change order includes an increase in project cost of $269,018.95 for Schedule 1 which is the 2006 Transportation Bond Fund and a decrease in cost of $22,530.10 for Schedule 2 which is the Water and Sewer Fund. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS: Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves Change Order No. 1 to the contract with Sweetser Construction, Inc. for the construction of the Old Wire Road Protected Bike Lane and Sidewalk Project in the amount of $246,488.85. A copy of Change Order No. 1 is attached to this Resolution and made a part hereof. Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget adjustment, a copy of which is attached to this Resolution. City of Fayetteville, Arkansas Paye 1 Printed on 1/812020 City of Fayetteville Staff Review Form 2019-0931 Legistar File ID 1/7/2020 City Council Meeting Date - Agenda Item Only N/A for Non -Agenda Item Matt Casey 12/13/2019 ENGINEERING (621) Submitted By Submitted Date Division / Department Action Recommendation: Approval of Change Order #1 in the amount of $246,488.85 for the construction of the Old Wire Road Protected Bike Lane & Sidewalk Project. The change order includes an increase in project cost of $269,018.95 for Schedule 1 which is the Transportation Bond Fund and a decrease in cost of $22,530.10 for Schedule 2 which is the Water and Sewer Fund and approval of a budget adjustment. 5400.720.5600-5808.00 4520.800.9556-5809.00 Account Number 06035.2600 Project Number Budgeted Item? Yes Does item have a cost? Yes Budget Adjustment Attached? Yes Budget Impact: Water and Sewer Fund Transportation Bond Street Improvements Fund Old Wire Road (Mission to 265) Current Budget Funds Obligated Current Balance Item Cost Budget Adjustment Remaining Budget Project Title $ 12,403,158.00 $ 10,171, 844.03 $ 2,231,313.97 $ 246,488.85 $ 269,019.00 $ 2,253,844.12 V20180321 Purchase Order Number: 2018-00000286 Previous Ordinance or Resolution # Change Order Number: Approval Date: Original Contract Number: Comments: CITY OF CD FAYETTEVILLE WNWARKANSAS MEETING OF JANUARY 7, 2020 TO: Mayor and City Council THRU: Don Marr, Chief of Staff Garner Stoll, Development Services Director Chris Brown, City Engineer FROM: Matt Casey, Engineering Design Manager DATE: December 18, 2019 CITY COUNCIL MEMO SUBJECT: Approval of Change Order #1 in the amount of $246,488.85 for the construction of the Old Wire Road Protected Bike Lane & Sidewalk Project. RECOMMENDATION: Staff recommends City Council approval of Change Order #1 in the amount of $246,488.85 for the construction of the Old Wire Road Protected Bike Lane & Sidewalk Project. The change order includes an increase in project cost of $269,018.95 for Schedule 1 which is the 2006 Transportation Bond Fund and a decrease in cost of $22,530.10 for Schedule 2 which is the Water and Sewer Fund. BACKGROUND: At the March 6, 2018 meeting the City of Fayetteville City Council approved a contract with Sweetser Construction, Inc. for the construction of this project. This project included storm sewer improvements, curb and gutter, a two-way cycle track and a 5' wide sidewalk along the east side of Old Wire Road. The Walton Family Foundation provided a 50/50 matching grant that paid $1,361,428.00 towards the construction of the cycle track along this project. DISCUSSION: City staff worked with the contractor to provide a quality project for the city as well as all of the property owners along the project. During the construction of this project, there were many adjustments and changes that were required given the complexity and nature of this type of project. These changes, while necessary to create a quality end product, resulted in additional construction costs. Major changes that resulted in additional costs include: • An overlay of the entire width of Old Wire Road instead of just the east half as originally designed • Placing extra thickness of asphalt at Township to avoid total removal and reconstruction of the roadway, thereby reducing the inconvenience to the traveling public • Additional driveway removal and replacement to create more comfortable slopes into and out of properties • Additional retaining wall construction to protect adjacent properties Mailing Address: 113 W. Mountain Street www.fayetteville-ar.gov Fayetteville, AR 72701 Secondly, the construction period exceeded the contract time by 200 days. Giving consideration to the field changes made during construction as well as the number of weather days experienced, the contractor was credited with 80 days of additional time. According to the contract agreement the contractor is to pay $750 for each additional day required to complete the project over the days allowed in the contract. This amounts to a $90,000 credit to the City. BUDGET/STAFF IMPACT: The roadway, cycle track, sidewalk and storm sewer portions of this project are funded by the Transportation Bond Fund and the grant from the Walton Family Foundation. The water and sewer relocations in this project are funded by the Water and Sewer Fund. The change order includes an increase in project cost of $269,018.95 for Schedule 1 which is the 2006 Transportation Bond Fund and a decrease in cost of $22,530.10 for Schedule 2 which is the Water and Sewer Fund. A budget adjustment will be required in the amount of $269,019 and will come from recognizing unallocated bond interest and closing out prior bond retainage. Attachments: Change Order 1 Vicinity Map CHANGE ORDER CITY OF EVILLE ARKANSAS Contract Title: Old Wire Road Protected Bike Lane& Sidewalk Project (Ash St. to Gulley Park) Change Order No. Reconciliation Change Order Date of Issuance December 11, 2019 To Contractor. Sweetser Construction, Inc. ORDINANCVMOLU7'ION: The Contract is changed as follows: Effective December 11, 2019 Bid Item Bid Iran Descri hon No. P Estimated Previous Quantity Unit of Measure Concttact Unit Price Revised Esdrr�ated Quantity Revised Unit Price Original Estimated Cost Revised Estimated Cost 1 Mobilization 1 IS $90.000.00 0 $0.00 $90,000.00 $0.00 6 R&D Existing Storm Sewer 726 LF $10.00 752 $10.00 $7,260.00 $7,520.00 7 R&D Existing Curb and Gutter 1805 LF 1 $10.00 1817 $10.00 $18,050.00 $18,170.00 8 R&D Existing Asphalt Pavement 1156 SY $10.00 2119 $10.00 $11,560.00 $21,190.00 9 R&D Existing Concrete Pavement 1600 SY $10.00 176 $10.00 $16,000.00 $1,760.00 10 R&D Existing Concrete Driveway 628 SY $10.00 713 _ $10.00 $6,280.00 $7,130.00 13 R&D Existing 6' WoodPrivacy Fence 605 1 LF $5.00 944 $5.00 $3,025.00 $4,720.00 14 Remove and Salvage xishng - Rail White Fence 360 LF 1 $10.00 0 $10.00 $3.600.00 $0.00 16 Existing Saw gign and Return to Owner 19 EA $100.00 7 $100.00 $1,900.00 $700.00 19 R&D Existing Concrete Sidewalk 645 SY $10.00 1 649 $10.00 $6.450.0D $6,490.00 24 Rock Excavation 100 CY $225.00 37.4 $225.00 $22,500.00 $8,415.00 26 4" Topsoil Placement 10200 SY 1 $4.50 13075.22 $4.50 $45.900.00 $58,838.49 27 *Undercut and Stone Backfill 100 CY $38.00 0 $38.00 $3,800.00 $0.00 28 1 " R , Class R Under Pavement 398 LF $50.00 73 $50.00_ $19,900.00 $3,650.00 29 18" RCP, Class X 1613 IF $43.00 1863 $43.00 $69,359.00 $80,109.00 30 24s RCP, Class Ill, nder Pavement 302 LF $77.00 105 $77.00 $23,254.00 $8,085.00 31 24" RCP, Class M 920 IF $66.00 1253 1 $66.00 $60,720.00 $82,698.00 32 30" RCP, Class M l 1 IF $90.00 7.5 $90.00 $990.00 $675.00 34 36" RCP, Class 111 114 IF $151.50 110 $151.50 $17,271.00 $16,665.00 35 42" RCP, Class M 19 LF $17250 24 $172.50 $3,277.50 $4,140.00 36 Class III, 1n Pavement 168 LF $213.00 115 $213.00 $35,784.00 $24,495.00 37 48" RCP, Class lit 547 LF $177.50 619 $177.50 $97,09250 $109,872.50 38 18" RCP FES w/Curtain Wall 8 EA $850.00 7 $850.00 $6,800.00 $5,950.00 39 Concrete Collar (Connection to Existing Storm Sewer) 3 EA $200.00 1 $200.00 $600.00 $200.00 41 5' DLA. Drop Inlet 2 EA $3.800.00 3 $3,800.00 $7,600.00 $11,400.00 50 17 Nyloplast Drain Basin with Grate 2 EA $1.800.00 _ 3 $1,800.00 $3,600.00 $5,400.00 51 12" ADS N12 Storm Sewer Pipe 112 LF $34.00 132 $34.00 $3,808.00 $4,488.00 53 Rip Rap wl Filter Blanket 25 SY $75.00 150.11 $75.00 $1,875.00 $11,258.25 54 Pavement Milting 7821 SY $2.90 4316 $2.90 $22,680.90 $12,516.40 55 Class 7 Aggregate Base Course 1269 TON $28.00 1587.07 $28.00 $35,532.00 $44,437.96 56 HMAC Surface Course (PG70-22) 1255 TON $77.30 2278.82 $77.30 $97,011.50 $176,152.79 57 HMAC Binder Course (PG70.22) 261 TON $73.85 1334.27 $73.85 $19,274.85 $98,535.84 58 Asphalt Concrete Patching for Maintenance of Traffic 75 TON $125.00 94.19 $125.00 $9,375.00 $11,773.75 59 Aggregate ase or way Maintenance 50 TON $28.00 50.79 $28.0(1 $1,40(1.00 $1,422.12 Page 1 of 4 Bid hem Bid hem Description Previous Estimated Unit of Contract Revised Estimated Revised Unit Original Revised Estimated Cost No. Quantity Measure Unit Price Quantity Price Estimated Cost 60 Asphalt Street T -Patch _ 250 SY $75.00 263.53 $75.00 $18,750.00 $19,764.75 Class B 40WPSI tete 61 Pavement (For Road Widening) 545 SY $52.00 831.94 $52.00 $28,340.00 $43,260.88 62 18" Concrete Curb & Gutter 5880 LF _ $14.00 6767 $14.00 $82,320.00 $94,738.00 63 24" Concrete Curb & Gutter 428 LF $14.00 500 $14.00 $5,992.00 $7,000.00 64 Stamped Concrete Buffer 1620 SY $136.18 1555 $136.18 $220,611.60 $211,759.90 4' Concrete Cycle Tra w ass 65 7 Base 4900 SY $45.00 4241 $45.00 $220,500.00 $190,845.00 Concrete Stdewailt w ass 66 Base 2300 SY $45.00 3351 $45.00 $103,500.00 $150,795.00 Wide Concrete Sidewalk 67 Turndown 40 LF $20.00 42 $20.00 $800.00 $840.00 oncrete Dnveway w/Class 7 68 Base 940 SY $56.00 2222.99 $56.00 $52,640.00 $124,487.44 71 Modular Block Retaining Wall 4450 SF $48.00 5944 $48.00 $213,600.00 $285,312.00 Brown Washed Ever Rock with 72 Fabric 345 SY $35.00 164.36 $35.00 $12,075.00 $5,752.60 73 Furnish and Install Mailbox 19 EA $200.00 20 $200.00 $3,800.00 $4,000.00 74 Solid Sod 10200 SY $4.00 13075.22 $4.00 $40,800.00 $52,300.88 75 6' Wood Privacy Fence 940 LF $30.00 1054 $30.00 $28.200.00 $31,620.00 76 2 Rail Wood Fence 70 LF $25.00 0 $25.00 $1,750.00 $0.00 77 Ameristar Fence 363 LF $50.00 393 $50.00 $18,150.00 $19,650.00 78 Temporary Chain Link Fence 100 LF $26.00 608 $26.00 $2,600.00 $15,808.00 Tree Protection Fencing (Use as 79 Directed) 500 LF $5.00 0 $5.00 $2,500.00 $0.00 24" Solid White Pavement 80 Marking (Thermoplastic) 44 LF $25.00 46 $25.00 $1,100.00 $1,150.00 Brick Panem Pavement Maddag 81 (7hervtoplastic) 192 SF $35.00 178.25 $35.00 $6,720.00 $6,238.75 8 Solid Yellow Pavement - 82 Marking (Paint) 4250 LF $5.00 0 $5.00 $21,250.00 $0.00 6 olid White Pavement - 83 Markings (Thernmplastic) 940 LF $1.25 1116 1 $125 $1,175.00 $1,395.00 4" Solid White Pavement 84 Markings (Thermoplastic) 20 LF $1.00 0 $1.00 $20.00 $0.00 Solid Yellow Favement 85 Markings (Paint) 406 1F $2.00 4439 $2.00 $812.00 $8,878.00 6" Yellow avement Markings 86 (Paint) 16 LF $3.00 0 1 $3.00 $48.00 $0.00 6" White Pavement Marldfigs 87 (Paint) 16 LF 1 $3.00 0 1 $3.00 $48.00 $0.00 p Yellow Pavement 88 Marldngs (Paint) 1162 LF $2.00 1167 $2.00 $2,324.00 $2,334.00 6" Solid Double Yellow Pavemeflt 89 Markings (Thermoplastic) 4868 LF $2.50 5337 $2.50 $12,170.00 $13.34250 12 olid White Stop Bar 90 IThermoplastic) 245 LF $15.00 221 $15.00 $3,675.00 $3,315.00 72" x White .rossw tripe 91 (Thermoplastic) 84 EA $150.00 _ 8.9 $150.00 $12,600.00 $13,350.00 20" x 20" White Elephant Feet 92 (The moplastic) 140 EA $30.00 128- - $30.00 $4,200.00 $3,840.00 Green Bicycle Lane ting or 93 Intersections 4458 SF $25.00 5339 $25.00 $111,450.00 $133,475.00 White Pavement Sym is Arrows 94 -Thermoplastic) 35 EA $400.00 1 10 $400.00 $14,000.00 $4,000.00 White Pavement ymbols ("Only" 95 Thermoplastic) 6 EA $450.00 8 $450.00 $2,700.00 $3,600.00 Pavement SymboLS (Helmeted 96 Bicyclist Symbol - Thermoplastic) 21 EA $750.00 0 $750.00 $15,750.00 $0.00 24 x 30" R2-1 Speed Latmit sagn 97 w/Support 7 EA $400.00 1 6 $400.00 $2.800.00 $2,400.00 Page 2 of 4 Bid Item Bid Item Description Previous Estimated Unit of Contract Revised Revised Unit Estimated Original Revised Estimated Cost No. Quantity Measure Unit Price Price Quantity Estimated Cost 05-1 Stred Name Sign 99 w/Mounting Hardware 10 EA $400.00 12 $400.00 $4,000.00 $4.800.0.0 24"x 24"W24TrafTc Sign with 103 18" x 9" W(Special) Look Sign 20 EA $400.00 0 $400.00 $8,000.00 $0.00 30"x 30- K10-15'rrattic sign 104 w/Support 29 EA $400.00 20 $400.00 $11,600.00 $8,000.00 110 Relocate Existing Udit-Y Sign I EA $200.00 0 $200.00 $200.00 $0.00 Erosion ntrol Sediment =g - 114 Check 2 EA $350.00 0 $350.00 $700.00 $0.00 Erosion Control Mg�� 115 Protection 32 EA $200.00 2 1 $200.00 $6,400.00 $400.00 116 Erosion Control Silt Fence 5122 IF $5.00 4509 $5.00 $25,610.00 $22,545.00 118 Street Light Pulibox 6 x 8 58 EA $275.00 57 $275.00 $15,950.00 $15,675.00 119 1 1/2" Electrical Conduit 4300 LF $13.00 4785 $13.00 $55,900.00 $62,205.00 Street Light SM-e.-PoTe and 120 Foundation 56 EA $3,875.00 55 $3,875.00 $217,000.00 $213,125.00 Remove Section and Set New Post 122 for Existing 3 -Rail Wood Fence 1 LS $700.00 0 $700.00 $700.00 $0.00 Extend shng m Line and 123 Connect to Drop Inlet _ I EA $700.00 4 $700.00 $700.00 $2,800.00 TrafficSignal le7GI4 131 A.W.G.) 424 LF $2.00 961 $2.00__ $848.00 $1,922.00 Traffic Signal Cable (20Ct14 _ 132 A.W.G.) 735 LF $4.45 641 $4.45 $3,270.75 $2,852A5 133 lead in Cable (Feeder Wire) 719 LF $1.00 _ _ 736 $1.00 $719.00 $736.00 134 Nan-MciallicConduit (3") 559 LF $24.50 590 $24.50 $13,695.50 $14,455.00 147 Video Cable 1402 LF $2.65 1428 $2.65 $3,715.30 $3,784.20 148 Coax Cable (8281) 1402 IF $0.70 1428 $0.70 $981.40 $999.60 ectncal Conductors -in -conduit 150 (108 A.W.G.,EGC) 582 LF $1.30 563 $1.30 $756.60 $731.90 Electrical uctorsfor 151 Luminaires (2C/12 AWG) 559 IF $1.15 470 $1.15 $642.85 $540.50 ra is r e (7C/14 158 A.W.G.) 275 LF $2.00 514 $2.00 $550.00 $1,028.00 Traffic Signal Cable ( L 159 A.W.G.) 72 LF $5.30 12 $530 $381.60 $63.60 160 Lead in Cable (Feeder Wire) 130 _ IF $1.15 125 $1.15 $149.50 $143.75 161 Non -Metallic Conduit (3") 94 LF $24.50 _ 96 $24.50 $2,303.00 $2,352.00 162 Non -Metallic Conduit (2") 20 IF 1 $9.00 31 $9.00 $180.00 $279.00 163 Galvanized Steel Conduit (1.25) 8 LF $12.85 0 $12.85 $102.80 $0.00 164 Concrete Pull Box (Type t) 2 EA $690.00 3 $690.00 $1,380.00 $2,070.00 Traffic Signal este le (5.5) 168 with Foundation 2 EA $1,800.00 1 $1,800.00 $3,600.00 $1,800.00 Electrical Conductors -m unduit 169 (2016 A.W.G., EGC) 8 _ IF _ $4.60 81 $4.60 $36.80 $372.60 Elecinical Cmductors-in-Canduit 170 (108 A.W.G.,EGC) 150 LF $1.30 136 $1.30 $195.00 $176.80 Electrical Conductors for 17.1 Luminaires (2012 AWG) 124 LF $1.15 131 $1.15 $142.60 $150.65 Service Point Assembly (2 173 Circuits) 1 EA $1,500.00 2 $1,500.00 $1,500.00 $3,000.00 198 24"RCP FES with Curtain Wall 0 EA $0.00 1 1 $1,100.00 $0.00 $1,100.00 Amenstar Access Gates Sel 199 Closing 0 EA $0.00 2 $562.20 $0.00 $1,124.40 200 Precast Manhole (Township) 0 LS $0.00 _ _ 1 $8,080.00 $0.00 $8,080.00 Men cnt Marking Stripe 201 Grinding 0 LF $0.00 240 $1.20 $0.00 $288.00 Refiectorized Paint Helmeted Bike 202 Rider w/Arrow Symbol 0 EA $0.00 24 $360.00 $0.00 $8,640.00 Bike/Ped. Crossing (W11-15) with 203 1 Arrow 0 EA $0.00 2 $400.00 $0.00 $800.00 Page 3 of 4 Bid hem Bid item Description Previous ted Unit of Contract Revised Revised Unit Original The new Contract Price including this Change Order will be No. The Contract Time(s) will be increased by Quantity Measure Unit Price ed Quantity Price Estimated CostIlike Revised Estimated Cost e Ends se c e me 204 Sign (Special) 0 EA $0.00 1 $275.00 $0.00 $275.00 205 No Right Turn on Red Arrow Sign 0 EA 1 $0.00 1 $275.00 $0.00 $275.00 meet Light rxture, a an 206 Foundation, Material Only 0 EA $0.00 1 $2,529.25 $0.00 $2,529.25 Schedule 1 Summation of Cost $2,425,21L55 $2x694,23030 Net Cost for Schedule 1 $269,01895 , Class 2 175 Water Main 320 LF $39.50 195 $3950 $12,640.00 $7,702.50 176 Water Main 20 LF $35.50 53 $35.50 $710.00 $1,88150 177 1" Copper Water Service Tubing 60 LF $26.00 57 $26.00 $1,560.00 $1,482.00 178 8" Gate Valve with Box -M 2 EA $2,400.00 1 $2,400.00 $4,800.00 $2,400,00 Epoxy Coated Ductile 182 Finings 3500 LB $7.00 1343 $7.00 $24,500.00 $9,401.00 184 Remove Existing Meter Setting I EA $500.00 0 $50Qo0 $500.00 $0.00 1Direct Bury Steel Casing 186 (Direct Bury) 99 LF $120.00 100 $120.00 $11,880.00 $14000.00 187 2" HDPE Casing 50 LF $13.00 30 $13.00 $650.00 $390.00 Cut and Cap Existing ater 188 Main 4 EA $450.00 3 $450.00 $1,800.00 $1,350.00 Adjust Existing Water Valve to 189 Grade 9 EA $300.00 3 $300.00 $2,700.00 $900.00 Adjust Sewer Manhole to Grade 192 Using Riser Rings 4 EA $300.00 0 $300.00 $1,200.00 $0.00 193 Concrete Anchor Collar 2 EA $200.00 1 $200.00 $400.00 $200.00 Remove Cone a nsuuct 195 Sewer Manhole to Grade 1 EA $1,500.00 2 $1,500.00 $1,500.00 $3,000.00 196 6" Gate Valve with Box 0 EA $0.00 1 $883.50 $0.00 $883.50 197 12" Direct Bury Steel Casing 0 LF $0.00 I2 $59.95 $0.00 $719.40 Schedule 2 Stmtmatlon of Cost $64,840.00 $42,30990 Net Cost for Schedule 2 ($22,530.10) i ne ongmai t_ontract Price was 7891372.55 Net change by previously authorized change orders -r- The Contract Price prior to this Change Order was $ 3,891 72.55 The Contract Price will be increased by 246.488.85 The new Contract Price including this Change Order will be $ 4.137 1A0 The Contract Time(s) will be increased by So calendar d. - Required dates of Completion as of the date of this Change Order therefor are: Substantial Completion 23,Tun-19 Final Completion 23 -Jul -19 NOTE:7hi5 summary does not affect changes in the Contract Price or Sweet ns c ' ,Inc. ATE Page 4 of 4 OLID WIRE FROAg:) PFROTECTEn BIKE LANE . 8& SI 13lEWALK PFROJ ECT (ASH ST. TO G V L L EY PARK) for the City of Fayetteville VICINITY MAP E BID No. 18-21 Aft CITY of JANUARY 2018 FAYETTEVILLE ARKANSAS ENGINEERING DIVISION PHONE: (479) 5758206 FAX NO: (479) 575-6202 Gulley Park Pavilion ownship St /Township I St o E Stewart St AD m a z z CA. E p,jerctest St m E Elm St E A71ber DW 3 o`a = BMW COA57RUcn01V c Z - Fairview Memorial E Ash St Cemetery E BID No. 18-21 Aft CITY of JANUARY 2018 FAYETTEVILLE ARKANSAS ENGINEERING DIVISION PHONE: (479) 5758206 FAX NO: (479) 575-6202 City of Fayetteville, Arkansas - Budget Adjustment Form (Legistar) Budget Year Division Adjustment Number ENGINEERING (621) 2020 (BY) /Org2 Requestor: Matthew Maddox BUDGET ADJUSTMENT DESCRIPTION / JUSTIFICATION: Approval of Change Order #1 in the amount of $246,488.85 for the construction of the Old Wire Road Protected Bike Lane & Sidewalk Project. The change order includes an increase in project cost of $269,018.95 for Schedule 1 which is the Transportation Bond Fund and a decrease in cost of $22,530.10 for Schedule 2 which is the Water and Sewer Fund and approval of a budget adjustment. RESOLUTION/ORDI NANCE COUNCIL DATE: 1/7/2020 LEGISTAR FILE ID#: 2019-0931 Matthew Maddaw 12/18/2019 3:21 PM Budget Director Date TYPE: D - (City Council) JOURNAL #: GLDATE: 1/7/2020 CHKD/POSTED: TOTAL 269,019 269,019 v.20191211 Increase / (Decrease) Proiect.Sub# Account Number Expense Revenue Project Sub.Detl AT Account Name 4520.800.9556-5809.00 269,019 - 06035 2600 EX Improvements - Street 4520.900.0952-4999.99 - 269,019 RE Use Fund Balance - Current H:\Budget Adjustments\2020_Budget\City Council\01-07-2020\BA20 - 2019-0931 Old Wire Change Order 1 of 1