HomeMy WebLinkAbout20-19 RESOLUTION113 West Mountain Street Fayetteville, AR 72701 (479) 575-8323 Resolution: 20-19 File Number: 2018-0769 GARVER, LLC AMENDMENT NO. 1: A RESOLUTION TO APPROVE AMENDMENT NO. 1 TO THE PROFESSIONAL ENGINEERING SERVICES AGREEMENT WITH GARVER, LLC IN THE AMOUNT OF $80,100.00 FOR ADDITIONAL DESIGN AND CONSTRUCTION PHASE SERVICES RELATED TO THE MEADOW STREET PARKING DECK REHABILITATION PROJECT, TO APPROVE ADDITIONAL PROJECT CONTINGENCY IN THE AMOUNT OF $8,010.00, AND TO APPROVE A BUDGET ADJUSTMENT WHEREAS, on September 5, 2017, the City Council approved Resolution 184-17 authorizing a professional engineering services agreement with Garver, LLC in the amount of $39,950.00 for the design, bidding and construction phase services related to the Meadow Street Parking Deck Rehabilitation project; and WHEREAS, on August 21, 2018, the City Council approved Resolution 177-18 authorizing a contract with Steve Beam Construction, Inc. in the amount of $291,477.00 for the construction work associated with the project; and WHEREAS, since construction began, unforeseen conditions have appeared which require additional engineering services in the amount of $80,100.00 and construction work in the amount of $230,000.00 as estimated by Garver, LLC. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS: Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves Amendment No. 1 to the professional engineering services agreement with Garver, LLC in the amount of Page 1 Printed on 1116119 Resolution: 20-19 File Number: 2018-0769 $80,100.00 for additional design and construction phase services related to the Meadow Street Parking Deck Rehabilitation Project, and further approves a project contingency in the amount of $8,010.00. Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget adjustment, a copy of which is attached to this Resolution. PASSED and APPROVED on 1/15/2019 Attest: Sondra E. Smith, City Clerk T#r'r►►�� Y p ego I AYEnEVILL',.;I0= `%$.• ��A ids=�' '`,: 16411611%0 - Page 2 Printed on 1116119 City of Fayetteville, Arkansas 113 West Mountain Street Fayetteville, AR 72701 (479) 575-8323 y� Text File -- File Number: 2018-0769 Agenda Date: 1/15/2019 Version: 1 Status: Passed In Control: City Council Meeting File Type: Resolution Agenda Number: C. 1 GARVER, LLC AMENDMENT NO. 1: A RESOLUTION TO APPROVE AMENDMENT NO. 1 TO THE PROFESSIONAL ENGINEERING SERVICES AGREEMENT WITH GARVER, LLC IN THE AMOUNT OF $80,100.00 FOR ADDITIONAL DESIGN AND CONSTRUCTION PHASE SERVICES RELATED TO THE MEADOW STREET PARKING DECK REHABILITATION PROJECT, TO APPROVE ADDITIONAL PROJECT CONTINGENCY IN THE AMOUNT OF $8,010.00, AND TO APPROVE A BUDGET ADJUSTMENT WHEREAS, on September 5, 2017, the City Council approved Resolution 184-17 authorizing a professional engineering services agreement with Garver, LLC in the amount of $39,950.00 for the design, bidding and construction phase services related to the Meadow Street Parking Deck Rehabilitation project; and WHEREAS, on August 21, 2018, the City Council approved Resolution 177-18 authorizing a contract with Steve Beam Construction, Inc. in the amount of $291,477.00 for the construction work associated with the project; and WHEREAS, since construction began, unforeseen conditions have appeared which require additional engineering services in the amount of $80,100.00 and construction work in the amount of $230,000.00 as estimated by Garver, LLC. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS: Section I : That the City Council of the City of Fayetteville, Arkansas hereby approves Amendment No. 1 to the professional engineering services agreement with Garver, LLC in the amount of $80,100.00 for additional design and construction phase services related to the Meadow Street Parking Deck Rehabilitation Project, and further approves a project contingency in the amount of $8,010.00. Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget adjustment, a copy of which is attached to this Resolution. City of Fayetteville, Arkansas Page 1 Printed on 1/16/2019 City of Fayetteville Staff Review Form 2018-0769 Legistar File ID 1/15/2018 City Council Meeting Date - Agenda Item Only N/A for Non -Agenda Item Justin Clay 12/21/2018 PARKING MANAGEMENT (430) Submitted By Submitted Date Division / Department Action Recommendation: Approving a resolution to amend the scope of the professional engineering services agreement with Garver Engineering, LLC, and to increase the agreement amount to $80,100 to perform additional services associated with the Meadow Street Parking Deck Rehabilitation project, to approve a contingency in the amount of $8,010, and to approve a budget adjustment. Budget Impact: 2130.430.9130-5819.00 2130 Account Number 15004 Project Number Budgeted Item? Yes Does item have a cost? Yes Budget Adjustment Attached? Yes Purchase Order Number: Change Order Number: Original Contract Number: Comments: 2017-00000623 2017-00000028 Fund Meadow Street Parking Deck Improvements Project Title Current Budget $ 357,277.00 Funds Obligated $ 343,729.62 Current Balance Item Cost $ 88,110.00 Budget Adjustment $ 88,110.00 Remaining Budget 3,547.38 Previous Ordinance or Resolution # 184-17 Approval Date: V20180321 CITY OF FAYETTEVILLE �~ ARKANSAS JANUARY 15, 2019 TO: Mayor and City Council THRU: Don Marr, Chief of Staff FROM: Justin Clay CITY COUNCIL MEMO CC: Wade Abernathy, Facilities & Building Projects Manager DATE: December 21, 2018 SUBJECT: Approving a resolution to amend the scope of the professional engineering services agreement with Garver Engineering, LLC, and to increase the agreement amount to $80,100 to perform additional services associated with the Meadow Street Parking Deck Rehabilitation project, to approve a contingency in the amount of $8,010, and to approve a budget adjustment. RECOMMENDATION: Staff recommends approving a resolution to amend the scope of the professional engineering services agreement with Garver Engineering LLC (Garver), to perform additional services associated with the exit ramp and north stairwell of the Meadow Street Parking Deck and to increase the amount to $80,100 and to approve a contingency in the amount of $8,010. BACKGROUND: On September 5, 2017, the City Council approved Resolution 184-17 authorizing a professional services agreement with Garver in the amount of $39,950 for the design, bidding, and construction phase services related to the Meadow Street Parking Deck Rehabilitation project. The Meadow Street Parking Deck was constructed in the late 1970's in conjunction with the construction of the (then) Hilton Hotel. Restoration work was performed on the deck in 2005 that included concrete repairs, shoring, latex modified concrete placement and patching, trowel applied concrete repairs, sealants, waterproofing, expansion joints, supplemental floor drains, painting and miscellaneous other repairs to the Meadow Street Parking Deck. More recent observations of the parking deck identified several maintenance issues that have developed since the deck was last repaired, leading to the original agreement with Garver. The repair items for this project include: the replacement of metal stair treads, the demolition and complete replacement of both stairs serving the deck, repair and patching of concrete and stucco surfaces, crack repair, painting, installation of drains and associated PVC piping, application of a protective membrane to the top level of the deck, removal and replacement of concrete sidewalk, and other miscellaneous items. On August 21, 2018, the City Council approved Resolution 177-18 to award Bid #18-41 and authorize a contract with Steve Beam Construction, Inc. (Steve Beam Construction), in the Mailing Address: 113 W. Mountain Street www.fayetteville-ar.gov Fayetteville, AR 72701 amount of $291,477 for construction work associated with the Meadow Street Parking Deck Rehabilitation project. DISCUSSION: Since the construction phase began, some unforeseen conditions have appeared. 1. The sidewalk replacement on the northwest corner of the structure exposed the stair tower foundation blocks without steel reinforcements. Staff requested x-ray of the foundation and supporting side walls of the tower which revealed lack of reinforcements in all the walls. The engineers recommend demolishing the tower and design of an open- air, free-standing stair tower modular unit that will remain independent from the parking deck structure. The existing stairwell has not been deemed inoperable or unsafe for use at this juncture, but it will continue to be monitored and evaluated prior to demolition. 2. Patching of the exit ramp at the southeast corner of the deck uncovered greater deterioration in size and depth of the concrete slab than originally quantified. Upon further analysis Garver has determined that remedial repairs could not be done, and the demolition and replacement of the post -tensioned exit ramp concrete slab is necessary. The existing exit ramp has been determined to be unsafe to use in its current condition and is inaccessible at this juncture. The entry ramp to the west has been converted to a dual -use entry/exit ramp and safety precautions have been installed to allow for two-way traffic to enter and exit the third level of the deck. Staff negotiated with Garver on the fee proposal for this additional work. In good faith, Garver reduced their original quote 20%. This amendment only includes the additional scope and fees associated with the engineering design work and construction administration, however Garver has provided preliminary cost estimates for the additional construction work of approximately $230,000. Approximately $88,000 worth of work is estimated to be removed from the original scope, resulting in an anticipated net additional construction cost of approximately $142,000. A change order request will be forthcoming once a lump sum figure is provided by the on-site contractor. BUDGET/STAFF IMPACT: A budget adjustment from the Parking Fund Reserves in the amount of $88,110 will be necessary to fund this amendment. This amount includes a 10% contingency. Attachments: Garver Contract Amendment #1 Original Meadow Street Parking Deck Plans Budget Adjustment AMENDMENT TO AGREEMENT FOR PROFESSIONAL SERVICES City of Fayetteville Fayetteville, Arkansas Project No. 16047031 CONTRACT AMENDMENT NO. 1 This Contract Amendment No. 1, effective on the date last written below, shall amend the original contract between the City of Fayetteville (Owner) and GARVER, LLC (GARVER), dated September 5, 2017 referred to in the following paragraphs as the original contract. This Contract Amendment No.1 adds professional services for the: Rehabilitation of the Meadow Street Parking Deck The original contract is hereby modified as follows: SECTION 5 — PAYMENTS TO ENGINEER Section 5 of the original contract is hereby amended as follows., The maximum not -to -exceed amount as specified in Section 5.1 shall be increased $80,100 from $39,950 to $120,050. APPENDIX A — SCOPE OF SERVICES The following items shall be added to the Scope of Services as detailed in Appendix A of the original contract: 2.3 Geotechnical Services Garver will subcontract with Terracon Consultants, Inc. to provide geotechnical services associated with the Meadow Street Parking Deck Stair Tower replacement. Services include providing one (1) bore approximately 20 -ft in depth, laboratory testing of the soil material to evaluate pertinent physical properties and engineering characteristics of the soils to develop foundation recommendations. 2.8 Final Design — Stair Tower Construction plans will be prepared for the demolition and replacement of the stair tower located at the northwest corner of the Meadow Street Parking Deck that is more particular described below: • Design of a free-standing stair tower modular unit that is independent from the parking deck structure that will provide access to all three levels. The stair tower will be open to the environment with a roof structure. • The relocation of the existing fire protection shall be designed to meet the current fire protection codes and the limitations of the open stair tower. • Lighting for the new stair tower shall be designed to meet current electrical and fire protection Contract Amendment No. 1 1 of 3 Meadow Street Parking Deck Garver Project No. 16047031 codes. If necessary, the exterior light pole and fixture located to the west of the existing stair tower will be designed to be removed and replaced with a fixture attached to the stair tower. Prepare specifications for the additional improvements. p Coordinate the proposed improvements with the existing contractor to determine costs. 2.8 Final Design — Exit Ramp Construction plans will be prepared for the demolition and replacement of the post -tensioned exit ramp concrete slab located at the southeast corner of the Meadow Street Parking Deck that is more particular described below: On-site examination of the exit ramp by a registered professional structural engineer. Develop construction drawings for the removal and replacement of the exit ramp concrete slab complete with a plan of the improvements and structural detailing. Prepare specifications for the additional improvements ■ Coordinate the proposed improvements with the existing contractor to determine costs. 2.10 Construction Phase Services — Partial During the construction phase for the additional work, Garver will provide the following additional services: ■ Provide up to 29 additional hours to evaluate and respond to construction material submittals and shop drawings associated with the stair tower replacement, exit ramp concrete slab replacement, and appurtenances. ■ Provide up to 11 additional hours to issue instructions to the Contractor on behalf of the City and issue necessary clarifications regarding the construction contract documents. • Provide up to 18 additional hours for on-site meetings to assist the City during the construction contract performance time. 2.12 Extra Work The following items are not included under this agreement but will be considered as extra work: 1. Preparation and coordination to obtain any City Building Permits and Planning Permits. All Items in conjunction with City permitting will be handled by the City. 2. Design of supplemental supporting columns and foundations associated with the southeast parking deck ramp. 3. Redesign of the stair towers and ramp for the City's convenience due to changed conditions after previous alternate direction and/or approval including the redesign to meet budgets. 4. Hourly work in addition to the specific time limitations during the construction phase. APPENDIX B — FEE SPREADSHEETS The spreadsheets contained in the attached Appendix B shall be added to the fee spreadsheets contained in Appendix B of the original agreement. Contract Amendment No. 1 2 of 3 Meadow Street Parking Deck Garver Project No. 16047031 GrARVER This Agreement may be executed in two (2) or more counterparts each of which shall be deemed an original, but all of which together shall constitute one and the same instrument. IN WITNESS WHEREOF, Owner and GARVER have executed this Amendment effective as of the date last written below. Title; Mayor _ Date: Attest: .■ .' Gly Y pZ. •; S' FAYETTEKLE: �r• ■ 1^ � 4 T O N C,"; /14111111 '•• '1flitrtWO GARVER, LLC By: Signature Name: Ronald S. Petrie Printed Name Title: Sr. Pm'ect Manager Date: 12 h -a p Attest: Contract Amendment No. 1 3 of 3 Meadow Street Parking Deck Garver Project No. 16047031 S�] APPENDIX B Meadow Street Parking Deck - Amendment No. 1 Garver Hourly Rate Schedule: July 2018 - June 2019 Classification Rates Engineers I Architects E-1.............................................................................. $ 105.00 E-2.............................................................................. $ 122.00 E-3.............................................................................. $ 148.00 E-4.................................................................:............ $ 173.00 E-5.................._....................................... ................... $ 210.00 E-6............................................................................. $ 264.00 E-7.............................................................................. $ 351.00 Planners I Environmental Specialist P-1 .................. .......... $ 127.00 P-2.......... .. $ 159.00 P-3 ........................... .. .... ......... $ 198.00 P-4 ......................................... .... ...... .............. $ 225.00 P-5 ................................... ......... $ 261.00 P-6 ................ .......................... $ 297.00 P-7 .................. ................................ $ 359.00 Designers D-1 ... ....... ................... .................. . $ 99.00 D-2 ........... ............................................................ $ 115.00 D-3........................................................................ $ 137.00 D-4 .......................... •.•--•.------- .............................. $ 159.00 Technicians T-1 ........................................ .:....................... ....... ....., $ 77.00 T-2..................................................................... $ 97.00 T-3 ........................ ................ ::................................ .... $ 119.00 Surveyors S-1 .................. .... ..................... $ 47.00 S-2 .................. ...... ---------- $ 62.00 S-3 ..................... ........... $ 84.00 S-4 ...................... .... $ 120.00 S5........................................................................ $ 159.00 S-6 ....................................... ......... $ 181.00 2 -Man Crew (Survey) ............ .... $ 192.00 3 -Man Crew (Survey)........... $ 239.00 2 -Man Crew (GPS Survey) $ 212.00 3 -Man Crew (GPS Survey) .. . .............. ............... $ 259.00 Construction Observation C-1 ................... ... ... ................ $ 93.00 C-2 .......................... ........................... $ 119.00 C-3 ....................... ............................. $ 146.00 C-4........................................................................... $ 179.00 Management/Administration M-1 $ 359.00 X-1 ........... . $ 60.00 X-2 ................... $ 82.00 X-3 ..................$ 114.00 X-4 .......................... $ 145.00 X-5........ $ 178.00 X-6 ......................... $ 227.00 X-7 ...................... .............. .. $ 270.00 Agreement for Professional Services Meadow Street Parking Deck -Amendment No 1 Garver Project No. 16047031 APPENDIX B CITY OF FAYETTEVILLE MEADOW STREET PARKING DECK AMENDMENT NO. 1 FEE SUMMARY Estimated Fees Original Amendment Title I Services Agreement No. 1 Geotechnical Services (Terracon) $0.00 $2,600.00 Surveys $0.00 $0.00 Conceptual Design $0.00 $0.00 Preliminary Design $0.00 $0.00 Final Design $29,600.00 $0.00 Final Design (Stair Tower) $0.00 $51,200.00 Final Design (Ramp) $0.00 $17,350.00 a[dding Services $2,950.00 $0.00 Subtotal for Title I Services $32,550.00 $71,150.00 Title II Services Construction Materials Testing $0.00 $0.00 Construction Phase Services $7,400.00 $0.00 Construction Phase Services (Stair Tower) $0.00 $5,700.00 Construction Phase Services (Ramp) $0.00 $3,250.00 Subtotal for Title II Services $7,400.00 $8,950.00 Totals $39,950.00 $80,100.00 L:\2016\16047031 - Meadow Street Parking Deck Rehab\Contracts\Client\Draft\Amendment No. 1\APPENDIX B - Meadow Street Parking Deck Amendment 1.xlsx APPENDIX B CITY OF FAYETTEVILLE MEADOW STREET PARKING DECK AMENDMENT NO. 1 FINAL DESIGN - STAIR TOWER WORK TASK DESCRIPTION E-6 $264.00 hr E-5 $210.00 hr E-4 $173.00 hr E-3 $148.00 hr E-2 $122.00 hr E-1 $105.00 hr D-4 $159.00 hr D-1 $99.00 hr 1. Civil Engineering $119.00 Postage/Freight/Courier $0.00 Travel Costs $35.00 Civil Site Design $154.00 4 $51,200.00 6 $0.00 Coordination and Meetings with Owner 4 10 Coordination Wth Construction Company 2 8 Specifications/Contract Documents 4 Subtotal - Civil Engineering 6 0 26 0 0 6 0 0 2. Architecture Architectural Design 2 6 Architectural Detailing 8 12 Specifications 8 QC 2 Subtotal - Architecture 4 0 14 0 12 0 0 8 3. Structural Engineering Structural Design 60 1 30 Structural Detailing 12 70 Specifications 8 QC 6 Subtotal - Structural Engineering 6 0 0 0 80 0 100 0 4. Mechanical Engineering Fire Protection & Drainage Relocation 10 8 Subtotal - Mechanical Engineering 0 0 10 0 8 0 0 0 5. Electrical Engineering Electrical Relocation/Replacement 50 Subtotal - Electrical Engineering 0 0 50 0 0 0 0 0 Hours Salary Costs 16 $4,224.00 0 100 0 100 6 100 8 $0.00 $17,300.00 $0.00 $12,200.00 $630.00 $15,900.00 $792.00 SUBTOTAL - SALARIES: $51,046.00 DIRECT NON -LABOR EXPENSES Document Printing/Reproduction/Assembly $119.00 Postage/Freight/Courier $0.00 Travel Costs $35.00 SUBTOTAL - DIRECT NON -LABOR EXPENSES: $154.00 SUBTOTAL: $51,200.00 SUBCONSULTANTS FEE: $0.00 TOTAL FEE: $51,200.00 APPENDIX B CITY OF FAYETTEVILLE MEADOW STREET PARKING DECK AMENDMENT NO. 1 FINAL DESIGN - EXIT RAMP WORK TASK DESCRIPTION E-6 $264.00 hr E-5 $210.00 hr I E-4 E-3 E-2 E-1 D-4 D-1 $173.00 $148.00 $122.00 $105.00 $159.00 $99.00 hr hr hr hr hr hr 1. Civil Engineering Civil Site Design Coordination and Meetings with Owner 4 8 Preparation of Construction Change Order Coordination with Construction Company 4 Specifications/Contract Documents 2 Subtotal - Civil Engineering 4 0 14 0 0 0 0 0 2. Structural Engineering Structural Design 18 Structural Detailing 18 30 Specifications 6 Site Visit 8 QC 8 5 Subtotal - Structural Engineering 8 0 0 0 55 0 30 0 Hours Salary Costs SUBTOTAL - SALARIES: DIRECT NON -LABOR EXPENSES Document Printing/Reproduction/Assembly Postage/Freight/Courier Travel Costs 12 0 14 $3,168.00 $0.00 $2,422.00 $17,070.00 $100.00 $0.00 $180.00 SUBTOTAL - DIRECT NON -LABOR EXPENSES: $280.00 SUBTOTAL: $17,350.00 SUBCONSULTANTS FEE: $0.00 TOTAL FEE: $17,350.00 0 55 0 30 0 $0.00 $6,710.00 $0.00 $4,770.00 $0.00 APPENDIX B CITY OF FAYETTEVILLE MEADOW STREET PARKING DECK AMENDMENT NO. 1 CONSTRUCTION PHASE SERVICES - STAIR TOWER ADDITIONAL SERVICES WORK TASK DESCRIPTION E-6 $264.00 hr E-5 $210.00 hr E-4 $173.00 hr E-3 $148.00 hr E-2 $122.00 hr E-1 $105.00 hr T-2 $97.00 hr 1. Civil Engineering Monthly Pay Requests 4 Shop Drawings/Material Submittals 2 On -Site Meetings 2 6 Subtotal - Civil Engineering 2 0 12 0 0 0 0 2. Structural Engineering Response to Inquiries 4 Material Submittals/Shop Drawings 8 Subtotal - Structural Engineering 0 0 0 0 12 0 0 3. Mechanical Engineering Material Submittals/Shop Drawings 4 Subtotal - Mechanical Engineering 0 0 4 0 0 0 0 4. Electrical Engineering Material Submittals/Shop Drawings 5 Subtotal - Electrical Engineering 0 0 5 0 0 0 0 Hours Salary Costs SUBTOTAL - SALARIES: DIRECT NON -LABOR EXPENSES Document Printing/Reproduction/Assembly Postage/Freight/Courier Travel Costs SUBTOTAL - DIRECT NON -LABOR EXPENSES: SUBTOTAL: SUBCONSULTANTSFEE: 2 0 21 $528.00 $0.00 $3,633.00 $5,625.00 $50.00 $0.00 $25.00 $75.00 $5,700.00 $0.00 TOTAL FEE: $5,700.00 0 12 0 0 $0.00 $1,464.00 $0.00 $0.00 APPENDIX B CITY OF FAYETTEVILLE MEADOW STREET PARKING DECK AMENDMENT NO. 1 CONSTRUCTION PHASE SERVICES - EXIT RAMP ADDITIONAL SERVICES WORK TASK DESCRIPTION E-6 $264.00 hr E-5 $210.00 hr E-4 $173.00 hr E-3 $148.00 hr E-2 $122.00 hr E-1 $105.00 hr T-2 $97.00 hr 1. Civil Engineering Monthly Pay Requests Shop Drawings/Material Submittals 2 On -Site Meetings 6 Subtotal - Civil Engineering 0 0 8 0 0 0 0 2. Structural Engineering Response to Inquiries 7 Material Submittals/Shop Drawings 8 Subtotal - Structural Engineering 0 0 0 0 15 0 0 Hours Costs SUBTOTAL - SALARIES: DIRECT NON -LABOR EXPENSES Document Printing/Reproduction/Assembly Postage/Freight/Courier Travel Costs SUBTOTAL - DIRECT NON -LABOR EXPENSES: SUBTOTAL: SUBCONSULTANTS FEE: 0 0 8 $0.00 $0.00 $1,384.00 $3,214.00 $22.00 $0.00 $14.00 $36.00 $3,250.00 $ 0.00 TOTAL FEE: $3,250.00 0 15 0 0 $0.00 $1,830.00 $0.00 $0.00 NOliVilll9VH38 N030 ' - a, ONINHVd 133His A400V36V 0: c y �y% J} j�z°�� MNIV".1 1•\Jll'.IAVI ?, r O �° � Quo •��a.3c7r, 31 A3i.L3AVd d0 WO b $ a v o •� p u 9-1 D Z U y .�D] NN'C� W zw W W W a �'_ I W' J U.. N z =o -2 _ n G O O N W O U n.n x W w O zF LE m Q W _ ,� s !m N z — N _ C Q F O LLI Q � L (r = U o a � t }} •� f- N N N N N f ,= F-m5m0 �w zv LL Q maz0~ z E 2 o. goLd Faw MMN__ Wa> > o v� W vWgz� .2G -E Oa V/ m SZ U` k2o �5 71� LJJ 2 � 1..t..� `QJz < ` U) I..L z r U Q a O W � w Q O COr LL r �Q 8 Z N NR r....+..,, ' oU �a W 3 . z > N mw� W - ;i ww >� LL W w oQ Q oi, M of w 75 wu :r O 9h 3 'J� g0. _ NOI1Vl{"im?"Sw N030 ffu � •- ONjNHVd 13MJIS MOOV3LN3"IA=iI1=IAV4 dOJWO yY V N w�Xw� owfi � wpb w°Iu�"k'° s=rmmm 512 eva�ry�>mLa�o�° / W-moa75 w � sg Q�Fu z�ai Ogg 301rygv a!aE co �uo�`¢uoa`w>>wo G22��4 u�w�z _�iF� �u¢d F(LL Ln�iYw gs ULAjO �S Fan ��jk�a pOU FP 'aw U2S6ZHH ui 3� c, - aUNLL V ¢ Srn=.,r v�iH p,gx'gn F da'ea r 7NNv-suwno3s ism:i w .� ; w v,hw�oiF u "M-4; w �W p 2 K 3 � o2 r i °aoso��u p� L � 5s, ._ A .E{Ti �rk[�t�t�l•� � � � `JrN>I23Vd 1332315 MOOV3W Y�I',a'3�5�e��� � ' f S� �• �6b:11tNtlb'3llli\3113Atl3 � � C � � i .p=: � Y�•i� :sJ{ �w au.w �iw �, 311lAgi-OAtljj0AllO ` m ° o`J n G •ui beim a of i a 'W o � � = a " o i oz4y��4�Z° %NG��o o w ieiuw ww ��' F� •J w -s�. oN �w3i� �iugya�w� � wo �,;;_�s��p �p m� � s"=5`�p>>p o wsw ��•"o¢m "'�, 8`pS `�woa�"� � ii� "'aewW'4`` LL ' x�r jm¢¢ w y i -oapyN Egg -m �iawiw Na° ¢p ru �a<LL: is 4 2 HI yy €"•^W�wa< `wo xwi o��" ia 9<S�a t<l 3�o52 •'z pra im Z`<F rszxuN _ LLU'g°""�oapz ,wN° "oil az& =4aw� &w e$°ti w==w5="Qa .oz .e w';�ok� ��" <`��J=h°g �aOR s?w �°^.gwkweorco��¢o;,`,"rz4 am-2S'•�w" H�aso 2owawzao-� g? ha._ 3s u� wS� T oz -w `u ` ui`m w�uLL St <z��rtaz Ww�ss vy� pn<zg� wa 3Jw wwp omp< sg�o3�5na�<:�Q v)"' -m �aoF w_5 yyssLLmwpao c�m�i��~o¢O ��p 6¢�do �0 ^ rxio 68g'or<<-maoti�ass�p�- 'oma WLLa�wp r. rHH". F'S3LLw�sow a uwrc iw g$Z �a wo o'" o wou Q � w 4 3m p gra���<azQQ �2Sa -yo' S`oa ao�'"m��w 2 s m ns �= ua><` z w�zwiSnU��w`<ww'� www o4�k' ~�N a=w=LLw www" = a a3o�w="3`=� << « �3�P w LL$�o a swa=n�w.<o= z oewoom�� w$ or w So¢a p Min ., a Lu w� u<"c <3�a _Scm X33 ou{�u <53� X Mz.g. uLL3� zsLLuasa u<i C7 N VJ n n m n W- \\ Q Q .n " it I I i I o w 3 $ois _tpi 32 �+ as^wqqw x3 "- N ' "�a2Soka av w m ` sz Mffij� W z w n- z w uloll ff oI C� ---O=p` gR - �t p �� v ¢ a I gu J �~Oz�„ `LL�y w°gq¢mZ �� z3 m o z c" I S = pRx< Pwg =U �FunO I LL U` LL R N I Jw°€s-�`�marca m u . up3w�acaw 09 i lzd w4�s Qz`auw wW 12 w -_.c. I XUL >~C tna n 2 I U• Ev jL 1 zoot° zmiovi of.Qu I § -I �o LLoclI!w�2 2 Qe w.. E- "u % hp " V _�o wg Asa ` I L� r� ! FI =w w my wa C� m.,ro_�Tmwm-- wi JDz- rcw "N I wpb" `ups wad I I os w' [ 8 11 Oun3a no - 4 I � A.I' -0•A d9 pE1 _f11 � R'nl -Z-ol .o -.G -w'1I .L•., Aa .0' .w.� t7 �1 F== Q�f x• t NOIIVIIIIBVH98 H030 `ONININd 13:RUS MOOV3A o Nowaaw�'o,�oa x° az4y��4o Q 1 Oo d2S¢3 Fw �� o Oy i?W_N• .3�rc�No 2-S >w uo Ziz35 vrp w ? °p Ommm Omm w a�a Y=oaoQi � (F �w Saa �<°�m�w520 i xrc wnu < <0 ' LU 12. o "=y�� = W ''>nNw�"o°ioo �0 Uozoo�<o-_4 ui 3�=m3�=1aR�wg` °��swrcs HyJe�$$mw"s_ N`�'°ai3�moi`, �' 2N€NwNLL�yrta w$ o- `aoa "Z{ <=?ss ww�go 2 �3 IMI%8w � �a<�s�=s m w Jam' F� �- m <M, w moo" o- w- w tea` oLN-ado w=''s �!?'Dw o �u uw a's a u�8d•.ww�aowauwa>LLaam=°=woF.>6w9mQQww�w _ O ��r y.-,wwa K aoR�l�owu'"aa�w� Z �s�4kwm' �- ia� �N'.nn p iQ-ai�wiN Z W�zwmau�$°= aw=WWQFm W ¢� wo [Y i�o°w<��i)Ru<<«���'�A w LL�w uw�F K ?W��nw�Jii �r aha<zeW� owaoom�vwi .3�u�awx o - w - w u•c"�""«s v,n 3G"wa 33�. ouimuca7a33N ��e mamma rcm1.00 �,m.3 iia .amu r s rZA r_N r-l� C L L r C: 1` L r T T �• TT, .rrao- J III I o�a�a�oi� m� oZ t3 u$ 1 a ¢w r6m<O N a O T W C 0" w0i¢aY w0-0 ylJt u .:a J Coir 5 �f aqua i-•. U A w m �y�yaQ$Qixa ��<<oqr v m °-_ ❑ ao m o ']i2S�u,"nF i`La o F9 ori' m o QQ rc _� i N a w'w`6n�Oa.i��Z�ss� b 0 2 m c a� 01 o Cywr`oi J ry OF una d wo-EmLL�oii 1 OvW au Ev � -15 rJ [Coc2w�ag �. o+a.+ �, U m -. c m arsrt��_"__, W CLt-wsav w I <Oo I I fig= -I 4 I " I --= --^---- ---- __'-.- I I 2o�� j=LLN I LLww �w"w i .m do u 1 uo m" W�*�ywsm � ���40 zo 1•;11µl iR �.11 -.P�Ah_ . .�_�,i ... i m - � per• � +. pg r. � l 32A03O JNINbVd 133HiS F MOOV31Y � � � .{' •t � � _ q\ u'" � !�, ...'.1�\n y!-3lll\31131 HJ iJ _ ] •� 9� � � T- u.ltl:.�, t 31�inRLL3A1'3 JO AIIO y 1w - - i��R rto_ - 4.. w8' K _2 -- o o:� `•�w3FLL' � wee €a� kp¢�u� fA 3zo�iwrc = Nor.7� semis an ..: f�1]� � a� r M1waFoE --�Unw., :` owu - s�z raw': ti� o F. �dw u" LLslmr.p w'•uou O :iw ? i�;•w�i:'n"'-<oo �i -- � coR RwW I133 - � as W `oR .;5 `a - u'o t. `n5 •� a'd w- Qour ¢ =5 <°u!3a°wuwa.c twa�aw=R��rO ..."laux_�.u_:..ua�..�.r.,..R .rte .aj.o-.., - 1 1 - i ir�r''rc LLn�o�Wa �� p7 cinyJp >nw=oryy I � S I IT I I _ mf II JIYVtl ... [ I 7I 3 5 � dY1Vtl I � jl IE �^-___-• .L`,i .RS+.�R�r.�:�l iAf �?{Y � Ol A.r� : -v Yl ill �.-ili _�i! � I ]•.l [�j - 1: 't _ - T. nFn w xu_�m w � a W NTn U T - _ F)° ELm E ¢ w-Ev w-w5n � S I IT I I _ mf II JIYVtl ... [ I 7I 3 5 � dY1Vtl I � jl IE �^-___-• .L`,i .RS+.�R�r.�:�l iAf �?{Y � Ol A.r� : -v Yl ill �.-ili _�i! � I ]•.l [�j NOUVAIIEVH38 NOM ,�v� 4 ONIA8Vd 1338iS MOOV3W .. , lti .;...5^�.:..:_� 6tlSNVMMV'3111A3113AVi �"'� 1 •i. •I:.ii::�tt v F 3111173ll3h1+d d0 h1!'J c°S v o o �� °' I.i i 1;D�311k! _ § N k Q 6 / W :.i71•7 H n 1 _..._.+ - �I P w O f • a mFQG (Y Gem 1 LIN � °f _LL�yU fn azJi K II i O lom wwp rt ❑ m o of f• IN 1 .i0l,? •iiW�b .ri•.b m l! °� 3� SJ w gg ° xs a LL c LIN II i / y f• IN 1 K L un �o 5z �/ u W L` Z • �� �. tr H b rn •� i aw k W �. NOUVlIIISVH3i{)1030ONINaVd 1332115 MOOV3 nil, E: • rsi�' � air.: �•re 3"11N3d.J�AVd dO 1.,LI3 10 me w°u c uS'� � � Icada�rrt�f1' —� W —� -Fz � o ,+ } " d c - 1 � Ju LL u II I xo wu t � I u r * ` m IYI u S ���y2S a Imo' o�ii; F LL Imo/ u �5nww_5 r I 3U�pV w; I'0 c I a 1 � Ju LL u :s 3 L o � E_ u f � elA l'ynC; Y1 s Imo/ u ��Fg3s ' I 3U�pV Jrx 6l ° `� _ : ILLLIIkfL:iV7%Jlll w; I'0 c I a 1 � Ju LL u L o � I u f � elA l'ynC; Y1 r � I a � I L o � r •� � I of :- a N e �'� � i�1� •f i . w3 NOIlVIIl18VH3H )4030 ONI)4LMd 133?!1S MOOV3W '�• R I�rycm , s 1'•'M yu a•itl �- _ x' 0z _ y�o lo f5 rcE 6YSNVMMV'3111.13113AV3 Z �i I 'i ; .::�i ..1• _ f '� 3run�ii3�'���A� �i vwi� i2 9�d�o Pr �Nc 5 , !�. !ilaY '!.1 z<CI h h n b, ruin 4Z, b I:�1 1: Nj=!�j F Ou 5 n.m.zl�a:�;ly uu I P . J Fit J� �-6 a , E-2 ww Z ug �� 8 0 m a ;6 s LL 'I 1 y In C? r� w 5 n� TxCwB = 'i ;Nl.rb n_s3'An eu of + y a N e . w3 i yu �3 � 0z _ y�o lo f5 rcE A3w `u� inLL wu f C LL W z<CI + y a N e . W ruin I:�1 1: Nj=!�j F Ou 5 n.m.zl�a:�;ly uu NOIlV11lI8VH3M NOW ONMNVd 133diS MOOV3W � iy53r i •:�-*''ff igY��7 ' �r - - nw 311V53113AVd JO Alb I.i0 &UIN iso LZo ;€ Z =w oSz NJ t �' Z LD wu w�QwU'' ix �✓ v a Jx P �% ga 8 ON 'n m n J, J L JJJ w i oN wx a N oN "s w 5 o Co 5 s" >ll,l �...0 f 11 § �. 1•e OJ Sa �% NOI1VIIIIGVH321 HO3O y5•:�c'=%Grs i:=g ;'.i1�3� :a:i:ii_i �.� - - ONINNVd 13321 i R ry pw mN ARTc `! go yL'IGlh•�YY"TTn]la3AYJ '� �' P S �N d} �m )� a et;:'•: ... w� Hall +.^[n 7 -n ✓•* 3TIIn311,3aV� �o I.Il9 Roo o g w w awrn p ogar5�d iu�U wYWN n m 8 O00 I 4 p v Y-� w U$ . F y 4 �jg i a 3W z Co 3 e bid.. 2 f �t �4 C7 Z4 6i 3� _ 1 fl Nam 6! aw u£ oxw u Awig� Nusa p a�'. oar Gn' J rZ uF 1 O .4 1 rc d U LU !nn �r P `� wr w UA �a CJ J p O yea xYxu �3y� w w v6 S r F a o rr rci� Ux�Fn S rv— O IS �� l'I 20w_ ,r yY `JNI)lifdd HWd 133TJ15 IIBb' M Cr030 / MOOH3W R � n VGNMV'311IA3113AVi n .. ,I� .,� anln�laxyd da A119 R $ v Go `. O r � " O 0 IL } d 6 i e� r e O r r r N 10 O 4 0 r � r O O O a� iY f' 1 N O M O O 4 r j[ 0 0 O O 6 IL 6 d NOIIVIIIIGVH32I N330 a5. VNIAWd laall.LS MOGV3N nllk:.ii.LBAVd :10 A.LIO N Ly Al 9 *0* 0 0 I.- f� I.- 2A 0 I- Lim i a ax 0 z s; NOIIVIIIISVH38 NOW VNIANd 1238iS MOGVBVJ R CL -wo LIJ NZ. -Z R S W a 3yIH JIM 49 Lw:t llgR n -j IN 2 I., F 7 V E 7 P- . .. . .. .... n. VNINNVd 133815 MOCIV3N ��S?4" HVI IIIA3113AVA vOillAY3 AO IW3 WE w ill2 In w ; Tv� uj JIM ....... .. NO F. - NOliVil-IIEVH38 A030 ONINWd AMUS MOGV3V4 � / / % § �!q| ®e}� / E �k/{\77 . E Z 2 �- - Z '5 -6 8,2 0 0 I i2 -R 'e?M L-21 I NOIlVlIIISVH3NHO30 �{c q I! �� ONPANd 13R81S MOOV31Ncm 15 • Yi I`i>i�ir lu :.i�,-.0 ,�v.• .z� 3iiIA3l13AV� doh1TJ �+ 9 � o �� a O _ E L m rn 4 acoaN•y ooU��m i MM o w m m F v ani w?L�L L OOG i� L Z Q O li U � tx Si (� r Cis— r' --.i ��"�.---..-:.�__��-�=__---_�—__—�—��pc�•�az�aa�.x�_ar--� ».�____�_��_ � — � I I ! ,,...... -- =.._-..-... .... -..- U - w m.m = m___NM . . »_dam __. �\/\]�� }■/ •�(/__gym !@-!� u ■§ 19, §& - 72=t$§ g \a!!! .: # � / ]{§k�®( (}f l;f2; \ « x \ s c « �l § City of Fayetteville, Arkansas - Budget Adjustment Form (Legistar) Budget Year Division Adjustment Number /Org2 PARKING MANAGEMENT (430) 2019 (BY) Requestor: Justin Clay BUDGET ADJUSTMENT DESCRIPTION / JUSTIFICATION: A budget adjustment is necessary to increase the professional engineering services agreement with Garver Engineering, LLC, in the amount of $80,100 to perform additional demolition and replacement services associated with the north stairwell and southeast exit ramp of the Meadow Street Parking Deck, and to approve a contingency in the amount of $8,010. During the construction phase of the Meadow Street Deck Rehabilitation Project these additonal repair needs that fall outside of the original scope were identified. RESOLUTION/ORDINANCE COUNCIL DATE: 1/15/2019 LEGISTAR FILE ID#: 2018-0769 HoVy 3lac 12/21/2018 2:51 PM Budget Director TYPE: DESCRIPTION: GLDATE: POSTED/CH KD: Date D - (City Council) TOTAL 88,110 88,110 v.20181127 Increase / (Decrease) Proiect.Sub;r Account Number Expense Revenue Project Sub.Detl AT Account Name 2130.430.9130-5819.00 88,110 - 150041 EX Parking Lot Improvements - Parking Lot Ir 2130.430.9130-4999.99 - 88,110 RE Use Fund Balance - Current C:\Users\hgordon\Desktop\fe462dae-253b-4b09-9066-ef4d212a55e3 1 of 1