HomeMy WebLinkAbout205-18 RESOLUTION113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
Resolution: 205-18
File Number: 2018-0517
ALLGEIER, MARTIN AND ASSOCIATES, INC.:
A RESOLUTION TO APPROVE SUPPLEMENTAL AGREEMENT NO. 2 WITH ALLGEIER, MARTIN
AND ASSOCIATES, INC. IN AN AMOUNT NOT TO EXCEED $35,000.00 FOR ADDITIONAL
ELECTRICAL ENGINEERING SERVICES ASSOCIATED WITH ELECTRICAL WORK AT THE
NOLAND WATER RESOURCE RECOVERY FACILITY
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Jordan
to sign Supplemental Agreement No. 2 with Allgeier, Martin and Associates, Inc. in an amount not to
exceed $35,000.00 for additional electrical engineering services associated with electrical work at the
Noland Water Resource Recovery Facility.
PASSED and APPROVED on 10/2/2018
61'
Attest:
Soiidr-a E. Smith, City Clerk Treasurer
z�3���ERK 1 TA?,"iii
FAYETTEVILLE;�Or
kANS
�t%
Page 1 Printed on 1013118
City of Fayetteville, Arkansas 113 West Mountain Street
Fayetteville, AR 72701
l (479) 575-8323
Text File
File Number: 2018-0517
Agenda Date: 10/2/2018 Version: 1 Status: Passed
In Control: City Council Meeting File Type: Resolution
Agenda Number: A. 3
ALLGEIER, MARTIN AND ASSOCIATES, INC.:
A RESOLUTION TO APPROVE SUPPLEMENTAL AGREEMENT NO. 2 WITH ALLGEIER, MARTIN
AND ASSOCIATES, INC. IN AN AMOUNT NOT TO EXCEED $35,000.00 FOR ADDITIONAL
ELECTRICAL ENGINEERING SERVICES ASSOCIATED WITH ELECTRICAL WORK AT THE
NOLAND WATER RESOURCE RECOVERY FACILITY
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Jordan to sign
Supplemental Agreement No. 2 with Allgeier, Martin and Associates, Inc. in an amount not to exceed
$35,000.00 for additional electrical engineering services associated with electrical work at the Noland Water
Resource Recovery Facility.
City of Fayetteville, Arkansas Page 1 Printed on 10/312018
Tim Nyander
City of Fayetteville Staff Review Form
Legistar File ID
10/2/2018
City Council Meeting Date - Agenda Item Only
N/A for Non -Agenda Item
9/14/2018
Submitted By Submitted Date Division / Department
Action Recommendation:
WATER SEWER (720)
Staff recommends approval of Supplemental Agreement No. 2 Allgeier, Martin and Associates, Inc. for additional
electrical engineering services in the not to exceed amount of $35,000.00. The requested services include
expediting the design of the 15kV portions of the electrical work for the Noland WWTP into an additional
construction contract with additional inspection time required. The proposed contract cost will be increased
$35,000.00 from the existing $526,193.00 to $561,193.00.
5400.730.5800-5400.00
Account Number
02032.1
Project Number
Budgeted Item? Yes
Budget Impact:
Water and Sewer
Fund
WWTP Building Improvements
Project Title
Current Budget
Funds Obligated
Current Balance
Does item have a cost? Yes Item Cost
Budget Adjustment Attached? No Budget Adjustment
Remaining Budget
$
563,681.00
$
528,324.70
f $ 35,356.30
$
35,000.00
'
'56.30
V20180321
Purchase Order Number: 2017-00000796 Previous Ordinance or Resolution # 262-17, 143-18
Change Order Number:
Original Contract Number: 2017-0000040
Comments:
Approval Date:
CITY OF
FAYETTEVILLE
ARKANSAS
MEETING OF OCTOBER 2, 2018
TO: Mayor and City Council
THRU: Don Marr, Chief of Staff
Water & Sewer Committee September 11, 2018
FROM: Tim Nyander, Utilities Director
DATE: September 5, 2018
CITY COUNCIL MEMO
SUBJECT: Supplemental Agreement No. 2 to the Engineering Services Contract with
Allgeier, Martin and Associates, Inc. for electrical engineering services
RECOMMENDATION:
Staff recommends approval of Supplemental Agreement No. 2 Allgeier, Martin and Associates,
Inc. for additional electrical engineering services in the not to exceed amount of $35,000.00.
The requested services include expediting the design of the 15kV portions of the electrical work
for the Noland WWTP into an additional construction contract with additional inspection time
required. The proposed contract cost will be increased $35,000.00 from the existing
$526,193.00 to $561,193.00.
BACKGROUND:
The current contract with Allgeier, Martin and Associates, Inc for electrical engineering services
was approved by the City Council on December 5, 2017 by Resolution 262-17, with previous
Supplemental Agreement No. 1 added by Resolution 143-18 on July 3, 2018.
DISCUSSION:
The proposed electrical engineering services contract Supplemental Agreement is requested to
expedite the15kV portions of the electrical work for the Noland WWTP.
BUDGET/STAFF IMPACT:
Funding is available in the WWTP Building Improvements project.
Attachments:
Proposed Supplemental Agreement No. 1 with attached Appendix A
Mailing Address:
113 W. Mountain Street www.fayetteville-ar.gov
Fayetteville, AR 72701
561,193.00.Supplemental Agreement No. 2
Allgeier, Martin and Associates, Inc.
Date: October 2, 2018
Whereas, the City of Fayetteville, Arkansas (Owner) and Allgeier, Martin and Associates, Inc.
(Engineer) entered into an Agreement for Professional Engineering Services (Agreement) on
December 5, 2017 by City of Fayetteville Resolution 262-17; and, Resolution 143-18,
Supplemental Agreement no. 1 dated July 3, 2018.
Whereas, the City of Fayetteville has requested that the Engineer perform additional services
outside the scope of the Agreement.
Now therefore, the following modifications will be made to the Agreement to include the
additional services requested:
Modifications:
1. Section 2.1.1—the additional scope of services dated 08/30/2018 by Allgeier, Martin
and Associates, Inc. to add a second construction contract per attached four pages
Appendix A.
2. Section 5.1- the maximum not -to -exceed amount is increased $35,000.00 from
$526,193.00 to $561,193.00.
In witness whereof, the parties execute this Supplemental Agreement No. 2, to be effective on
the date executed by the Mayor, City of Fayetteville and as noted above.
Allgeier, Martin and Associates, Inc.
City of I
BY:
City of I
AGREEMENT FOR ENGINEERING SERVICES
APPENDIX A — SCOPE OF SERVICES
This is Appendix A, consisting of four (4) pages, referred to in and part of the Agreement For
Professional Services between the CITY OE FA T E-;V1LLr3, ARKANSAS and ALLGEIER, MARTIN
AND ASSOCIATES, INC. dated iov
Initial:
CITY OF FAYETTEVILL
ALLGEIER, MARTIN AND ASSOCIATES, INC.
The following contains additional Scope of Services tasks:
A.1 General Scope
The work covered by this Amendment includes separating the original scope of work for the
Agreement into an additional part. This additional pant includes a faster schedule on the design,
solicitation of bids for material and construction, contract procurement, inspection and
construction support of the 15kV electrical upgrades and their associated 480V equipment to the
Paul R. Noland Wastewater Treatment Plant (WWTP). This additional part will require one
additional construction contract.
A.2 Specific Scope of Services
ALLGEIER, MARTIN AND ASSOCIATES, INC. shall provide a suitable engineering staff to
obtain the necessary field information required to provide the following services:
A.2.1 Bidding
ALLGEIER, MARTIN AND ASSOCIATES, INC. shall prepare documentation and
specifications and solicit bids for the project to qualified electrical contractors. This shall
utilize one construction contract. ALLGEIER, MARTIN AND ASSOCIATES, INC. shall
review all bids and recommend the lowest bidder. The contract shall cover all of the 15kV
portions and their associated 480V equipment.
A.2.2 Contract Procurement
ALLGEIER, MARTIN AND ASSOCIATES, INC. shall review invoices from the successful
bidder and make recommendations for payment to the CITY OF FAYETTEVILLE, AR.
Z:IMUNICIPALTayetteville ARIIGENERAL\Proposals1262-17 Noland WWTP1Agmt 2 PES Fayetteville.doex
A —14 022403
Once construction is completed, ALLGEIER, MARTIN AND ASSOCIATES, INC. shall
perform a closeout of the contract.
A.2.3 Construe i. Suppai t
ALLGEIER, MARTIN AND ASSOCIATES, INC. shall provide construction support for the
duration of the construction phase. This includes phone calls, e-mails, meetings and field
visits.
A.3 Project Deliverables
The following shall be submitted to the CITY OF FAYETTEVILLE, AR.;
Drawings and as -built records of new equipment at the Paul R. Noland WWTP
Electrical schematics of new equipment at the Paul R. Noland WWTP
A.4 Com,pensatioii
In consideration of the performance of the foregoing services by ALLGEIER, MARTIN
AND ASSOCIATES, INC., the CITY OF FAYETTEVILLE, AR. shall pay to ALLGEIER,
MARTIN AND ASSOCIATES, INC. compensation as set forth in Section 5 of the
Agreement for Professional Engineering Services.
A.4.1 Attachments
A.4.1.1 Exhibit A - ALLGEIER, MARTIN AND ASSOCIATES, INC. Rate Schedule
A.4.1.2 Exhibit B — Estimates of Expenses
A.5 Schedule
ALLGEIER, MARTIN AND ASSOCIATES, INC. will begin immediately on this contract
procurement. AM shall prepare the contract and plans and specification documents for bid
solicitations. AM shall then forward these documents to the city for review. Once approved,
bid solicitation should take approximately eight weeks to complete.
Z:WUNICIPALTayetteville AR\1GENERAL\Proposals\262-17 Noland WWTP\Agmt 2 PPS Fayetteville.docx
A — 15 022403
EXHIBIT A
ALLGEIER, MARTIN AND ASSOCIATES, INC. RATE SCHEDULE
2018-2019
LABOR RATES
Note: All pre -approved overtime hours shall be invoiced at 1'/2 times the hourly billing rate shown above.
NON -LABOR RATES
Item
Travel
Subsistence
Lodging
Special Postage or Shipping
Printing
Surveying Materials
Subcontract Specialty Services
Rate
$0.54 per mile (or current IRS rate)
Actual Cost
Actual cost
Actual cost
Actual cost
Actual cost
Cost + 10%
Z:\MUNICIPAUFayetteville ARIIGENERAUProposals1262-17 Noland WWTPWgrnt 2 PES Fayetteville.docx
A —16 022403
Hourly
Billing Ratti
01/01/2018
01/01/2019
thru
thru
Classification12/31/2018
12/31/2019
Principal/Engineer IV
$195
$199
Principal/Engineer 111
$180
$185
Principal/Engineer 11
$150
$155
Principal/Engineer I
$140
$145
Designer III/GIS Specialist
$132
$136
Designer/Technician 111
$112
$116
Designer/Technician 11
$80
$85
Designer/Technician 1
$75
$80
Two -Man GPS Survey Crew
$185
$189
One -Man GPS Survey Crew
$145
$150
Three -Man Survey Crew
$201
$201
Two -Man Survey Crew
$160
$165
Registered Land Surveyor H
$170
$174
Registered Land Surveyor 1
$150
$155
Survey Crew Member
$76
$80
Right of Way Specialist
$116
$120
Project Representative 111
$112
$116
Project Representative 11
$100
$105
Project Representative 1
$92
$96
Clerical
$70
$75
Print Specialist
$70
$75
Note: All pre -approved overtime hours shall be invoiced at 1'/2 times the hourly billing rate shown above.
NON -LABOR RATES
Item
Travel
Subsistence
Lodging
Special Postage or Shipping
Printing
Surveying Materials
Subcontract Specialty Services
Rate
$0.54 per mile (or current IRS rate)
Actual Cost
Actual cost
Actual cost
Actual cost
Actual cost
Cost + 10%
Z:\MUNICIPAUFayetteville ARIIGENERAUProposals1262-17 Noland WWTPWgrnt 2 PES Fayetteville.docx
A —16 022403
X111= _
ESTIMATES OF EXPENSES
Paul R. Noland WWTP Electrical Upgrades
Engineer 111 112 hrs.
$20,160
Technician 111 30 hrs.
$3,360
Clerical 147 hrs.
$10,290
Print Specialist 14 hrs.
$980
Non -Labor Costs
210
Subtotal Estimated Engineering Cost
$35,000
Total Cost for Engineering
$35,000
Z:\Iv1UNICIPALWayetteville AR\1GENERAL\Proposa1s\262-17 Noland WWTP\Agmt 2 PES Fayetteville,docx
A -- 17 022403