Resolution: 199-18
File Number: 2018-0482
81 CONSTRUCTION GROUP, INC.:
A RESOLUTION TO APPROVE A CHANGE ORDER TO THE CONTRACT WITH 81
CONSTRUCTION GROUP, INC. IN THE AMOUNT OF $53,750.00 FOR THE EAST SPYGLASS
HILL DRIVE DRAINAGE IMPROVEMENTS PROJECT TO EXPAND THE SCOPE OF SERVICES TO
INCLUDE ADDITIONAL ROCK EXCAVATION AND TO ADD 45 DAYS TO THE CONTRACT TIME
DUE TO DELAYS CAUSED BY THE UNPLANNED ROCK EXCAVATION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves a change order
to the contract with 81 Construction Group, Inc. in the amount of $53,750.00 for the East Spyglass Hill
Drive Drainage Improvements Project to expand the scope of services to include additional rock
excavation and to add 45 days to the contract time due to delays caused by the unplanning rock
excavation.
PASSED and APPROVED on 9/18/2018
Attest:
Sondra E. Smith, City Clerk Treasurer �N"pitI11111�rir
�� G . G�"[ `I nF •'per+•►
'`
rrr:'S';�vG i0N
Page 1 Printed on 9124118
City of Fayetteville, Arkansas 113 West Mountain Street
Fayetteville, AR 72701
1 (479) 575-8323
Text File
3:•
File Number: 2018-0482
Agenda Date: 9/18/2018 Version: 1 Status: Passed
In Control: City Council Meeting File Type: Resolution
Agenda Number: A. 10
81 CONSTRUCTION GROUP, INC.:
A RESOLUTION TO APPROVE A CHANGE ORDER TO THE CONTRACT WITH 81
CONSTRUCTION GROUP, INC. IN THE AMOUNT OF $53,750.00 FOR THE EAST SPYGLASS
HILL DRIVE DRAINAGE IMPROVEMENTS PROJECT TO EXPAND THE SCOPE OF SERVICES
TO INCLUDE ADDITIONAL ROCK EXCAVATION AND TO ADD 45 DAYS TO THE CONTRACT
TIME DUE TO DELAYS CAUSED BY THE UNPLANNED ROCK EXCAVATION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS:
Section 1 : That the City Council of the City of Fayetteville, Arkansas hereby approves a change order to the
contract with 81 Construction Group, Inc. in the amount of $53,750.00 for the East Spyglass Hill Drive
Drainage Improvements Project to expand the scope of services to include additional rock excavation and to
add 45 days to the contract time due to delays caused by the unplanning rock excavation.
City of Fayetteville, Arkansas Page 1 Printed on 912512018
City of Fayetteville Staff Review Form
Legistar File ID
9/18/2018
City Council Meeting Date - Agenda Item Only
N/A for Non -Agenda Item
Engineering /
Matt Casey 8/29/2018 Development Services Department
Submitted By Submitted Date Division / Department
Action Recommendation:
Approval of a change order in the amount of $53,750.00 to the contract with 81 Construction Group, Inc. for the
construction of the E. Spyglass Hill Dr, Drainage Improvements Project.
4470.621.8810-5817.00
Account Number
02108.1802.40
Project Number
Budgeted Item? Yes
Budget Impact:
Other Drainage Improvements
Fund
E Spyglass Hill Drainage Improvments
Current Budget
Funds Obligated
Current Balance
Does item have a cost? Yes Item Cost
Budget Adjustment Attached? No Budget Adjustment
Previous Ordinance or Resolution #
Original Contract Number:
Comments:
134-18
Remaining Budget
Project Title
$
573,078.00
$
200,368.29
372,709.71
$
53,750.00
$
318,959.71
Approval Date:
V20140710
CITY OF
FAYETTEVILLE
W Arg ARKANSAS
MEETING OF SEPTEMBER 18, 2018
TO: Mayor and City Council
THRU: Don Marr, Chief of Staff
Garner Stoll, Development Services Director
Chris Brown, City Engineer
FROM: Matt Casey, Engineering Design Manager
CITY COUNCIL MEMO
DATE: August 29, 2018
SUBJECT: Approval of a change order in the amount of $53,750.00 to the contract with
81 Construction Group, Inc. for the construction of the E. Spyglass Hill Dr,
Drainage Improvements Project.
RECOMMENDATION:
Staff recommends City Council approval of change order #1 in the amount of $53,750.00 to the
contract with 81 Construction Group, Inc. for the construction of the E. Spyglass Hill Dr.
Drainage Improvements Project.
BACKGROUND:
The City of Fayetteville Engineering Division has prepared the design for this 36" storm sewer
that is planned behind several homes along E. Spyglass Hill Drive. A large drainage basin
drains runoff across the Stonebridge Meadows golf course into the yards and to these homes
along the northeast end of this street. In an effort to provide relief from future flood damage to
these properties, the City of Fayetteville coordinated with the owner of the golf course to get a
drainage easement dedicated to allow the installation of the necessary storm sewer pipes and
inlets to capture and convey this runoff to the nearby retention pond.
On June 19, 2018 the City Council approved a contract in the amount of $118,881.18 with 81
Construction Group, Inc., who was the low bidder for this project.
DISCUSSION:
81 Construction Group, Inc. has been diligently working to get this project completed.
Unfortunately after getting the first 150' of storm sewer installed, rock was encountered. This
slowed the construction considerably. The contractor continued on and we expected to get out
of the rock quickly to finish the construction. Instead, the rock depth was worse as they
progressed. On every construction project, we put in a small amount of rock excavation in the
contract in case we encounter some rock. If rock is known or expected to be encountered, this
amount is raised based on the amount of construction proposed. For this project a small
amount of 20 cubic yards was in the bid. That amount was quickly used up. We estimate that
the total amount of rock excavation for this project will be 235 cubic yards. Staff is also
Mailing Address:
113 W. Mountain Street www.fayetteville-ar.cgov
Fayetteville, AR 72701
recommending that an additional 45 days be added to the contract due to the delays from the
rock excavation.
BUDGET/STAFF IMPACT:
This project is paid for out of the "Other Drainage Improvements" project of the Sales Tax
Capital Improvements Bridge and Drainage Improvements Fund.
Attachments:
Change Order 1 Form
Vicinity Map
2W,
rel
�I
00
- d
4 Oi
M�
� d
z
o ti
0
yU
FAA] • O
0 PQ
O
r C
k o
ug- kn
t-
W uCr v W
r•4 +•� O r -I
Y4
CIOn06 n b
000 wmn
ro
c
U
b4 1,146-1 V. 6'4
kn
le
z
rl
b
O
a
o
U
fn
GU
w,
�
cq
o
«7
U.
0
fn
69
O
N
a.
S
O
N
U
r�wa
O
4
•�
^^�
C)
fil
J
•C
O
r C
k o
ug- kn
t-
W uCr v W
r•4 +•� O r -I
Y4
CIOn06 n b
000 wmn
ro
c
U
b4 1,146-1 V. 6'4
kn
le
z
rl
E !BRVG LASS HILL 13 Ft
a FtAI N^C3i E I M P R aVE M E N7a
for the
City of F'ayettevilje
BID # 18-35, CONSTRUCTION
APRIL, 2018
V
v
J i
Project
Location :
o
a
VICINITY MAP
Alft CITY OF
FAYETTEVILLE
ARKANSAS
www,fayetteviUe-ar.gov
ENGINEERING DIVISION
PHONE: (479) 575-8206 FAX NO: (479) 575-8202
PROJECT: ENGR. No. 8126