Resolution: 208-17
File Number: 2017-0505
GARDEN DISTRICT TOWNHOMES, LLC:
A RESOLUTION TO APPROVE A COST SHARE AGREEMENT WITH GARDEN DISTRICT
TOWNHOMES, LLC FOR CONSTRUCTION OF A SEWER MAIN ALONG A PORTION OF 9th
STREET BETWEEN SOUTH COLLEGE AVENUE AND SOUTH WASHINGTON AVENUE WITH
THE TOTAL COST TO GARDEN DISTRICT TOWNHOMES NOT TO EXCEED $5,611.14
WHEREAS, Garden District Townhomes, LLC will be developing property located at the corner of 9th
Street and South Washington Avenue and has requested that the City share in the cost of constructing
an 8 -inch sewer main along a portion of 9th Street between South College Avenue and South Washington
Avenue, a distance of approximately 130 feet; and
WHEREAS, constructing this segment of 8 -inch main will allow Garden District Townhomes, LLC to
develop the property, and will also allow for ample future capacity which the City recognizes will be
necessary for the area that is served by this sewer main; and
WHEREAS, § 51.113 of the Fayetteville City Code provides that "the City shall pay the excess material
cost of facilities of a size larger than required to serve subdivisions when such excess size is specified
and required by the Water and Wastewater Director for the general benefit of the sewerage system."
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves a cost share
agreement with Garden District Townhomes, LLC for construction of a sewer main along a portion of
9th Street between South College Avenue and South Washington Avenue, with the total cost to
Page 1 Printed on 1014117
Resolution: 208-17
File Number 2017-0505
Garden District Townhomes, LLC not to exceed $5,611.14.
PASSED and APPROVED on 10/3/2017
Attest:
Sondra E. Smith, City Clerk Treasurer
W1111TtrifiI
,f
r�
�`��# �;• X13 y 0,� D. 6,;,
5�
�. FAYFT7TEVILLE a#
4,4
�IFEOElilll
Page 2 Printed on 10/4117
City of Fayetteville, Arkansas 113 West Mountain Street
Fayetteville. AR 72701
(479) 575-8323
,r Text File
File Number: 2017-0505
Agenda Date: 10/3/2017 Version: 1 Status: Passed
In Control: City Council Meeting File Type: Resolution
Agenda Number: A. 14
GARDEN DISTRICT TOWNHOMES, LLC:
A RESOLUTION TO APPROVE A COST SHARE AGREEMENT WITH GARDEN DISTRICT
TOWNHOMES, LLC FOR CONSTRUCTION OF A SEWER MAIN ALONG A PORTION OF 9th
STREET BETWEEN SOUTH COLLEGE AVENUE AND SOUTH WASHINGTON AVENUE WITH
THE TOTAL COST TO GARDEN DISTRICT TOWNHOMES NOT TO EXCEED $5,611.14
WHEREAS, Garden District Townhomes, LLC will be developing property located at the corner of 9th Street
and South Washington Avenue and has requested that the City share in the cost of constructing an 8 -inch sewer
main along a portion of 9th Street between South College Avenue and South Washington Avenue, a distance of
approximately 130 feet; and
WHEREAS, constructing this segment of 8 -inch main will allow Garden District Townhomes, LLC to develop
the property, and will also allow for ample future capacity which the City recognizes will be necessary for the
area that is served by this sewer main; and
WHEREAS, § 51.113 of the Fayetteville City Code provides that "the City shall pay the excess material cost
of facilities of a size larger than required to serve subdivisions when such excess size is specified and required
by the Water and Wastewater Director for the general benefit of the sewerage system."
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1 : That the City Council of the City of Fayetteville, Arkansas hereby approves a cost share agreement
with Garden District Townhomes, LLC for construction of a sewer main along a portion of 9th Street between
South College Avenue and South Washington Avenue, with the total cost to Garden District Townhomes, LLC
not to exceed $5,611.14.
City of Fayetteville, Arkansas Page 1 Printed on 101412017
City of Fayetteville Staff Review Form
2017-0505
Legistar File ID
10/3/2017
City Council Meeting Date - Agenda Item Only
N/A for Non -Agenda Item
Tim Nyander 9/12/2017
Submitted By Submitted Date
Action Recommendation:
Utilities Director /
Utilities Department
Division / Department
A RESOLUTION TO APPROVE A COST SHARE AGREEMENT WITH GARDEN DISTRICT TOWNHOMES, LLC FOR
CONSTRUCTION OF A SEWER MAIN ALONG A PORTION OF 9TH STREET BETWEEN SOUTH COLLEGE AVENUE AND
SOUTH WASHINGTON AVENUE, WITH A TOTAL ESTIMATED COST OF $5,611.14 INCLUDING A 20% PROJECT
CONTINGENCY
5400.720.5700-5815.00
Account Number
04039.1
Budget Impact:
Water/Sewer
- Fund
Water/Sewer Impact Fee Cost Sharing Project
Project Number
Project Title
Budgeted Item? Yes
Current Budget
$
1,230,231.00
Funds Obligated
$
227,873.15
Current Balance
$
1,002,357.85
Does item have a cost? Yes
Item Cost
$
5,611.14
Budget Adjustment Attached? No
Budget Adjustment
$
-
Remaining Budget
$
996,746.71
a
V20140710
Previous Ordinance or Resolution #
Original Contract Number: Approval Date:
Comments:
CITY OF
FAYETTEVILLE
ARKANSAS
MEETING OF OCTOBER 3, 2017
TO: Mayor and City Council
THRU: Don Marr, Chief of Staff
Water & Sewer Committee
FROM: Tim Nyander, Utilities Director
DATE: September 12, 2017
CITY COUNCIL MEMO
SUBJECT: Cost Share Agreement with Garden District Townhomes, LLC for
Construction of a Sewer Line on 911 Street
RECOMMENDATION:
Staff recommends approval of a cost share agreement between the City of Fayetteville and
Garden District Townhomes, LLC to share the costs of constructing a 130 ft. sewer line on 9th
Street, between South College Avenue and South Washington Avenue in the not -to -exceed
amount of $4,675.95, and approval of a project contingency in the amount of $935.19 for a
total cost of $5,611.14.
BACKGROUND:
On September 5, 2017, City Council approved Ordinance 5995 for the City to share in the costs
of building a waterline on 9th Street with Garden District Townhomes, LLC. This water portion
of the cost share is being performed by a contractor so that item included a bid waiver
ordinance.
DISCUSSION:
Garden District Townhomes, LLC has requested that the City share in the cost of constructing
an 8 -inch sewer line along a portion of 9th Street between South College Avenue and South
Washington, a distance of approximately 130 feet. The sewer portion of the cost share will be
done in-house by City of Fayetteville sewer crews. The City of Fayetteville will furnish the
labor, materials and equipment for the sewer main installation, and Garden District
Townhomes, LLC will pay no more than $$5,611.14 (includes 20% contingency). The City of
Fayetteville will bear any costs beyond that amount.
Installing this approximately 130 -foot segment of 8 -inch sewer main will allow Garden District
Townhomes, LLC to develop the property, and also allow for ample future capacity.
Mailing Address:
113 W. Mountain Street www.fayetteville-ar.gov
Fayetteville, AR 72701
BUDGET/STAFF IMPACT:
Funds for the City's portion are available in the Water/Sewer Impact Fee Cost Sharing Project.
Attachments:
Cost Share Agreement
Map of Area
Ordinance 5995
CONTRACTUAL AGREEMENT FOR
COST SHARE OF SEWER MAIN INSTALLATION COSTS
This Agreement, made and entered into on this 3" day of October 2017, by and between
the City of Fayetteville, Arkansas ("City") and Garden District Townhomes, LLC., witnesseth:
WHEREAS, Garden District Townhomes, LLC received approval by the City's Planning
Department on April 11, 2016, for lot splits at the corner of 91, Street and South Washington
Avenue; and
WHEREAS, Garden District Townhomes, LLC has requested that the City construct and
share in the cost of constructing an 8 -inch sewer main along a portion of 91 Street between South
College Avenue and South Washington Avenue, a distance of approximately 130 feet, to
facilitate the lot splits and increase population density.
WHEREAS, constructing this segment of 8 -inch main will allow Garden District
Townhomes, LLC to develop the property, and also allow for ample future capacity which the
City recognizes will be necessary for the area that is served by this sewer main; and
WHEREAS, § 51.113 of the Fayetteville City Code provides that "the City shall pay the
excess material cost of facilities of a size larger than required to service subdivisions when such
excess size is specified and required by the water and wastewater director for the general benefit
of the sewerage system."
NOW, THEREFORE, the City of Fayetteville, Arkansas and Garden District
Townhomes, LLC agree as follows:
1. The City of Fayetteville, Arkansas agrees to:
A. Furnish the labor, materials, and equipment to install approximately 130 linear
feet of 8 -inch sewer main on 91h Street between South College Avenue and South
Washington Avenue.
13. Bear any costs associated with the sewer main installation that exceed the amount
Garden District Townhomes, LLC agrees to pay below.
2, Garden District Townhomes, LLC. agrees to:
A. Reimburse the City for the materials cost of the sewer main installation up to a
maximum -not -to -exceed amount of 54,675.95 plus a 20% contingency of
$935.19, for a total cost of $5,6111.14 which represents the cost estimated by
the City of Fayetteville.
B. Make payment to the City of Fayetteville within thirty (30) days utter receipt
of a valid invoice.
IN AGREEMENT WITH ALL THE TERMS AND CONDITIONS ABOVE, WE
SIGN BELOW;
GARDEN DISTRICT
TOWNHOMES, LLC
By4d"r
ZINIEDERMAN,
g Member
ATTEST:
By: 4-466-uu-
OFFiGIAL SEAL
MAN01 Mc6UJPE
NOTARY PUBLIC ARKo�N$A$
WASHINGTON COUNTY
COMMISSION # 1237%37
C Om I$$I N EXP VI55%=
CITY
OF FAYETTEVILLE,
ATTEST:
By; r+-- E. 4"'y
SONDRA SMITH, City Clerk
0111111111/111,
Ci
• FAYETTEVILLE.
�`rr'�is•a�kAi co
•
113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
Ordinance: 5995
.File Number: 2017-0461
GARDEN DISTRICT TOWNHOMES, LLC:
AN ORDINANCE TO WAIVE THE REQUIREMENTS OF FORMAL COMPETITIVE BIDDING AND
APPROVE A COST SHARE AGREEMENT WITH GARDEN DISTRICT TOWNHOMES, LLC FOR THE
INSTALLATION OF WATER MAIN ALONG A PORTION OF 9TH STREET BETWEEN SOUTH
COLLEGE AVENUE AND SOUTH WASHINGTON AVENUE, WITH THE ESTIMATED AMOUNT
TO BE PAID BY THE CITY OF FAYETTEVILLE NOT TO EXCEED $16,327.50, AND TO APPROVE
A PROJECT CONTINGENCY IN THE AMOUNT OF $1,632.75
WHEREAS, Garden District Townhomes, LLC will be developing property located at the corner of 9th
Street and South Washington Avenue and has requested that the City share in the cost of constructing a
6 -inch sewer main along a portion of 9th Street between South College Avenue and South Washington
Avenue, a distance of approximately 3=40 feet; and
WHEREAS, the City of Fayetteville would benefit from the cost share as it will upgrade infrastructure
in the core of the City, improve service and fire protection for residents and business in the area, allow
for a secondary water loop to help prevent the possibility of residents losing water service in the event
of a . water teak in the area, and provide for ample future capacity which will facilitate future
development; and
WHEREAS, § 51.112 of the Fayetteville City Code provides that "the City shall pay the excess material
cost of facilities of a size larger than required to service subdivisions when such excess size is specified
and required by the water and wastewater director for the general benefit of the sewerage system"; and
WHEREAS, waiving formal competitive bidding will save time and cost by utilizing the developer's
contractor who will be on-site installing the line for the developer's project.
Page I Prinfed on 916117
Ordinance: 5995
File Number 2017-0461
NOW, THEREFORE, BE IT ORDAINED BY THE CITY COUNCIL, OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section l: That the City Council of the City of Fayetteville. Arkansas hereby determines an
exceptional situation exists in which competitive bidding is deemed not feasible or practical and
therefore waives the requirements of formal competitive bidding and approves a cost share agreement
with Garden District Townhomes, LLC for the installation of a 6 -inch water main along a portion of 9th
Street between South College Avenue and South Washington Street with the estimated amount to be paid by
the City of Fayetteville not to exceed $16,327.50, and further approves a project contingency in the
amount of $1,632.75.
PASSED and APPROVED on 9/5/2017