Resolution: 115-17
File Number: 2017-0270
BENCHMARK CONSTRUCTION OF NWA, INC. CHANGE ORDER NO. 3:
A RESOLUTION TO APPROVE CHANGE ORDER NO. 3 TO THE CONTRACT WITH
BENCHMARK CONSTRUCTION OF NWA, INC. IN THE AMOUNT OF $42,021.00 FOR THE
CONSTRUCTION OF A GRAVEL ACCESS DRIVE, CONCRETE PIER PADS AND IRRIGATION
SYSTEM AT THE FIRE DEPARTMENT TRAINING FACILITY, AND TO APPROVE A PROJECT
CONTINGENCY IN THE AMOUNT OF $4,202.10
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves Change Order No. 3
to the contract with Benchmark Construction of NWA, Inc. in the amount of $42,021.00 for the construction
of a gravel access drive, concrete pier pads and irrigation system at the Fire Department Training Facility,
and further approves a project contingency in the amount of $4,202.10.
PASSED and APPROVED on 6/6/2017
Page 1
Attest:
Sondra E. Smith, City Clerk Treasur ►�ca+��trr��
Y C)'�'
i
may•
=':FAYFIF- 4 -LL:
fyd, 9RkA' A -I' , •`j ,''
r:�N[1
Printed on 6!1/17
City of Fayetteville, Arkansas
a
Text File
-J— File Number: 2017-0270
Agenda Date: 6/6/2017 Version: 1
In Control: City Council Meeting
Agenda Number: A. 5
BENCHMARK CONSTRUCTION OF NWA, INC. CHANGE ORDER NO. 3:
113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
Status: Passed
File Type: Resolution
A RESOLUTION TO APPROVE CHANGE ORDER NO. 3 TO THE CONTRACT WITH
BENCHMARK CONSTRUCTION OF NWA, INC. IN THE AMOUNT OF $42,021.00 FOR THE
CONSTRUCTION OF A GRAVEL ACCESS DRIVE, CONCRETE PIER PADS AND IRRIGATION
SYSTEM AT THE FIRE DEPARTMENT TRAINING FACILITY, AND TO APPROVE A PROJECT
CONTINGENCY IN THE AMOUNT OF $4,202.10
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves Change Order
No. 3 to the contract with Benchmark Construction of NWA, Inc. in the amount of $42,021.00 for the
construction of a gravel access drive, concrete pier pads and irrigation system at the Fire Department
Training Facility, and further approves a project contingency in the amount of $4,202.10.
City of Fayetteville, Arkansas Page 1 Printed on 8!7/2017
City of Fayetteville Staff Review Form
2017-0270
Legistar File ID
6/6/2017
City Council Meeting Date - Agenda Item Only
N/A for Non -Agenda Item
David Dayringer 5/17/2017
Submitted By Submitted Date
Action Recommendation:
Fire /
Fire Department
Division / Department
Staff recommends approval of Change Order #3 and a 10% Contingency to the contract with Benchmark
Construction for a gravel access drive to the river, additional concrete pier pads, and irrigation for trees.
r�Idr�:IrIi �iL� [iIi;
Account Number
17001.1
Project Number
Budgeted Item? Yes
Budget Impact:
Sales Tax Capital
FundW��
Fire Training Grounds
Current Budget
Funds Obligated
Current Balance
Does item have a cost? Yes Item Cost
Budget Adjustment Attached? No Budget Adjustment
Project Title
$
948,684.00
$
819,218.18
$—
129,465,82 l
$
46, 223.10
Remaining Budget $ 83,242.7E
V20140710
Previous Ordinance or Resolution # #03-17
Original Contract Number:
Approval Date:
Comments: City Council approved on January 3, 2017 through Resolution No. 03-17 awarding Bid Number 16-64
authorizing a contract with Benchmark Construction of NWA, Inc. in the amount of $485,058.00.
Change Order #1 added $32,603.56 to the contract. Change Order #2 added $195,377 to the contract.
Proposed Change Order #3 will add $42,021 to the contract. This will make the total contract amount
with Benchmark $755,059.56 as reflected in the Change Order Summary.
CITY OF
FAYETTEVILLE
ARKANSAS
MEETING OF JUNE 6, 2017
TO: Mayor Jordan and City Council
FROM: David Dayringer, Fire Chief
DATE: May 17, 2017
CITY COUNCIL MEMO
SUBJECT: Approval of Change Order #3—Fire Training Grounds and approval of a
10% Contingency
RECOMMENDATION:
Staff recommends approval of Change Order #3 and a 10% Contingency to the contract with
Benchmark Construction for a gravel access drive to the river, additional concrete pier pads,
and irrigation for trees.
BACKGROUND:
City Council approved on January 3, 2017 through Resolution No. 03-17 awarding Bid Number
16-64 authorizing a contract with Benchmark Construction of NWA, Inc. in the amount of
$485,058.00. Change Order #1 was approved in February,2017 in the amount of $32,603.56.
Change Order #2 was approved in April,2017 in the amount of $195,377 plus a contingency of
$29,307 utilizing IMPACT FEE funds. Proposed Change Order #3 will add $42,021 to the
contract plus a contingency of $4,202.10. This will make the contract with Benchmark
$755,059.56 ($485,058 +$32,603.56 + $195,377 + $42,021)
DISCUSSION:
Benchmark Construction has provided a cost for a 1500 ft. gravel access drive to the river,
additional concrete pier pads, and irrigation for trees which totals $42,021.00 plus a 10%
Contingency. The gravel drive will allow access to the White River for Fire Department swift
water rescue training. The additional pier pads were recommended per the manufacturer_ The
irrigation system will ensure the proper care and longevity of the trees planted at the Fire
Training Grounds.
BUDGET/STAFF IMPACT:
The finances- required for this project are already budgeted in the Fire Sales Tax Project: Fire
Training Grounds
Attachments:
Change Order #3 Document
Mailing Address:
113 W. Mountain Street www.fayetteville-ar.gov
Fayetteville, AR 72701
CHANGE ORDER
T *41
ayve le
Contract Title Fire Department Training Facility
Change Order No 3 Date of Issuance
To Contractor: Benchmark Construction of NWA, Inc. ORDINANCE/RESOLUTION: 03-17
The Contract is changed as follows:
Effective January 3, 2017
Bid
Bid
Previous
Unit
Contract
Revised
Revised
Original
Revised
Item
Item
Estimated
of
Unit
Estimated
Unit
Estimated
Estimated
No.
Description
Quantity
Measure
Price
Quantity
Price
Cost
38
Gravel Access Drive to River
0
LS
$0.00
1
$24,535.00
$0.00
$24,535.00
39
Additional Concrete Pier Pads
0
LS 1
$0.00
1 1
$1,956.00
50.00
$1,956.00
40
Irrigation for Trees
0
LS
$0.00
1
$15,530.00
50.00
$15,530.00
until signed by the
The ori-in'al Contract Price was
Net change by previously authorized change orders
The Contract Price prior to this Change Order was
The Contract Price will {increased byi Jrtbm,,:........hanged]
The new Contract Price including this Change Order will be
The Contract Time(s) will be [greased b ]jdeerease' L.-'r�d= :� • y -kge "
Required dates of Competion as of the date of this Change Order therefore are:
Summation of Cost $0.00 $42,021.00
Net Cost for this Change Order $42,021.00
227
calendar days
Substantial Completion 4/21/17
Final Completion ---------- 8/15/17
NOTE: This summary does not reflect changes in the Contract Price or Time(s) which have been authorized by Work Change Directives not incorporated in this
or previous Change Orders. The additional 57 days is for the change order work only. The concrete pad will still be required to meet the 4P7/17
s
Benchmark Construction of NWA, Inc. CITY FILYETT IL
4Z� 5-1-17
BY DATE f Y DATE