T -N -T, INC. CHANGE ORDER NO. 3:
A RESOLUTION TO APPROVE CHANGE ORDER NO. 3 TO THE CONTRACT WITH T -N -T, INC. OF
VAN BUREN, ARKANSAS IN THE AMOUNT OF $21,096.00 FOR ROAD AND PARKING
IMPROVEMENTS AT WILSON PARK, AND TO APPROVE A BUDGET ADJUSTMENT
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves Change Order No.
3 to the contract with T -N -T, Inc. of Van Buren, Arkansas in the amount of $21,096.00 for additional road
and parking improvements at Wilson Park.
Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget
adjustment, a copy of which is attached to this Resolution.
PASSED and APPROVED on 5/2/2017
Attest:
Sondra E. Smith, City Clerk Treasurer
0�%N`*,FK•/ T R:
N,ol Y C,c
=v; FAYETTEVILLE:
Page 1 '" / F
��i�;NG ii
City of Fayetteville, Arkansas 113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
rl Text File
=� File Number: 2017-0203
Agenda Date: 5/2/2017 Version: 1 Status: Passed
In Control: City Council Meeting File Type: Resolution
Agenda Number: A. 3
T -N -T, INC. CHANGE ORDER NO. 3:
A RESOLUTION TO APPROVE CHANGE ORDER NO. 3 TO THE CONTRACT WITH T -N -T,
INC. OF VAN BUREN, ARKANSAS IN THE AMOUNT OF $21,096.00 FOR ROAD AND
PARKING IMPROVEMENTS AT WILSON PARK, AND TO APPROVE A BUDGET
ADJUSTMENT
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTE.VILLE,
ARKANSAS:
Section l: That the City Council of the City of Fayetteville, Arkansas hereby approves Change Order
No. 3 to the contract with T -N -T, Inc. of Van Buren, Arkansas in the amount of $21,096.00 for
additional road and parking improvements at Wilson Park.
Section 2: That the CityCouncil of the City of Fayetteville, Arkansas hereby approves a budget
adjustment, a copy of which is attached to this Resolution.
City of Fayetteville, Arkansas Page 1 Printed on 51112017
City of Fayetteville Staff Review Form
2017-0203
Legistar File ID
5/2/2017
City Council Meeting Date - Agenda Item Only
N/A for Non -Agenda Item
Ken Eastin 4/12/2017
Parks & Recreation /
Parks & Recreation Department
Submitted By Submitted Date Division / Department
Action Recommendation:
Staff recommends approval of Change Order #3 in the amount of $21,096 to Contract #2016-00000014 with T -N -T,
Inc. for the installation of additional select road base fill and a change in pavement surfacing from asphalt to fiber -
reinforced concrete for extended durability, and approval of a budget adjustment.
2250.520.9255-5806.00
4470.900.9470-5819.00
Account Number
13001.1601
16004.1
Project Number
Budgeted Item? Yes
Budget Impact:
Park Development Fund
Sales Tax Cap Imp
Fund
Wilson Park Grant Match
Park Paving Improvements
Current Budget
Funds Obligated
Current Balance
Does item have a cost? Yes Item Cost
Budget Adjustment Attached? Yes Budget Adjustment
Remaining Budget
Project Title
$ 724,227.00
$ 583,598.00
$ 140,629.00
$ 21,096.00
$ 30,777.00
$ 150,330.00
V20140710
Previous Ordinance or Resolution # 231-16
Original Contract Number: 2016-0000001,
Comments:
Approval Date:
CITY OF
•
PayeeVlIe
ARKANSAS
MEETING OF MAY 2, 2017
TO: Mayor Lioneld Jordan
CITY COUNCIL AGENDA MEMO
THRU: Don Marr, Chief of Staff
Connie Edmonston, Parks and Recreation Director
Alison Jumper, Park Planning Superintendent
FROM: Ken Eastin, Park Planner II
DATE: April 10, 2017
SUBJECT: Approval of Change Order #3 in the amount of $21,096 to Contract #2016-
-00000014 with T -N -T, Inc. for the installation of additional structural select
road base fill and a change in pavement surface materials for road and
parking improvements at Wilson Park, and approval of a budget adjustment
RECOMMENDATION:
Staff recommends approval of Change Order #3 in the amount of $21,096 to Contract #2016-
00000014 with T -N -T, Inc. for the installation of additional select road base fill and a change in
pavement surfacing from asphalt to fiber -reinforced concrete for extended durability, and
approval of a budget adjustment.
BACKGROUND:
The City of Fayetteville contracted with T -N -T, Inc. to construct new curb and gutter along both
sides of the westernmost entry drive off Prospect Street at Wilson Park and along the
northwestern most edge of the parking lot. The contractor was also to remove the existing
asphalt from the entry drive, compact the subsurface soils, install a 4" compacted gravel base,
lay new asphalt surfacing, and construct a new van -accessible parking space adjacent to the
playground.
Change Order #1 was requested to receive approval for a. change in the contract scope in order
to include grading of a drainage swale into the lawn area on the north side of the western end of
the parking lot. This change was necessary to create a swale in the lawn that will contain and
direct runoff into an existing storm inlet. This will prevent continuation of a situation where the
drainage flows across Wilson Avenue and into a neighboring driveway and garage.
Change Order #2 was submitted after excavation of the existing asphalt drive began and
subsurface continues were discovered. Upon removal of the old asphalt, extensive clay soils
were encountered and the clay was totally saturated. Project specifications require compaction
of the immediate subgrade to a depth of 24". Due to the clay soils and high moisture conditions,
this compaction can not be accomplished. This has required complete removal of the existing
clay and replacement with select fill that will hold compaction, for a minimum depth of 24".
Mailing Address:
113 W. Mountain Street www.fayetteville-ar.gov
Fayetteville, AR 72701
DISCUSSION:
Change Order #3 is requesting approval for the following contract changes:
1) Unforeseen subsurface conditions and excessive moisture have required removal of a
larger amount of encountered expansive clay, requiring replacement with a larger
amount of select fill than originally anticipated plus an additional 9 SY of class 7 base (+
$1,816).
2) Due to a change in the layout of the parking and driveway to protect trees and provide
safe turning radius for buses, additional curb and gutter is required to complete the new
design (+ $1,425).
3) Change order #1 added scope for grading a drainage swale into the adjacent lawn area
in order to prevent runoff from flowing across Wilson Avenue and into a neighboring
garage. The site's regrading will now direct runoff into a stormwater drain inlet. Change
order #1 included costs for the grading, but site restoration costs were not included. The
regrading resulted in an increase of 3,130 SF of site restoration at a unit cost of $4.00/
SF (+ $12,520).
4) Poor subsurface conditions encountered resulted in a reevaluation of the pavement
section. It.has been determined that a fiber -reinforced concrete drive surface would
better support the anticipated traffic loads than asphalt. The current contract specifies a
2" asphalt surface course atop a 3" asphalt binder course for a total surface thickness of
5". For the greater strength and durability, Parks --requests a change from the 5" thick
asphalt to a 6" thick fiber -reinforced concrete slab. This needed change will increase
the project cost by + $2,835)
5) Consideration of design alternatives resulting from the subsurface conditions
encountered and Council approval of Change Order 3 has caused a delay in work. The
contractor is requesting $2,500 for remobilization fees (+$2,500).
These changes are necessary to"provide a firm and stable -structural roadway subgrade
combined with a strong, durable fiber -reinforced concrete surface that will not be subject to
vertical pumping movement and subsequent cracking and accelerated deterioration from high
levels of subsurface moisture. In addition, the positive drainage conditions which direct runoff
into the existing storm drain preventing this drainage impact to neighboring properties.
BUDGET/STAFF IMPACT:
Total cost for Change Order #3 is $21,096. Approximately $218 currently remains in the
contingency budget for this project making a budget adjustment necessary. Unrecognized
Southwest Quadrant Park Land Dedication Funds in the amount of $30,777 are available and
being requested to be recognized. $20,878 of this is required for the revised budget. The
remaining $9,899 is requested as contingency.
Attachments:
Change Order #3 Form
Resolution 231-16
Budget Adjustment Form
r�-. OW''IARK;,PJSAS
CHANGE ORDER NO. 3 Cost Plus Pre -Agreed Unit Price X
Project Name and Number: Wilson Park Grant Match 13001.1601
Name of Contractor:. . TNT. Inc.
Address of Contractor:. 4884. Alma.Hiahway, Van Buren, AR 72956
Date of -Contract: December 20, 2016
Original Contract Sum: ........................................................................................................... $97,560.00
Total Amount of All Previous Approved Change Orders: :....::......::.:>:::.:::::.:::.:.::::.::.::....::.. $9,538.00
Contract Sum prior to this Change Order: ........................................................................... $107,098.00
Contract Sum increase this Change Order: (not to exceed) ................................................... $21,096.00
New Contract Sum including this Change Order:.: .....:........:..::....:.:.................:.:,.......:..... $128,194.00
Subject and Reason for this Chance Order: Staff is requesting approval for the following changes:
1) Unforeseen subsurface conditions and excessive moisture have required removal of a larger amount of
encountered expansive clay, requiring replacement with a larger amount of select fill than originally
anticipated plus an additional 9 SY of class 7 base (+ $1,816).
2) Due to a change in the layout of the parking and driveway to protect trees and provide safe turning radius
for buses, additional curb and gutter is required to complete the new design (+ $1,425).
3) Change order #1 added scope for grading a drainage Swale into the adjacent lawn area in order to prevent
runoff from flowing across Wilson Avenue and into a neighboring garage. The site's regrading will now
direct runoff into a stormwater drain inlet. Change order #1 included costs for the grading, but site
restoration costs were not included. The regrading resulted in an increase of 3,130 SF of site restoration at
a unit cost of $4.001 SF. $12,520 us being requested.
NJtfitr
4) . Poor subsurface conditions encountered resulted, in a reevaluation�o(.,the pavement section. It has been
determined that a fiber -reinforced concrete drive surface would•better"support the anticipated traffic loads
than asphalt. The current contract specifies,a 2",,Aphalt surface cours& top a 3" as binder course for
a total surface thickness of 5". For the greater strength and durability, Parks requests a change from the 5"
thick asphalt to a 6" thick fiber -reinforced concrete slab: This needed change will increase the project cost
by + $2,835)
5) Consideration of design alternatives resulting,from-the subsurface conditions encountered and Council
approval of Change Order 3 has caused a del ay'in,work. The contractor is requesting $2,500 for
remobilization fees (+$2,500). ; 1,, f.y;t,;;
!..t:Iu _; :;:.`•i„rS,
PA KS & RECRE.4 0r1
These changes are recommended in order to provide:
I ) A firm and stable structural roadway surface and subgrade combined with a strong, durable fiber -
reinforced concrete surface that will not be subject to a vertical pumping movement and subsequent
cracking and accelerated deterioration from high levels of subsurface moisture.
2) Positive drainage conditions which direct runoff into existing stormwater drains and prevents impacting
neighboring properties.
Additional Time Requested: 21 Calendar Days' (*Period of time necessary for review of change order budget
request)
Dated this I 1 th day of April. 2017
.CITY OF FAYETTEVILLE
Parks & Rec . ation Department
By:, -
Ken Eastin, ark Planner 11
T -N -T. Inc.
Contractor
Title: Pf e 51 d e n t -
ATTEST:
I&1.e,�., w+tress
��``�F,F;K•� T
•�\J Y OF
_v; FAYETTEVILLE;
••.'AKA NSP •. Z��.
�GTO j ON,`
2
s
4
113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
Resolution: 231-16
File Number: 2016-0628
BID NO. 16-63 T -N=T, INC.:
A :RESOLUTION TO AWARD BID NO. 16-63 AND AUTHORIZE A CONTRACT WITH T -N -T,
INC. OF VAN BUREN, ARKANSAS IN THE AMOUNT OF $.97,560.00 FOR CONSTRUCTION OF
AN ACCESS DRIVE, CURB AND GUTTER, AND PARKING IMPROVEMENTS AT WILSON
PARK, AND TO APPROVE A PROJECT CONTINGENCY IN THE AMOUNT OF $9,756.00.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF .FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby awards Bid No. 16-63 and
authorizes a contract with T -N -T, Inc. of Van Buren, Arkansas in the amount of $97,560.00 for
construction of an access drive, curb and gutter, and parking improvements at Wilson Park, and further -
approves a project contingency in the amount of $9,756.00. _
PASSED and APPROVED on 12/20/2016
Page 1 Printed on 12121116
``�111r�+titltirr�
K
_
• r.
Attest:
Sondra E. Smith, City Clerk Treasurer
Page 1 Printed on 12121116
C
City of Fayetteville, Arkansas - Budget Adjustment Form (Legistar)
Budget Year Division Adjustment Number
/Org2 PARKS & RECREATION (520)
2017
Requestor: Alan Bearden
BUDGET ADJUSTMENT DESCRIPTION / JUSTIFICATION:
To recognize Park Land Dedication (SW Quadrant) revenues received into the Wilson Park Grant Match subproject. This
relates to Change Order #3 (T -N -T, Inc. contract #2016-00000014) and will be used for installation of additional select
e
road base fill and for a change in pavement surfacing from asphalt to fiber -reinforced concrete for extended durability.
RESOLUTION/ORDI NANCE
COUNCIL DATE: 5/2/2017
LEGISTAR FILE ID#: 2017-0203
Lik Hutcherw
4/14/2017 10:48 AM
Budget Director
TYPE:
DESCRIPTION:
GLDATE:
POSTED:
Date
TOTAL 30,777 30,777 v.20161220
Increase / (Decrease) Project.Sub#
Account Number Expense Revenue. Project Sub AT Account Name
2250.520.9256-5806.00 30,777 - 13001 1601 - EX Park Improvements - Park Improvements
2250.520.9256-4419.02 - 30,777 13001 1601 RE Greenspace Fees. - SW
C:\Users\losmith\AppData\Roaming\L5\Temp\f937e00f-6354-4c18-9cod-d8c671efda57 1 of 1