Resolution: 228-16
File Number: 2016-0624
HOGWASH CARWASH, LLC:
A RESOLUTION TO APPROVE A 50/50 COST SHARE AGREEMENT WITH HOGWASH
CARWASH, LLC FOR CONSTRUCTION OF A SEWER MAIN ALONG A PORTION OF EAST
HUNTSVILLE ROAD BETWEEN SOUTH ERIKA AVENUE AND SOUTH SEVEN HILLS DRIVE AT
A TOTAL COST OF $8,232.00.
WHEREAS, Hogwash Carwash, LLC has requested that the City construct and share in the cost of
constructing an 8 -inch sewer main along a portion of East Huntsville Road between South Erika Avenue and
South Seven Hills Drive, a distance of approximately 100 feet, so Hogwash may develop property located on
East Huntsville Road; and
WHEREAS, construction of the sewer main will provide sewer service to an infill project which is
increasing the population density in this area, and will also allow for ample future capacity which the
City recognizes will be necessary for the area that is served by this sewer main; and
WHEREAS, § 51.113 of the Fayetteville City Code provides that "the City shall pay the excess material
cost of facilities of a size larger than required to serve subdivisions when such excess size is specified
and required by the Water and Wastewater Director for the general benefit of the sewerage system."
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves a cost share
agreement with Hogwash Carwash, LLC for construction of a sewer main along a portion of East
Huntsville Road between South Erika Avenue and South Seven Hills Drive, with the total estimated
project cost of $8,232.00 to be shared equally between the City and Hogwash Carwash, LLC.
Page 1 Printed on 12121116
Resolution: 228-16
File Number 2016-0624
PASSED and APPROVED on 12/20/2016
Approved:
Attest:
1 �Esrieiririr
Sondra E. Smith, City Clerk_- ? e & r' • • ' 'qqey
` • I� AYETTEViL4_F
r` 9 c, •�':
GTO O
iy %%%%%
'
Page 2 Printed on 12121/16
City of Fayetteville, Arkansas 113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
I,,
Text File
-- File Number: 2016-0624
Agenda Date: 12/20/2016 Version: 1 Status: Passed
In Control: City Council Meeting File Type: Resolution
Agenda Number: A. 11
HOGWASH CARWASH, LLC:
A RESOLUTION TO APPROVE A 50150 COST SHARE AGREEMENT WITH HOGWASH
CARWASH, LLC FOR CONSTRUCTION OF A SEWER MAIN ALONG A PORTION OF EAST
HUNTSVILLE ROAD BETWEEN SOUTH ERIKA AVENUE AND SOUTH SEVEN HILLS DRIVE
AT A TOTAL COST OF $8,232.00
WHEREAS, Hogwash Carwash, LLC has requested that the City construct and share in the cost of
constructing an 8 -inch sewer main along a portion of East Huntsville Road between South Erika Avenue
and South Seven Hills Drive, a distance of approximately 100 feet, so Hogwash may develop property
located on East Huntsville Road; and
WHEREAS, construction of the sewer main will provide sewer service to an infill project which is
increasing the population density in this area, and will also allow for ample future capacity which the
City recognizes will be necessary for the area that is served by this sewer main; and
WHEREAS, § 51.113 of the Fayetteville City Code provides that "the City shall pay the excess
material cost of facilities of a size larger than required to serve subdivisions when such excess size is
specified and required by the Water and Wastewater Director for the general benefit of the sewerage
system."
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves a cost share
agreement with Hogwash Carwash, LLC for construction of a sewer main along a portion of East
Huntsville Road between South Erika Avenue and South Seven Hills Drive, with the total estimated
project cost of $8,232.00 to be shared equally between the City and Hogwash Carwash, LLC.
City of Fayetteville, Arkansas Page 1 Printed on 1212112018
Tim Nyander
Submitted By
City of Fayetteville Staff Review Form
2016-0624
_egistar File ID
1?17 _/2016
City Council Meeting Date - Agenda Item Only
N/A for Non -Agenda Item
12/2/2016 Utilities Director/
Utilities Department
Submitted Date Division / Department
Action Recommendation:
Staff recommends approval of a cost -share agreement between the City of Fayetteville and Hogwash Carwash, LLC
to share the costs of installing a sewer main on East Huntsville Rd. between S. Erika Ave. and S. Seven Hills Dr. The
estimated total cost of the project is $8,232.00. The cost share is one-half of the estimated project cost, in the
amount of $4,116.00.
5400.720.5600-5808.00
Account Number
02067.1
Budget Impact:
Water/Sewer
Fund
Water and Sewer Cost Sharing Project
Project Number
Project Title
Budgeted Item? Yes
Current Budget
$
96,796.00
Funds Obligated
$
4,510.00
Current Balance
Does item have a cost? Yes
Item Cost
$
4,116.00
Budget Adjustment Attached? No
Budget Adjustment
Remaining Budget
V20140710
Previous Ordinance or Resolution #
Original Contract Number:
Approval Date:
Comments:
CITY OF
Tay7 s
le
ARKANSAS
MEETING OF DECEMBER 20, 2016
TO: Fayetteville City Council
THRU: Mayor Lioneld Jordan
Don Marr, Chief of Staff
Water and Sewer Committee
FROM: Tim Nyander, Utilities Director
DATE: December 1, 2016
CITY COUNCIL AGENDA MEMO
SUBJECT: Cost Share Agreement with Hogwash Carwash, LLC
RECOMMENDATION:
Staff recommends approval of a cost -share agreement between the City of Fayetteville and
Hogwash Carwash, LLC, to share the costs of installing a sewer main in East Huntsville Road
between S. Erika Avenue and S. Seven Hills Drive. The estimated total cost of the project is
$8,232.00. The City's portion of the cost share is one-half the estimated project cost, in the
amount of $4,116.00.
BACKGROUND:
Hogwash Carwash has requested that the City construct -and share in the cost of constructing
an 8 -inch sewer main along a portion of East Huntsville Road between South Erika Avenue and
South Seven Hills Drive, a distance of approximately 100 feet, so that Carwash may develop the
property located on 1096 East Huntsville Road and 1116 East Huntsville Road.
DISCUSSION:
Constructing this segment of 8 -inch main will allow development of these properties and will
also provide for ample future capacity which the City recognizes will be necessary for the area
that is served by this sewer main.
BUDGET/STAFF IMPACT:
The Water & Sewer Division will be able to provide the labor and equipment needed without
impeding upon the overall mission of the Utilities Department.
ATTACHMENTS:
Staff Review Form
Cost -Share Agreement
Map of Area
Mailing Address:
113 W. Mountain Street www.fayetteville-ar.gov
Fayetteville, AR 72701
CONTRACTUAL AGREEMENT FOR
COST SHARE OF SEWER MAIN INSTALLATION COSTS
This Agreement, made and entered into on this dU
-i-4- y of December, 2016, by and
between the City of Fayetteville, Arkansas ("City") and Hogwash Carwash, LLC, ("Hogwash"),
witnesseth:
WHEREAS, Hogwash has requested that the City construct and share in the cost of
constructing an 8 -inch sewer main along a portion of East Huntsville Road between South Erika
Avenue and South Seven Hills Drive, a distance of approximately 100 feet, so that Carwash may
develop the property located on 1096 East Huntsville Road and 1116 East Huntsville Road; and
WHEREAS, constructing this segment of 8 -inch main will allow development of these
properties and will also provide for ample future capacity which the City recognizes will be
necessary for the area that is served by this sewer main; and
WHEREAS, § 51.113 of the Fayetteville City Code provides that "the City shall pay the
excess material cost of facilities of a size larger than required to service subdivisions when such
excess size is specified and required by the water and wastewater director for the general benefit
of the sewerage system."
NOW, THEREFORE, the City of Fayetteville, Arkansas and Hogwash Carwash, LLC
agree as follows:
1. The City of Fayetteville, Arkansas agrees to:
A. Furnish the labor, materials, and equipment to install approximately 100 linear
feet of 8 -inch sewer main on East Huntsville Road between South Erika Avenue
and South Seven Hills Drive.
B. Bear any costs associated with the sewer main installation that exceed the
amount Carwash agrees to pay below.
2. Hogwash Carwash, LLC agrees to:
A. Reimburse the City for one-half of the cost of the sewer main installation up to
a maximum -not -to -exceed amount of $4,116.00 which represents one-half of
the project cost estimated by the City of Fayetteville.
B. Deposit the funds in the amount of $4,116.00 with the City of Fayetteville prior
to City Council consideration of the agreement.
Page 1 of 2
IN AGREEMENT WITH ALL THE TERMS AND CONDITIONS ABOVE, WE
SIGN BELOW:
HOGWASH CARWASH, LLC
By:
JSON RODDEY
ine Mernber
ATTEST:
; L,
By:
Mandy Mack
Notary Public - State of Arkansas
Benton County
Commission Expires August 1, 2026
L_ Commission # 12698551
CITY OF FAYETTEVILLE,
ARKANSAS
ATTEST:
By:�
SONDRA SMITH, City C1q�%"�- RK
-( YI
�f,�� � �iriils ► � �'r�w
Page 2 of 2
T1T5
10"
�1
VV -(25)407P
IN -s• CIP2aa
w e• IP618
�
I
W-(25MW
w
s
till
C
x
H4vs
1049BLUE
G�
v
�
go
N
s
�
0 12.5 25 50
75 100
Feat