HomeMy WebLinkAbout197-16 RESOLUTION113 West Mountain Street Fayetteville, AR 72701 (479) 575-8323 Resolution: 197-16 File Number: 2016-0479 SWEETSER CONSTRUCTION, INC. CHANGE ORDER NO. 1: A RESOLUTION TO APPROVE CHANGE ORDER NO. 1 TO THE CONTRACT WITH SWEETSER CONSTRUCTION, INC. IN THE AMOUNT OF $390,568.20 FOR THE RELOCATION OF APPROXIMATELY 1,100 FEET OF 12 -INCH WATER MAIN ASSOCIATED WITH THE RUPPLE ROAD - PERSIMMON TO CONGRESSIONAL PROJECT. BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS: Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves Change Order No. 1 to the contract with Sweetser Construction, Inc. in the amount of $390,568.20 for the relocation of approximately 1,100 feet of 12 -inch water main associated with the Rupple Road - Persimmon to Congressional Project. PASSED and APPROVED on 11/1/2016 Attest: 11 `�4•1i Y FAYETT1I11.P Wit• `. • 7 C� �•?` i 1 Sondra E. Smith, City Clerk Treasurer Page 1 Printed on 1112116 113 West Mountain Street City of Fayetteville, Arkansas % Fayetteville, AR 72701 (479) 575-8323 Text File f File Number: 2016-0479 Agenda Date: 11/1/2016 Version: 1 Status: Passed In Control: City Council Meeting File Type: Resolution Agenda Number: A. 7 SWEETSER CONSTRUCTION, INC. CHANGE ORDER NO. 1: A RESOLUTION TO APPROVE CHANGE ORDER NO. 1 TO THE CONTRACT WITH SWEETSER CONSTRUCTION, INC. IN THE AMOUNT OF $390,568.20 FOR THE RELOCATION OF APPROXIMATELY 1,100 FEET OF 12 -INCH WATER MAIN ASSOCIATED WITH THE RUPPLE ROAD - PERSIMMON TO CONGRESSIONAL PROJECT BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS: Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves Change Order No. 1 to the contract with Sweetser Construction, Inc. in the amount of $390,568.20 for the relocation of approximately 1,100 feet of 12 -inch water main associated with the Rupple Road - Persimmon to Congressional Project City of Fayetteville, Arkansas Page 1 Printed on 11/2/2016 Matt Casey Submitted By City of Fayetteville Staff Review Form 2016-0479 Legistar File ID 11/1/2016 City Council Meeting Date - Agenda Item Only N/A for Non -Agenda Item 10/11/2016 Engineering / Development Services Department Submitted Date Division / Department Action Recommendation: Approval of Change Order No.1 for the Rupple Rd. - Persimmon to Congressional Project for the relocation of approximately 1100 feet of 12" water main. 5400.720.5600-5808.00 Account Number 12009.1 Project Number Budgeted Item? Yes Does item have a cost? Yes Budget Adjustment Attached? No Previous Ordinance or Resolution # 74-16 Original Contract Number: Comments: Existing PO# 16-0000388-001 Budget Impact: Water and Sewer Fund Water System Rehabilitation/Replacement Project Title Current Budget $ 3,736,723.21 Funds Obligated Current Balance Item Cost Budget Adjustment Remaining Budget $ 390,568.20 _.i Approval Date: V20140710 CITY OF ae ARKANSAS MEETING OF NOVEMBER 1, 2016 TO: Mayor and City Council CITY COUNCIL AGENDA MEMO THRU: Don Marr, Chief of Staff Jeremy Pate, Development Services Director Chris Brown, City Engineer FROM: Matt Casey, Engineering Design Manager DATE: October 11, 2016 SUBJECT: Approval of Change Order #1 in the amount of $390,568.20 with Sweetser Construction, Inc. for the Rupple Road —Persimmon to Congressional Project. RECOMMENDATION: Staff recommends City Council approval of Change Order #1 in the amount of $390,568.20 with Sweetser Construction, Inc. for the Rupple Road — Persimmon to Congressional Project for the relocation of approximately 1100 linear feet of 12" water main. BACKGROUND: The City of Fayetteville Engineering Division developed the design plans for the construction of this portion of Rupple Road. Rupple Road is shown on the City of Fayetteville Master Street plan as a Principal Arterial Parkway from Martin Luther King Blvd. (Highway 62) north to Howard Nickell Road. The street cross section for this project includes four lanes with a center median, a 12' trail and an 8' sidewalk. On April 5, 2016, the City Council approved a contract with Sweetser Construction, Inc. in the amount of $2,537,900 for the construction of this project. The notice to proceed was issued on June 20, 2016 and construction began shortly after. DISCUSSION: There is an existing 12" water line that runs along the east side of Rupple along this project. The design called for the water line to remain in place with the City Water Department making some minor adjustments where needed. During the excavation for the roadway, it was discovered that the portion of existing 12" water line that runs under the proposed roadway was previously installed at a much shallower depth than expected. With the waterline being too shallow, Sweetser Construction is unable to perform the earthwork necessary for the roadway construction. City staff provided a design for the waterline relocation and Sweetser Construction has provided a cost for this work and is included in this change order. Mailing Address: 113 W. Mountain Street www.fayettevilie-ar.gov Fayetteville, AR 72701