HomeMy WebLinkAbout197-16 RESOLUTION113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
Resolution: 197-16
File Number: 2016-0479
SWEETSER CONSTRUCTION, INC. CHANGE ORDER NO. 1:
A RESOLUTION TO APPROVE CHANGE ORDER NO. 1 TO THE CONTRACT WITH SWEETSER
CONSTRUCTION, INC. IN THE AMOUNT OF $390,568.20 FOR THE RELOCATION OF
APPROXIMATELY 1,100 FEET OF 12 -INCH WATER MAIN ASSOCIATED WITH THE RUPPLE
ROAD - PERSIMMON TO CONGRESSIONAL PROJECT.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves Change Order No.
1 to the contract with Sweetser Construction, Inc. in the amount of $390,568.20 for the relocation of
approximately 1,100 feet of 12 -inch water main associated with the Rupple Road - Persimmon to
Congressional Project.
PASSED and APPROVED on 11/1/2016
Attest:
11
`�4•1i Y
FAYETT1I11.P
Wit• `.
• 7 C� �•?` i
1
Sondra E. Smith, City Clerk Treasurer
Page 1 Printed on 1112116
113 West Mountain Street
City of Fayetteville, Arkansas
% Fayetteville, AR 72701
(479) 575-8323
Text File
f File Number: 2016-0479
Agenda Date: 11/1/2016 Version: 1 Status: Passed
In Control: City Council Meeting File Type: Resolution
Agenda Number: A. 7
SWEETSER CONSTRUCTION, INC. CHANGE ORDER NO. 1:
A RESOLUTION TO APPROVE CHANGE ORDER NO. 1 TO THE CONTRACT WITH
SWEETSER CONSTRUCTION, INC. IN THE AMOUNT OF $390,568.20 FOR THE RELOCATION
OF APPROXIMATELY 1,100 FEET OF 12 -INCH WATER MAIN ASSOCIATED WITH THE
RUPPLE ROAD - PERSIMMON TO CONGRESSIONAL PROJECT
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves Change Order
No. 1 to the contract with Sweetser Construction, Inc. in the amount of $390,568.20 for the relocation of
approximately 1,100 feet of 12 -inch water main associated with the Rupple Road - Persimmon to
Congressional Project
City of Fayetteville, Arkansas Page 1 Printed on 11/2/2016
Matt Casey
Submitted By
City of Fayetteville Staff Review Form
2016-0479
Legistar File ID
11/1/2016
City Council Meeting Date - Agenda Item Only
N/A for Non -Agenda Item
10/11/2016 Engineering /
Development Services Department
Submitted Date Division / Department
Action Recommendation:
Approval of Change Order No.1 for the Rupple Rd. - Persimmon to Congressional Project for the relocation of
approximately 1100 feet of 12" water main.
5400.720.5600-5808.00
Account Number
12009.1
Project Number
Budgeted Item? Yes
Does item have a cost? Yes
Budget Adjustment Attached? No
Previous Ordinance or Resolution # 74-16
Original Contract Number:
Comments: Existing PO# 16-0000388-001
Budget Impact:
Water and Sewer
Fund
Water System Rehabilitation/Replacement
Project Title
Current Budget $ 3,736,723.21
Funds Obligated
Current Balance
Item Cost
Budget Adjustment
Remaining Budget
$ 390,568.20
_.i
Approval Date:
V20140710
CITY OF
ae
ARKANSAS
MEETING OF NOVEMBER 1, 2016
TO: Mayor and City Council
CITY COUNCIL AGENDA MEMO
THRU: Don Marr, Chief of Staff
Jeremy Pate, Development Services Director
Chris Brown, City Engineer
FROM: Matt Casey, Engineering Design Manager
DATE: October 11, 2016
SUBJECT: Approval of Change Order #1 in the amount of $390,568.20 with Sweetser
Construction, Inc. for the Rupple Road —Persimmon to Congressional
Project.
RECOMMENDATION:
Staff recommends City Council approval of Change Order #1 in the amount of $390,568.20 with
Sweetser Construction, Inc. for the Rupple Road — Persimmon to Congressional Project for the
relocation of approximately 1100 linear feet of 12" water main.
BACKGROUND:
The City of Fayetteville Engineering Division developed the design plans for the construction of
this portion of Rupple Road. Rupple Road is shown on the City of Fayetteville Master Street
plan as a Principal Arterial Parkway from Martin Luther King Blvd. (Highway 62) north to Howard
Nickell Road. The street cross section for this project includes four lanes with a center median,
a 12' trail and an 8' sidewalk.
On April 5, 2016, the City Council approved a contract with Sweetser Construction, Inc. in the
amount of $2,537,900 for the construction of this project. The notice to proceed was issued on
June 20, 2016 and construction began shortly after.
DISCUSSION:
There is an existing 12" water line that runs along the east side of Rupple along this project.
The design called for the water line to remain in place with the City Water Department making
some minor adjustments where needed. During the excavation for the roadway, it was
discovered that the portion of existing 12" water line that runs under the proposed roadway was
previously installed at a much shallower depth than expected. With the waterline being too
shallow, Sweetser Construction is unable to perform the earthwork necessary for the roadway
construction. City staff provided a design for the waterline relocation and Sweetser
Construction has provided a cost for this work and is included in this change order.