Resolution: 98-16
File Number: 2016-0212
ALLIANCE PUMP & MECHANICAL, INC.:
A RESOLUTION TO APPROVE A CHANGE ORDER TO THE CONTRACT WITH ALLIANCE PUMP
& MECHANICAL, INC. IN THE AMOUNT OF $43,521.00 PLUS APPLICABLE TAXES FOR
ADDITIONAL REPAIR SERVICES REQUIRED TO REBUILD SEVEN (7) GEARBOXES AT THE
NOLAND WASTEWATER TREATMENT PLANT.
WHEREAS, on October 6, 2015, the City Council passed Resolution No. 174-15, authorizing a contract
with Alliance Pump & Mechanical, Inc. to rebuild seven gearboxes at the Noland Wastewater Treatment
Plant; and
WHEREAS, after the gearboxes were delivered to and disassembled by Alliance for further inspection,
additional issues were identified requiring more repairs than first estimated, though the total cost of the
rebuilds will still be significantly less than purchasing new gearboxes.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves a change
order, a copy of which is attached to this Resolution, to the contract with Alliance Pump & Mechanical,
Inc. in the amount of $43,521.00 plus applicable taxes for additional repair services required to rebuild
seven (7) gearboxes at the Noland Wastewater Treatment Plant.
PASSED and APPROVED on 5/17/2016
Page 1 Printed on 5118116
File Number: 2016-0212
Resolution: 98-16
Attest:
Sondra E. Smith, City Clerk Treasurer
x 4('I+Tf.'�r
FA YOTEVILL � : ;U=
r
..4N% A'•' ;�.�.,
*fill i� N4
Page 2 Printed on 5118116
City of Fayetteville, Arkansas 113 West Mountain Street
Fayetteville, AR 72701
r�- t (479) 575-8323
n 17,
r
Text File
--- File Number: 2016-0212
Agenda Date: 5/17/2016 Version: 1 Status: Passed
In Control: City Council Meeting File Type: Resolution
Agenda Number: A 4
ALLIANCE PUMP & MECHANICAL, INC.:
A RESOLUTION TO APPROVE A CHANGE ORDER TO THE CONTRACT WITH ALLIANCE
PUMP & MECHANICAL, INC. IN THE AMOUNT OF $43,521.00 PLUS APPLICABLE TAXES
FOR ADDITIONAL REPAIR SERVICES REQUIRED TO REBUILD SEVEN (7) GEARBOXES AT
THE NOLAND WASTEWATER TREATMENT PLANT
WHEREAS, on October 6, 2015, the City Council passed Resolution No. 174-15, authorizing a
contract with Alliance Pump & Mechanical, Inc. to rebuild seven gearboxes at the Noland Wastewater
Treatment Plant; and
WHEREAS, after the gearboxes were delivered to and disassembled by Alliance for further inspection,
additional issues were identified requiring more repairs than first estimated, though the total cost of the
rebuilds will still be significantly less than purchasing new gearboxes.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves a change
order, a copy of which is attached to this Resolution, to the contract with Alliance Pump & Mechanical,
Inc. in the amount of $43,521.00 plus applicable taxes for additional repair services required to rebuild
seven (7) gearboxes at the Noland Wastewater Treatment Plant.
City of Fayetteville, Arkansas Page 1 Printed on 511812016
City of Fayetteville Staff Review Form
2016-0212
Legistar File ID
5/17/2016
City Council Meeting Date - Agenda Item Only
N/A for Non -Agenda Item
Billy Ammons 4/6/2016 Wastewater Treatment Plant /
Utilities Department
Submitted By Submitted Date Division / Department
Action Recommendation:
Fayetteville City Administration recommends approval of a change order for an additional $43,521.00 plus
applicable taxes with Alliance Pump & Mechanical Inc. for additional repairs needed to the seven (7) gearboxes
currently being rebuilt for the Noland WWTP. Resolution 174-15 awarded Alliance Pump & Mechanical Inc. Bid
15-48 for $78,950.00 plus applicable taxes to rebuild the gearboxes and a contract/PO was created in late 2015
for the rebuilds; the units have been disassembled and upon inspection additional repairs are needed. Funds
for the additional repair needs are available within the Wastewater Treatment Plant CIP — Plant Pumps and
5400.5800.5414.00
Account Number
02069.1
Project Number
Budget Impact:
Water/Sewer
Fund
Plant Pumps and Equipment - WWTP
Project Title
Budgeted Item? Yes Current Budget
Funds Obligated
Current Balance
Does item have a cost? Yes Item Cost
Budget Adjustment Attached? No Budget Adjustment
Remaining Budget
Previous Ordinance or Resolution # 174-15
Original Contract Number: N/A
Comments:
$
659,981.00
$
307,800.00
i
35;?,181.00
$
47,765.00
��•`s.:.:� S. �SxVld
Approval Date:
V20140710
CITY OF
Fayv'erev—ille
ARKANSAS
MEETING OF MAY 17, 2016
TO: Mayor and Fayetteville City Council
THRU: Don Marr, Chief of Staff
Water & Sewer Committee
Tim Nyander, Utilities Director
FROM: Billy Ammons, Wastewater Treatment
DATE: April 6, 2016
STAFF MEMO
SUBJECT: Approval of a change order in the amount of $43,521.00 with Alliance Pump &
Mechanical Inc. for additional repair services needed for seven (7) gearboxes for the Noland
WWTP.
RECOMMENDATION:
Fayetteville City Administration recommends approval of a change order for an additional
$43,521.00 plus applicable taxes with Alliance Pump & Mechanical Inc. for additional repairs
needed to the seven (7) gearboxes currently being rebuilt for the Noland WWTP. Funds are
available within the Wastewater Treatment Plant CIP — Plant Pumps and Equipment project.
BACKGROUND:
The Noland WWTP uses a biological nutrient removal system to treat the City's wastewater.
Each of the two basins uses a series of six mixers and eight large mechanical aerators to
provide the mixing and necessary oxygen for the microorganisms to treat the wastewater. The
existing mixers and aerators are more than 25 years old and many are in need of repair. Even
though they have exceeded their life expectancy, rebuilding the gearboxes is significantly more
cost effective than replacing them with new units and generally provides a similar life
expectancy.
DISCUSSION:
On 16 October, 2015, the City Council passed and approved Resolution 174-15 awarding
Alliance Pump and Mechanical, Inc. Bid 15-48 to rebuild the seven (7) gearboxes in the amount
of $78,950.00. Since that time, the gearboxes were removed, delivered to Alliance Pump and
Mechanical Inc., and disassembled for inspection. Upon inspection, additional items were found
in need of repair. The additional repairs total $43,521.00. With this change order, the total
amount to rebuild and repair the gearboxes is $122,471.00 plus applicable taxes. Even with the
additional repairs needed, the cost is significantly less than purchasing new gearboxes.
BUDGET/STAFF IMPACT:
Funds are available in the Wastewater Treatment Plant CIP — Plant Pumps and Equipment
project.
ATTACHMENTS:
Staff Review Form
Change Order 1
Resolution 174-15
Mailing Address:
113 W. Mountain Street www.fayetteville-ar.gov
Fayetteville, AR 72701
Change Order
PROJECT DATA
Project Name: CearboxRebulld Clivrit City of Fayettevilic, AR
Project No.: 15-48 Project ,,cation: ['an] R. Noland WWFI;
Report No: I )a tv; 4/'l 9/2016
coi,TRAcT r,4oDMCA'rION DATA-
niondmont
X Chan ye Order A -
To. Alliance Pump & MechanicalService, tric.
Project Gearbox Rebuilds 48
Owner: City of Fayetteville, AR
Fngintvr, CH2M
The foHowing modification to the Contractor are hereby ordered use additional pages if re uired
Conduct additional repairs on seven (7) gearboxes in the amount of $43,521
Reason for Modification(s):
Additional repairs were needed once the gearboxes were opened and inspected.
Attachments (Ust Supporting D curner%4).
Repair Costs from Alliance Pump & Mechanical Service, Inc_
ContractAmount or Price
Contract Times (Calculate Qays)
Original
$78,950
Ori 'nal Duration
Previous Contract Modification(s)
Add Deduct
Da s
Previous Contract Modification(s)
(Add/Deduct)
$0
Days
This Contract Modification
(Add)
$43,521
This Contract Modification
Add Deduct
Days
Revised Contract
1$122,471
Revised Contract Time
Days
Revised Contract Com pletiun Date;
SIGNATURE RECORD
Heidi Lee -Alliance Pump
LJA4-14- Date: 4/19/20I6
Mayo Miller, CHZM
4/19/2016
Tim Nyander, Utilities
Director
Date: 4/19/2016
Sondra E. Smith, City Clerk
Lioneld jDrdDn, Mayor
Date.
Page I of I WB -P46 -006363-F1
Form Rev. 1. April -2011
�Allrlr��e
Siv) PlIM1) & A f 641AN)Cr 1f 41 ItV11:1 1,+lr:
627 South Coffage
Independence. MO 64050
(81b) 833-8109
(816) 833-8035 fax
Www. alliallcepvmp. co
4/4/2016
City of Fayetteville
Additions/Change Order for Noland WWTP Gearbox Rebuild Project 15-48 **REVISED**
83Q5 — Unit A
• Repair/Rebuild Upper Support Bearing Housing
• Replace (2) Oil Seals (#115410PSP) $12.50ea (Reduced to below cost) $ 25.00
• Replace (2) Ball Bearings (#116683PSP) $369.50ea (Reduced to below cost) $ 739.00
• Replace (1) Oil Breather $75.00ea $ 75.00
Additional Labor: (9 Hours @ $85.00/hr) $ 765.00
UNIT A TOTAL: $1,604.00
83Q5 — Unit B
• Repair/Rebuild Upper Support Bearing Housing
• Repair/Rebuild Upper Bearing Cage
• Repair/Rebuild Lower Bearing Housing
• Microfinish (2) Lip Seal Areas $700.00ea $1,400.00
• Replace (2) Adapter Sleeve (#138821STL) $270.00ea $ 540.00
• Replace (1) Bevel Gear & Pinion (#600983PSP) $4,525.00ea $4,525.00
• Replace (2) Oil Seals (#115410PSP) $12.50ea (Reduced to below cost) $ 25.00
• Replace (2) Ball Bearings (#116683PSP) $369.50ea (Reduced to below cost) $ 739.00
• Replace (1) Oil Breather $75.00ea $ 75.00
Additional Labor: (24 Hours @ $85.00/hr) $2,040.00
UNIT B TOTAL: $9,344.00
83Q5 — Unit C
•
Repair/Rebuild Upper Support Bearing Housing
•
Repair/Rebuild Upper Bearing Cage
•
Repair/Rebuild Lower Bearing Housing
•
Repair/Rebuild Lower Bearing Cage
•
Microfinish (2) Lip Seal Areas $700.00ea
$1,400.00
•
Replace (1) Tapered Adapter Sleeve (#113995STL) $820.00ea
$ 820.00
•
Replace (1) Locknut Washer $72.00ea
$ 72.00
•
Replace (2) Oil Seals (#115410PSP) $12.50ea (Reduced to below cost)
$ 25.00
•
Replace (2) Ball Bearings (#116683PSP) $369.50ea (Reduced to below cost)
$ 739.00
•
Replace (1) Oil Breather $75.00ea
$ 75.00
Additional Labor: (17 Hours @ $85.00/hr)
$1,445.00
UNIT C TOTAL:
$4,576.00
LAT130 — Unit A
• Repair/Rebuild Upper Output Shaft
• Repair/Rebuild Collar
• Repair/Rebuild Lower Output Shaft
• Repair/Rebuild Lower Sleeve
• Microfinish (6) (2 main fits, 1 pinion shaft fit, 1 shaft fit & 2 collet slvs) $700.00ea $4,200.00
• Replace (1) Oil Seal (#115329PSP) $54.50ea (Reduced to below cost) $ 54.50
• Replace (1) Ball Bearing (#117031PSP) $422.50ea (Reduced to below cost) $ 422.50
• Replace (1) Oil Breather (#121217PSP) $75.00ea $ 75.00
Additional Labor: (14 Hours @ $85.00/hr)
UNIT A TOTAL:
LAT130 — Unit B
$1,190.00
$5,942.00
• Repair/Rebuild Upper Output Shaft
• Repair/Rebuild Collar
• Repair/Rebuild Lower Sleeve
• Microfinish (6) (2 main fits, 1 pinion shaft fit, 1 shaft fit & 2 collet slvs) $700.00ea $4,200.00
• Replace (1) Oil Seal (#115329PSP) $54.50ea (Reduced to below cost) $ 54.50
• Replace (1) Ball Bearing (#115329PSP) $422.50ea (Reduced to below cost) $ 422.50
• Replace (1) Oil Breather (#121217PSP) $75.00ea $ 75.00
Additional Labor: (12 Hours @ $85.00/hr) $1,020.00
UNIT B TOTAL: $5,772.00
LAT160 — Unit C
•
Repair/Rebuild Upper Output Shaft
•
Repair/Rebuild Collar
•
Repair/Rebuild Lower Output Shaft
•
Repair/Rebuild High Speed Pinion
•
Repair/Rebuild Upper Sleeve
•
Repair/Rebuild Lower Sleeve
•
Repair/Rebuild Fixed Bearing Housing
•
Repair/Rebuild Floating Bearing Housing
•
Microfinish (6) (2 main fits, 1 pinion shaft fit, 1 shaft fit & 2 collet slvs) $700.00ea
$4,200.00
•
Replace (1) Flexible Coupling Grid (#202299PSP)
$ 600.00
•
Replace (1) Double Row Taper Bearing Cup
$ 940.00
•
Replace (1) Oil Seal (#115405PSP) $58.50ea (Reduced to below cost)
$ 58.50
•
Replace (1) Ball Bearing (#117035PSP) $910.50ea (Reduced to below cost)
$ 910.50
•
Replace (1) Oil Breather (#121217PSP) $75.00ea
$ 75.00
Additional
Labor: (22 Hours @ $85.00/hr)
$1,870.00
UNIT C TOTAL:
$8,654.00
LAT160 — Unit D
•
Repair/Rebuild Upper Output Shaft
•
Repair/Rebuild Collar
•
Repair/Rebuild Lower Output Shaft
•
Repair/Rebuild High Speed Pinion
•
Repair/Rebuild Upper Sleeve
•
Repair/Rebuild Lower Sleeve
•
Repair/Rebuild Fixed Bearing Housing
•
Repair/Rebuild Floating Bearing Housing
•
Mlcrofinish (6) (2 main fits, 1 pinion shaft fit, 1 shaft fit & 2 collet slvs) $700.00ea
$4,200.00
•
Replace (1) Double Row Taper Bearing Cup
$ 940.00
•
Replace (1) Oil Seal (#115405PSP) $58.50ea (Reduced to below cost)
$ 58.50
•
Replace (1) Ball Bearing (#117035PSP) $910.50ea (Reduced to below cost)
$ 910.50
•
Replace (1) Oil Breather (#121217PSP) $75.00ea
$ 75.00
Additional Labor: (17 Hours @ $85.00/hr)
$1,445.00
UNIT D TOTAL:
$7,629.00
CHANGE ORDER TOTAL: $43,521.00
113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
Resolution: 174-15
File Number: 2015-0411
BID NO. 15-48 ALLIANCE PUMP & MECHANICAL, INC.:
A RESOLUTION TO AWARD BID NO. 15-48 AND AUTHORIZE A CONTRACT WITH
ALLIANCE PUMP & MECHANICAL, INC. IN THE AMOUNT OF $78,950.00 PLUS APPLICABLE
TAXES TO REBUILD SEVEN (7) GEARBOXES AT THE NOLAND WASTEWATER TREATMENT
PLANT
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby awards Bid No. 15-48 and
authorizes a contract with Alliance Pump & Mechanical, Inc. in the amount of $78,950.00 plus applicable
taxes to rebuild seven (7) gearboxes at the Noland Wastewater Treatment Plant.
PASSED and APPROVED on 10/6/2015
TRt�rrrr
��� �� �.. • • :ilS Irr
op
Attest:
b w� yam.
Sondra E. Smith, City Clerk Treasurer
Page i Primed on 10/7/15
City of Fayetteville, Arkansas
4. Text File
File Number: 2015-0411
Agenda Date: 10/6/2015 Version: 1
In Control: City Council Meeting
Agenda Number: A. 5
BID NO. 15-48 ALLIANCE PUMP & MECHANICAL, INC.:
113 west Mountain Street
Fayetteville, AR 72701
(479) 575-8323
Status: Passed
File Type: Resolution
A RESOLUTION TO AWARD BID NO. 15-48 AND AUTHORIZE A CONTRACT WITH
ALLIANCE PUMP & MECHANICAL, INC. IN THE AMOUNT OF $78,950.00 PLUS APPLICABLE
TAXES TO REBUILD SEVEN (7) GEARBOXES AT THE NOLAND WASTEWATER
TREATMENT PLANT
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby awards Bid No. 15-48 and
authorizes a contract with Alliance Pump & Mechanical, Inc. in the amount of $78,950.00 plus
applicable taxes to rebuild seven (7) gearboxes at the Noland Wastewater Treatment Plant.
City of Fayetteville, Arkansas Page 1 Printed on 10!7/2015