HomeMy WebLinkAbout136-16 RESOLUTION113 West Mountain
Street Fayetteville,
AR 72701
(479) 575-8323
Resolution: 136-16
File Number: 2016-0311
CROSSLAND CONSTRUCTION COMPANY, INC. CHANGE ORDER NO. 12:
A RESOLUTION TO APPROVE CHANGE ORDER NO. 12 TO THE CONTRACT WITH
CROSSLAND CONSTRUCTION COMPANY, INC. IN THE AMOUNT OF $436,555.00 TO ADD THE
CONSTRUCTION OF A PARKING LOT, SIDEWALK AND ASSOCIATED ROAD IMPROVEMENTS
AT THE REGIONAL PARK, TO APPROVE AN ADDITIONAL PROJECT CONTINGENCY IN THE
AMOUNT OF $80,202.00, AND TO APPROVE A BUDGET ADJUSTMENT.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves Change Order No. 12
to the contract with Crossland Construction Company, Inc. in the amount of $436,555.00 to add the
construction of a parking lot, sidewalk and additional road improvements at the Regional Park, and further
approves an additional project contingency in the amount of $80,202.00.
Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget adjustment,
a copy of which is attached to this Resolution.
PASSED and APPROVED on 7/5/2016
rra.. • rV'..�.��yy�"
FAYETTEVILL
Attest: �'.s'''kAl�•'�`+:
11110) N
Sondra E. Smith, City Clerk
Treasurer
Page 1 Printed on 716116
City of Fayetteville, Arkansas 113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
Text File
File Number: 2016-0311
Agenda Date: 7/5/2016 Version: 1 Status: Passed
In Control: City Council Meeting File Type: Resolution
Agenda Number: C. 6
CROSSLAND CONSTRUCTION COMPANY, INC. CHANGE ORDER NO. 12:
A RESOLUTION TO APPROVE CHANGE ORDER NO. 12 TO THE CONTRACT WITH
CROSSLAND CONSTRUCTION COMPANY, INC. IN THE AMOUNT OF .$436,555.00 TO ADD
THE CONSTRUCTION OF A PARKING LOT, SIDEWALK AND ASSOCIATED ROAD
IMPROVEMENTS AT THE REGIONAL PARK, TO APPROVE AN ADDITIONAL PROJECT
CONTINGENCY IN THE AMOUNT OF $80,202.00, AND TO APPROVE A BUDGET
ADJUSTMENT
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves Change Order
No. 12 to the contract with Crossland Construction Company, Inc. in the amount of $436,555.00 to add
the construction of a parking lot, sidewalk and additional road improvements at the Regional Park, and
further approves an additional project contingency in the amount of $80,202.00.
Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget
adjustment, a copy of which is attached to this Resolution.
City of Fayetteville, Arkansas Page 1 Printed on 71612016
City of Fayetteville Staff Review Form
2016-0311
Legistar File ID
7/5/2016
City Council Meeting Date - Agenda Item Only
N/A for Non -Agenda Item
/
Alison Jumper 6/17/2016 Parks & Recreation
Parks & Recreation Department
Submitted By Submitted Date Division / Department
Action Recommendation:
Staff recommends approval of Change Order Number twelve to contract #2359 with Crossland Construction for a
contract increase in the amount of $436,555 forth e construction of a parking lot, sidewalk and associated road
improvements and approval of a budget adjustment.
Budget Impact:
2250.9255.5806.00
Account Number
'02002
Project Number
Parks Development
Fund
Regional Park
Project Title
Budgeted Item?
Yes
Current Budget
$
5,930,181.00
Funds Obligated
$
5,727,447.00
Current Balance
S
)0)7Z4 01
Does item have a cost?
Yes
Item Cost
$
436,555.00
Budget Adjustment Attached?
Yes
Budget Adjustment
$
314,023.00
Remaining Budget
y
V20140710
Previous Ordinance or Resolution #
56-15
Original Contract Number: 2359
Comments:
Approval Date: