HomeMy WebLinkAbout217-14 RESOLUTIONRESOLUTION NO. 217-14
A RESOLUTION TO APPROVE CHANGE ORDER NO. 2 TO THE
CONTRACT WITH BENCHMARK CONSTRUCTION IN THE AMOUNT OF
$6,703.00 FOR INSTALLATION OF A SIDEWALK AND AN AMERICANS
WITH DISABILITIES ACT COMPLIANT RAMP FOR THE FIRE STATION
NO. 1 DRIVEWAY REPLACEMENT PROJECT
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1. That the City Council of the City of Fayetteville, Arkansas hereby approves
Change Order No. 2 to the contract with Benchmark Construction in the amount of $6,703.00 for
installation of a sidewalk and an Americans with Disabilities Act compliant ramp for the Fire
Station No. 1 Driveway Replacement Project.
PASSED and APPROVED this 16th day of December, 2014.
APPROVED:
ATTEST:
By: a Lia. -a- 6
SONDRA E. SMITH, City Clerk/Treasurer
!>�`®1ti199Pt1i////
�®o�RK / : f >1''°.
�' • G\T Y o,� ,sG'.
: FAYETTEVILLE�
®Jy�11ANSP••�..
City of Fayetteville, Arkansas
Text File
File Number: 2014-0540
113 West Mountain Street
Fayetteville, AR 72701
479-575-8323 TDD -
479-521-1316
Agenda Date: 12/16/2014
In Control: City Council
Agenda Number: A3.
Version: 1 Status: Passed
File Type: Resolution
A RESOLUTION TO APPROVE CHANGE ORDER NO. 2 TO THE CONTRACT WITH
BENCHMARK CONSTRUCTION IN THE AMOUNT OF $6,703.00 FOR INSTALLATION OF A
SIDEWALK AND AN AMERICANS WITH DISABILITIES ACT COMPLIANT RAMP FOR THE
FIRE STATION NO. 1 DRIVEWAY REPLACEMENT PROJECT
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section 1. That the City Council of the City of Fayetteville, Arkansas hereby approves Change Order
No. 2 to the contract with Benchmark Construction in the amount of $6,703.00 for installation of a
sidewalk and an Americans with Disabilities Act compliant ramp for the Fire Station No. 1 Driveway
Replacement Project.
City of Fayetteville, Arkansas
Page 1 Printed on 12/17/2014
City of Fayetteville Staff Review Form
2014-0540
Legistar File ID
12/16/2014
City Council Meeting Date - Agenda Item Only
N/A for Non -Agenda Item
David Dayringer
Submitted By
11/18/2014
Submitted Date
Fire /
Fire Department
Action Recommendation:
Division / Department
Approval of Change Order No. 2 for the Fire Station #1 Driveway Replacement to add construction of sidewalk and
an ADA ramp to the contract.
Budget Impact:
4470.9470.5400.00
Account Number
02006.1
Project Number
Budgeted Item? Yes
Does item have a cost? Yes
Sales Tax Capital Improvements
Fund
Fire Facility Maintenance
Current Budget
Funds Obligated
Project Title
178,530.00
66,514.91
Current Balance $ 112,015.09 1
Item Cost $ 6,703.00
Budget Adjustment Attached? No Budget Adjustment
Remaining Budget
105,312.09 I
Previous Ordinance or Resolution #
Original Contract Number: Approval Date:
V20140710
12-ILQ-IL4
Comments: Original Contract was in Legistar #2014-0355 Change Order #1 was in Legistar #2014-0424
CITY OF
veaeviiie
ARKANSAS
TO: Mayor Lioneld Jordan
FROM: David Dayringer, Fire Chief
DATE: November 18, 2014
SUBJECT: Change Order #2 — Fire Station #1
RECOMMENDATION:
Staff recommends approval of Change Order #2 to the contract with Benchmark Construction
for the Fire Station #1 Driveway Replacement project.
DISCUSSION:
On August 19, 2014, the City Council approved a contract with Benchmark Construction for the
replacement of the concrete driveway and parking area in front of Fire Station #1. During the
construction of the driveway repairs, it was requested by the Development Services Department
that a sidewalk be incorporated into the driveway apron. A sidewalk in this location fills in a gap
between sidewalks along Center Street and Locust Avenue. In order to construct the sidewalk,
additional work was necessary to form the sidewalks to the proper grade. This also resulted in
twice the number of anticipated "pours" that the contractor had planned in the initial bid.
Benchmark Construction has provided a cost of $6,703.00 for the additional labor and materials
required for the sidewalk and ADA ramp installation for this project. This project was approved
with an original contract of $42,879.00 with an $8,575.90 contingency. $5,632.00 of this
contingency has been used for Change Order #1 for replacement of the unsuitable soils in a
portion of the project.
BUDGET/STAFF IMPACT:
The finances required for this project are already budgeted in the Fire Sales Tax Capital Project:
Fire Facility Maintenance.
Attachments:
Change Order #2
Mailing Address:
113 W. Mountain Street
Fayetteville, AR 72701
www.fayettevi l l e -a r. g o v
aee�le
ARKANSAS
Change Order No. 2
CHANGE ORDER
Contract Title Fire Station #1 Driveway Replacement
Date of Issuance
To Contractor: Benchmark Construction of NWA, Inc.
The Contract is changed as follows:
ORDINANCE/RESOLUTION:
Effective August 19, 2014
Summation of Cost $0.00
$6,703.00
Net Cost for this Change Order $6,703.00
Not valid until signed by the Owner
The original Contract Price was
Net change by previously authorized change orders
The Contract Price prior to this Change Order was
The Contract Price will be [increased][decreased] by
$ 42,879.48
$ 5,632.00
$ 48,511.48
6,703.00
The new Contract Price including this Change Order will be
The Contract Time(s) will be [remain unchanged]
Required dates of Competion as of the date of this Change Order therefore are:
Substantial Completion
Final Completion
$
55,214.48
60 calendar days
NA
NA
NOTE: This summary does not reflect changes in the Contract Price or Time(s) which have been authorized by Work Change Directives not incorporated in
this or previous Change Orders.
Benchmark Construction of NWA, Inc.
Bid
Bid
Previous
Unit
Contract
Revised
Revised
Original
Revised
Contract
Item
Item
Estimated
of
Unit
Estimated
Unit
Estimated
Estimated
Changes
No.
Description
Quantity
Measure
Price
Quantity
Price
Cost
Cost
8
Sidewalk Installation
0
LS
$0.00
1
$6,703.00
$0.00
$6,703.00
Summation of Cost $0.00
$6,703.00
Net Cost for this Change Order $6,703.00
Not valid until signed by the Owner
The original Contract Price was
Net change by previously authorized change orders
The Contract Price prior to this Change Order was
The Contract Price will be [increased][decreased] by
$ 42,879.48
$ 5,632.00
$ 48,511.48
6,703.00
The new Contract Price including this Change Order will be
The Contract Time(s) will be [remain unchanged]
Required dates of Competion as of the date of this Change Order therefore are:
Substantial Completion
Final Completion
$
55,214.48
60 calendar days
NA
NA
NOTE: This summary does not reflect changes in the Contract Price or Time(s) which have been authorized by Work Change Directives not incorporated in
this or previous Change Orders.
Benchmark Construction of NWA, Inc.