HomeMy WebLinkAbout180-14 RESOLUTIONRESOLUTION NO. 180-14
A RESOLUTION TO APPROVE AMENDMENT NO. 3 TO THE CONTRACT
WITH GARVER, LLC FOR CONSTRUCTION ADMINISTRATION
SERVICES ON THE SPRING STREET PARKING DECK PROJECT IN AN
AMOUNT NOT TO EXCEED $168,600.00
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves
Amendment No. 3 to the contract with Garver, LLC for construction administration services on
the Spring Street Parking Deck project in an amount not to exceed $168,600.00.
PASSED and APPROVED this 7th day of October, 2014.
ATTEST:
By: � Aiyzw
SONDRA E. SMITH, City Clerk/Treasurer
Agenda Date: 10/7/2014
In Control: City Council
Agenda Number: A. 10
City of Fayetteville, Arkansas
Text File
File Number: 2014-0418
Version: 1
113 West Mountain Street
Fayetteville, AR 72701
479-575-83 TDD -
479-521-1316
Status: Agenda Ready
File Type: Resolution
A RESOLUTION TO APPROVE AMENDMENT NO. 3 TO THE CONTRACT WITH GARVER,
LLC FOR CONSTRUCTION ADMINISTRATION SERVICES ON THE SPRING STREET
PARKING DECK PROJECT IN AN AMOUNT NOT TO EXCEED $168,600.00
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves Amendment No.
3 to the contract with Garver, LLC for construction administration services on the Spring Street Parking
Deck project in an amount not to exceed $168,600.00.
City of Fayetteville, Arkansas
Page 1 Printed on 10/9/2014
City of Fayetteville Staff Review Form
2014-0418
Legistar File ID
10/7/2014
City Council Meeting Date - Agenda Item Only
N/A for Non -Agenda Item
Chris Brown
Submitted By
9/23/2014
Submitted Date
Engineering /
Development Services Department
Action Recommendation:
Division / Department
Approval of Amendment No. 3 in the amount of $168,600 to the Contract with Garver, LLC for Construction Phase
Services on the Spring Street Parking Deck
Budget Impact:
4560.9560.5314.00
Account Number
11028.1203
Project Number
Budgeted Item? Yes
Does item have a cost? Yes
Parking Deck Project Expenses
Fund
Entertainment District Parking
Facility/Construction
Project Title
Current Budget $ 5,003,175.00
Funds Obligated $ 524,388.47
Current Balance
$ 4,478,786.53
Item Cost $
Budget Adjustment Attached? No Budget Adjustment
Remaining Budget
168,600.00
$ 4,310,186.53
Previous Ordinance or Resolution # -12,252-12,75-
Original Contract Number: 2230
Comments:
Approval Date:
1-10
V20140710
CITY OF
Taetre.Tit
ARKANSAS
MEETING OF OCTOBER 7, 2014
TO: Mayor and City Council
CITY COUNCIL AGENDA MEMO
THRU: Don Marr, Chief of Staff
Jeremy Pate, Development Services Director
FROM: Chris Brown, City Engineer
DATE: September 19, 2014
SUBJECT: Approval of Amendment No. 3 in the amount of $168,600 to the Contract
with Garver, LLC for Construction Phase Services on the Spring Street
Parking Deck
RECOMMENDATION:
Staff recommends approval of a contract amendment with Garver, LLC, in the not to exceed
amount of $168,600 for construction administration services on the Spring Street Parking Deck.
BACKGROUND:
A design team led by Garver, LLC was selected by a City selection committee in November,
2011 for engineering and architectural services on the Spring Street Parking Deck. Services
under this selection cover all three phases for the overall outcome of a designed parking deck in
downtown Fayetteville: Phase 1, Site Selection & Preliminary Design; Phase 2, Schematic
Design & Project Development; and Phase 3, Construction Administration Services. The
contract for Phase 1, Site Selection & Preliminary Design, was awarded on February 12, 2012.
The contract amendment for Phase 2, Schematic Design & Project Development, with the
objective of designing the structure, and performing all associated work required to develop the
design and construct the project, was approved in December 2012.
DISCUSSION:
This contract amendment with Garver will provide for construction administration services by
Garver and their subconsultants, Carl Walker Parking Consultants and and AFHJ Architects.
Services provided under this amendment will include review of construction material submittals
and other contractor/supplier submittals, design support for changes to the plans as required or
requested during construction, and periodic construction observation during the construction
period.
BUDGET/STAFF IMPACT:
Funding for this portion of the contract is coming from parking revenue bond proceeds.
Attachments:
Contract Amendment No. 3 with Garver
Mailing Address:
113 W. Mountain Street
Fayetteville, AR 72701
www.fayetteville-ar.gov
AMENDMENT TO AGREEMENT FOR PROFESSIONAL ENGINEERING SERVICES
CITY OF FAYETTEVILLE
FAYETTEVILLE, ARKANSAS
Project No. 11047180
SPRING STREET PARKING DECK
CONTRACT AMENDMENT NO. 3
This Contract Amendment No. 3, dated 0,,\-[)a9.ir '� , 2014 shall amend the original contract
between the CITY OF FAYETTEVILLE (Owner) and GARVER, LLC (Engineer), dated February 21,
2012 referred to in the following paragraphs as the original contract.
This Contract Amendment No. 3 adds additional professional services during the construction phase
of the project for the:
Construction of a Parking Deck to be located in the Downtown/Dickson Street area including the
associated liner buildings and infrastructure improvements.
The original contract is hereby modified as follows:
SECTION 5 - PAYMENTS TO GARVER
5.1 Compensation
Increase the not to exceed amount by $168,600.
EXHIBIT A - SCOPE OF SERVICES
Add Section 1.3.to the Exhibit A - Scope of Services for additional services as attached to and
made a part of this amendment.
EXHIBIT B - SUMMARY OF COSTS
Add the Exhibit B sheets attached hereto to Exhibit B contained in the original contract and
Amendment Nos. 1 & 2.
Contract Amendment No. 3 1 of 2
Fayetteville Downtown Parking Deck Garver Project No 1104-7180
This Agreement may be executed in two (2) or more counterparts each of which shall be deemed an
original, but all of which together shall constitute one and the same instrument.
OWNER ENGINEER
CITY OF - ETTEVI / GARVE LLC _
B, • ��L11_' -. By:
'v.
Title: Title: Xe.C Vr
ATTEST: 5614461'x" ,114,7x> ATTEST: /
ezi, C t�4
ilimirtitt
iN
Y ..,;,.4..,y./.,.,'
.
FAYETTEVILLE•1=
"iiii if int"
Contract Amendment No. 3 2 of 2
Fayetteville Downtown Parking Deck Garver Project No 1104-7180
AMENDMENT NO. 3 - EXHIBIT A
DOWNTOWN PARKING DECK
SCOPE OF SERVICES
1.3 PHASE 3 — CONSTRUCTION ADMINISTRATION SERVICES
Garver will subcontract with Carl Walker, Inc. and AFHJ Architects to perform portions of the
Phase 3 services. The scope for the services for the Project Team will include:
1.3.1 Pre -Construction Services
A. Garver will Issue a Notice to Proceed letter to the Contractor.
B. Garver will provide coordination with the franchise utilities.
C. The Project Team will evaluate and respond to construction material submittals and shop
drawings. Corrections or comments made by the Project Team on the shop drawings
during this review will not relieve Contractor from compliance with requirements of the
drawings and specifications. The check will only be for review of general conformance
with the design concept of the project and general compliance with the information given
in the contract documents. The Contractor will be responsible for confirming and
correlating all quantities and dimensions, selecting fabrication processes and techniques
of construction, coordinating his work with that of all other trades, and performing his
work in a safe and satisfactory manner. The Project Team's review shall not constitute
approval of safety precautions or constitute approval of construction means, methods,
techniques, sequences, procedures, or assembly of various components. When
certification of performance characteristics of materials, systems or equipment is required
by the Contract Documents, either directly or implied for a complete and workable
system, Garver shall be entitled to rely upon such submittal or implied certification to
establish that the materials, systems or equipment will meet the performance criteria
required by the Contract Documents. One set of approved shop drawings and
construction material submittals will be prepared and delivered to the City.
1.3.2 Construction Services
A. Garver will attend progress/coordination meetings on a bi-monthly basis with the
City/Contractor.
B. The Project Team will issue instructions to the Contractor on behalf of the City and issue
necessary clarifications (respond to RFIs) regarding the construction contract documents.
C. Review of the Contractor's progress payment requests is excluded from the scope of
services.
D. Resident construction observation services for the construction are excluded from the
scope of services. Garver will provide up to 110 hours of onsite consultation on an as -
needed basis.
In performing limited construction observation services, Garver will endeavor to protect
the City against defects and deficiencies in the work of the Contractor(s); but Garver
cannot guarantee the performance of the Contractor(s), nor be responsible for the actual
supervision of construction operations or for the safety measures that the Contractor(s)
Exhibit A Scope - Amendment No. 3 A-1 09/23/2014
takes or should take. However, if at any time during construction Garver observes that
the Contractor's work does not comply with the construction contract documents, Garver
will notify the Contractor of such non-compliance and instruct him to correct the
deficiency and/or stop work, as appropriate for the situation. Garver will also record the
observance, the discussion, and the actions taken. If the Contractor continues without
satisfactory corrective action, Garver will notify the City immediately, so that appropriate
action under the City's contract with the Contractor can be taken.
E. As a Subconsultant to Garver, Carl Walker, Inc. will provide Specialty Services during the
construction phase for the parking garage structure as specified in the attached proposal
and as follows:
1. Material submittal reviews and response to RFIs for responsible items.
2. One concrete pre -placement meeting with the Construction Manager, concrete
sub -contractor, ready -mix supplier prior to the parking garage concrete pour.
3. Provide one on-site observation of the work to help ensure the work is being
performed in conformance with the intent of the design documents.
4. Assist in the preparation and closeout of the project punch list. This includes one
site visit to create a punch list of items related to the parking deck superstructure.
F. As a Subconsultant to Garver, AFHJ Architects, with assistance from KB Architects, will
provide Architectural services during the construction phase for the parking garage
structure and Northern Liner Building as specified in the attached proposal and as
follows:
1. Material submittal reviews and response to RFI's for responsible items.
2. Provide periodic site visits for observation of the Architectural components which
include steel screening, windows, storefronts, curtain walls, guardrails, handrails,
lighting fixtures, cement board, metal siding & flashing, concrete for screening
coordination, elevator, glazing, green screen, expansion joints, skylight, roof
hatch, metal soffit, metal roof, insulation, sheathing, paint, stair nosing, TPO
roofing, steel studs, channels, fire proofing, gypsum board, joint sealers, doors
and hardware. In addition to the site visits by AFHJ Architects, fees include three
(3) site visits from KB Architects during the construction phase.
3. Provide LEED documentation.
4. Attend coordination meetings as necessary.
5. Attend final project walkthrough and assist in the preparation of the closeout
documents and project punch list.
G. Survey crew time for field checking quantities, contractor's layout, etc. have been
excluded from the scope of services
H. When authorized by the City, the Project Team will prepare change orders for changes in
the work from that originally provided for in the construction contract documents. If
redesign or substantial engineering or surveying is required in the preparation of these
change order documents, the City will pay the Project Team an additional fee to be
agreed upon by the City and Garver.
1.3.3 Project Close -Out
A. Garver will attend and participate in the Pre -Final Inspection and the entire Project Team
will participate in the final project inspection, prepare punch list, review final project
closing documents, and review the final pay request.
B. Garver will review whether the Punch list Items have been addressed in a satisfactory
manner.
Exhibit A Scope - Amendment No. 3 A-2 09/23/2014
C. The Project Team will review the Contractor's As -Built drawings and transfer items to the
originals with applicable notes. One set of drawings will be provided to the City along
with the digital copy.
Exhibit A Scope - Amendment No. 3 A-3 09/23/2014
EXHIBIT B -AMENDMENT NO. 2
CITY OF FAYETTEVILLE
SPRING STREET PARKING DECK
FEE SUMMARY
Original
Phase 1 - Site Selection Agreement Amendment 1 Amendment 2 Amendment 3 Totals
Geotechnical SeMces (Grubbs, Hoskyn, Barton & Wyatt 576,000.00 $0.00 $0.00 50.00 $76,000.00
Architectural SeMces (AFHJ Architects/KB Architects) 564,900.00 $0.00 50.00 50.00 564,900.00
Parking Garage Specialist (Carl Walker, Inc.) $55,000.00 $0.00 50.00 $0.00 555,000.00
Prime Consultant - Garver 540,000.00 50.00 $0,00 50.00 $40,000.00
Subtotal for Phase 1 Services $235,900.08 50.00 50.00 $0.00 $235,900.00
Phase 2 - Schematic Design and Project Development
Utility Marking (ARKUPS) 50.00 5750.00 50.00 $0.00 5750.00
Title Research (Elite Title) 50.00 5250.00 50.00 50.00 5250.00
Geotechnical Services (Grubbs, Hoskyn, Batton & Wyatt) $0.00 528,000.00 50,00 50.00 528,000,00
Surveys 30.00 $15,000.00 50.00 $0.00 $15,000.00
Property Line Adjustment 50.00 $0.00 $6,000.00 $0.00 $6,000.00
Schematic Design Development
Garver $0.00 579,700.00 $0,00 $0.00
Carf Walker - Perking Deck Specialist *0.00 $38,400.00 50.00 50.00
AFHJ Architects 50.00 $28,100.00 50.00 $0.00 5146,200.00
Preliminary Project Design
Garver $0.00 3102,300.00 50.00 50.00
Carl Walker - Parking Deck Specialist $0,00 $45,000,00 $0.00 $0.00
AFHJ Architects 50.00 537,500.00 $0.00 $0.00 $184,800.00
Construction Documents
Garver 50.00 5106,100.00 50.00 $0.00
Cart Walker- Parking Deck Specialist $0.00 586,700.00 50.00 $0.00
AFHJ Architects $0.00 575,000.00 50.00 50.00 5267,800.00
Additional Services
Garver 50.00 $0.00 517,300.00 50.00
Carf Waiker- Parking Deck Specialist $0.00 $0.00 50.00 50.00
AFHJ Architects $0.00 $0.00 548,525.00 $0.00 563,825.00
Construction Contract Procurement
Garver 50.00 517,900.00 50.00 50.00
Carl Walker -Parking Deck Specialist 50.00 54,900.00 50.00 50.00
AFHJ Architects $0.00 59,400.00 50.00 50.00 332,200.00
Subtotal for Phase 2 Services $0.00 $875,000.00 $69,825.00 $0.00 5744,825.00
Phase 3 - Construction Administration Services
Construction Materials Testing 50.00 50.00 $0.00 50.00 50.00
Construction Phase Services
Garver 50.00 50.00 $0.00 579,500.00 5168,600.00
Carl Walker - Parking Deck Specialist $38,600.00
AFHJ Architects $0.00 $0.00 50.00 $50,500.00
Subtotal for Phase 3 Services $0.00 $0.00 *0.00 5188,800.00 5188,600.00
C: UserelRSPeelelDocumenmlAPPENDIX 13 - Amendment 3 CPS
EXHIBIT B - AMENDMENT NO. 2
CITY OF FAYETTEVILLE
SPRING STREET PARKING DECK
CONSTRUCTION PHASE SERVICES
WORK TASK DESCRIPTION
0-6
E-5
0-4
E3
E-2
0-1
C-3
C-2
C-1
X-1
523800
5195.00
5159.00
5137.00
5114.00
598.00
5161,00
5122.00
588.00
556.00
hr
hr
hr
hr
hr
hr
hr
hr
hr
hr
1. Civil Engineering/Construction Administration
Precons8uclion Meetings
4
4
Utility Coordination
16
8
Progress Meetings vAth Contractor/City (12 r0n01a181-monthly)
12
48
Monthly Progress Paymens (12 Pay Rewests 8 RCO)
Shop DravAngslMaterlel Submittals2
40
10
Record Drawings
6
14
Onsite Meetings
20
60
30
Resident Construction Observation
Field surveys for checking Contractor's layout, etc.
Prepare Change Orders
Final Project Inspection and Panellist
6
8
Subtotal - ChM Engineering
0
44
0
182
0
60
0
0
0
0
2. Structural Engineering - Deck Foundations & NLB Structure
Response to Inquiries
24
Shop Drawings
90
Site Visits (3 visits)
24
Subtotal -Structural E ring
0
0
0
0
138
0
0
0
0
0
3. 31ecMnical Engineering
Response to 160hfea.
40
Shop Dray n sIMaterlal Submittals
20
20
Site Visits (2 visits)
16
Subtotal • Msstoudeal Enalnaaring
0
0
76
0
0
20
0
0
0
0
4. Elsetrlal Ergirwating
Response to014tddea
Shop Drawings/Material Submittals
30
10
Site Visits (2 visits)
16
Subtotel - Eleehleat Engineering
0
0
46
0
0
10
0
0
0
0
Hours
Salary Coat
SUBTOTAL SALARIES:
0
50.E
PIRECT NON -LABOR EXPENSES
Document Penang/Reproduction/Assembly
Postage/Freight/Courier
Survey Supplies
Travel Costs
5426.00
560.E
50.00
31,550.00
MANHOUR
SUBTOTALS
44 122 182 138 80 0 0 0 0 576
58,580.00 519,398.00 524,934.00 515,732.00 58,820.00 50.00 50.00 50.00 50.00 :77,464.00
577,464.00
SUBTOTAL - DIRECT NON -LABOR EXPENSES: $2,036.00
TOTAL FEE:
579,500.00
AFHJ PROPOSAL
REVISED CONSTRUCTION ADMINISTRATION TASKS - SEE NOTES AT BOTTOM HOURS FEE
BASED ON CURRENT QUOTED COMPLETION DATE
41902
Pre- Construction meeting, notes, documentations
Construction coordination / kick off meeting / notes
Construction progress meetings, notes, communication 22
RFI receipts, log in, response, issue required drawings 55
Sample receipts, log in, review, response, communication. 25
(Samples include all materiels specified under architectural sections)
Shop drawings receipts, log in, review, response, log out 80
(Shop drawings include all sections Issued under architectural sections)
LEED submittals, log in, review, response, separate filing required, logout 65
Construction observation hours 40
Field reports, document filing, communication 70
Proposal requests, change orders, log in, drawing, review response, communication 90
Substantial completion walk through 4
Punch list, documentation, communication 3 BALANCE BY OWNER
Final walkthrough, closeout documents 3 BALANCE BY OWNER
SUBTOTAL 457 $45,700
3 trips by KBA $4,800
TOTAL $50,500
1.THESE HOURS DO NOT INCLUDE CHANGE OF SCOPE OR REDESIGN OF THE PROJECT
2.THESE HOURS DO NOT INCLUDE SCHEDULE BEYOND CURRENT COMPLETION DATE
3.THE FEE CAN BE CHARGED ON AN HOURLY NOT TO EXCEED, BASED ON $100/HR. AFHJ WILL LIMIT THEIR
HOURS AS SCHEDULED UNLESS OTHEREWISE REQUESTED BY OWNER, IN WRITING, AS AN INCREASED SCOPE OF WORK
4 .AFHJ IS REQUIRED TO PERFORM TASKS THAT WILL AFFECT THEIR LIABILITY
5. ABOVE HOURS ARE REDUCED FROM WHAT AFHJ CONSIDERS A PROFESSIONAL LEVEL OF SERVICE TO A MINIMUM
LEVEL OF SERVICE BASED ON OWNER'S REQUEST.
6ARCHITECT WILL RECEIVE DOCUMENTATION ON LINE ITEMS PERFORMED BY OWNER
7. IF TRIPS BY KBA ARE FURTHER REDUCED AFHJ WILL HAVE TO FILL IN FOR THEIR PORTION OF THE WORK AND
COMMUNICATE LONG DISTANCE ANY ISSUES THAT MIGHT ARISE, THEREFORE THE TOTAL HOURS FOR THAT LINE ITEM
MAY BE REDUCED BUT WILL NOT BE ELIMINATED. IF IN OUR PROFESSIONAL JUDGEMENT ISSUES REQUIRE THEIR DIRECT
ATTENTION, THEY WILL BE REQUIRED TO MAKE THE TRIP.
8. ANY UNKNOWN CONDITIONS THAT ARISE DURING CONSTRUCTION, WHICH MAY RESULT IN WORK IN ADDITION TO THE
QUOTED HOURS WILL BE CONSIDERED ADDITIONAL SERVICE
9. DECISIONS REGARDING DETAILS, AND DESIGN OF ARCHITECTURAL ELEMENTS AS WELL AS OTHER ELEMENTS THAT
AFFECT ARCHITECTURAL DESIGN HAVE TO BE REVIEWED AND APPROVED BY THE ARCHITECTS
10. ARCHITECTS HOURS LISTED NEXT TO WORK TO BE PERFORMED BY OWNER ARE FOR REVIEW OF DOCUMENTATION ONLY
11. THE HOURS QUOTED ARE ESTIMATES AND THE OVERALL BALANCE MAY BE SHIFTED FROM ONE LINE ITEM TO ANOTHER.
EACH LINE ITEM AND ANY ADDITIONAL SERVICES WILL BE DOCUMENTED INDIVIDUALLY. THE FINAL TOTAL HOURS WILL BE
BALANCED AGAINST THE QUOTED HOURS. ONLY IF ANY OF ADDITIONAL SERVICE HOURS EXCEED BEYOND THE TOTAL QUOTED
HOURS, ADDITIONAL FEE WILL BE INCURRED.
Ca r1
WalWeir
September 22, 2014
Mr. Ron Petrie, P.E.
Senior Project Manager
Garver, LLC
2049 East Joyce Blvd
Suite 400
Fayetteville, AR 72703
rspetrie@garverusa.com
Re: Spring Street Parking Deck - Phase 3 Construction
Fayetteville, Arkansas
Carl Walker, Inc. Proposal N1-14-515
Dear Ron:
Carl Walker, Inc. is pleased to submit this proposal to you to provide professional Parking Facility
Design Consulting services for the above mentioned project in Fayetteville, Arkansas. Our scope
of services is described in detail below, but in general we will provide consulting services
incorporating the disciplines of Structural Engineering and Parking Consulting for this third phase
of this parking facility project, the construction phase.
As specialists in the design and construction of multi-level parking structures, we believe that our
expertise will be an asset for you and the owner in developing a user-friendly and cost-effective
parking facility. As we work through our firm's 3151 year in business, our experienced staff of
designers can proudly reflect on thousands of projects, hundreds of parking structures and
millions of parking spaces for clients nationwide.
PROJECT UNDERSTANDING
Based upon our involvement in the site selection and design phases of this project, we
understand that construction will proceed on the 236 space, 3 -level parking structure. The
construction will be of long -span post -tensioned concrete, and include cast -in-place concrete
stair and elevator towers. Additionally, the design includes an enclosed south liner building
partially within the footprint of the garage, and a partially -enclosed east liner building adjacent
to the southeast corner of the garage.
This third phase of the project will cover construction administration services for the parking
structure. We understand the City of Fayetteville has a timeline of approximately 12 months for
the construction of the parking structure immediately following design, and upon notice to
proceed given to the contractor. Length of schedule increases brought forth by parties outside
of Carl Walker, Inc.'s control, which increase the need for labor and expenses on our part
beyond the basic services included with this proposal will be subject to additional services
increases in the fee set forth in this proposal for our work.
Ideas for parking. 2801 Network Blvd, Suite 101, Frisco TX 75034
SOLUTIONS FOR QEOPLE, Tel: 214.619.0700 Fax:214.619.0505 1 carlwalker.com
Mr. Ron Petrie
Spring Street Parking Deck
September 22, 2014
SCOPE OF SERVICES
Ca r1
Walker
As noted above, Carl Walker, Inc. will function as the Parking facility Design Consultant for this
new facility. In this capacity, we will provide functional and structural design consulting and
construction administration with our in-house staff. See below and attached for a detailed
Scope of Services for our work.
Not included in our scope is construction administration for other building designs (e.g. the WAC
Administration Building), architecture, geotechnical engineering, foundations (piers, piles, caps,
retaining walls, grade walls, pits) structural engineering, MEP engineering, civil engineering,
landscape architecture, surveying, street traffic engineering (roadway/intersection
improvements), traffic impact analysis, environmental, security systems, architectural graphics or
construction costing and scheduling. If necessary, we can assist in obtaining these services.
Carl Walker, Inc. will...
Construction Administration Phase
A. Review shop drawings and submittals on work specified and/or detailed by Carl
Walker, Inc.
B. Respond to RFIs on work specified and/or detailed by Carl Walker, Inc.
C. Coordinate with project consultants, where necessary.
D. Attend scope related meetings during construction in conjunction with site
observation visits, if possible. Our fee covers a maximum of three (3) site visits
during construction.
E. Provide final punch list (punch list site visit is included in the above) and record
drawings for parking and structural items.
PROFESSIONAL FEES
Based upon our project understanding and the Scope of Services discussed above, we are
proposing a professional fee, on an hourly not -to -exceed basis, of $36,300. Project related
expenses such as travel, communications, delivery, reproductions, printing, etc. are not included
in this fee. We estimate project related expenses in the amount of $2,300. Expenses will be
billed in addition to our hourly not -to -exceed fee.
FEE EXCLUSIONS
Carl Walker, Inc.'s project related coordination efforts with the following tasks and consultants
are included within the proposed design fees. Costs for these Owner and Contractor provided
surveys, testing, inspections and consultants are not part of the above referenced design fees.
• Permits, Fees, or Other Related Miscellaneous Expenses
• Topographic and Utilities Survey
• Boundary Line Surface Survey
• Hydrology Study
• Architecture
Ideas for parking. 2
SOLUTIONS FOR QEOPLE.
Mr. Ron Petrie 41Ca rl
Spring Street Parking Deck Walker
September 22, 2014
• Civil Engineering
• MEP Engineering
• Construction Soils Testing
• Construction Materials Testing
• Special Inspections
• Environmental Impact Assessment
• Interior Design
• Traffic Engineering of Street or Intersection Improvements
• Geotechnical Engineering Consultant
• Foundations Structural Engineering
• Other buildings Structural Engineering
• Landscape Architect
• Security Systems Consultant
• Costing and Scheduling Consultant
ADDITIONAL SERVICES
Additional services outside the Scope of Services listed above, when requested and authorized
in writing, shall be performed on an hourly fee basis per the attached Fee Schedule, or a lump
sum basis as negotiated with you.
TERMS AND CONDITIONS
We anticipate that this proposal will be an addendum to the formal contract agreement
between Garver, LLC and Carl Walker, Inc. for the above mentioned project.
We trust we have responded to your request for proposal. If you are in agreement with the
scope of services, professional fees, and terms of this proposal, your signature in the space
provided below will serve as our notice to proceed. Please return one (1) copy to our office.
If you have any questions regarding this proposal, please give me a call. We look forward to
continuing working with you, the City of Fayetteville and the rest of the Project Team.
Ideas for parking. 3
SOLUTIONS FOR QEOPLE:
Mr. Ron Petrie
Spring Street Parking Deck
September 22, 2014
Thank you for considering Car! Walker, Inc.!
Carl
Walker
Sincerely, ACKNOWLEDGED AND ACCEPTED
Garver, LLC
Carl Walker, Inc.
SIGNATURE
Jeffrey R. Hanson, P.E.
Senior Project Manager NAME / TITLE
Michael C. Ortlieb, P.E.
Executive Vice President
FIRM
cc: Fabio Serrato - Cart Walker, Inc. DATE
Ideas for parking. 4
SOLUTIONS FOR QEOPLE.
McCoy, Dee
From: Brown, Chris
Sent: Friday, October 10, 2014 3:00 PM
To: McCoy, Dee
Subject: Garver Contract Amendment 3 -Parking Deck
Dee,
Regarding the unsigned page in the referenced agreement: the subcontract with Carl Walker that has not been signed
by Garver was provided for reference, and is not part of our contract with Garver, so we should not require that it be
signed before the Mayor signs the contract amendment.
Thanks,
Chris
Chris Brown, P.E.
City Engineer
City of Fayetteville, Arkansas
479.575.8207
Website 1 Facebook 1 Twitter 1 YouTube
1
Mr. Ron Petrie
Spring Street Parking Deck
September 22, 2014
Carl
alk
PARKING FUNCTIONAL AND STRUCTURAL DESIGN
SCOPE OF SERVICES
Page 1 of 1
A. Construction Administration
1. Attend pre -construction meetings as follows:
a. One (1) concrete pre -placement meeting with the General Contractor and their
concrete sub -contractor, ready -mix supplier, etc. prior to placing and finishing
supported level concrete in the garage.
2. Review appropriate shop drawings and submittals related to our scope of work.
3. Respond to Requests for Information (RFI's) related to our scope of work.
4. Provide one (1) on-site observation of the Work, to help assure the work is being
performed in conformance with the intent of the design documents.
5. Assist in preparation and closeout of the project punch list. This includes one (1) site
visit to create punch list items relating to Cart Wacker, Inc. scope of work.
Ideas for parking. 5
SOLUTIONS FOR QEOPLE.
Mr. Ron Petrie
Spring Street Parking Deck
September 22, 2014
CARL WALKER, INC.
FEE SCHEDULE FY 2014
FSWP:201 4
Carl
alker
President $281.00 $281.00 /Hr
Executive/Senior Vice President $209.00 $249.00 /Hr
Vice President; Managing Principal $183.00 - $209.00 /Hr
Principal $145.00 $173.00 /Hr
Restoration Manager; Chief Engineer $183.00 $209.00 /Hr
Senior Project Manager $138.00 - $162.00 /Hr
Project Manager; Senior Engineer $119.00 - $162.00 /Hr
Senior Architect; Senior Planner $122.00 - $127.00 /Hr
Senior Parking/Restoration Specialist $135.00 $154.00 /Hr
Parking/Studies Specialist $124.00 - $133.00 /Hr
Project Engineer/Architect; Design Engineer $ 93.00 - $126.00 /Hr
Chief/Senior Design Technician $111.00 - $133.00 /Hr
Design/Parking Technician $ 80.00 - $ 86.00 /Hr
Restoration Specialists $ 84.00 $104.00 /Hr
Restoration Technician $ 71.00 - $101.00 /Hr
Clerical $ 52.00 $ 90.00 /Hr
Hourly billing rates are effective March 1, 2014 through February 28, 2015.