HomeMy WebLinkAbout40-13 RESOLUTIONRESOLUTION NO.40-13 A RESOLUTION AWARDING BID 413-16 AND AUTHORIZING THE PURCHASE OF PRECAST BOX CULVERT SECTIONS FROM SCURLOCK INDUSTRIES OF FAYETTEVILLE IN THE TOTAL AMOUNT OF $71,404.71 FOR THE CONSTRUCTION OF A TRAIL TUNNEL FOR THE TSA LA GI TRAIL, AND APPROVING A FIVE PERCENT (5%) PROJECT CONTINGENCY BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS: Section 1. That the City Council of the City of Fayetteville, Arkansas hereby awards Bid #13-16 and authorizes the purchase of precast box culvert sections from Scurlock Industries of Fayetteville in the total amount of $71,404.71 for the construction of a trail tunnel for the Tsa La Gi Trail. Section 2. That the City Council of the City of Fayetteville, Arkansas hereby approves a project contingency of five percent (5%). PASSED and APPROVED this 5 h day of March, 2013. APPROVED: am ATTEST: By: ;• SONDRA E. SMITH, City Clerk/Treasurer t���lt►1 If r ►►►►►,r iAYL11',.Vli.! . ref P.- City of Fayetteville Staff Review Form Matt Mihalevich t, Submitted By City Council Agenda Items and Contracts, Leases or Agreements March 5, 2013 City Council Meeting Date Agenda Items Only Engineering Division Action Required: Development Services Department Approval of a resolution awarding Bid #13-16 and approving the purchase of precast box culvert sections from Scurlock Industries of Fayetteville in the amount of $65,359.00 plus sales tax in the amount of $6,045.71 for a total contract amount of $71,404.71 for installation through an existing tunnel under the Arkansas & Missouri Railroad Tsa La Gi (Cherokee). Approval of a 5% contingency in the amount of $3,570.24 is also requested. 74,974.95 $ Cost of this request 4470.9470.5814.05 Account Number 02016/1203 Project Number Budgeted Item 1,548,000.00 Category / Project Budget $ 135,107.26 Funds Used to Date $ 1,412,892.74 Remaining Balance Budget Adjustment Attached u Trail Development Program Category / Project Name Trail Improvements Program / Project Category Name Sales Tax Capital Improvements Fund Name (,. ( ,V 13 Previous Ordinance or Resolution # Date Original Contract Date: 16— Iv Original Contract Number: Date 401& a . (�z - is zit, Finance and Internal Services Director Date //L A,a �f 13 Chief of�ff Date ate Received in City 02_ t`F= Clerk's Office Ott Itl: Received in tst Mayor's Office Revised January 15, 2009 ZayPV.! e XANSASM CITY COUNCIL AGENDA MEMO To: Mayor and City Council Thru: Don Marr, Chief of Staff �Q Jeremy Pate, Development Services Director u+ Chris Brown, City Engineer G2> From: Matt Mihalevich, Trails Coordinator PA Date: February 14th, 2013 Subject: Tsa La Gi (Cherokee) Trail — Precast Box Culvert Bids RECOMMENDATION: THE CITY OF FAYETTEVILLE, ARKANSAS DEPARTMENT CORRESPONDENCE Staff recommends approval of a resolution awarding Bid #13-16 and approving the purchase of precast box culvert sections from Scurlock Industries of Fayetteville in the amount of $65,359.00 plus sales tax in the amount of $6,045.71 for a total contract amount of $71,404.71 for installation through an existing tunnel under the Arkansas & Missouri Railroad Tsa La Gi (Cherokee). Approval of a 5% contingency in the amount of $3,570.24 is also requested. PROPOSAL: The Tsa La Gi (Cherokee) Trail is a 1.6 mile trail that will run along an abandoned railroad corridor just south of Martin Luther King Jr. Blvd. This trail will provide a safe alternative transportation route for the numerous new student housing and commercial developments along the corridor. The trail will include a tunnel for safe crossing under the Arkansas & Missouri Railroad. There is existing tunnel that was installed in the early 1900's as part of the Ozark & Cherokee Central Railroad. The concrete tunnel is showing signs of age and the Arkansas & Missouri Railroad has requested the tunnel be upgraded to current railroad loading design to use for the trail. Staff reviewed several alternatives to preserve the historic look of the existing tunnel, however due to the degrading condition of the concrete, salvaging the old tunnel is cost prohibitive. The cost effective solution includes inserting the 12' by 12' precast concrete box culvert sections as a liner in the old tunnel and backfilling the sides and top with clean stone to accomplish the required loadings. The City's in-house trails construction crew has been working diligently on the trail project and will install the tunnel using the precast box culvert sections from this bid. BUDGET IMPACT: Funds for the purchase of the precast box culvert sections have been budgeted as part of the Capital Improvements Program for Trail Development. 3 bids were received and low bidder is Scurlock Industries of Fayetteville — see attached bid tabulation. RESOLUTION NO. A RESOLUTION AWARDING BID #13-16 AND AUTHORIZING THE PURCHASE OF PRECAST BOX CULVERT SECTIONS FROM SCURLOCK INDUSTRIES OF FAYETTEVILLE IN THE TOTAL AMOUNT OF $71,404.71 FOR THE CONSTRUCTION OF A TRAIL TUNNEL FOR THE TSA LA GI TRAIL, AND APPROVING A FIVE PERCENT (5%) PROJECT CONTINGENCY BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS: Section 1. That the City Council of the City of Fayetteville, Arkansas hereby awards Bid #13-16 and authorizes the purchase of precast box culvert sections from Scurlock Industries of Fayetteville in the total amount of $71,404.71 for the construction of a trail tunnel for the Tsa La Gi Trail. Section 2. That the City Council of the City of Fayetteville, Arkansas hereby approves a project contingency of five percent (5%). PASSED and APPROVED this 51h day of March, 2013. APPROVED: LIONELD JORDAN, Mayor ATTEST: 51 SONDRA E. SMITH, City Clerk/Treasurer Tsa La Ci (Cherokee) Trail R 5T 4 ,� z a x NETTLESHIP ST W MAIN E ST W rnUJI Q > Q V Z O STONE ST Uj W Z QW ,+�. ir�tf�efl',Ul.il _ Q' rA o W MITCHELL ST VENDS ST 1-'= r"",: ;lrrrr" a c� �G FAIRVIE ST MEADOW ST 2 Oak Ridge Trail O QIT aa� MEADOW ST 4111 lrh �l;•fi'r r•; �� O Z n 'r/ W �geTr.,Q 4 f:• �;,II' iirl! �P CENTER ST CLIN�O�O TRFr4DWELL 5T 0 11;, i=11.1 v 7 > r Q Ar Q 1 av:t.:r . riles PUTMAN LEROY POND DR ST o � w y �O S N M ^ W M w W > C� > L W Q } LU Z 1K Tl e&LLDOGBLV.D W v Q = Q W I > Z A > SOUTH ST PUBLIC US OR Z J w o CARLSON filtliti ti.7ir ;S = Q W —1 U : L._{ .it. W N _j m Q c :..,. Z a m MARTIN LUTHER-KING.BLVD U _ CAP ELLA ST Tsa-La-Gi Trail W & S o l % > O+ 0 W W > > Q Q OFFICE DR ST ROCHIER 77 Tsa La GiTraF1 Tsa-�a "-Trail _ W z STORAGE DR '•e+l i N� WAREProposed Precast Box Culvert Tunnel : '4BRIEL CIR — re CHEBFiIRE CT . Linder the Arkansas & Missouri Railroad sus O a� '! 0 �g w r . ATHLE71C'DR 2E '['�110 o� .. G 9s7 E.egend..,.. Tsa La Gi Trail - 1.8 Miles S� Qa+�*■■■ 11TH ST 11TH ST O■�' W H Future Trails m y ■■. Q v Existing Multi -Use Trail Multi-U 0 ccyas .11%4 < y } 0 ; : 12TH ST -a Uj W Nature Trail `FP■. Q • ----------• Park Trail :, y■• �'rnrla:!- C'. Sidewalk Connection " l'ilr' ■r•■ I `�i•C',�/� �/ Q 13TH ST s 0 0.05 0.1 0.2 0.3 0.4 0.5 4L z z '; Ut�►� � yR D13 Miles'o yy sy Tayv�el, r e 1T T 11 e A R K A N S A S Bid 13-16, Pre -Cast Concrete Box Culverts Item # Descriptloii , i1n af:Meisvre = . Fs6_pry..- Hanson Pipe and Precast Industrial Precast Inc. Scurlock Industries --.t1nhPifcr -:;'•:=F..,lm+dcdPiice '11ri�✓r+ios$*- .-.'kilaiid�dPiier:'= '� t3ralPiiae�•:. • ..Extc+idod-prtce:. .:. • ..�• ";' . . Five (5) foot section of 12 ft wide by 12 ft tall pre -cast concrete t box culvert. PRICE PER EACH 5 FT SECTION Fer 5 FT 20 $ 7,610.00 $ 152 200.00 $ 4,950.00 $ 99,000.00 $ 3,233.75 S 64,675.00 Section 2 12" wide ConSeal CS-212 Joint membrane wrap with CS-75 Per Linear 684 $ 2.40 S 1.641.60 S 3.00 $ 2.052.00 $ 1.00 $ 684.00 primer. PRICE PER LINEAR FOOT Foot Total Bid Price = $ 153,841.60 $ 101,052.00 _.' _= $ 65,359.00 'NOTICE: Bid award is contingent upon vendor meeting minimum specifications and formal authorization by City officials. BIO:13-16 DATE: 02/14/13 TIME, 2:00 PM CITY OF FAYETTEVILLE Requisition No.: Date City Of Fayetteville - Purchase Order (PO) Request 3/5/2013 (Not a Purchase order) P.0 Number: _xpeciea ueiivery ME All purchases under $2500 shall be used on a P-Card unless medical or 1099 service related. (Call x256 with questions) All PO Request shall be scanned to the Purchasing e-mail: Purchasing ci.fayetteville.ar.us Vendor #: Vendor Name: iviai 17158 Scurlock Industries of Fay, Inc. Yes: X No: Address: Fob Point: Taxable Quotes Attached Yes:_C No:_ Yes:' No:_X. City: State: Zip Code: Ship to code: Divison Head Approval: 104 Requester: Requester's Employee # Extension: Q.--- Ginny Gundlach 2283 x3489 (� i Item Description Quantity Unit of Issue Unit Cost Extended Cost Account Numbers Project/Subproject # Inventory # Fixed Asset # 1 Precast Concrete Box Culvert for Tsa La Gi Trail 1 LOT 65,359.00 $65,359.00 4470.9470.5814.05 020161 1203 2 $0.00 3 $0.00 4 $0.00 5 $0.00 6 $0.00 7 $0.00 8 $0.00 9 $0.00 10 $0.00 Shipping/Handling Lot $0.00 apeciai instructions: Per Bid 13-16 and Res 5utstC!al $65,359.00 Tax: $6,045.71 Total: $71,404.71 Approvals: Mayor: Department Director: Purchasing Manager: Finance & Internal Services Director: Budget Manager. IT Manager: Dispatch Manager: Utilities Manager: Other - Re ,s-d 1 ._--- ...