HomeMy WebLinkAbout33-12 RESOLUTIONRESOLUTION NO. 33-12
A RESOLUTION APPROVING AMENDMENT #3 TO THE ENGINEERING
SERVICES AGREEMENT WITH MCCLELLAND CONSULTING
ENGINEERS IN THE AMOUNT OF $68,515.00 FOR CONSTRUCTION
PHASE SERVICES FOR THE SECOND PHASE OF THE HIGHWAY 265
WATER AND SEWER RELOCATION PROJECT FROM JOYCE AVENUE
TO ALBRIGHT ROAD, MAINTAINING A PROJECT CONTINGENCY OF
$20,000.00, AND APPROVING A BUDGET ADJUSTMENT
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1. That the City Council of the City of Fayetteville, Arkansas hereby approves
Amendment #3 to the engineering services agreement with McClelland Consulting Engineers, a
copy of which is attached as Exhibit "A", in the amount of $68,515.00 for construction phase
services for the second phase of the Highway 265 Water and Sewer Relocation Project from
Joyce Avenue to Albright Road, and maintains a project contingency of $20,000.00.
Section 2. That the City Council of the City of Fayetteville, Arkansas hereby approves a
budget adjustment, a copy of which is attached as Exhibit "B".
PASSED and APPROVED this 21St day of February, 2012.
APPROVED:
By: 1
L ON" DJ
ATTEST:
N, Mayor LISA BRANSON, Deputy City Clerk
,a„i4F7if 7p�pI
‘‘‘`,F1VTh, q
na''
&‘:3° 6i‘'('
o rooj:
�,�k�
°,ea / V
r.0o d
:F AY ETT EV ILLE
Shannon Jones
Submitted By
City of Fayetteville Staff Review Fomi
City Council Agenda Items
and
Contracts, Leases or Agreements
2/21/2012
City Council Meeting Date
Agenda Items Only
Utilities Capital Projects
Division
Action Required:
Utilities
Department
Approval of Amendment #3 to the engineeering services agreement with McClelland in the amount of $68,515.00 for
construction phase services for the second phase of the Hwy. 265 W&S relcoation project, Joyce to Albright,
maintain a contingency of $20,000.00, and approve a budget adjustment. Expected is AHTD funding of
approsimately $49,110.00 (federal grant) and City funding of $2;405.00.
(41,110.00)
41,110.00
27,405.00
Cost of this request
5400.0940.4309.00
5400.5600.5314.00
5400.5640.5314.00
Account Number
08072.1102
08072.1102
09018.0902
Project Numbers
Budgeted Item
XX
ttorney
107,472.30
1,723,660.00
Category / Project Budget
(41,110.00)
107,472.30
27,405.00
Funds Used to Date
1,696,255.00
Remaining Balance
Budget Adjustment Attached
AHTD Federal Grant 66%
W/S Relocations for Street Bond Projs.
Program Category / Project Name
AHTD Federal Grant 66%
W/S Relocations for Street Bond Projs.
Program / Project Category Name
W/S
W/S bonds
XX
Fund Name
Previous Ordinance or Resolution # 64-11, 234-08
Date
Original Contract Date: 12/16/2008
Date
`Cash 2-1-2cart,
Finance and Internal Services Director
Date
Original Contract Number: 2064
01-31-12P02:55
Received in City
Clerk's Office
Revised January 15, 2009
AMENDMENT NO. 3
To
AGREEMENT FOR PROFESSIONAL ENGINEERING SERVICES
Between
CITY OF FAYETTEVILLE, ARKANSAS
And
McCLELLAND CONSULTING ENGINEERS, INC.
FAYETTEVILLE, ARKANSAS
For The
HIGHWAY 265 (CROSSOVER ROAD) WATER & SEWER IMPROVEMENTS
The December 16, 2008 Agreement between the CITY OF FAYETTEVILLE and
McCLELLAND CONSULTING ENGINEERS, INC. is hereby amended to provide for
engineering services during the construction phase of Phase II of the Crossover Road Water and
Sewer Improvement Project from the vicinity of Joyce Boulevard to the vicinity of Albright Road
(AHTD Job 040518).
The Scope of Services for the Phase II (AHTD Job 040518, Joyce to Albright)
Construction Phase Services shall generally include resident construction observation services,
conduct and attend a preconstruction conference, preparation and/or review of monthly progress
payments, construction administration assistance, periodic and final inspections, final punch list
preparation and follow up, preparation of record drawings, coordinate as appropriate with AHTD,
and project closeout.
The total estimated compensation for the previously approved engineering services,
including Amendment No. 1 and No. 2, and these additional services will be increased from
$719,627.08 to $788,141.84 as further defined in Appendix A to this Amendment No. 3.
All other provisions, covenants, recitals, terms and conditions of the Agreement, which
are not expressly amended herein, shall remain in full force and effect.
i_oeryThe parties hereby have executed this Amendment No. 3 on this date, the AA Si -day of
tk&A2012.
CITY OF FA TTEVILLE, ARKANSAS McClelland Consulting Engineers, Inc.
By:
ATTES
By:
ayor
By: X‘f,04./er,—.._
ATTEST:
atranra►►►
eoo�o By:
City Clerk ••-VvY0°;fel',`
FAYETTEVILLE
'o-ys elikANS��J���
":,15% tl••°@0 os. see Groh °ee°
°eeeeaaisaaeeea®
FY112118 Amendment No. 3
President
Page 1
APPENDIX A
TO
AMENDMENT NO. 3
HIGHWAY 265 WATER & SEWER IMPROVEMENTS
NOVEMBER 22, 2011
Phase II Project (AHTD Job 040518, Joyce to Albright)
Construction Phase Services, Fee Proposal
Labor Classification
Construction Observer II
Construction Observer III
Project Manager
Draftsman II
Chief Draftsman
Clerical
Hours Labor Rate
920 $16.22
70 $20.70
140 $46.59
24 $16.94
16 $22.25
20 $17.79
Subtotal
Payroll Expense (96.10%)
Indrect Costs (58.66%)
Subtotal
Profit 12%
Total Construction Phase Services
Extended
$14,922.40
$1,449.00
$6,522.60
$406.56
$356.00
$355.80
$24,012.36
$23,075.88
$14,085.65
$61,173.89
$7,340.87
$68,514.76
City of Fayetteville, Arkansas
Budget Adjustment Form
V11.0425
Budget Year
2012
Division: Utilities Director
Department: Utilities Director
Request Date
1/30/2012
Adjustment Number
BUDGET ADJUSTMENT DESCRIPTION / JUSTIFICATION
Move funds for Amendment # 3 - McClelland - Hwy. 265 W&S construction oversight for Joyce to Albright (North).
There are two funding sources, one is a grant from AHTD and one is City bond funds.
Division Head
Date
Depa ent '-ctor
Prepared By:
Reference:
kspringer
Budget & Research Use Only
Type: A B C D E P
g� r Date
�� . t i ,�,� 9,-1-10), General Ledger Date
Finan &, • l irector e)-- Posted to General Ledger
Date
Chief Sta Date
Checked / Verified
yor / ate
Account Name
TOTAL BUDGET ADJUSTMENT
Account Number
41,110
Initial Date
Initial Date
41,110
Increase / (Decrease)
Project.Sub
Expense Revenue Number
Federal Grants -Capital 5400.0940.4309.00 .
41 .,110 08072 . 1102
Professional services
**ADD**Water line improvements
5400.5600.5314.00 41,110 08072. 1102
5400.5740.580.,8.00 (27,405) 09018 . 0902
•
Professional services
5400.5640.5314.00 27,405 08072 . 1102
J:\EXCEL\Proj 08072 McClelland\Budget Adjustment\Move funds for C0#3 McClelland 01302012.xls
• 1 of 1
ave eville
CITY COUNCIL AGENDA MEMO
MEETING DATE OF FEBRUARY 21, 2012
THE CITY OF FAYETTEVILLE, ARKANSAS
ARKANSAS
www.accessfayetteville.org
To: Fayetteville City Council
Thru: Mayor Lioneld Jordan
Don Marr, Chief of Staff
David Jurgens, Utilities Director
From: Shannon Jones, Utilities Engineer
Fayetteville Water and Sewer Comm ttee
Date: January 31, 2012
Subject: Amendment No. 3 to the McClelland Consulting Engineers agreement for $68,515 for construction phase
services of the Hwy. 265 Water and Sewer Relocation project.
RECOMMENDATION
Staff recommends approval of Amendment No. 3 to the McClelland Consulting Engineers agreement for
$68,515 for construction phase services for the second phase of the Hwy. 265 Water and Sewer Relocation
project from Joyce to Albright, maintain a $20,000 contingency, and approve a budget adjustment.
BACKGROUND
The original design contract was awarded to McClelland Consulting Engineers in December, 2008 to design
relocated water and sewer lines as a result of the combined Arkansas Highway Department (AHTD) and City
widening of Phase I of Crossover Road (Hwy 265) between Mission and Joyce, upsizing the existing pipes and
connecting a 36" transmission line. Work includes installing a 36" and 24" transmission main along Crossover
from Joyce to connect to the existing 24" main on Crossover at Mission and to connect to the existing 36" main
on Old Wire Road. This work will complete the eastern portion of the loop that was initially constructed when
the southern section of Crossover Road between Mission and Huntsville was widened by the AHTD.
Construction phase services were added by amendment.
Design work for relocating and/or upgrading water and sewer lines for Phase II of the widening of Hwy 265
from Joyce to Albright was authorized and awarded to McClelland Consulting Engineers in April, 2011. The
design for relocating water and sewer lines on both sides of the highway is complete.
DISCUSSION
This amendment covers the construction phase engineering services for the Highway 265 water/sewer
relocations from Joyce to Albright. The work includes one full time construction observer, attending
preconstruction conferences, reviewing contractor schedules and submittals, monthly progress meetings, weekly
stormwater compliance monitoring, reports to the City and the AHTD, partial pay requests, regular site visits,
change order processing, final inspection, final pay request review, developing as-builts, and related activities.
Construction is anticipated to begin this summer and be completed by March 2013.
BUDGET IMPACT
This project is partially reimbursable by AHTD. The City's portion will be funded from Water and Sewer
revenue bonds; the remainder will be paid by the AHTD. The cost share split is approximately 1/3 City of
Fayetteville and 2/3 AHTD.
Telecommunications Device for the Deaf TDD (479) 521-1316 113 West Mountain - Fayetteville, AR 72701
McClelland Amendment 3 CCMemo 30Jan2012.doc
RESOLUTION NO.
A RESOLUTION APPROVING AMENDMENT #3 TO THE ENGINEERING
SERVICES AGREEMENT WITH MCCLELLAND CONSULTING
ENGINEERS IN THE AMOUNT OF $68,515.00 FOR CONSTRUCTION
PHASE SERVICES FOR THE SECOND PHASE OF THE HIGHWAY 265
WATER AND SEWER RELOCATION PROJECT FROM JOYCE AVENUE
TO ALBRIGHT ROAD, MAINTAINING A PROJECT CONTINGENCY OF
$20,000.00, AND APPROVING A BUDGET ADJUSTMENT
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1. That the City Council of the City of Fayetteville, Arkansas hereby approves
Amendment #3 to the engineering services agreement with McClelland Consulting Engineers, a
copy of which is attached as Exhibit "A", in the amount of $68,515.00 for construction phase
services for the second phase of the Highway 265 Water and Sewer Relocation Project from
Joyce Avenue to Albright Road, and maintains a project contingency of $20,000.00.
Section 2. That the City Council of the City of Fayetteville, Arkansas hereby approves a
budget adjustment, a copy of which is attached as Exhibit "B".
PASSED and APPROVED this 21st day of February, 2012.
APPROVED: ATTEST:
By: By:
LIONELD JORDAN, Mayor SONDRA E. SMITH, City Clerk/Treasurer
City Of Fayetteville - Purchase Order (PO) Request
Requisition No.:
Date:
1/3012012
(Not Purchase Order)
All purchases under $2500 shall be used on a P -Card unless medical or 1099 service related. (Call x256 with questions)
P.O Number:
Expected Delivery Date:
All PO Request shall be scanned to the Purchasing e-mail:;Purchasing@ci.fayetteville.ar.us
7460
Vendor Name:
McClelland Engineers
Mail
Yes:_ XX No:
Address:
P.O. Box 1229
Fob Point:
Taxable
Yes: No:_XX_
Quotes Attached
Yes: No: XX
City:
Fayetteville
State:
AR
Zip Code:
72702
Ship to code:
Div' ' n Head Approval:
1
Requester:
Shannon Jones
Requester's Employee #:
2689
Exte ion:
452
Item
Description
Quantity
Unit of Issue
Unit Cost
Extended Cost
Account Numbers
Project/Subproject #
Inventory #
Fixed Asset #
1
2
3
4
5
6
7
8
9
10
Professional Services (AHTD)
1
$41,110.00
5400.5600.5314.00
8072.1102
The above line is a grant
Preofessional Services
1
$27,405.00
5400.5640.5314.00
8072.1102
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
Shipping/Handling
Lot
$0.00
Special Instructions:
Subtotal: $68,515.00
Tax:
Total: $68,515.00
Approvals:
Mayor: Department Director:
L
J Purchasing Manager:
r
Finance & Internal Services Director: Budget Manager: IT Manager:
Dispatch Manager: Utilities Manager: Other:
Revised 1/2/2008