HomeMy WebLinkAbout100-12 RESOLUTIONRESOLUTION NO. 100-12
•
A RESOLUTION APPROVING A COST -SHARE AGREEMENT WITH THE
ARKANSAS STATE HIGHWAY AND TRANSPORTATION COMMISSION
FOR THE CONSTRUCTION OF WATER AND SEWER RELOCATIONS
RELATED TO THE WIDENING OF CROSSOVER ROAD (HIGHWAY 265)
FROM JOYCE BOULEVARD TO ALBRIGHT ROAD
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS
Section 1. That the City Council of the City of Fayetteville, Arkansas hereby approves a
cost -share agreement, a copy of which is attached to this Resolution as Exhibit "A", with the
Arkansas State Highway and Transportation Commission for the construction of water and sewer
relocations related to the widemng of Crossover Road (Highway 265) from Joyce Boulevard to
Albright Road.
PASSED and APPROVED this 15th day of May, 2012.
APPROVED:
By:
A.I.L.,;a_ _se _AP
rIO ELD JOjPii'; Mayor
ATTEST:
By:
SONDRA E. SMITH, City Cleric/Treasurer
... ,,,,
�‘rWFVTRE9S''�
°G •GY OF'•L%
z•/..._ • • •QI•P
c .tAYETTEVILLE'
9s'97,KANSP\Y'
y
iiiiiiiiiiiiii,i
• City of Fayetteville Staff Review Form •
City Council Agenda Items
and
Contracts, Leases or Agreements
5/15/2012
David Jurgens
Submitted By
City Council Meeting Date
Agenda Items Only
Utilities
Division
Action Required:
Utilities
Department
Resolution approving an agreement with the Arkansas Highway and Transportation Department for the construction o
water and sewer relocations relating to the widening of Crossover Road (Highway 265) between Joyce Boulevard and
Albright Road,
Cost of this request
Account Number
08072.1102
Project Number
Budgeted Item
Category / Project Budget
Funds Used to Date
l
Remaining Balance
Budget Adjustment Attached
Hwy 265 W -S Relocations
Program Category / Project Name
Water/Sewer Improvements
Program / Project Category Name
Water and Sewer
Fund Name
Depa
!nt Dirtctor
Ci y At
•
ney
2 WI/
Date
Date
110):1-1Al2..
Finance and Internal Services Director Date
Date
Previous Ordinance or Resolution #
Original Contract Date:
Original Contract Number:
91-11
6/7/211
Received inCity04-77-171'03:06 RCVD
Clerk's Office
Comments:
Revised January 15, 2009
Sterile •
ay COUNCIL AGENDA MEMO
MEETING DATE OF MAY 15, 2012
THE CITY OF FAYETTEVILLE, ARKANSAS
ARKANSAS
www.accessfayetteville.org
To:
Thru:
From:
Fayetteville City Council
Mayor Lioneld Jordan
Don Marr, Chief of Staff
David Jurgens, Utilities Director
Water/Sewer Committee
Date: April 27, 2012
Subject: Crossover Road- Northern Section- Water and Sewer Relocation AHTD-Utility Agreement for
Construction
RECOMMENDATION
City Administration recommends approval of an agreement with the Arkansas Highway and Transportation
Department for the construction of water and sewer relocations relating to the widening of Crossover Road
(Highway 265) between Joyce Boulevard and Albright Road.
BACKGROUND
The project involves relocating water and sewer lines as required in preparation for the Arkansas Highway and
Transportation Department (AHTD) widening of Crossover Road (Hwy 265) between Joyce and the northern
City limits. The contract design and construction phase services has been awarded to McClelland Consulting
Engineers as a change order to their design on the Mission — Joyce section of the work.
DISCUSSION
This agreement obligates the AHTD to pay an estimated 62.67% of the total project construction cost with
utility betterment, or an estimated $937,480.38, and the City to pay the remaining 37.33%, estimated at
$558,419.38. AHTD also agrees to pay 84.46% of replacement in-kind costs relating to easement procurement
and bidding phase services, estimated at $204,280.02, and the City to pay the remaining 15.54%, estimated at
$37,585.98. In general, the AHTD pays for relocating lines currently existing outside the existing ROW, and
the City pays for lines that are currently inside the ROW and any increases in capacity. The final cost will be
based on the actual bids. In this arrangement, the City designs, awards, and supervises construction of the
utility relocation project, and will submit monthly requests for reimbursement from the AHTD.
BUDGET IMPACT
The City's portion will be funded from Water and Sewer revenue bonds and other Water/Sewer funds; the
remainder will be paid by the AHTD.
AHTD Hwy 265 North W -S Constmction Agmt CCMemo ApriI20I2.doc
• •
RESOLUTION NO.
A RESOLUTION APPROVING A COST -SHARE AGREEMENT WITH THE
ARKANSAS STATE HIGHWAY AND TRANSPORTATION COMMISSION
FOR THE CONSTRUCTION OF WATER AND SEWER RELOCATIONS
RELATED TO THE WIDENING OF CROSSOVER ROAD (HIGHWAY 265)
FROM JOYCE BOULEVARD TO ALBRIGHT ROAD
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1. That the City Council of the City of Fayetteville, Arkansas hereby approves a
cost -share agreement, a copy of which is attached to this Resolution as Exhibit "A", with the
Arkansas State Highway and Transportation Commission for the construction of water and sewer
relocations related to the widening of Crossover Road (Highway 265) from Joyce Boulevard to
Albright Road.
PASSED and APPROVED this 15`h day of May, 2012.
APPROVED: ATTEST:
By: By:
LIONELD JORDAN, Mayor SONDRA E. SMITH, City Clerk/Treasurer
Rev. 01-05-2012
•
• 100-12
ARKANSAS STATE HIGHWAY COMMISSION
HIGHWAY - UTILITY CONSTRUCTION/RELOCATION AGREEMENT
State Job No. 040518 (Utilities) County Washington
Federal Aid Project STP -9142(27)
AC X
LS
Route 265 Section 2
Job Location E. Joyce Blvd. -City Limits Utility Owner City of Fayetteville
(Fayetteville)(S) Water and Sewer
THIS AGREEMENT, made and entered into this 3/ day of MA y , 20/2- by and between the
Arkansas State Highway Commission, acting by and through the duly authorized representatives of the Arkansas State
Highway and Transportation Department, with headquarters at Little Rock, Arkansas, hereinafter referred to as the
"Department," and the City of Fayetteville Water and Sewer of Fayetteville, Arkansas acting by and through its duly
authorized representatives, hereinafter referred to as the "Owner" WITNESSETH:
The Department proposes to make highway improvements as specified under the above referenced job
number and, the Owner will adjust or relocate its existing facilities as set out in the attached plans and cost estimate.
The Department will participate in the cost of said adjustment/relocation to the extent that eligibility is
hereinafter established.
Payment will be made on a actual cost basis as mutually agreed between Owner and Department.
This agreement is governed by all applicable State and Federal laws, rules, and regulations including the
Arkansas State Highway Commission Utility Accommodation Policy adopted by Commission Minute Order 2010-
146 as amended and supplemented, the Federal Aid Program Guide on Utility Adjustments and Accommodation on
Federal Aid Highway Projects as amended and supplemented, and the provisions of 23 CFR § 645 as amended and
supplemented.
DESCRIPTION OF WORK: See attached Exhibit A
The Department agrees that the required adjustment is See Exhibit A eligible for reimbursement for the
actual cost which is estimated to be $1,737,765.76 of which $1,141,760.40 to be paid by the Department and
$596,005.36 is to be borne by Owner.
Owner will not commence work until authorized by the Department, and will then endeavor to begin within
165 calendar days and complete within 180 calendar days thereafter.
On completion of said work, Owner is responsible for the cleanup and restoration of the work area
including the disposal of surplus materials and debris.
Final billing must include all supporting detail. Owner shall also submit one (1) set of as -built drawings at
this time.
Payment will be 100% of lump sum bills and actual cost bills, at the discretion of the Department a 10%
retainage can be withheld and released upon completion of an audit review. All final bills for utility relocation are
subject to review and audit by state and/or federal auditors.
•
Rev. 01-05-2012
• •
Expenses incurred under an actual cost agreement may be billed to the Department monthly in increments
of $5,000.00 or more.
Owner must maintain cost records and accounts to support the agreed adjustment/relocation work. Said
records to be retained and available for inspection for a period of three (3) years from date of final payment.
Owner shall be responsible for any and all hazards to persons, property, and traffic.
With respect to traffic control, Owner shall adhere to the requirements of the Manual of Uniform Traffic
Control Devices, as amended and supplemented.
Owner shall be responsible for and shall hold harmless the Arkansas State Highway Commission, the
Department and their officers and employees from any and all claims, actions, causes of action, suits, damages,
losses or liability whatsoever, arising out of Owner's performance of the work subject to this Agreement.
Notwithstanding anything hereinbefore written, neither the Owner nor the Department by execution of this
Agreement waives or relinquishes any rights which either may legally have within the limits of the Law or
Constitution, either State or Federal.
City of Fayetteville
Water and Sewer
ARKANSAS STATE HIGHWAY COMMISSION
Acting By and Through The
ARKANSAS STATE HIGHWAY AND
TRANSPORTATION DEPARTMENT
Lionel& 3ordan NLC �
Name (Typed or Printed) (For) Dir for of Highways & Transportation
Pnoav-
Tide
1
ture
11- (001V -H02_
FEDERAL TAXPAYER DENTIFICATION#
8oYL& & E . Sru
Name (Typed or Printed)
T tle
Signature
�.��coRKi I R Iff fir S.„
.U• ••�:
;FAYETTEVILLEt•
••
;761 . KANSP�J��
.....N�
GTON q)‘`‘.
Right of ay Division
1�
Head
t—C2Dof21"
Section Head Uf lities Section
Right of Way Division
draffir
• •
Job 040518 (Utilities)
City of Fayetteville Water and Sewer
EXHIBIT A
Adjust water facilities to clear highway construction by abandoning approximately 3,130
feet of twelve (12) inch water main, 500 feet of eight (8) inch water main, 194 feet of six
(6) inch water main and 887 feet of one (1) inch water service line complete with
appurtenances. Adjust sewer facilities to clear highway construction by abandoning
approximately 1,536 feet of eight (8) inch sewer main, 280 feet of four (4) inch sewer
service line and 1,164 feet of six (6) inch sewer force main complete with appurtenances.
Restore water service by installing 3,126 feet of twelve (12) inch PVC water main, 538
feet of eight (8) inch PVC water main, 240 feet of six (6) inch DIP water main, 50 feet of
two (2) inch water service tubing and 475 feet of one (1) inch water service tubing
complete with appurtenances. Restore sewer service by installing 460 feet of ten (10)
inch DI sewer main, 1,084 feet of eight (8) inch PVC sewer main, 265 feet of four (4)
inch sewer service pipe and 1,174 feet of six (6) inch PVC force main complete with
appurtenances. Owner is not adequately staffed to perform this work; therefore, contract
forces will be utilized and selected by low bid process.
Owner will be upgrading facilities during construction in which a betterment has been
addressed. Owner has developed a replacement in-kind and betterment factor for
reimbursement in which the Department concurs. This factor is to be updated based on
low bids and final quantities installed.
Owner will be securing easements based on Owner's documented practice. During
easement acquisition, the Owner's practice is to offer up to 25% of the full fee simple
value of the property, along with damages applicable to each individual property before
consulting with legal council regarding condemnation.
Owner's estimated timeframe for completion is as follows:
Secure easements by
First advertisement for bids
Complete Construction
June 29, 2012
June 29, 2012
April 10, 2013
• •
The pro rata factor for reimbursement will be determined as follows:
Replacement in-kind factor:
Est. reimb. replacement in-kind construction cost $ 894,567.00 = 84.46%
Total est. replacement in-kind construction cost $1,059,150.00
Reimbursement factor for betterment:
Est. reimb. replacement in-kind project cost
Total est. project cost with betterment
Cost Summary
Construction Cost
Construction Engineering Cost
Reimbursement Factor for betterment 62.67%
$ 894,567.00 = 62.67%
$1,427,385.00
$ 1,427,385.00
$ 68,514.76
$ 1,495,899.76
Health Department Review $ 500.00
Advertisement $ 1,000.00
Storm Water Prevention Plan $ 3,056.00
Easement Filing $ 625.00
Easement Mapping and Preparation $ 46,685.00
Easement Cost $ 175,000.00
Easement Procurement Cost $ 15,000.00
Reimbursement Factor for in-kind 84.46% $ 241,866.00
$ 937,480.38
$ 204,280.02
Total Cost $ 1,737,765.76
Total Reimbursable Cost $ 1,141,760.40