HomeMy WebLinkAbout222-11 RESOLUTIONRESOLUTION NO. 222-11
A RESOLUTION TO APPROVE A CHANGE ORDER WITH PICK -IT
CONSTRUCTION, INC. IN THE AMOUNT OF $19,710.00 AND TO
APPROVE A BUDGET ADJUSTMENT TO RECOGNIZE A DONATION
FROM THE FAYETTEVILLE YOUTH BASEBALL LEAGUE UP TO
$33,600.00 TO COMPLETE THIS PROJECT
WHEREAS, the City of Fayetteville did not have sufficient funds budgeted to complete
the entire improvement project for the Walker Park ball fields; and
WHEREAS, the Fayetteville Youth Baseball League has offered to donate up to
$33,600.00 to complete this project which enables the City to approve change orders to add back
parts of the project which had to be removed for lack of funding.
NOW, THEREFORE BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves a
change order to the existing contract with Pick -It Construction, Inc. so that all of the Walker Park
dugout and fan bleacher improvements can now be constructed.
Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a
budget adjustment for up to $33,600.00 in donation revenue as needed to complete this whole
Walker Park project, with the proviso that the City will expend all of its budgeted revenue
(including contingency) first and use only that portion of the $33,600.00 donation as needed to
complete the project and will return to Fayetteville Youth Baseball League any money not
necessary to completely pay for this project.
PASSED and APPROVED this 20th day of December, 2011.
APPROVED: ATTEST:
L 1 NELD AN, Mayor
By: 44idig) £'ii
SONDRA E. SMITH, City Clerk/Treasurer
`,`,����er nrrrr®r�
a���•� gi R�S..�'.
``.�:�G °OA. Y (:),c. °° G�,„
;�. ®�.
r. U . . r
.
FAYETf E V I LLE :
:i....., ®�®
1:.17 ea
ii) s° PkANS. J�edi
li4ietasaa000►``
Bron Humphry
Submitted By
City of Fayetteville Staff Review Form
City Council Agenda Items
and
Contracts, Leases or Agreements
12/20/2011
City Council Meeting Date
Agenda Items Only
Park Maintenance
Division
Action.Required;
`A resolution approving'a change order with Pick -it Construction, Inc:\to re -instate deductive alternates #2 and #3 in
the amount of $19,710 and approval of a Budget Adjustment to recognize a $33,600 donation from Fayetteville Youth
Baseball League and reimburse the Parks Development fund. Any portions of the donated funds that are not needed
to complete the project will be returned to Fayetteville Youth Baseball.
Parks and Recreation
Department
19.71.0..00
Cost of this request
2250.9255.,5315.00
Account Number
11024.1101 '
Project Number
Budgeted Item
116,419.00
Category / Project Budget
4,066.00
Contract Servs/Walker Park Baseball
Program Category / Project Name
Parks Development / Contract Srvs
Funds Used to Date Program / Project Category Name
112,353.00
Parks Development Capital
Remaining Balance Fund Name
Budget Adjustment Attached
Previous Ordinance or Resolution # 132-11
Original Contract Date: 12/6/2011.
Zj ( Original Contract Number:
City Attorney
Finance and Internal Services Director
-5-,4
Date
Received in City 2-0 2-1 i P03:04 R C V D
Clerk's Office
1,61,7
Received in
Mayor's Office
Comments:
Revised January 15, 2009
ttevll1e
THE CITY OF FAYETTEVILLE, ARKANSAS
DEPARTMENT CORRESPONDENCE
ARKANSAS
www.accessfayetteville.org
CITY COUNCIL AGENDA MEMO
To: Mayor Lioneld Jordan and City Council
Thru:
From:
Don Marr, Chief of Staff
Connie Edmonston, Parks and Recreation Directo
Byron Humphry, Maintenance Superintendent
Date: December 2, 2011
ee?
Subject: Fayetteville Youth Baseball Donation and Change Order
PROPOSAL:
The Fayetteville Youth Baseball Board of Directors has requested improvements to the Baseball Complex at
Walker Park for many years. The Baseball Complex was built by volunteers starting in 1960. It is an old facility
that needs improvements to serve the baseball community until the Regional Park's Baseball Complex is built.
On August 2, 2011, the City Council passed Resolution Number 132-11 to approve a budget adjustment in the
amount of $100,000 to be used to fund Walker Park Baseball Improvements. The Parks Department worked
with Fayetteville Youth Baseball to develop plans for new dugouts and bleacher covers at Walker Park. After
the expense of developing the plans and advertising the bid, there is $95,934 left to be spent on the project. We
were uncertain if we could accomplish all of the work within our budgeted amount, therefore three deductive
alternates were identified that could be removed from the bid to make the contract affordable. The project was
advertised for bid and two vendors including Pick -It Construction, Inc. and Heckathorn Construction Company,
Inc. submitted bids. Pick -It Construction, Inc. presented the low bid in the amount of $143,904. Deducting all
of the deductive alternates and negotiating with Pick -it Construction, Inc. to change the scope of work on
materials required, we were able to reduce the contract price to $102,139. The Parks Department submitted a
contract for approval to the City Council along with a Budget Adjustment from Park Development Funds to
make up the difference in the amount that was budgeted. We are anticipating that on December 6, City Council
will approve Bid #11-67 with Pick -it Construction, Inc. in the amount of $102,139 with a 10% contingency of
$10,214 for a total project cost of $112,353.
Upon considering the contract price in relation to what the City originally budgeted and realizing that some
needed improvements had to be deducted from the contract due to cost considerations, the Fayetteville Youth
Baseball Board of Directors met and approved a donation to the City of Fayetteville up to $33,600. This
donation is to be used as needed to reinstate deductive alternates #2 (bleacher cover on Field 6 - $6,570) and
deductive alternate #3 (bleacher covers on Field 3 - $13,140) which total $19,710. The remaining $13,890 will
be used to offset the initial contract price exceeding the $95,934 that the City had budgeted for the project. The
THE CITY OF FAYETTEVILLE, ARKANSAS
donation is made with the understanding that any donated funds not needed to complete the project be returned
to Fayetteville Youth Baseball.
RECOMMENDATION:
A resolution approving a change order with Pick -it Construction, Inc. to re -instate deductive alternates #2 and
#3 in the amount of $19,710 and approval of a Budget Adjustment to recognize a $33,600 donation from
Fayetteville Youth Baseball League and reimburse the Parks Development fund. Any portions of the donated
funds that are not needed to complete the project will be returned to Fayetteville Youth Baseball.
BUDGET IMPACT:
This project is funded with Park Development Funds, including Parkland Dedication/Impact Fees, and donated
funds. The initial project cost was $102,139 with a 10% project contingency of $10,214. The addition of
change order #2 ($19,710) brings the project cost to an estimated $121,849. A budget adjustment of $15,230 to
reimburse the Parks Development fund will require $1,340 of the $10,214 contingency. The available funds for
the project will be $130,723 which includes a remaining contingency of $8,874.
Project Budget
12/6/11 Approved budget with 10% contingency $112,353
Donation from Fayetteville Youth Baseball $33,600
Budget Adjustment to Reimburse Parks Development Fund ($15,230)
Available Budget
$130,723
Contract
12/6/11 Approved Contract with Pick -it Construction, Inc.
Requested Change Order
New Contract Price with Change Order
$102,139
$19,710
$121,849
Contingency
Total Available Project Budget
New Contract Price with Change Order
Remaining Contingency
$130,723
($121,849)
$8,874
Attachments:
Budget Adjustment
Pick -It Construction Change Order No. 2 Cost Estimate
Change Order No. 2
Commitment letter with Fayetteville Youth Baseball
RESOLUTION NO.
A RESOLUTION TO APPROVE A CHANGE ORDER WITH PICK -IT
CONSTRUCTION, INC. IN THE AMOUNT OF $19,710.00 AND TO
APPROVE A BUDGET ADJUSTMENT TO RECOGNIZE A DONATION
FROM THE FAYETTEVILLE YOUTH BASEBALL LEAGUE UP TO
$33,600.00 TO COMPLETE THIS PROJECT
WHEREAS, the City of Fayetteville did not have sufficient funds budgeted to complete
the entire improvement project for the Walker Park ball fields; and
WHEREAS, the Fayetteville Youth Baseball League has offered to donate up to
$33,600.00 to complete this project which enables the City to approve change orders to add back
parts of the project which had to be removed for lack of funding.
NOW, THEREFORE BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves a
change order to the existing contract with Pick -It Construction, Inc. so that all of the Walker Park
dugout and fan bleacher improvements can now be constructed.
Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a
budget adjustment for up to $33,600.00 in donation revenue as needed to complete this whole
Walker Park project, with the proviso that the City will expend all of its budgeted revenue
(including contingency) first and use only that portion of the $33,600.00 donation as needed to
complete the project and will return to Fayetteville Youth Baseball League any money not
necessary to completely pay for this project.
PASSED and APPROVED this 20th day of December, 2011.
APPROVED: ATTEST:
By: By:
LIONELD JORDAN, Mayor SONDRA E. SMITH, City Clerk/Treasurer
a'F�ite eville
THE CITY OF FAYETTEVILLE, ARKANSAS
•:_.: PARKS AND RECREATION DEPARTMENT
113 West Mountain
Fayetteville, AR 72701
P (479) 4443471 F (479) 521-7714
ARKANSAS
www.accessfayetteville.org
CHANGE ORDER NO. 2 Cost Plus X Pre -Agreed Unit Price X
Project Name and Number: Bid 11-67, Construction of Walker Park Dugouts and Bleacher Covers
Name of Contractor: Pick -It Construction, Inc.
Address of Contractor: 10024 N. Campbell Rd., Fayetteville, AR 72701
Date of Contract: December 6, 2011
Original Contract Sum: $ 143,904.00
Total Amount of Deductive Alternates (#1, #2 and #3): $ -32,850.00
Total Amount of All Previous Approved Change Orders: $ -8,915.00
Contract Sum prior to this Change Order: $ 102,139.00
Contract Sum Increase this Change Order: $ 19,710.00
New Contract Sum including this Change Order: $ 121,849.00
Subject and Reason for this Change Order: Staff is requesting several changes to the existing specifications that will
reduce overall construction costs while maintaining a quality, low maintenance product. Requested changes include:
1) Replacement of the redwood fascia boards with treated boards; 2) Deletion of requirement to paint treated boards;
and 3) Deletion of plywood soffit.
Additional Time Requested: 0 Calendar Days
Dated this 6th day of December, 2011
CITY OF FAYETTEVILLE
Parks & Recreation Department Contractor
By:
Pick -It Constru tion Inc.
yron um
Park Maintenance S
CITY OF FA TTEVIL
p
tendent
011M111/110,
•`o\' �YJTRF4So
;`�V••G0�CY O1c •G.pc
•-A
FAYETTEVILLE
iG•%9JO
•�a
NrQ dew
Title:
ATTEST:
Telecommunications Device for the Deaf TDD (479) 521-1316
113 West Mountain - Fayetteville, AR 72701
:ITEM#, "''t
,DESCRIPTION;.. , s.
..."„ UNIT ,•,° .,®;EST.OTY.
`EST. UNIT,PRICE..,•?ESTIMATE.
'`
1
Reinstate Deductive Alternate #2 - 1 Bleacher Cover on Field 6
L.S.
1
$ 6,570.00
$ 6,570.00
2
Reinstate Deductive Alternate #3 - 2 Bleacher Covers on Field 3
L.S.
1
- $ 13,140.00
$ 13,140.00 ,
Respectfully submitted,
Finn Name: Pi -It Construction, Inc.
Air• r.
By:
Date: A:17///
TOTAL
$ 19,710.00
City of Fayetteville, Arkansas
Budget Adjustment Form
V11.0425
Budget Year
2011
Division: Parks & Recreation
Department: Parks & Recreation
Request Date
12/2/2011
Adjustment Number
BUDGET ADJUSTMENT DESCRIPTION / JUSTIFICATION
A budget adjustment in the amount of $33,600 to add funding in the Walker Park Baseball Project and to recognize
donation from Fayetteville Youth Baseball Association to assist with the Walker Park Baseball Project.
Byron Humphry 12/2/2011
Division Head Date
%2 -
dget Director
Connie Edmonsto
Department Directo Date
Date
12/2/2011
Fin.nce Director Date
12- 12.-2 if
/2-/3-/
hie ftaff
yor
Date
D. -e
Prepared By: Tracie Martin
Reference:
kspringer
Budget & Research Use Only
Type: A B C D E P
General Ledger Date
Posted to General Ledger
Checked / Verified
Initial Date
Initial Date
TOTAL BUDGET ADJUSTMENT 33,600 33,600
Increase / (Decrease) Project.Sub
Account Name Account Number Expense Revenue Number
Contract services 2250.9255.5315.00 33,600 11024 . 1101
Donations 2250.0925.4809.00 33,600 11024 . 1101
Park improvements 2250.9255.5806.00 15,230
Contract services 2250.9255.5315.00 (15,230)
02002. 1
11024 . 1101
C:\DOCUME-1\KSPRIN-1\LOCALS-1\Temp\XPgrpwise\BA BA 12.2.11 Donations_V2.xls 1 of 4
City of Fayetteville, Arkansas
Budget Adjustment Form
V11.0425
Budget Year
2011
Division: Parks & Recreation
Department: Parks & Recreation
Request Date
12/2/2011
Adjustment Number
BUDGET ADJUSTMENT DESCRIPTION / JUSTIFICATION
A budget adjustment in the amount of $33,600 to add funding in the Walker Park Baseball Project and recognize
donation from Fayetteville Youth Baseball Association to assist with the Walker Park Baseball Proje
Byron Humphry (44— 12/2/2011
Division Head
Date
Budget D. ector
Connie Edmonston
Gate
/i !/l/ 12/2/2011
Department Directdr9 Date
Tad
Fi . nce Director
Staff
Date
yor
D
Prepared By: Tr. ie Martin
Reference:
tmartin
udget & Research Use Only
Type: A B C D E P
eral Ledger Date
Posted to General Ledger
Checked / Verified
Initial Date
Initial Date
Account Name
TOTAL B 4 DGET ADJUST ENT 33,600 33,600
Increase / (Decrease) Project.Sub
Account Number Expense Revenue Number
Contract services 2250.9255.5315.00 33,600 11024. 1101
Donations 2250.0925.4809.00 33,600 11024. 1101
Park improvements 2250.9255.5806.00 15,230 02001. 1
Contract services 2250.9255.5315.00 15,230) 11024 . 1101
C:\DOCUME-1\tmartin\LOCALS-1\Temp\XPgrpwise\BA BA 12.2.11 Donations_V2 1 of 1
FAYETTEVILLE YOUTH BASEBALL
To Fayetteville City Council,
Fayetteville Youth Baseball League, Board of Directors would like to make a donation to
the City of Fayetteville in the amount of $33,600 to be used for improvements at Walker
Park Baseball complex. We would like the donation to be used to add bleacher covers to
fields 3 and 6 and to offset the cost of the contract that exceeded what the City had
budgeted. We ask that any donated funds that are not needed to complete the contract be
returned to us.
Fayetteville Youth Baseball League
w rt n
a.
John Long — Executive Vice President/Treasurer
RESOLUTION NO.
A RESOLUTION TO APPROVE A CHANGE ORDER WITH PICK -IT
CONSTRUCTION, INC. IN THE AMOUNT OF $19,710.00 • ND TO
APPROVE A BUDGET ADJUSTMENT TO RECOGNIZE A PiNATION
FROM THE FAYETTEVILLE YOUTH BASEBALL LE • G E UP TO
$33,600.00 TO COMPLETE THIS PROJECT
WHEREAS, the City of Fayetteville did not have sufficieA t funds budgeted to complete
the entir- improvement project for the Walker Park ball fields;
WHE' ' : S, the Fayetteville Youth Baseball Le.:ue has offered to donate up to
$33,600.00 to comp te this project which enables the City, o approve change orders to add back
parks of the project whh had to be removed for lack of ding.
NOW, TH r' FORE BE IT RESO VED BY THE CITY COUNCIL OF
THE CITY OF FAYETTEV,ILLE, ARKANSAS:
Section 1: That the City Oquncil of the C;° y of Fayetteville, Arkansas hereby approves a
change order to the existing contradwith Pick -I 'Construction, Inc. so that all of the Walker Park
dugout and fan bleacher improvements scan no . be constructed.
Section 2: That the City Council o be City of Fayetteville, Arkansas hereby approves a
budget adjustment for up to $33,600.00 donation revenue as needed to complete this whole
Walker Park project, with the proviso,` hat the city will expend all of its budgeted revenue
(including contingency) first and use ly that porti . of the $33,600.00 donation as needed to
complete the project and will retu to Fayetteville euth Baseball League any money not
necessary to completely pay for thi '•roject.
PASSED and APPRO 1) this 20th day of December, 2011
APPROVED:
By:
LIONELD JORDAN, Mayor
ATTEST:
By:
SONDRA E. SMITH, City Clerk/Treasurer