HomeMy WebLinkAbout189-10 RESOLUTIONRESOLUTION NO. 189-10
A RESOLUTION APPROVING A CHANGE ORDER TO A CONTRACT
WITH JOE PERME CONSTRUCTION, INC. FOR IMPROVEMENTS TO A
PUBLIC FACILITY BUILDING IN THE AMOUNT OF $3,300.00 AS PART
OF THE COMMUNITY DEVELOPMENT BLOCK GRANT SUBRECIPIENT
PROGRAM
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1. That the City Council of the City of Fayetteville, Arkansas hereby approves a
change order, a copy of which is attached as Exhibit "A," to a contract with Joe Perme
Construction, Inc. for improvements to a public facility building in the amount of $3,300.00 as
part of the Community Development Block Grant Subrecipient Program.
PASSED and APPROVED this 2nd day of November, 2010.
APPROVED: ATTEST:
By:
. ,A,:t' ,_
SONDRA E. SMITH, City Clerk/Treasurer
Sliteville
v
ARKANSAS
COMMUNITY DEVELOPMENT BLOCK GRANT
CHANGE ORDER AUTHORIZATION
Property Location: 1932 S. Garland Fayetteville AR, 72701
Contractor: Joe Penne Construction Inc.
The following is a Change Order to the original Resolution No. 93-10 passed and approved on June 1st,
2010. This Change Order is made to modify or change the work under the above -captioned Resolution and
this Change Order is made part of the Resolution. This Change Order supersedes any previous drawings,
specifications and agreements. Work shall be completed no Iater than 14 days after approval of change
order. All work shall be performed in a workmanlike manner according to common construction practices,
according to the specifications set forth in the Community Services Program's General Specification
Manual, and with adherence to city, state and national codes.
CHANGES:
Original Contract Sum
Contractor Sum Paid -To -Date
Due on Original Contract
Amount of This Change Order
Total Due
$21,800.00
$6,840.00
$14,960.00
$3,300.00
$25,100.00
zv(V
Date
C9 /.s — 2-ai CJ
Date
to
)1- -i0
113 W MOUNTAIN ST 1 FAYETTEVILLE AR 72701 1 PHONE 479.575.82601 FAX 479.444.3445
Form CD 135
EXHIBIT
� A
Yolanda Fields
Submitted By
City of Fayetteville Staff Review Form
City Council Agenda Items
and
Contracts, Leases or Agreements
11/2/2010
City Council Meeting Date
Agenda Items Only
Community Services
Division
Action Required:
Deveiopment Services
Department
Approval of change order for Public Facility Building as part of the Community Development Block Grant subrecipient
program
3,300.00
Cost of this request
2180.4990.5390.27
Account Number
Project Number
Budgeted Item
21,800.00
Category1 Project Budget
6,840.00
$
Program Category / Project Name
Funds Used to Date Program 1 Project Category Name
14,960.00 Community Development
Remaining Balance Fund Name
Budget Adjustment Attached �1
y... AAI• Air4
"
Depa
Attorney
Finance and Internal Services Director
Chief of Staff
ayor
- Up. VIk6 Previous Ordinance or Resolution #
Date
Original Contract Date:
(a—(s --gyp Original Contract Number:
Date
16-1e.zO 16
Date
Ip r$ -w
Date
/0 D
Date
Received in City 10-14-10A09:05 R C V D
Clerk's Office
Comments: Staff recommends approval of change order
Revised January 15, 2009
ave evi le
THE CITY OF FAYETTEVILLE, ARKANSAS
DEPARTMENT CORRESPONDENCE
+1 ARKANSAS
www.accessfayetteville.org
CITY COUNCIL AGENDA MEMO
To: Mayor and City Council
Thru: Jeremy Pate, Development Services Department Director
From: Yolanda Fields, Community Services Di
Date: October 13, 2010
Subject: CDBG Public Facility Program- Approval of Change Order at 1932 S. Garland
PROPOSAL:
A contract with Joe Penne Construction for the moderate rehabilitation of 1932 S. Garland was approved on
June I, 2010, in resolution #93-10. Once work on the project began, it was determined that a change order
would be needed in order to complete the rehabilitation of the property due to the discovery of some unexpected
problems.
1) The scope of work stated that the kitchen cabinets were to be removed with only a portion of them replaced.
Once the cabinets were removed, it was discovered that the materials used on the wall behind the cabinet area
was different than the walls in the rest of the kitchen area. To make the kitchen area uniform in appearance the
wall behind the cabinet area needs to be removed and replaced with drywall. Some areas of drywall also need to
be patched and skim coated.
2) The scope of work stated that the entry deck would be replaced. Once the entry deck was removed, it was
discovered that the sill plate was rotten and not able to be used for the replacement of the deck. If left
uncorrected the flooring will begin to sag under the door and cause structural problems in the area. To repair the
problem, some siding must be removed and jacks installed to support the weight of the structure while a section
of the sill and bottom plate are replaced and leveled. Jacks will need to be removed and siding returned to its
original condition.
RECOMMENDATION:
Staff recommends approval of change order for Public Facility Project located 1932 S. Garland
BUDGET IMPACT:
Change Order Cost is approximately $3,300
RESOLUTION NO.
A RESOLUTION APPROVING A CHANGE ORDER TO A CONTRACT
WITH JOE PERME CONSTRUCTION, INC. FOR IMPROVEMENTS TO A
PUBLIC FACILITY BUILDING IN THE AMOUNT OF $3,300.00 AS PART
OF THE COMMUNITY DEVELOPMENT BLOCK GRANT SUBRECIPIENT
PROGRAM
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1. That the City Council of the City of Fayetteville, Arkansas hereby approves a
change order, a copy of which is attached as Exhibit "A," to a contract with Joe Perme
Construction, Inc. for improvements to a public facility building in the amount of $3,300.00 as
part of the Community Development Block Grant Subrecipient Program.
PASSED and APPROVED this 2"d day of November, 2010.
APPROVED: ATTEST:
By: By:
LIONELD JORDAN, Mayor SONDRA E. SMITH, City Clerk/Treasurer
Seville
THE CITY OF FAYETTEVILLE, ARKANSAS
DEPARTMENT CORRESPONDENCE
.......,:: ARKANSAS
www.accessfayetteville o g
CITY COUNCIL AGENDA MEMO
To: Mayor and City Council
4-2
Thru: Jeremy Pate, Development Services Department Director -5)
From: Yolanda Fields, Community Services D
Date: October 13, 2010
Subject: CDBG Public Facility Program- Approval of Change Order at 1932 S. Garland
PROPOSAL:
A contract with Joe Perme Construction Inc. for the moderate rehabilitation of 1932 S. Garland was approved
on June 1, 2010, in resolution #93-10. Once work on the project began, it was determined that a change order
would be needed in order to complete the rehabilitation of the property due to the discovery of some unexpected
problems.
1) The scope of work stated that the kitchen cabinets were to be removed with only a portion of them replaced.
Once the cabinets were removed, it was discovered that the materials used on the wall behind the cabinet area
was different than the walls in the rest of the kitchen area. To make the kitchen area uniform in appearance the
wall behind the cabinet area needs to be removed and replaced with drywall. Some areas of drywall also need to
be patched and skim coated.
2) The scope of work stated that the entry deck would be replaced. Once the entry deck was removed, it was
discovered that the sill plate was rotten and not able to be used for the replacement of the deck. If left
uncorrected the flooring will begin to sag under the door and cause structural problems in the area. To repair the
problem, some siding must be removed and jacks installed to support the weight of the structure while a section
of the sill and bottom plate are replaced and leveled. Jacks will need to be removed and siding returned to its
original condition.
RECOMMENDATION:
Staff recommends approval of change order for Public Facility Project located 1932 S. Garland
BUDGET IMPACT:
Change Order Cost is approximately $3,300
Joe Penne Construction Inc.
1874 S. Doral
Fayetteville, Ar 72701-7794
Name / Address
City of Fayetteville
1932 Garland
Estimate
Date
Estimate #
10/6/2010
120
Project
Description
Rate
Amount
Markup
Total
Change order 61 1932 S. Garland: Install temporary
beam, jack up and support necessary floor joist. Remove
necessary siding. Remove approximately 5' of rotted sill
and bottom plate behind deck. Install new treated sill and
bottom plate. Level and support new sill and bottom plate.
Remove jacks and temporary bean. Reinstall siding.
0.00
0.00
1,500.00
1,500.00
ITotal
$1,500.00
Phone #
Fax #
E-mail
479-659-3416
479-439-0811
joe@joeperineconstruction.com
Joe Penne Construction Inc.
1874 S. Doral
Fayetteville, Ar 72701-7794
Name / Address
City of Fayetteville
1932 Garland
Estimate
Date
Estimate #
10/4/2010
117
Project
Description
Change Order 92 1932 S. Garland: Remove frp board,
patch drywall and skim coat to make walls smooth and
uniform in kitchen.
Rate
Amount
Markup
Total
0.00
0.00
1,800.00
1,800.00
ITotal
Phone #
I Fax #
E-mail
479-659-3416 1
jI
479-439.0811 I
joe@joepermeconstruction.com
$1,800.00
Perme Construction Inc.
1874 S. Doral
Fayetteville, Ar 72701-7794
Name / Address
City of Fayetteville
1932 Garland
Estimate
Date
Estimate k
10/6/2010
120
Project
Description
Rate
Amount
Markup
Total
Install temporary beam, jack up and support necessary
floor joist. Remove necessary siding. Remove
approximately 5' of rotted sill and bottom plate behind
deck. Install new treated sill and bottom plate. Level and
support new sill and bottom plate. Remove jacks and
temporary beam. Reinstall siding.
0.00
0.00
1,500.00
1,500.00
Total $1.500.00
Phone 9
Fax 9
E-mail
479-659-3416
479-439-0811
joepermeconstruction@cox.net
Perme Construction Inc.
1874 S. Doral
Fayetteville, Ar 72701-7794
Name / Address
City of Fayetteville
1932 Garland
Estimate
Date
Estimate 4
10/4/2010
117
Project
Description
Rate
Amount
Markup
Total
Remove frp board, patch drywall and skim coat to make
walls smooth and uniform in kitchen.
0.00
0.00
1,800.00
1,800.00
Total $1,800.00
Phone 0
Fax 4
E-mail
479-659-3416
479-439-0811
joepermeconstruction @cox.net
Highland Home Builder, Inc.
Bruce Ken 479-903-0966
Community Services Spec writer
bruceekerr netzero.com
Community Services Division
Energy Efficiency Rehabilitation Project
Scope of Project: Replace all flooring, replace some interior doors. Drywall, paint, and trim
specified areas. Demo old cabinets. Replace kitchen cabinets, sinks, and counter tops. Replace
bathroom vanities, minors, and toilets. Replace light fixtures and add GFCI outlets. Add new
entry decks.
Owner's Name: City of Fayetteville (Office Building, formerly a women's shelter)
Project Location: 1932 S Garland, Fayetteville, AR
Project # 09029-1002
Administrator: Brent Johnson Phone: 479-575-8240 Fax: 479-444-3445
Contractors Description of Work:
Minimum requirements for bidder: Proof of current Arkansas Residential Contractor's license (or
Commercial Contractor's license if required by law) which is provided by the State of Arkansas
Contractors Licensing Board, Certificate of Liability Insurance, and a statement of Completion of
EPA/HUD Approved Lead Safety Training if applicable.
GENERAL:
The contractor will be responsible for all aspects of the construction, installation, repairs, and
cleanup as stated in the Scope of Work and Specifics at the project location stated above.
Each bidder will be responsible for a complete inspection of the property at the project location
before submitting bid. All the distances, measurements, procedures, and listed materials should
be verified before submitting your bid to complete the work. The requirements listed here, in the
description of work, are general requirements and it will be the responsibility of the winning
bidder to assure the City of Fayetteville that the finished project is in compliance with all
applicable codes and standards and achieves the goal of raising the efficiency of the building.
The contractor's duties and responsibilities include, but are not limited to, the following:
1) Purchasing of all materials.
2) Supervision of all employees and subcontractors.
3) Coordination with the City of Fayetteville CDBG Administrator, the City of Fayetteville
Code Compliance Office and owners.
4) Project design.
5) Clean up and restoration of all lawns, planters, walking and driving surfaces to their original
condition.
6) Keep job site safe for others and practice safe working practices as required.
SPECIFICS:
A: ELECTRICAL
A - 1 Replace all interior light fixtures with white surface mount fixtures, except for fan in
office 4. Lights in offices and living rooms should be 3 bulb fixtures. Replace light
fixtures in bathrooms. All bulbs should be energy efficient compact florescent light bulbs
(CLS's). Some lights may need different solutions to optimize lighting plan.
A - 2 Add ground fault plugs in kitchen by the sink Per. code 210.50 B.3, 2008 National
Electric Code
A - 3 Add any missing covers on switches or plugs.
A - 4 Remove kitchen stove plug and vent hood and cap off electricity for addition of cabinets.
B: INTERIOR DOORS
B - 1 Remove and replace the doors entering the following numbered offices.
1,9,10,11,12,13,14,16,17.
B - 2 Remove and replace the doors entering the following numbered bathrooms. 2,3,4
B - 3 Replace or add closet doors in the following numbered offices. 9,10,11,13,17.
B - 4 Remove and replace the two full size closet doors in hallway number 19. Do not replace
the half doors.
B - 5 Reinstall all old door knobs.
C : KITCHEN REMODEL AND STORAGE CABINETS
C - 1 Tear out all kitchen cabinets and storage cabinets or shelves in the following numbered
offices: 1,4,6,7.
C - 2 Tear out all ceiling soffits in kitchen.
C - 3 Add 10 feet of new base cabinets in kitchen in area where sink is now. Install new upper
cabinets over the base cabinets (when area is exluded because of the window the uppers
are about a total of 6 ft. (there will be no stove area)
C - 4 Install and plumb new sink and faucet under window. (Similar sink to what is in now)
D: DRYWALL
D - 1 Remove shinny white wall paneling in hallway #19. Repair possible existing drywall
behind paneling or redrywall the walls if not existing. Drywall the ceiling. The whole
hallway should have a uniform look.
D - 2 Repair the drywall in areas that had the cabinets or shelves removed.
E: INTERIOR TRIM AND PAINT
E - 1 Trim all added doors. Add trim against any ceilings that were drywalled that have
paneling on the walls. Add baseboards to any rooms that do not have them.
E - 2 Paint all interior doors that have been added and paint old doors that have not been
painted very recently.
E - 3 Paint all newly added or repaired drywalled areas.
E - 4 Paint the ceilings in the kitchen and in the following numbered offices. 4,10,12,13,14.
Room number 10 needs the one ceiling tile tacked up straight before painting. Paint the
ceiling in bathrooms 3 and 4.
E - 5 Paint or replace the few bad looking ceiling duct vents.
F: BATHROOM REPAIRS
F - 1 Remove and replace all toilets with new ones. (In bathroom # 5 install full size toilet)
F - 2 Replace all bath vanity cabinets and tops. In bathroom # 5 install full size pedestal sink.
F - 3 Install and plumb new vanity faucets
F - 4 Remove old mirrors and install new ones over sinks.
G: FLOORING
G - 1 Remove all existing carpet. Remove all existing hard flooring unless the new flooring can
be installed over it in a smooth way.
G - 2 . Install new commercial carpet in all offices, living rooms, and storage rooms.
(Approximately 2700 square feet)
G - 3 Install new commercial vinyl flooring or similar product in the kitchen, utility room, both
hall ways, and all bathrooms. (Approximately 1092 square feet)
H: ENTRY DECKS
H - 1 Remove the two entry decks and steps on the east side and replace them with new treated
lumber.
I: CLEANUP
I - 1 All new, used, and excess construction materials that relate to the job or a change order(s)
belongs to the contractor and can be removed from the property by the contractor as
needed during the project and shall be removed at completion.
I - 2 All trash shall be hauled off by contractor and preferably recycled if possible.
I - 3 All affected areas shall be left broom clean.
I - 4 If lead paint is present, cleanup will be compliant with EPA/HUD Approved Lead Safety
standards.
J: OTHER
J - 1 All work or materials which are not directly noted in the Scope of Work and Specifics,
but are necessary for the proper carrying out of the obvious intentions thereof, are to be
understood as implied work and will be provided for by the contractor as if specifically
described or drawn.
J - 2 All work shall be performed in a workmanlike manner according to common construction
practices, according to the specifications set forth in the Community Services Program's
General Specification Manual, and with adherence to city, state, and national codes.
J - 3 Any damage to the dwelling or property caused by the contractor, his/her worker(s) or
delivery person, and/or their vehicles during the project shall be repaired to like new
conditions.
J 4 Where applicable, all plumbing work shall be performed by a Arkansas State licensed
plumbing contractor with adherence to the current Arkansas Plumbing Code.
J 5 Where applicable, all electrical work shall be performed by a Arkansas State licensed
electrical contractor with adherence to the current National Electrical Code.
J - 6 Where applicable, all HVAC work shall be performed under the supervision of a licensed
HVAC contractor with adherence to all codes.