HomeMy WebLinkAbout110-09 RESOLUTIONRESOLUTION NO. 110-09 A RESOLUTION TO APPROVE A CONSTRUCTION CONTRACT WITH SWEETSER CONSTRUCTION, INC. IN THE AMOUNT OF $3,773,418.22 FOR WIDENING AND IMPROVEMENTS TO MOUNT COMFORT ROAD AND TO APPROVE A CONTINGENCY IN THE AMOUNT OF $377,340.00 BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS: Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves a construction contract (attached as Exhibit A) with Sweetser Construction, Inc. in the amount of $3,773,418.22 for widening and improvements to Mount Comfort Road and to approve a contingency in the amount of $377,340.00. PASSED and APPROVED this 19th day of May, 2009. ATTEST: By: A40(44ki 6. 6iptiztu SONDRA E. SMITH, City Clerk/Treasurer tovol1illrrrr,r k\'' �T Y 0 `s ' ' ' =U• r73S, ▪ r r ▪ ° FAYETTEVILLE; v�• ra.`, IF, -�s,�,� KA�i 'J .,�o icy F..,,.o `��.� GrON �..�� Chris Brown Submitted By City of Fayetteville Staff Review Form City Council Agenda Items and Contracts, Leases or Agreements 5/19/2009 City Council Meeting Date Agenda Items Only Engineering Division Division Action Required: Development Services Department A resolution to award a contract to Sweetser Construction, Inc. in the amount of $3,773,418.22 for construction of improvements to Mount Comfort Road, Alpine Avenue to Rupple Road, and approve a project contingency of 10% in the amount of $377,340 3,773,418.22 Cost of this request 4520.9520.5809.00 Account Number 06035.1500 Project Number 19, 343,175.00 Category / Project Budget Mt. Comfort (Alpine to Rupple Rd) Program Category / Project Name 5,789,687.40 Street Improvements $ Funds Used to Date Program / Project Category Name 13,553,487.60 2006A Sales Tax Construction Remaining Balance Fund Name Budgeted Item I-1 Budget Adjustment Attached Ci Finance and Internal Services Director Date -01 Date S --'1- 2 o09 Date dy ate to Previous Ordinance or Resolution # Original Contract Date: Original Contract Number: Comments: Revised January 15, 2009 City Council Meeting of May 19, 2009 CITY COUNCIL AGENDA MEMO To: Mayor and City Council Thru: Don Marr, Chief of Staff Jeremy Pate, Development Services Director From: Chris Brown, City Engineer CZ Date: April 30, 2009 Subject: A resolution to award a contract to Sweetser Construction, Inc. in the amount of $3,773,418.22 for construction of improvements to Mount Comfort Road, Alpine Avenue to Rupple Road, and approve a project contingency of 10% in the amount of $377,340 RECOMMENDATION: Staff recommends approval of a resolution awarding a contract to Sweetser Construction, Inc. in the amount of $3,773,418.22 for construction of improvements to Mount Comfort Road Contract 2, Alpine Avenue to Rupple Road, and approval of a project contingency of 10% in the amount of $377,340. BACKGROUND: Mount Comfort Road Improvements are a part of the Transportation Improvement Bond Program. The project includes major intersection improvements at the I540/Shiloh Drive Intersection, relocation of Shiloh Drive to the west, signalization of 4 intersections along Mount Comfort, and widening of Mount Comfort to 4 lanes from I-540 to Rupple Road. The improvements have been designed by Garver Engineers. DISCUSSION: Bids were received on April 28, 2009 for Contract 2 of the improvements. Contract 2 includes widening Mount Comfort Road to 4 lanes from Alpine Avenue to Rupple Road, with an additional turn lane and signalization at Salem Road and Rupple Road. The project also includes relocation of water and sewer lines to allow for the improvements. Nine bids were received, ranging from a high of $4,955,513.01 to the low bid of $3,773,418.22. The low bid was submitted by Sweetser Construction, Inc. of Fayetteville. Sweetser Construction is a•well-known local contractor that has demonstrated their ability to complete a contract of this size and type. BUDGET IMPACT: This Contract will be funded with a portion of the 2006 Transportation Bond Issue proceeds. The contract amount plus contingency is within the original project estimate of $4,432,020 for construction of this portion of the project. 1 BID: 09-32 4/28/2009 2:00 PM, Local Time CITY OF FAYETTEVILLE TaTett-011e Bid 09-32, Mount Comfort Road Improvements Contract 2, Rupple Road to Alpine Avenue 1 APAC-Arkansas, Inc. $4,240,263,30 2 Dean Crowder Construction, Inc. x $4,121,874.87 3 Decco Contractors -Paving $4,471,121.30 4 Ground Zero Construction, Inc. " $4,286,036.55 5 Jimmy Jones Excavation, Inc. $4,206,709.60 Mobley Contractors, Inc, $4,955,513.01 7 N.E.C., Inc. $3,778,978,77 8 Sweetser Construction, Inc. $3,773,418.22 9 Tomlinson Asphalt Co., Inc. $4,064,404.78 NOTICE: Bid award is contingent upon vendor meeting minimum specifications and formal authorization by City officials. * indicates adjustment in bid price for calculation error CERTIFIED: ../1 r v N-PURCH'GENT 11,01, 44(4,, r/i fie ITNESS DAT RESOLUTION NO. A RESOLUTION TO APPROVE A CONSTRUCTION CONTRACT WITH SWEETSER CONSTRUCTION, INC. IN THE AMOUNT OF $3,773,418.22 FOR WIDENING AND IMPROVEMENTS TO MOUNT COMFORT ROAD AND TO APPROVE A CONTINGENCY IN THE AMOUNT OF $377,340.00 BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS: Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves a construction contract (attached as Exhibit A) with Sweetser Construction, Inc. in the amount of $3,773,418.22 for widening and improvements to Mount Comfort Road and to approve a contingency in the amount of $377,340.00. PASSED and APPROVED this 19th day of May, 2009. APPROVED: ATTEST: By: By: LIONELD JORDAN, Mayor SONDRA E. SMITH, City CIerk/Treasurer DOCUMENT 00500 -- AGREEMENT BETWEEN OWNER AND CONTRACTOR Contract Name/Title: MOUNT COMFORT ROAD IMPROVEMENTS CONTRACT 2 — RUPPLE ROAD TO ALPINE AVENUE. Contract No.: THIS AGREEMENT is dated as of the day of in the year 20_ by and between The City of Fayetteville, Arkansas and .(hereinafter called Contractor). ARTICLE 1 - WORK 1.01 Contractor shall complete all Work as specified or indicated in the Contract Documents. The work under this Contract includes, but is not limited to: 11,500 Tons of Asphalt Concrete Hot Mix, 39,300 SY of aggregate base (six to eight inches thick), 11,600 LF of Curb and Gutter; 5,200 SY of concrete sidewalk, 5,700 LF of 18" — 51x-31" Reinforced Concrete Pipe, 2,600 LF of 12" PVC water line, 720 LF of 8" PVC water line, 5,000 LF of 8" PVC gravity sewer, and miscellaneous related items. Refer to Section 00400-13id Form for quantities: ARTICLE 2 - ENGINEER 2.01 The Contract Documents have been prepared by GARVER ENGINEERS, LLC. GARVER ENGINEERS, LLC assumes all duties and responsibilities, and has the rights and authority assigned to GARVER ENGINEERS LLC in the Contract Documents in connection with completion of the Work in accordance with the Contract Documents. ARTICLE 3 - CONTRACT TIME 3.01 TIME OF THE ESSENCE: A. All time limits for milestones, if any, Substantial Completion, and completion and readiness for final payment as stated in the Contract Documents are of the essence of the Contract. 00500 - 1 Garver Project No. 0605-1200 00500 Agreement Mount Comfort Road Improvements DOCUMENT 00500 — AGREEMENT (continued) 3.02 DATES FOR SUBSTANTIAL COMPLETION AND FINAL PAYMENT: A. The Work will be Substantially Completed within 60 calendar days for Clearing and Grubbing, and within 120 calendar days for the Traffic Signal at Salem and Mt. Comfort. B. The Work will be Substantially Completed within 330 calendar days for the remaining Roadway and Drainage construction, after the date when the Contract Times commence to run as provided in the GENERAL CONDITIONS, and completed and ready for final payment in accordance with the GENERAL CONDITIONS within 360 calendar days after the date when the Contract Times commence to run. 3.03 LIOUIDATED DAMAGES: A. Owner and Contractor recognize that time is of the essence of this Agreement and that The City of Fayetteville will suffer financial loss if the Work is not completed within the time specified above, plus any extensions thereof allowed in accordance with the GENERAL CONDITIONS. The parties also recognize the delays, expense, and difficulties involved in proving the actual loss suffered by The City of Fayetteville if the Work is not Substantially Completed on time. Accordingly, instead of requiring any such proof, The City of Fayetteville and Contractor agree that as liquidated damages for delay (but not as a penalty) Contractor shall pay The City of Fayetteville Seven Hundred Fifty Dollars ($750.00) for each calendar day that expires after the time specified above in Paragraph 3.02 for Substantial Completion until the Work is Substantially Complete. After Substantial Completion, if Contractor shall neglect, refuse, or fail to complete the remaining Work within the time specified in Paragraph 3.02 for completion and readiness for final payment or any proper extension thereof granted by The City of Fayetteville, Contractor shall pay The City of Fayetteville Seven Hundred Fifty Dollars ($750.00) for each calendar day that expires after the time specified for completion and readiness for final payment. 00500 Agreement Mount Comfort Road Improvements 00500 - 2 Garver Project No. 0605-1200 DOCUMENT 00500 — AGREEMENT (continued) ARTICLE 4 - CONTRACT PRICE 4.01 The CITY OF FAYETTEVILLE agrees to pay, and the CONTRACTOR agrees to accept, as full and final compensation for all work done under this agreement, the amount based on the prices bid in the Proposal (BID FORM) which is hereto attached, for the actual amount accomplished under each pay item, said payments to be made in lawful money of the United States at the time and in the manner set forth in the Specifications. 4.02 As provided in the General Conditions estimated quantities are not guaranteed, and determinations of actual quantities and classifications are to be made by ENGINEER as provided in the General Conditions. Unit prices have been computed as provided in the General Conditions. 4.03 Changes, modifications, or amendments in scope, price or fees to this contract shall not be allowed without a prior formal contract amendment approved by the Mayor and the City Council in advance of the change in scope, cost or fees ARTICLE 5 - PAYMENT PROCEDURES 5.01 SUBMITTAL AND PROCESSING OF PAYMENTS: A. Contractor shall submit Applications for Payment in accordance with the GENERAL CONDITIONS. Applications for Payment will be processed by Engineer as provided in the GENERAL CONDITIONS. 5.02 PROGRESS PAYMENTS, RETAINAGE: A. The City of Fayetteville shall make progress payments on account of the Contract Price on the basis of Contractor's Applications for Payment as recommended by Engineer, on or about the 15th day of each month during construction. All such payments will be measured by the schedule of values established in the GENERAL CONDITIONS (and in the case of Unit Price Work based on the number of units completed) or, in the event there is no schedule of values, as provided in the General Requirements. 00500 Agreement Mount Comfort Road Improvements 00500 - 3 Garver Project No. 0605-1200 DOCUMENT 00500 — AGREEMENT (continued) 1. Prior to Substantial Completion, progress payments will be made in an amount equal to the percentage indicated below, but, in each case, less the aggregate of payments previously made and less such amounts as Engineer shall determine, or The City of Fayetteville may withhold, in accordance with the GENERAL CONDITIONS. a. 90% of Work Completed (with the balance being retainage). If Work has been 50% completed as determined by Engineer, and if the character and progress of the Work have been satisfactory to The City of Fayetteville and Engineer, The City of Fayetteville on recommendation of Engineer, may determine that as long as the character and progress of the Work subsequently remain satisfactory to them, there will be no additional retainage on account of Work subsequently completed, in which case the remaining progress payments prior to Substantial Completion will be an amount equal to 100% of the Work Completed less the aggregate of payments previously made; and b. 100% of Equipment and Materials not incorporated in the Work but delivered, suitably stored, and accompanied by documentation satisfactory to The City of Fayetteville as provided in the GENERAL CONDITIONS. 2. Upon Substantial Completion, The City of Fayetteville shall pay an amount sufficient to increase total payments to Contractor to 95% of the Contract Price (with the balance being retainage), less such amounts as Engineer shall determine, or The City of Fayetteville may withhold, in accordance with the GENERAL CONDITIONS. 5.03 FINAL PAYMENT: A. Upon final completion and acceptance of the Work in accordance with the GENERAL CONDITIONS, The City of Fayetteville shall pay the remainder 00500 Agreement Mount Comfort Road Improvements 00500 - 4 Garver Project No. 0605-1200 DOCUMENT 00500 — AGREEMENT (continued) of the Contract Price as recommended by Engineer and as provided in the GENERAL CONDITIONS. ARTICLE 6 - CONTRACTOR'S REPRESENTATIONS 6.01 In order to induce The City of Fayetteville to enter into this Agreement, Contractor makes the following representations: A. Contractor has examined and carefully studied the Contract Documents including the Addenda and other related data identified in the Bid Documents. B. Contractor has visited the Site and become familiar with and is satisfied as to the general, local, and Site conditions that may affect cost, progress, performance, and furnishing of the Work. C. Contractor is familiar with and is satisfied as to all federal, state, and local Laws and Regulations that may affect cost, progress, performance, and furnishing of the Work. D. Contractor has carefully studied all: (1) Reports of explorations and tests of subsurface conditions at or contiguous to the Site and all drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the Site; and (2) Reports and drawings of a Hazardous Environmental Condition, if any, at the Site. Contractor acknowledges that The City of Fayetteville and Engineer do not assume responsibility for the accuracy or completeness of information and data shown or indicated in the Contract Documents with respect to Underground Facilities at or contiguous to the Site. E. Contractor has obtained and carefully studied (or assumes responsibility of having done so) all such additional supplementary examinations, 00500 - 5 Garver Project No. 0605-1200 00500 Agreement Mount Comfort Road Improvements DOCUMENT 00500 — AGREEMENT (continued) investigations, explorations, tests, studies, and data concerning conditions (surface, subsurface, and Underground Facilities) at or contiguous to the Site or otherwise which may affect cost, progress, performance, and furnishing of the Work or which relate to any aspect of the means, methods, techniques, sequences, and procedures of construction to be employed by Contractor and safety precautions and programs incident thereto. F. Contractor does not consider that any additional examinations, investigations, explorations, tests, studies, or data are necessary for the performing and furnishing of the Work at the Contract Price, within the Contract Times, and in accordance with the other terms and conditions of the Contract Documents. G. Contractor is aware of the general nature of work to be performed by The City of Fayetteville and others at the Site that relates to the Work as indicated in the Contract Documents. H. Contractor has correlated the information known to Contractor, information and observations obtained from visits to the Site, reports and drawings identified in the Contract Documents, and all additional examinations, investigations, explorations, tests, studies, and data with the Contract Documents. _ I. Contractor has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Contractor has discovered in the Contract Documents and the written resolution thereof by Engineer is acceptable to Contractor. J. The Contract Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work. 00500 Agreement Mount Comfort Road Improvements 00500 - 6 Garver Project No. 0605-1200 DOCUMENT 00500 — AGREEMENT (continued) ARTICLE 7 - CONTRACT DOCUMENTS 7.01 CONTENTS: A. The Contract Documents which comprise the entire Agreement between The City of Fayetteville and Contractor concerning the Work consist of the following and may only be amended, modified, or supplemented as provided in the GENERAL CONDITIONS: 1. This Agreement. 2. Exhibits to this Agreement (enumerated as follows): a. Notice to Proceed — Right of Way and Easement Preparation, Traffic Signalization at Salem and Mt. Comfort, and Roadway and Drainage Construction. b. Contractor's Bid. c. Documentation submitted by Contractor prior to Notice of Award. 3. Performance, Payment, and other Bonds. 4. General Conditions. 5. Supplementary Conditions. 6. Specifications consisting of divisions and sections as listed in table of contents of Project Manual. 7. Drawings consisting of a cover sheet and sheets as listed in the table of contents thereof, with each sheet bearing the following general title: MOUNT COMFORT ROAD IMPROVEMENTS CONTRACT 2 — RUPPLE ROAD TO ALPINE AVENUE 00500 Agreement Mount Comfort Road Improvements 00500 - 7 Garver Project No. 0605-1200 DOCUMENT 00500 — AGREEMENT (continued) 8. Addenda numbers one (1) to ( ), inclusive. 9. The following which may be delivered or issued after the Effective Date of the Agreement and are not attached hereto: All Written Amendments and other documents amending, modifying, or supplementing the Contract Documents pursuant to the GENERAL CONDITIONS. ARTICLE 8 - MISCELLANEOUS 8.01 TERMS: A. Terms used in this Agreement which are defined in the GENERAL CONDITIONS shall have the meanings stated in the GENERAL CONDITIONS. 8.02 ASSIGNMENT OF CONTRACT: A. No assignment by a party hereto of any rights under or interests in the Contract Documents will be binding on another party hereto without the written consent of the party sought to be bound; and specifically but without limitation, moneys that may become due and moneys that are due may not be assigned without such consent (except to the extent that the effect of this restriction may be limited by Law), and unless specifically stated to the contrary in any written consent to an assignment, no assignment will release or discharge the assignor from any duty or responsibility under the Contract Documents. 8.03 SUCCESSORS AND ASSIGNS: A. The. City of Fayetteville and Contractor each binds himself, his partners, successors, assigns, and legal representatives to the other party hereto, its partners, successors, assigns, and legal representatives in respect to all covenants, agreements, and obligations contained in the Contract Documents. 00500 Agreement Mount Comfort Road Improvements 00500 - 8 Garver Project No. 0605-1200 DOCUMENT 00500 — AGREEMENT (continued) 8.04 SEVERABILITY: A. Any provision or part of the Contract Documents held to be void or unenforceable under any Law or Regulation shall be deemed stricken, and all remaining provisions shall continue to be valid and binding upon The City of Fayetteville and Contractor, who agree that the Contract Documents shall be reformed to replace such stricken provision or part thereof with a valid and enforceable provision that comes as close as possible to expressing the intention of the stricken provision. 8M5 FREEDOM OF INFORMATION ACT: A. City contracts and documents prepared while performing city contractual work are subject to the Arkansas Freedom of Information Act. If a Freedom of Information Act request is presented to the City of Fayetteville, the contractor will do everything possible to provide the documents in a prompt and timely manner as prescribed in the Arkansas Freedom of Information Act (A.C.A. §25-19-101 et. seq.). Only legally authorized photocopying costs pursuant to the FOIA may be assessed for this compliance. IN WITNESS WHEREOF, The City of Fayetteville and Contractor have signed this Agreement in quadruplicate. One counterpart each has been delivered to Contractor and Engineer. Two counterparts each has been delivered to The City of Fayetteville. All portions of the Contract Documents have been signed, initialed, or identified by The City of Fayetteville and Contractor or identified by Engineer on their behalf. 00500 Agreement Mount Comfort Road Improvements 00500 - 9 Garver Project No. 0605-1200 DOCUMENT 00500 — AGREEMENT (continued) This Agreement will be effective on , 20. which is the Effective Date of the Agreement. SWEETSER CONSTRUCTION, INC. CITY OF FAYETTEVILLE 590 W. Poplar, Fayetteville, AR 72703 By: By: Title: Title: (SEAL) (SEAL) Attest Attest Address for giving notices Address for giving notices License No. Agent for Service of process (If Contractor is a corporation, attach evidence of authority to sign.) 00500 Agreement Mount Comfort Road Improvements (attach evidence of authority to sign and resolution or other documents authorizing execution of Agreement) Approved As to Form: By: Attorney For: END OF DOCUMENT 00500 00500 - 10 Garver Project No. 0605-1200 I ayeev ARKANSAS City of Fayetteville Engineering Division 113 West Mountain Street Fayetteville, Arkansas 72701 SPECIFICATIONS AND CONTRACT DOCUMENTS FOR MOUNT COMFORT ROAD IMPROVEMENTS CONTRACT 2 - RUPPLE ROAD TO ALPINE AVENUE 2006 TRANSPORTATION BOND PROGRAM GARVER ENGINEERS PROJECT 0605-1200 BID # 09-32 Bid Opening: April 8, 2009 Garver, LLC 1088 East Millsap Road Fayetteville, Arkansas 72703 479-527-9100 FAX 479-527-9101 www.garverusa.com 04/27/2005 MON 8:44 1475279t01 Gayer Fayetteville Garver Engineers, LLC 1088 WS%) Fayettevitte.Arkansas 7270r 478-527.5100 FAX 478-527-9101 WWw.ciargepancanasrSZOrn April 24, 2009 Addendum No. 1 To Plans, Contract Documents and Specifications Garver Project Number - 06051200 Mt. Comfort Road Improvements Contract 2 — flupple Road to Alpine Avenue Fax:14794420119 Apr 27 2009 09:2Sam UUL/ Ui P0011 I�{100 This addendum shall be a part of the Plans, Contract Documents and Specifications to the same extent as though it were originally included Therein, and it shall supersede anything contained in the Plans, Contract Documents and Specifications with which it might conflict, Acknowledgement of receipt of this Addendum must be provided in the Proposal included in the Contract Documents and by signing the first sheet of this form in the location provided below and taxing back to Garver. This addendum shall also be stapled to the inside cover of the Contract Documents. Acknowledgement Receipt Acknowledgement of receipt of this addendum shall be provided to Garver Engineers by signing below and faxing back to Garver Engineers at 479-527-9101: y r)7 Received by; ( 6,- Z6' Date' Company: _Si() � s ( t .�;s * C r1i o,J) rsc. . Addenda: Plan Clarifications: 1. Underdrain will not be constructed in combination with the storm sewer pipe unless as directed by the Engineer. When directed by Engineer, the underdrain will be paid for per SP -11 Pipe Underdrains. 2. The asp alt "bid index" is 381.25. By: /A AA .' marl mer 1{ : •� Pr.ject Manager Attachments: Page 1 of 1 CITY OF FAYETTEVILLE FAYETTEVILLE, ARKANSAS MOUNT COMFORT ROAD IMPROVEMENTS CONTRACT 2 - RUPPLE ROAD TO ALPINE AVENUE 2006 TRANSPORTATION BOND PROGRAM SPECIFICATIONS AND CONTRACT DOCUMENTS I hereby certify that the MOUNT COMFORT ROAD IMPROVEMENTS CONTRACT 2 - RUPPLE ROAD TO ALPINE AVENUE, 2006 Transportation Bond Program plans and specifications were prepared by me or under my direct supervision and that I am duly Licensed Engineer under the laws of the State of Arkansas. (Seal) Name: Date: 117/701 siT E ARKSAS, * * * REGISTERED PROFESSIONAL ENGINEER 4, No* .11931 1Cs s.1y., I hereby certify that the MOUNT COMFORT ROAD IMPROVEMENTS CONTRACT 1 - ALPINE AVENUE TO I-540, 2006 Transportation Bond Program plans and specifications were prepared by me or under my direct supervision and that I am duly Licensed Engineer under the laws of the State of Arkansas. (Seal) Name: lit M1 lige—Date: Sj ATE ARSAS * * * REGISTERED PROFESSIONAL 4 ENGINEER W * if No.8658 I hereby certify that the MOUNT COMFORT ROAD IMPROVEMENTS CONTRACT 2 - RUPPLE ROAD TO ALPINE AVENUE, 2006 Transportation Bond Program plans and specifications were prepared by me or under my direct supervision and that I am duly Licensed Engineer under the laws of the State of Arkansas. (Seal) Name: Date: 9- -U, I' T EsQ ARKANSAS ' REGISTERED PROFESSIONAL ENGINEER % > No.8141 41,1 Ocpl D. I hereby certify that the MOUNT COMFORT ROAD IMPROVEMENTS CONTRACT 2 - RUPPLE ROAD TO ALPINE AVENUE, 2006 Transportation Bond Program plans and specifications were prepared by me or under my direct supervision and that I am duly Licensed Engineer under the laws of the State of Arkansas. (Seal) Name: Date: S� Az. L /' ARIISAS ,‘ ** REGISTERED PROFESSIONALz ENGINEER NI *** --4.42.1,",SI 5 . No.12716 op CERTIFICATE OF AUTHORIZATION BY GARVER ENGINEERS, LLC ,`,,►►►111CF Atity 111Iil1►►►/, j�� : GARVER *• .-FA Egui:ENGINEERSI.Z5F.-. =v'LLC • \.No. 766./4„5-4:1'