HomeMy WebLinkAbout04-09 RESOLUTIONRESOLUTION NO. 04-09
A RESOLUTION TO APPROVE A TWO YEAR AGREEMENT
TO CONTINUE SEWER SERVICE FOR GREENLAND.
WHEREAS, the Fayetteville -Greenland Sewer Contract entered into on December 21,
1993, officially expires after December 21, 2008; and
WHEREAS, only a short (one year) extension of this Sewer Contract is needed before
the anticipated acquisition of Greenland's sewer system into the Fayetteville sewer system can
be accomplished.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas, hereby approves
the attached Two Year Agreement to Continue Sewer Service For Greenland and authorizes
Mayor Jordan to execute this contract.
PASSED and APPROVED this 6th day of January, 2009.
ATTEST.
��•••G\TY Oc'%GP
:FAYETTEVILLE;
oy g:4
;9s RtANs Jam':
11/4/11111111 %%%%
l7/[/ By: 1 -1) & q zz L
SONDRA E. SMITH, City Clerk/Treasurer
TWO YEAR AGREEMENT TO CONTINUE
SEWER SERVICE BY FAYETTEVILLE FOR GREENLAND
Come now the City of Fayetteville and the City of Greenland and
agree to a two year sewer contract for the period of January 6, 2009 until
January 5, 2011. The cities agree as follows:
1. Fayetteville agrees that it will continue to operate and maintain
the Greenland sewer system and shall treat all wastewater collected within
the Greenland city limits (but only for customers who have individual
water services provided by Fayetteville). Sewer service to Greenland
residents not having Fayetteville water service may be furnished provided
mutual agreement on the method of billing such customers can be reached
by Fayetteville and Greenland.
2. Greenland agrees that it will require its citizens receiving
Fayetteville water service to purchase sewer service from Fayetteville
under the, same sewer availability criteria as required of Fayetteville
citizens. Greenland agrees that its citizens will be subject to pay sewer
rates on a cost -of -service basis pursuant to the current sewer service rates
adopted by the Fayetteville City Council (§51.137 of the Code of
Fayetteville) and any amendments approved thereto.
3. Greenland agrees that it will require its citizens (by ordinance or
otherwise adopted no later than March 31, 2009) receiving new sewer
service from Fayetteville to pay sewer impact fees to Fayetteville in the
same amount as new development in Fayetteville pays pursuant to the
current ordinance and any amendments to §159.02 Water and Wastewater
Impact Fees of the Unified Development Code of Fayetteville.
4. Paragraphs 5, 6, 7, 8, 9, 10, 11, 12, 13, 15, 16, 17, 18, 19, 21 and 22 of
the 1993 Fayetteville - Greenland Sewer Contract are adopted and
incorporated herein as if set forth word for word.
5. Fayetteville and Greenland anticipate that the City of Fayetteville
shall either assume ownership and operation of the Greenland sewer
system in 2009-2010 or that another, Long-term Fayetteville - Greenland
Sewer Contract shall be adopted in 2010 in which Fayetteville will agree to
continue to operate and maintain the sewer system within and serving
Greenland residents.
IN AGREEMENT WITH ALL PROMISES, OBLIGATIONS AND
TERMS STATED ABOVE, the Mayors of the Cities of Fayetteville and
Greenland have signed below after having been properly authorized by
their respective City Councils.
By
CITY OF FAYETTEVILLE
Al LEST:
B
CITY OF GREENLAND
A I PEST:
By:M' By: 14J anti-, l ��
Sondra E. Smith, City Clerk Donna Cheevers, City Clerk
Date: p,is„3Q -0 7 Date:
C.•.�.i 1 R ? ".,,'
vA.C'�'J1Y OF�SGcn1.1
c : FAYETTEVILLE'
%.°'y; .
NGTON Gp`‘
11
AGENDA REQUEST
FOR: COUNCIL MEETING OF JANUARY 6, 2008
/ /j6109
GZenlana' tee'
FROM:
KIT WILLIAMS, CITY ATTORNEY
ORDINANCE OR RESOLUTION TITLE AND SUBJECT:
A Resolution To Approve A One Year Agreement to Continue Sewer Service For
Greenland
APPROVED FOR AGENDA:
cr\
or-bt0 16 Diu. 0 8
Water & Wastewater Director Date
Ci torney
May
Date
2'Y Q � l?,-�Z--aB
or
Date
C44% 07
FAYETTEVILLE
THE CIN OF FAYETTEVILLE, ARKANSAS
KIT WILLIAMS, CITY ATTORNEY
DAVID WHITAKER, ASST. CITY ATTORNEY
DEPARTMENTAL CORRESPONDENCE LEGAL DEPARTMENT
TO: Fayetteville Sewer Committee
CC: David Jurgens, Water & Wastewater Director
FROM: Kit Williams, City Attorney
DATE: December 16, 2008
RE• One Year Sewer Contract with Greenland
(
After I drafted a 25 -page contract (based upon the approved Farmington
sewer contract) for a long-term extension of Greenland's sewer contract with
Fayetteville (that expires December 21, 2008), Water & Wastewater Director
David Jurgens informed me that a long extension was not needed. Mr. Jurgens
Informed me that a one year extension was all that would be needed because city
staff and the City Sewer Committee desired to obtain ownership (as well as
continued operation and maintenance) of the Greenland Sewer System.
Therefore, I have drafted a one year contract that incorporates much of the
1993 contract, but also includes sewer connection requirements identical to the
requirements of Fayetteville residents as well as sewer impact fees identical to
what new development would have to pay in Fayetteville.
If this proposed one year agreement is satisfactory to the Sewer Committee,
I propose it be placed on the January 6, 2009 City Council Agenda for City
Council approval Once it meets the Sewer Committee's approval it should be sent
to Greenland for their City Council's approved at their first meeting in January
2009. All sewer services provided to Greenland residents by the City of
Fayetteville should continue unchanged through the approval of this contract by
both cities.
RESOLUTION NO.
A RESOLUTION TO APPROVE A ONE YEAR AGREEMENT
TO CONTINUE SEWER SERVICE FOR GREENLAND
WHEREAS, the Fayetteville -Greenland Sewer Contract entered into on December 21,
1993, officially expires after December 21, 2008; and
WHEREAS, only a short (one year) extension of this Sewer Contract is needed before
the anticipated acquisition of Greenland's sewer system into the Fayetteville sewer system can
be accomplished.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas, hereby approves
the attached One Year Agreement to Continue Sewer Service For Greenland and authorizes
Mayor Jordan to execute this contract.
PASSED and APPROVED this 6th day of January, 2009.
APPROVED: ATTEST.
By: By:
LIONELD JORDAN, Mayor SONDRA E. SMITH, City Clerk/Treasurer
ONE YEAR AGREEMENT TO CONTINUE
SEWER SERVICE BY FAYETTEVILLE FOR GREENLAND
Come now the City of Fayetteville and the City of Greenland and
agree to a one year sewer contract for the period of January 6, 2009 until
January 5, 2010. The cities agree as follows:
1. Fayetteville agrees that it will continue to operate and maintain
the Greenland sewer system and shall treat all wastewater collected within
the Greenland city limits (but only for customers who have individual
water services provided by Fayetteville). Sewer service to Greenland
residents not having Fayetteville water service may be furnished provided
mutual agreement on the method of billing such customers can be reached
by Fayetteville and Greenland.
2. Greenland agrees that it will require its citizens receiving
Fayetteville water service to purchase sewer service from Fayetteville
under the same sewer availability criteria as required of Fayetteville
citizens Greenland agrees that its citizens will be subject to pay sewer
rates on a cost -of -service basis pursuant to the current sewer service rates
adopted by the Fayetteville City Council (01.137 of the Code of
Fayetteville) and any amendments approved thereto.
3. Greenland agrees that it will require its citizens (by ordinance or
otherwise adopted no later than March 31, 2009) receiving new sewer
service from Fayetteville to pay sewer impact fees to Fayetteville in the
same amount as new development in Fayetteville pays pursuant to the
current ordinance and any amendments to §159.02 Water and Wastewater
Impact Fees of the Unified Development Code of Fayetteville.
4. Paragraphs 5, 6, 7, 8, 9, 10, 11, 12, 13, 15,16,17, 18, 19, 21 and 22 of
the 1993 Fayetteville - Greenland Sewer Contract are adopted and
incorporated herein as if set forth word for word.
5. Fayetteville and Greenland anticipate that the City of Fayetteville
shall either assume ownership and operation of the Greenland sewer
system in 2009 or that another, long-term Fayetteville - Greenland Sewer
Contract shall be adopted in 2009 in which Fayetteville will agree to
continue to operate and maintain the sewer system within and serving
Greenland residents.
IN AGREEMENT WITH ALL PROMISES, OBLIGATIONS AND
TERMS STATED ABOVE, the Mayors of the Cities of Fayetteville and
Greenland have signed below after having been properly authorized by
their respective City Councils.
CITY OF FAYETTEVILLE CITY OF GREENLAND
By: By:
LIONELD JORDAN, Mayor JOHN GRAY, Mayor
All EST: ATTEST:
By: By:
Sondra E. Smith, City Clerk Donna Cheevers, City Clerk
Date: Date:
•
•
•
•
•
•
RESOLUTION NO. 137-93
A RESOLUTION AUTHORIZING THE MAYOR AND CITY
CLERK TO EXECUTE THE GREENLAND SEWER LINE AND
LIFT STATION MAINTENANCE CONTRACT, WITH
MODIFICATIONS.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1. That the Mayor and City Clerk are hereby authorized to execute the
Greenland sewer line and lift station maintenance contract, with modifications. A copy of the
contracts are attached hereto marked Exhibit "A" and made a part hereof.
PASSED AND APPROVED this 2Ist day of December , 1991
ATTEST.
By:
�dlth4t/ it
Sherry L. Thomas, City Clerk
APPROVED:
By: ZY /✓'� "
red Hanna, Mayor
•
FAYETTEVILLE-GREENLAND SEWER CONTRACT
This Contract, made and entered into this,?/,,r day of ,9.c.t,,i...4
1993, by and between the City of Fayetteville, Arkansas, a
municipal corporation, hereinafter called Fayetteville, and the
City of Greenland, Arkansas, a municipal corporation, hereinafter
called Greenland.
WITNESSETH:
WHEREAS, Fayetteville owns and operates a public sewerage
system consisting of lateral, main and interceptor sewers, sewage
lift stations, and treatment facilities, and
WHEREAS, Fayetteville now has a sewage lift station near the
west city limits of Fayetteville from which sewage may be
transmitted to Fayetteville's treatment facilities for treatment,
and
WHEREAS, Fayetteville's sewerage system has a capacity in
excess than required by Fayetteville, and
WHEREAS, Greenland has a public sewerage system, including
sewer lines and a sewage pump station, and other appurtenances
thereto (hereinafter referred to as the Greenland System), and
WHEREAS, to maintain certain health standards and to alleviate
public health hazards to the citizens of Fayetteville and
Greenland, the parties hereto desire to provide for maintenance of
the Greenland System and treatment of sewage generated in
Greenland;
NOW. THEREFORE. IN CONSIDERATION OF THE MUTUAL COVENANTS AND
CONDITIONS HEREINAFTER SET FORTH. THE PARTIES HERETO MUTUALLY AGREE
AS FOLLOWS:
1. FAYETTEVILLE'S OBLIGATIONS: Fayetteville agrees that it
will, for a period of 15 years, from and after the date of the
execution of this contract, operate and maintain (as defined
hereinafter) the Greenland System and shall treat all waste water
collected within Greenland's City Limits. Provided, however, that
Greenland will provide individual sewer service only to customers
who have individual water services from Fayetteville. Sewer service
to Greenland residents not having Fayetteville water may be
furnished provided mutual agreement on method of billing can be
attained between Fayetteville and Greenland.
2. GREENLAND'S OBLIGATIONS: Greenland agrees that they will
purchase sewer service from Fayetteville for the period above
specified for sewer customers within Greenland's City Limits.
1
Greenland agrees that Fayetteville will be permitted to charge
individual customers the rates and charges hereinafter provided.
3. DEFINITION OF LIMITS OF GREENLAND: The term "Greenland
City Limits" as used in this contract shall mean the legal
corporate limits of Greenland as they exist at the time this
contract is executed, or as may be modified by Greenland in the
future in whatever manner that may be provided for by law for
annexation.
4. SEWER RATES: The rates for sewer service shall be on a
cost -of -service basis as computed by a Registered Professional
Engineer selected and employed by the City of Fayetteville.
Greenland shall have the right to review such rates and provide the
City with their comments prior to the time that the rates are
adopted by Fayetteville. The rates as of the date of this contract
shall be as shown on Exhibit "A" attached. The sewer rates include
maintenance and treatment costs, tapping fees, and surcharge rates
for excess BOD and Suspended Solids. Fayetteville reserves the
right to review the sewer rates at the end of each three year
period or at the same time Fayetteville rates are reviewed, and
make an adjustment in said rates if indicated, based upon a
demonstrable increase or decrease in cost of performance hereunder.
5. CHARGES AND REQUIREMENTS FOR SEWER SERVICE CONNECTIONS:
The charges for making individual connections to the Greenland
System shall be as established by the Fayetteville City Council and
as adjusted from time to time. A Plumbing Permit must be obtained
from the City of Fayetteville before a connection order can be
issued by Fayetteville.
6. BILLING, COLLECTIONS AND PAYMENT: Fayetteville shall issue
billing and collect all bills in accordance with ordinances of the
City of Fayetteville and the rules and regulations of the Sewer
Department of Fayetteville as now exist or hereafter adopted, and
if any customer fails or refuses to pay said billing, Fayetteville
shall discontinue water and sewer service to such customer in
accordance with said ordinances, rules and regulations.
7. COMPLIANCE WITH RULES AND REGULATIONS: The City of
Greenland and all sewer customers shall comply with, at all times,
the ordinances, rules and regulations of the City of Fayetteville
which may now exist or may hereafter be promulgated. Failure or
refusal of any customer to comply with such ordinances, rules or
regulations will subject the customer to immediate discontinuance
of water and sewer service. Neither Fayetteville nor Greenland
shall in any way be liable for any damages or expenses which may
result from such discontinuance.
Each customer shall obtain a Plumbing Permit from the City of
Fayetteville and install all plumbing in accordance with the
ordinances, rules and regulations of the City of Fayetteville in
2
effect at the time such plumbing is installed. Fayetteville shall
provide a copy of each and every regulation and ordinance so
alluded to this Contract to Greenland as they now exist and shall
provide changes to those regulations as soon as possible after. such
changes are made.
Greenland shall not be held liable under any rule or
regulation or ordinance that has not been properly transmitted to
them. Greenland will adopt an ordinance or ordinances providing for
the discontinuance of water and sewer service in the event of
failure or refusal of a customer to comply with the above
provisions. All plumbing shall be inspected by the City of
Fayetteville Plumbing Inspector, or his authorized agent. The
Plumbing Permit Fee/Inspection Fee shall be as prescribed by the
City of Fayetteville from time to time for outside of the City of
Fayetteville.
The Plumbing Permit Fees for Greenland shall be determined on
a cost of service basis and shall include but not be limited to the
costs of equipment used, man hours employed, and mileage, overhead
and administrative costs. The Plumbing Permit Fees shall be as
shown in Exhibit "8", attached, and as modified by Fayetteville
from time to time. Greenland will make provision by ordinance for
authorized agents of Fayetteville to enter any and all properties
for inspection where the possibility of violation of said plumbing
ordinances, rules and regulations may exist.
It is understood Greenland may issue it's own Plumbing Permits
and do its own inspections at such time as they develop the staff
and capabilities to do so.
8. OWNERSHIP OF SYSTEM: It
System, including all sewers, the
and appurtenances thereto are
Greenland.
9. OPERATION AND MAINTENANCE: Fayetteville shall operate and
maintain all of the existing Greenland System and all facilities
which may be constructed and become a part of the Greenland System
in the future. operation and Maintenance shall include:
a) Pump Stations: Fayetteville shall provide the
maintenance made necessary by the normal wear and tear
encountered by the system. It does not include the replacement
or enlargement'of the station made necessary either by the
increase in normal domestic flows or by an increase in the
infiltration and inflow within the Greenland System. Neither
does it include repair of extraordinary damages resulting from
Acts of God.
is understood that the Greenland
sewage lift station, force main,
the property of the City of
b) Gravity Sewers and Force Mains: Operation and
maintenance of the gravity sewers and force mains shall mean
3
the demand maintenance required as a result of a reported
gravity sewer or force main blockage, the preventive rodding
and cleaning of gravity sewer mains or force mains, and in-
house sewer rehabilitation activities. In-house sewer
rehabilitation shall include smoke testing, televising of
lines, manhole lining and repairs, chemical grouting, point
repairs, and line replacements not exceeding 15 feet.
Fayetteville agrees that it shall utilize the same criteria to
determine the extent and degree of in-house sewer
rehabilitation to be done within the Greenland System as we do
for the Fayetteville sewerage system.
10. CONSTRUCTION OF NEW FACILITIES: New gravity sewers, force
mains, pump stations, sewerage appurtenances, or enlargement
thereof shall be constructed without cost to Fayetteville. This
includes enlarging, replacing, moving, relocating, lowering, or
adjusting to grade of any of the facilities of the system should
they become overloaded or for the purpose of permitting
construction of other facilities. To the extent that such un -
included activities are undertaken they shall be undertaken without
cost to Fayetteville. Also included under this Paragraph are pump
station replacements or improvements, sewer line replacements,
construction of relief sewers, force main replacements and
improvements, Sewer System Evaluation Studies intended to define
excessive stormwater infiltration and inflow into the Greenland
System, and subsequent construction to eliminate such excessive
infiltration and inflow, all of which shall be accomplished without
cost to Fayetteville: The need for a Sewer System Evaluation Study
would be jointly determined by Greenland and Fayetteville.
Fayetteville and Greenland agree that Greenland may add a
surcharge to the amounts normally charged by Fayetteville for sewer
services provided under this Contract. The purpose shall be to
provide for the construction of new facilities as defined in this
Paragraph, and for other purposes as may be specified by Greenland.
The money collected under this provision shall be collected by the
City of Fayetteville and shall be dispersed to Greenland two times
per year beginning in January of 1994.
Any interest earned on said funds shall go to Fayetteville to
compensate for the administration, audit and payment of said funds.
Plans and specifications for any new construction as described
above must be approved by the Fayetteville City Engineer and the
Arkansas State Department of Health prior to the execution of any
construction contract. Pipe size for any facilities shall be in
keeping with prospects for future growth. Pipe and other materials
used in such construction shall be in accordance with the standard
construction practices of the Sewer Department of Fayetteville at
the time such work is done. The design and specifications for any
sewer facilities shall be in keeping with acceptable engineering
practices at the time of construction. All such construction shall
4
be planned and supervised by a Registered Professional engineer
licensed to practice in the State of Arkansas. Greenland shall not
extend any sewer lines beyond the Greenland City Limits as defined
in Paragraph 3 of this Contract.
Fayetteville shall be furnished two copies of the "As-Built"
plans of all work, with a certification from the Engineer that all
work was constructed in accordance with the approved plans and
specifications. Fayetteville shall have the right to inspect and
test the system within a reasonable time prior to accepting and
placing the system into service.
11. EXTENSIONS BY FAYE TEVILLE: Fayetteville shall have the
right to make extensions from Greenland's lines to serve adjacent
areas inside or outside the present limits of Fayetteville so long
as Fayetteville does not serve customers in the present limits of
Greenland. Thecost of replacement or enlargement of Greenland's
lines or pumping facilities required by loads imposed by
Fayetteville shall be borne by Fayetteville.
12. EASEMENTS: When easements are necessary in connection
with maintenance and/or construction activities provided for in
this Contract, those easements shall be acquired by and at the
expense of Greenland. The easements shall be of adequate width for
construction, installation and maintenance of lines and
appurtenances. Fayetteville shall be afforded the right to full use
of such easements. The form of such easements, together with the
provisions contained therein, shall be the same as used by
Fayetteville at the time such easements are obtained. All such
easements, whether acquired by condemnation proceedings or
otherwise, shall be obtained without cost to Fayetteville.
13. ORDINANCES AND REGULATIONS TO FACILITATE PERFORMANCE OF
CONTRACT: Greenland and Fayetteville will enact, adopt or execute
ordinances, motions, resolutions, rules, regulations or
supplemental agreements which may be necessary to carry out the
terms of this agreement. All ordinances required to be enacted by
Greenland under this contract shall be enacted within 90 days of
the contract execution date unless specifically stated otherwise in
the contract.
15. PROSECUTION FOR TAMPERING: Greenland agrees to enact an
ordinance or ordinances with provisions substantially as follows:
"It shall be unlawful for any person other than a person
authorized by the Water and Sewer Superintendent of the City
of Fayetteville, Arkansas, to make connection with the sewer
collection system in this City or to tamper with any manhole
or any appurtenance to the sewer collection system in this
City. Nothing in this ordinance shall be so constructed as to
prevent any person when acting under the authority of the
Superintendent of the Water and Sewer Department of the City
5
1
of Fayetteville, Arkansas, from changing, altering or
otherwise working with any portion of the sewer system located
in this City".
That violation of said ordinance or ordinances shall be a
Class "A" misdemeanor and shall be prosecuted within the fullest
limits of the law. Greenland agrees that it will prosecute all
offenders.
16. INDUSTRIAL PRETREATMENT:
a} Greenland Ordinance; Greenland agrees to adopt, within
6 months from the date of this Contract, a sewer use ordinance
which is no less stringent and is as broad in scope as the
sewer use ordinance as adopted by Fayetteville. Whenever
Fayetteville amends its sewer use ordinance, it will forward
a copy of such amendments within 10 business days of enactment
thereof. Greenland will enact amendments at least as stringent
as those adopted by Fayetteville within 30 business days of
receipt thereof. The Parties will periodically review their
respective sewer use ordinance and jointly draft and adopt
amendments (which are equivalent in scope and stringency) to
their respective sewer use ordinance when deemed necessary for
the effective administration and operation of the pretreatment
program. This review will be conducted no less than once
every 2 years. However either party may request a joint
review whenever such party believes that a review is
necessary.
A request for such point review must be forwarded by the
requesting party to all other parties, stating the reason for
the request and the date on which the review is requested to
take place. Within 10 days of receipt of the request, the
receiving party must respond to the request stating that the
proposed date is satisfactory or proposing an alternate
date(s) for the review. In any case, the joint review will
take place within 30 business days of the request.
b) Local Limits: Greenland will adopt and diligently
enforce local limits which address at least the same pollutant
parameters and are at least as stringent as the local limits
enacted by Fayetteville. If any revisions or additions are
made to Fayetteville's local limits, Fayetteville will forward
to Greenland a copy of any such revisions or additions to the
local limits within 10 business days of enactment thereof.
Greenland agrees to adopt any revisions or additions made to
Fayetteville's local limits within 30 business days.
6
•
cl Implementation of
designates Fayetteville as
purposes of implementation
sewer use ordinance against
System.
Greenland Ordinance; Greenland
the agent of Greenland for the
and enforcement of Greenland's
users connected to the Greenland
Fayetteville, on behalf of and as an agent for Greenland will
perform technical and administrative duties necessary to
implement and enforce Greenland's sewer use ordinance.
Fayetteville will: (1) update the industrial waste survey; (2)
issue permits to all users required to obtain a permit; (3)
conduct inspections, sampling, and analysis; (4) take all
appropriate enforcement action as outlined in the enforcement
response plan; and (5) perform any other technical or
administrative duties the parties to this agreement deem
appropriate.
Fayetteville may, as an agent of Greenland, take emergency
action to stop or prevent any discharge which presents or may
present an imminent danger to the health or welfare of humans,
which reasonably appears to threaten the environment, or which
threatens to cause interference, pass through, .or sludge
contamination..
d) Pretreatment Program Costs: Fayetteville will be
responsible for all costs (including labor, equipment,
attorney's fees, etc.) incurred in implementing and enforcing
Greenland's sewer use ordinance on behalf of Greenland. In the
event of- a lawsuit relating to the implementation or
enforcement of the pretreatment program in Greenland, the City
of Fayetteville shall be responsible for the defense of its
interest only. The City of Greenland will be responsible for
attorneys and other professional expertise that may be
required to defend it's interest.
Nothing in this paragraph should be construed to mean that
Fayetteville will not work with Greenland in every way
possible in the event of a lawsuit, nor does it prohibit the
combining of legal forces by Fayetteville and Greenland in the
defense of a lawsuit as long as the cost sharing of such a
defense is agreed upon beforehand.
el Outside Greenland Dischargers: No industrial user
outside the limits of the City of Greenland shall be allowed
to tie on to the Greenland System.
fl Arbitration of Disputes: Any disputes arising out of
this Contract concerning pretreatment issues will be submitted
to non-binding arbitration performed in accordance with the
rules of the American Arbitration Association. A decision
reached in arbitration will in no way limit Fayetteville's or
Greenland's power to enforce requirements directly against
7
•
•
users located in Greenland, nor will it preclude Fayetteville
or Greenland from seeking other remedies including, but not
limited to, specific performance.
q1 Review of Pretreatment Agreement: The portion of this
Contract dealing with industrial pretreatment will be reviewed
and revised to ensure compliance with the Federal Clean Water
Act (42 U. S. C. para. 1251 et seq.) and all rules and
regulations (see 40 CFR Part 403) issued thereunder as
necessary, but at least every (2) years.
17. LIABILITY: Fayetteville shall not be responsible for
damages resulting from acts of God, acts of war, insurrections or
rebellions, acts of a public enemy, acts of any unauthorized
persons, firms or corporations, or acts of Greenland or its agents
or employees.
18. TAXES PROHIBITED: Greenland will not during the period of
this contract or any renewal thereof levy any franchise tax,
occupation tax, or any other tax of any form whatsoever, by
whatever name it may be called, upon Fayetteville or the services
rendered pursuant to this contract without consent of all the
parties.
19. TERMINATION OF CONTRACT: This agreement may be
terminated by either party upon breach by the other of any of the
covenants or agreements contained herein, and the failure of the
party in breach to remedy such breach within thirty (30) days after
receipt of written notice of the existence of such breach.
20. OPTION TO RENEW CONTRACT: Greenland shall have the option
to renew this contract upon the same terms and conditions contained
herein for a period of fifteen (15) years by giving not less than
six months written notice of same in advance of the termination
date of this contract. Fayetteville shall notify Greenland within
one year.
21. NOTICES: The written notices provided for herein shall
be sufficient if sent by certified mail, return receipt requested,
postage prepaid, to the Mayor of the City of Fayetteville,
Arkansas, or the Mayor of the City of Greenland, Arkansas, but not
limited thereto.
22. SEVERABILITY: Should
null and void or rescinded by
the remaining terms of this
enforceable.
any term of this Agreement be held
a court of competent jurisdiction,
Agreement will be unaffected and
8
•
•
•
•
•
IN WITNESS WHEREOF, Fayetteville and Greenland have executed
these presents by their respective Mayors and have caused their
seals to be hereunto affixed and same attested to by the City Clerk
and City Recorder, having been authorized to do so by appropriate
resolution of their respective governing bodies.
CITY OF FAYETTEVILLE CITY OF GREENLAND
/��� ��//�//i
Fr Hanna, Mayor
ATTEST:
9
Roy 9hrrett, Mayor
ATTEST: MS
City Clerk
•
•
•
EXHIBIT "A"
GREENLAND SEWER RATES
Greenland Sewer Rates shall be as set forth in Section 51.137
of the Fayetteville Code of Ordinances and as may be modified from
time to time. The Quantity Charge and the Monthly Service Charge
(5/8" Meter) are:
QUANTITY CHARGE
MONTHLY SERVICE CHARGE
(5/8" Meter)
AS OF 01/01/93 BEGINNING 1/1/94
$ 4.08 $ 4.41
6.59 7.12
•
•
•
EXHIBIT "B"
GREENLAND PLUMBING PERMIT FEES
AS OF NOVEMBER, 1993
1. One (1) Fixture $ 12.00
2. Two (2) Fixtures 18.00
3. Three (3) Fixtures 24.00
4. Four (4) Fixtures 26.00
5. Five (5) Fixtures 28.00
6. Six (6) Fixtures 30.00
7. Seven (7) Fixtures 32.00
8. Additional Fixtures 0.75
9. Concrete Floor 10.00
10. Re -inspection Fee 10.00
The fees as shown are current charges and may be modified from