Project or Item Added/Increased:
$800,000 is requested in the Gregg- Fulbright to
Township ROW project to meet the needs of the AHTD
due to the actual project costs
Project or Item Deleted/Reduced:
$587,900 from the Street ROW/Intersection/Cost Sharing
capital project.
$212,100 from the Street Bond Program.
Justification of this Increase:
The Arkansas Highway & Transportation Department
has requested additional funding from the City for the
Gregg Avenue project due to the actual construction
costs.
Justification of this Decrease:
Excess funds available from the
Street/ROW/Intersection/Cost Sharing project. The Street
Bond Program identified $8.8 million dollars to be spent on
cost shares for street projects not contained in the
program.
Account Name
Increase Expense Budget (Decrease Revenue Budget)
Account Number Amount
Street improvements 4470 9470
Account Name
5809 00
Project Number
800,000 04010 1
Decrease Expense Budget (Increase Revenue Budget)
Account Number Amount
Street improvements 4470 9470
Trans from Transportation Bond 4470 0947
Project Number
5809 00 587,900 02116
6602 52 212,100 04010
Approval Signatures
Requested Bry Date
Budget Manager
Date
Department Director Date
LiLk
Finance & Intern
Mayor
10 ^14•200L
Date
/043A
Date
Budget Office Use Only
Type: A B C /D) E
Posted to General Ledger
Posted to Project Accounting
Entered in Category Log
Initial Date
Initial Date
Initial Date
Ron Petrie
Submitted By
City of Fayetteville
Staff Review Form
City Council Agenda Items
or
Contracts
Oef�q
Noverader7, 2006
City Council Meeting Date
Engineering
Division
Action Required:
lD/1�%dk
RIO/ 6 rtii
matt 06,05
Operations
Department
Approval of a payment in the amount of $800,000.00 to the Arkansas Highway and Transportation Department for
the widening of Gregg Avenue between Township Road and the Fulbright Expressway and approval of a budget
adjustment.
800,000.00
Cost of this request
4470.9470.5809.00
Account Number
360,000.00
Category / Project Budget
331,177.00
Funds Used to Date
04010 $ 28,823.00
Project Number
Budgeted Item
•
Remaining Balance
Budget Adjustment Attached
X
Gregg - Fulbright to Township ROW
Program Category / Project Name
Street Improvements
Program / Project Category Name
Sales Tax -Capital Improvements
Fund Name
Departmen Director
r
c
City Attorney
• L
Finance and Internal Service Director
Mayor
Ib • I1.0k,
Date
10t4 -o(,
Date
10 -19 -ob
Date
ate
Previous Ordinance or Resolution #
Original Contract Date:
Original Contract Number:
Received in City
erk's c
EN RED
ffice
Received in Mayor's Office
Comments:
Ittv?1e
ARKANSAS
City of Fayetteville
Engineering Division
113 West Mountain
Fayetteville, AR 72701
ph: 479-575-8206
fax: 479-575-8202
Date: October 20, 2006
To: Fayetteville City Council
Thru: Dan Coody, Mayor
Gary Dumas, Director of Operations
From: Ron Petrie, City Engineer
Subject: Approval of a payment in the amount of $800,000 to the Arkansas
Highway and Transportation Department for the widening of Gregg
Avenue between Township Road and the Fulbright Expressway and
approval of a budget adjustment.
RECOMMENDATION:
As approved by the Street Committee on October 5, 2006, staff recommends approval of
a payment in the amount of $800,000 to the Arkansas Highway and Transportation
Department (AHTD) for the widening of Gregg Avenue from Township Road to the
Fulbright Expressway and the associated budget adjustment.
BACKGROUND:
The City Council approved an agreement with the AHTD on August 7, 2001 to allow for
the widening of Gregg Avenue (State Hwy 180) between Township Road and Fulbright
Expressway. The agreement required the City to pay for all utility relocation costs, right-
of-way costs, widen Township Road from Gregg to North College Avenue, and take over
ownership of both Gregg Avenue and Township Road after completion.
Since the agreement was approved, the City has spent $1,448,092 for utility relocations
and right of way acquisition. The Engineering Division is currently completing design of
the Township Road widening and right-of-way acquisition has begun.
DISCUSSION:
The AHTD had bid the Gregg Avenue widening project on three different occasions and
rejected all bids due to the costs. This was also done for a project in the City of Rogers
(Horsebam Road). The AHTD contacted both the City of Fayetteville and the City of
Rogers requesting additional assistance in order to proceed with these projects.
According to the AHTD, the City of Rogers agreed to pay up to fifty percent of the
construction costs. The City of Fayetteville proposed to pay an additional $800,000
pending City Council approval in order to proceed with the Gregg Avenue project. In
addition the Township Road widening would occur after ownership is transferred to the
City. This proposal was presented and approved by the Street Committee on August 8
and October 5, 2006.
The AHTD has since re -bid the Gregg Avenue widening project a fourth time and
received a low bid in the amount of $6.49 million from McClinton -Anchor APAC. This
was less than the previous low bid of $6.49 million.
BUDGET IMPACT:
The Street Committee recommended that the funds for this $800,000 payment come from
two sources. The first is to utilize the remainder of the CIP funds in the Street
ROW/Intersection/Cost Share Project account which has a remaining balance of
$587,900. In addition, the remaining $212,100 is recommended to come from the Street
Bond program. The program set $8.8 million to go towards cost shares and right-of-way
acquisition for street projects not contained in the program. It is anticipated that cost
savings from the Township Road project could possibly reimburse these funds at a later
date.
RESOLUTION NO.
A RESOLUTION TO APPROVE AN ADDITIONAL PAYMENT
OF EIGHT HUNDRED THOUSAND DOLLARS ($800,000.00)
TO THE ARKANSAS HIGHWAY AND TRANSPORTATION
DEPARTMENT FOR THE WIDENING OF GREGG AVENUE
BETWEEN TOWNSHIP AND I-540 AND TO APPROVE A
BUDGET ADJUSTMENT OF $800,000.00 TO FUND THIS
PAYMENT
WHEREAS, the construction contract to widen Gregg Avenue from Township to
I-540 has been more expensive (about $6.5 million) than anticipated by the Arkansas
Highway and Transportation Department (AHTD); and
WHEREAS, the City Council Street Committee has agreed to recommend an
additional $800,000.00 be paid to the AHTD to help fund this construction contract to be
funded from the Cost Share and Bond program.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF
THE CITY OF FAYETTEVILLE, ARKANSAS*
Section 1. That the City Council of' the City of Fayetteville, Arkansas hereby
approves the payment of an additional Eight Hundred Thousand Dollars ($800,000 00) to
the Arkansas Highway and Transportation Department to help fund the $6.5 million
dollar construction contract to widen Gregg Avenue from Township to I-540.
Section 2. That the City Council of the City of Fayetteville, Arkansas hereby
approves the budget adjustment attached as Exhibit A in the amount of $800,000.00 to
fund the payment to the Arkansas Highway and Transportation Department.
PASSED and APPROVED this 19th day of October, 2006.
APPROVED:
By: By:
DAN COODY, Mayor SONDRA SMITH, City Clerk
ATTEST.fC
t
O*
(10.24.06)' Clarice Pearman - Res: 174-06
Page 1
From:
To:
Date:
Subject:
Attachments:
Clarice Pearman
Petrie, Ron
10.24.06 12:48 PM
Res 174-06
174-06 AHTD-Gregg Ave.pdf
CC: Audit; Fell, Barbara
Ron,
Attached is a copy of the above resolution passed by City Council, October 17, 2006 regarding AHTD and the Gregg
Avenue. I will forward to Budget & Research your budget adjustment via interoffice mail. If anything else is needed
please let me know.
Thanks.
Clarice
•
RESOLUTION NO. 174-06
A RESOLUTION TO APPROVE AN ADDITIONAL
PAYMENT OF EIGHT HUNDRED THOUSAND
DOLLARS ($800,000.00) TO THE ARKANSAS
HIGHWAY AND TRANSPORTATION DEPARTMENT
FOR THE WIDENING OF GREGG AVENUE
BETWEEN TOWNSHIP AND I-540 AND TO APPROVE
A BUDGET ADJUSTMENT OF $800,000.00 TO FUND
THIS PAYMENT
WHEREAS, the construction contract to widen Gregg Avenue from Township to
I-540 has been more expensive (about $6.5 million) than anticipated by the Arkansas
Highway and Transportation Department (AHTD); and
WHEREAS, the City Council Street Committee has agreed to recommend an
additional $800,000.00 be paid to the AHTD to help fund this construction contract to be
funded from the Cost Share and Bond program.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF
THE CITY OF FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby
approves the payment of an additional Eight Hundred Thousand Dollars ($800,000 00) to
the Arkansas Highway and Transportation Department to help fund the $6.5 million
dollar construction contract to widen Gregg Avenue from Township to I-540.
Section 2: That the City Council of the City of Fayetteville, Arkansas hereby
approves the budget adjustment attached as Exhibit A in the amount of $800,000.00 to
fund the payment to the Arkansas Highway and Transportation Department.
PASSED and APPROVED this 19th day of October, 2006.
APPROV 1: ATTEST:
By
DAN COODY "ayor
„C6KR1Sri•
��G:G\SY�opLp,A0•
•=
:FAYETTEVILLE:
4) SPSJam/
19J'iKAN
By: ®u-�c'`�cror�°.�`�`.
SONDRA SMITH, City Clerk 'lia,,,,,,,u+"`
1-