RESOLUTION NO. 150-05
A RESOLUTION APPROVING A CHANGE ORDER TO THE
CONTRACT WITH KING ELECTRICAL CONTRACTORS, INC.
IN THE AMOUNT OF $60,000.00 FOR ELECTRICAL UTILITY
RELOCATION ASSOCIATED WITH THE MOUNTAIN INN
PROJECT; AND ACCEPTING THE PROMISE OF EAST SQUARE
DEVELOPMENT COMPANY, LLC TO REIMBURSE THE CITY OF
FAYETTEVILLE IN AN AMOUNT NOT TO EXCEED $60,000.00.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1. That the City Council of the City of Fayetteville, Arkansas
hereby approves a Change Order to the contract with King Electrical
Contractors, Inc. in the amount of $60,000.00 for electrical utility relocation
associated with the Mountain Inn Project.
Section 2. That the City Council of the City of Fayetteville, Arkansas
hereby accepts and relies upon the promise of East Square Development
Company, LLC to reimburse the City of Fayetteville in an amount not to exceed
$60,000.00.
PASSED and APPROVED this 2nd day of August 2005.
ATTEST:
. S
•tV••c�a
E :FAYETTEVILLE:
;GTON G3%•`‘
aauuuua.
By:/Z JOVlo1.aJ y -Ev
SONDRA SMITH, City Clerk
APPROVE
By
fait A
DAN COODY, Mayor
• •
CHANGE ORDER
CITY OF FAYETTEVILLE
PROJECT: Mountain Inn Utility Reroute
CONTRACTOR:
Austin King, Inc.
2145 West Moore Lane
Fayetteville, Arkansas 72704
CHANGE ORDER NUMBER: 1
DATE• August 1, 2005
CHANGE ORDER AMOUNT: not to exceed $60,000.00
Signatures:
Contractor: Austin King, Inc.
2145 West Moore Lane
Fayetteville, Arkansas 72704
Date:
City of Fayetteville
113 West Mountain Str
Fayetteville, Arkansas
Date
•
• •
EAST SQUARE DEVELOPMENT COMPANY, LLC
11 N. WEST AVENUE
FAYETTEVILLE, AR 72701
(479) 521-9188
July 12, 2005
To Whom It May Concern.
In order to facilitate the continuing progress of the Mountain Inn Project, the undersigned
agree to pay up to $60,000 for electrical utility relocation above and beyond the $877,000
previously earmarked for demolition and utility relocation. Said money to be paid by increasing
the purchase price of the Mountain Inn property.
Sinc
Ric'' d P. Alexan... Member
FAYETTEVItLE
THE CITY OF FAYETTEVILLE. ARKANSAS
DEPARTMENTAL CORRESPONDENCE
•
i -r0
iso
/4 64 eines I
MEMORANDUM
TO: The Fayetteville City Council
THROUGH: Mayor Dan Coody
FROM: Stephen Davis, Finance and Internal Services Directo,_
Coy Hurd, Project Manager
DATE: July 14, 2005
RE: Electrical Relocation at the Mountain Inn site
Recommendation
Staff recommends that City Council approve a S60,000 Change Order to King Electrical
Contractors for the Mountain Inn Project. It is imperative to the success of the project
that the electrical relocation work continues to progress. We recommend that the City
accept the Developers' proposal for rcimbursement.
Discussion
On Junc 21, 2005, the Fayetteville City Council agreed to the action of increasing the
amount of work that King Electrical Contractors could be authorized to do regarding the
relocation of the electrical lines allowing the demolition of the Mountain Inn and adjacent
buildings. King's ceiling (according to his existing on-call contract with the City) is
S20,000 per project. This action by the City Council allowed the electrical relocation
work to move forward by expanding the ceiling to $100,000 for the Mountain Inn Project
only.
This limitation was communicated to Chris King (of King Electrical Contractors) on Junc
22. On July 8, a telephone call was placed to Chris King to discuss several matters
relative to the project. He had just been in contact with his subcontractor, Fayette Tree
and Trench, who is trenching at the site to allow for installation of underground conduit.
As reported to the City Council on July 12, Mr. King related that the cost of the trenching
had exceeded expectations due to the complications uncovered once actual trenching had
started. He related that the cost of all electrical relocation work to date was $104,540,
and was now expected to rise to near $ 160,000. Mr. King was instructed to prepare to
stop work on the site, as his $100,000 ceiling had been exceeded.
• •
Memo of 7/14, page two
This is a critical juncture for the project. If progress on the demolition is to be
maintained, the electrical transclosurc must be moved out of the way. Funds arc
available to pay this cost and reside in the project's contingency fund. The constraint that
must be accommodated is the $100,000 cap set on King Electrical Contractors' work.
This cost information was communicated to the Developers, and they have requested that
City continue this phase of the work uninterrupted. The Developers have agreed to
increase the purchase price of the land to reimburse for all electrical relocation costs
above the amount of $100,000 already authorized. This commitment was communicated
verbally by Mr. Richard Alexander to Stephen Davis (on July 11, 2005). Written
confirmation of this commitment has been attached to this memorandum. If the funds
presently residing in the contingency are not fully utilized for other unforeseen items,
they would be used toward paying these costs in lieu of the Developers having to pay.
• •
RESOLUTION NO.
A RESOLUTION APPROVING A CHANGE ORDER TO THE
CONTRACT WITH KING ELECTRICAL CONTRACTORS, INC.
IN THE AMOUNT OF $60,000.00 FOR ELECTRICAL UTILITY
RELOCATION ASSOCIATED WITH THE MOUNTAIN INN
PROJECT; AND ACCEPTING THE PROMISE OF EAST SQUARE
DEVELOPMENT COMPANY, LLC TO REIMBURSE THE CITY OF
FAYETTEVILLE IN AN AMOUNT NOT TO EXCEED $60,000.00.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1. That the City Council of the City of Fayetteville, Arkansas
hereby approves a Change Order to the contract with King Electrical
Contractors, Inc. in the amount of $60,000.00 for electrical utility relocation
associated with the Mountain Inn Project.
Section 2. That the City Council of the City of Fayetteville, Arkansas
hereby accepts and relies upon the promise of East Square Developme t
Company, LLC to reimburse the City of Fayetteville in an amount no -Coe,d
$60,000.00.
PASSED and APPROVED this 2nd day of Augti-st 005. I
APPROVED:.- 1
lL
DANT 9DY, Mavor
• •
CHANGE ORDER
CITY OF FAYETTEVILLE
PROJECT: Mountain Inn Utility Reroute
CONTRACTOR:
Austin King, Inc.
2145 West Moore Lane
Fayetteville, Arkansas 72704
CHANGE ORDER NUMBER: 1
DATE: August 1, 2005
CHANGE ORDER AMOUNT: not to exceed 560,000.00
Signatures:
Contractor: Austin King, Inc.
2145 West Moore Lane
Fayetteville, Arkansas 72704
Date:
City of Fayetteville
113 West Mountain Street
Fayetteville, Arkansas 72701
Date
Coy Hurd
Submitted By
• City of Fayetteville •
Staff Review Form
z -roc. -05
21 L 5 -
City Council Meeting Date
Building Services
Division
Action Required:
Financial and Internal Services
Department
The required action is a resolution to designate $60,000 toward the permanent utility placement work associated with
the construction of the new hotel to occupy the existing Mountain Inn site, and permission to exceed the $100,000
limit on King Electric's contract for this project. Further action required is to accept the Developers' proposal for
reimbursement to the City.
Developer pay ($60,000)
Expense $60,000
Cost of this request
4490 9490 5315.00
Account Number
05038.2
Project Number
Budgeted Item
XX
887,000.00
Cat
epory/Project Budget
$887,000.00
Funds Used to Date
0
Remaining Balance
Budget Adjustment Attached
Hwy 71 East Square
Redevelopment District #1
Program Category / Project Name
Other Improvements
Program / Project Category Name
TIF Capital Improvement Fund
Fund Name
partrient Director
Previous Ordinance or Resolution # 9716
Date Original Contract Date:
Original Contract Number.
c 9 (' r/,r//,
City Attomey 1
inane= and Internal Service Director
Mayor
0
L
Date
7/Lck
Date
Comments:
Clarice Pearman -King Electrical __ .. ��
• _.
Page 1
From: Clarice Pearman
To: Hurd, Coy
Subject: King Electrical
Coy,
The City Council passed a resolution approving a change order for King Electric for the Mountain Inn
Project. I do not have a signed change order to attach to the resolution. Please get me a signed change
order to continue the processing of this resolution.
Thanks.
Clarice
Clarice Pearrnan - Res. 150105 -
From: Clarice Pearman
To: Hurd, Coy
Subject: Res. 150-05
Coy,
Attached is a copy of the resolution passed by City Council August 2. 2005.
Thanks.
Clarice