HomeMy WebLinkAbout125-05 RESOLUTION• •
RESOLUTION NO. 125-05
A RESOLUTION AWARDING A CONSTRUCTION CONTRACT TO
T -G EXCAVATING, INC. IN THE AMOUNT OF $144,444.00 FOR
THE FARMINGTON SANITARY SEWER SYSTEM MANHOLE
REHABILITATION; AND APPROVING A 10% PROJECT
CONTINGENCY IN THE AMOUNT OF $14,444.00
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS•
Section 1: That the City Council of the City of Fayetteville, Arkansas, hereby
awards a construction contract to T -G Excavating, Inc. in the amount of $144,444.00 for
the Farmington Sanitary Sewer System Manhole Rehabilitation.
Section 2: That the City Council of the City of Fayetteville, Arkansas, hereby
approves a 10% project contingency in the amount of $14,444.00.
PASSED and APPROVED this 5'h day of July, 2005.
VT46zis:
F ••Ps CIc^?
.U• 6.131:
:FAYETTEVILLE•
;17 15KAt45P�$
ATTEST: •'!/APGTON CO'
"anu,wu"
BY: a,
•
SONDRA SMITH, City Clerk
1
1
3
1
1
1
• •
CITY OF FAYETTEVILLE, ARKANSAS
AGREEMENT
SANITARY SEWER MANHOLE REHABILITATION
THIS AGREEMENT, made this 5I day of 1411
the City of Fayetteville, Arkansas, a municipal corporation and
T G E e.thArt�; T�tC,. hereinafter referred to as Contractor.
2005, by and between
WITNESSETH:
WHEREAS, the City of Fayetteville has heretofore solicited Bids for all the work and
improvements for the doing of all things included within the hereinafter specified Manhole
Rehabilitation in the Farmington Sanitary Sewer System.
WHEREAS, the City of Fayetteville did on the 54k-__ day of July , 2005 find that
the Contractor was the lowest responsive, responsible Bidder for the hereinafter specified work
and did award the Contractor a Contract for said work.
NOW, THEREFORE, for and in consideration of their mutual promises, covenants, undertaking
and agreements, the parties do hereby agree as follows:
ARTICLE I - WORK TO BE DONE BY CONTRACTOR
The Contractor agrees, at its own cost and expense, to do all the work and to furnish all the labor,
materials, equipment and other property necessary to do, construct, install and complete all the
works and improvements included in the Manhole Rehabilitation in the Farmington Sanitary
Sewer System. All in full accordance with and in compliance with and as required by the
hereinafter specified Contract Documents and any addenda for said work, and to do, at his own
cost and expense, all other things required of Contractor by said Contract Documents for said
work.
ARTICLE II - CONTRACT DOCUMENTS
The Contract Documents arc defined in the General Conditions.
1
Agreement
City of Fayetteville
Sewer System improvements
1
1
1
1
1
Po
• •
ARTICLE ill - CONTRACT AMOUNT
The Contractor agrees to receive and accept the attached contract unit prices and/or lump sum
prices as full compensation for furnishing all materials and equipment for doing all the work
contemplated and embraced in this Agreement; also for all loss or damage arising out of the
nature of the work aforesaid, or from the action of the elements, or from any unforeseen
difficulties or obstructions which may arise or be encountered in the prosecution of the work
until its acceptance by the City of Fayetteville, and for all risks of every description connected
with the work; also for well and faithfully completing the work, and the whole thereof, in the
manner and according to and in compliance with the Contract Documents and the requirements
of the Engineer under them, also for any and all things required by the Contract Documents.
ARTICLE IV - LIQUIDATED DAMAGES OR ACTUAL DAMAGES AND EXCESS
ENGINEERING COSTS
The Contractor shall, and agrees to, pay to excess engineering as described in the General
Conditions.
The Contractor shall, and agrees to, pay for liquidated damages or actual damages if Contractor
fails to complete the project within the specified time in accordance with the General Conditions.
ARTICLE V - STARTING AND COMPLETION
The Contractor agrees to commence work under this Agreement within ten calendar days of
receipt of written Notice to Proceed and to complete all work included in this Contract to the
point of substantial completion no later than 90 Calendar Days from the date of Notice to
Proceed. The Contractor further agrees to complete all work to the point of final acceptance by
the City of Fayetteville no later than 110 Calendar Days from the date of Notice to Proceed.
The Contractor shall, and agrees to, famish and deliver to the City of Fayetteville, the Faithful
Performance Bond, the Contractor's Labor and Material Bond, the Maintenance Bond and the
insurance certificates and policies of insurance required of him by provisions of the Contract
Documents, and to do, prior to starting work, all other things which are required of him by the
Contract Documents as a prerequisite of starting work.
ARTICLE VI - PAYMENTS TO CONTRACTOR
The City of Fayetteville agrees with said Contractor to employ, and does hereby employ, the said
Contractor to provide the materials and do all the work, and do all other things hereinabove
contained or referred to, for the prices aforesaid, and hereby contracts to pay the same at the
time, in the manner and upon the conditions set forth or referred to in the Contract Documents;
and the said parties for themselves, their heirs, executors, administrators, successors and assigns,
do hereby agree to the full performance of the covenants herein contained.
Ihcre shall be no measurement or separate payment for any items not listed and all costs
pertaining thereto shall be included in the Contract unit prices for other items listed.
Agreement
City of Fayetteville
Sewer System Improvements
2
• •
ARTICLE VII — CHANGES TO CONTRACT
Changes, modifications or amendments to this contract shall he valid when approved in advance
using an appropriate written document (change order) describing the nature and intent of the
change. Such authorization shall be executed by duly authorized representatives of the
contracting parties. Material changes in contact costs, shall require approval by the Fayetteville
City Council and Mayor, with a material change being defined as one whose cost increase results
in the total contract amount exceeding the funding allocated for the project construction (base bid
plus construction contingency).
ARTICLE VIII — FREEDOM OF INFORMATION ACT
City contracts and documents prepared while perfbrming City contractual work are subject to the
Arkansas Freedom of Information Act (FOIA). If a Freedom of Information Act request is
presented to the CITY OF FAYETTEVILLE, the Contractor will do everything possible to
provide the documents in a prompt and timely manner as prescribed in the Arkansas Freedom of
Information Act (A.C.A. §25-19-101 et seq.). Only legally authorized photocopying costs
pursuant to the FOIA may be assessed for this compliance.
IN WITNESS WHEREOF, the parties hereto have caused this instrument to be executed in three
original counterparts the day and year first above written.
(SEAL)
I G rxe.AVA-htnq,�.aG
(Contractor)
Attest:
Name
RR 11. AIME, Name SAA/DRR X. f/LRR,Mb,
(please type)
case type)
Title Sift/2E6;41,
(SEAL)
Attest
Title RES/DENT
CITY OF F/AY TTEVILLE AR
By A i1�( 4n/i/
Name c--cQndra c�/h /' Name Dan good
n (please type) (please t
Title 0:46j epak/Sa.OtUvm„
Title
3
,
e
heir
Agreement
City of Fayetteville
Sewer System Improvements
1V
1
'1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
�s. gas -as _.
May 2005
Contract
Documents
City of Fayetteville
Manhole Rehabilitation in the
Farmington Sanitary Sewer System
Prepared for the
City of Fayetteville
Fayetteville, Arkansas
prepared by
RJN Group, Inc.
Consulting Engineers
Dallas, Texas
QOp ARI AS o
04� 't+r-.* Itt tz
REGISTERED 0
® PROFESSIONAL p
Z
ENGINEER g
e is * %t y Bab
o�' No.11277 5r a0
cygEL G•Mcaaa
"eiiitgs/1 0/04-
CONTRACT DOCUMENTS
CITY OF FAYETTEVILLE
MANHOLE REHABILITATION IN THE
FARMINGTON SANITARY SEWER SYSTEM
CITY OF FAYETTEVILLE
FAYETTEVILLE, ARKANSAS
MAY 2005
I hereby state that these Contract Documents were prepared under
my direct supervision and that I am a duly Registered Professional
Engineer under the laws of the State of Arkansas.
Date: /I0/'oST
Registration No. //Z77 ,m
ge�Ei1
gFn.
a®
se ARI AN A
S
"til
% Ba /e
• REGISTERED
PROFESENGISIONAL
d(o70";
%e�"c No. 11277 ay -p0
o4-494EL G•M%Yl
.•.iii.<.
1�
1
1
Il
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
TITLE
CONTRACT DOCUMENTS
FOR THE
CITY OF FAYETTEVILLE
SEWER SYSTEM IMPROVEMENTS
TABLE OF CONTENTS
SECTION Pages
BIDDING DOCUMENTS A
INVITATION TO BID I-2
INSTRUCTIONS TO BIDDERS' 1-10
# BID 1-10
# BID BOND 1-2
# BONDING COMPANY INFORMATION 1
# SUBCONTRACTORS 1
# STATEMENT OF EXPERIENCE OF BIDDER 1
# STATEMENT OF COMMITMENT 1
CONTRACTUAL DOCUMENTS B
AGREEMENT 1-3
ARKANSAS STATUTORY PERFORMANCE AND PAYMENT BOND I-2
MAINTENANCE BOND 1
CONDITIONS OF THE CONTRACT
GENERAL CONDITIONS*
SUPPLEMENTARY CONDITIONS
C
CI
CONSTRUCTION FORMS D
1-65
1-3
SUBMITTAL RECORD I
PERIODIC PAYMENT FORMS 1-5
CHANGE ORDER 1-3
CONSTRUCTION LETTER 1
* Section has individual Table of Contents.
# Items to be included in bid package.
CITY OF FAYETTEVILLE
INVITATION TO BID
SANITARY SEWER MANHOLE REHABILITATION
RECEIPT OF BIDS
Separate sealed bids for Sanitary Sewer Manhole Rehabilitation, in Farmington, Arkansas are
invited and will be received at the office of the Purchasing Officer located at 113 W. Mountain,
Fayetteville, Arkansas, 72701 on or before, but no later than 2:00 PM , Local Time, on
May 31, 2005. Immediately thereafter, or as soon thereafter as is practicable, all bids received
from contractors will be publicly opened and the bid prices read aloud.
Rehabilitaion of 15 manhole covers and frames, interior coating of approximately 10 manholes,
sealing of 120 manhole frames and grade adjustments, and installation of 240 watertight inserts..
Sealed envelopes or packages containing bids shall be marked or endorsed "City of Farmington
Sanitary Sewer Manhole Rehabilitation" and the Contractor's License Number and "Project
Bid No. " shall be clearly marked on the outside of the envelope.
CONTRACT DOCUMENTS
Copies of the Contract Documents are on file and are available for inspection at the offices of
McClelland Consulting Engineers, Inc., 1810 N. College Avenue, Fayetteville, Arkansas.
Said Contract Documents are by this reference incorporated into and made a part of this
Invitation to Bid and should be consulted for full particulars.
Copies of the Contract Documents required for review or bidding purposes may be obtained only
from the Office of McClelland Consulting Engineers, Inc., 1810 N. College Avenue, Fayetteville,
Arkansas, upon payment to McClelland Consulting Engineers, Inc., 1810 N. College,
Fayetteville, Arkansas, of 550.00 in check or money order for each set of documents obtained.
The Contract Document fee is non-refundable.
BID SECURITY
Each bid shall be accompanied by a certified check or a cashier's check or bid bond payable to
the order of the City of Fayetteville, Arkansas in an amount not less than five percent of the bid
as a guarantee that the bidder will, within ten (10) days after the date of the award of contract,
execute an agreement and file bonds and insurance as required by the Contract Documents if his
bid is accepted.
1
Invitation to Bid
City of Fayetteville
Sanitary Sewer Improvements
RIGHT TO REJECT BIDS
The City of Fayetteville reserves the right to reject all bids for failure to comply with all
requirements of this notice including pre -qualification or any of the Contract Documents;
however, the City of Fayetteville may waive any minor defects or informalities at its discretion.
The City of Fayetteville reserves the right to defer the acceptance of any bid and the execution of
a contract for a period not exceeding ninety (90) days after the date of opening of bids.
Extension of time beyond the ninety (90) day period after the date of opening of bids may be
made only by mutual agreement between the City of Fayetteville, the successful bidder and the
Surety for the successful bidder.
AWARD OF CONTRACT
Unless all bids are rejected the contract award will be made to the responsible, responsive Bidder
who submits the low bid. In determining who is the lowest responsive, responsible bidder, the
City of Fayetteville will consider all relevant factors which the City of Fayetteville may consider
in determining who is the lowest responsive, responsible bidder.
Any bid may be modified or withdrawn prior to the above scheduled time for the opening of bids.
No bidder may withdraw a bid within 90 days after the actual date of the opening thereof.
The successful bidder shall furnish a performance bond, labor and material bond, and a
maintenance bond each for one hundred (100%) percent of the Contract amount and shall file
certificates with the City of Fayetteville that he has obtained and will continue to carry
Workmen's Compensation Insurance, City of Fayetteville's and Engineer's Protective Insurance,
public and private liability and property damage insurance in adequate amount and for the life of
the Contract.
All questions or correspondence concerning the plans and specifications shall be directed to
Michelle Speaker, P.E., at the office of the Engineer, RJN Group, Inc., 12160 Abrams Road,
Suite 400, Dallas, Texas 75243, phone no. (817) 595-2199.
City of Fayetteville, Arkansas
Peggy Vice
Purchasing Officer
Publication:
P.O. m
Invitation to Bid
City of Fayetteville
Sanitary Sewer Improvements
2
1
1
1
1
1
1
1
1
1
1
1
1
1
TABLE OF CONTENTS
FOR
INSTRUCTIONS TO BIDDERS
SUBJECT PAGE
A EXAMINATION OF SITE 1
B EXAMINATION OF BIDDNG DOCUMENTS . 1
C INTERPRETATION OF CONTRACT DOCUMENTS 1
D MATERIAL SUBSTITUTION . 1
E APPROXIMATE QUANTITIES '?
F PREPARATION OF BID 2
G SIGNING OF BID 3
H BID SECURITY . 3
1 RETURN OF BID SECURITIES 3
J AGREEMENT, BONDS, INSURANCE 3
K DESIGNATION OF SUBCONTRACTORS 4
L BID SUBMITTAL 4
M WITHDRAWAL OF BID 4
N QUALIFICATION OF BIDDERS 4
0 DISQUALIFICATION OF BIDDERS 5
P PENALTY FOR COLLUSION 5
Q LICENSE 6
R PRECONSTRUCTION CONFERENCE 6
S BID OPENING 6
T AWARD OF CONTRACT . 6
U EFFECTIVE DATE OF AWARD 7
✓ EXECUTION OF AGREEMENT 7
W FAILURE TO EXECUTE AGREEMENT AND FILE BONDS AND INSURANCE
X PAYMENT FOR EXCESS COSTS AND LIQUIDATED DAMAGES 8
Y COMMENCEMENT AND COMPLETION OF WORK 8
Z INFORMATION NOT GUARANTEED 8
AA COVENANT AGAINST CONTINGENT FEES 9
BB GRATUITIES 9
CC SUBCONTRACTS UNDER CONSTRUCTION CONTRACTS. 10
DD PREVAILING WAGE DETERMNATION 10
INSTRUCTIONS TO BIDDERS
A. Examination of Site
Before submitting his Bid, each prospective Bidder shall familiarize himself with the
Work, the site where the Work is to be performed, local labor conditions and all laws,
regulations, and other factors affecting performance of the Work. He shall carefully
correlate his observations with the requirements of the Contract Documents and
otherwise satisfy himself of the expense and difficulties attending performance of the
Work. The submission of a Bid will constitute a representation of compliance by the
Bidder. There will be no subsequent financial adjustment for lack of familiarization.
B. Examination of Bidding Documents
Each Bidder by making his Bid represents that he has read and understands the Bidding
Documents. The Bidder shall include in his bid prices any and all costs that may be
necessary to complete the work in accordance with the requirements of the Contract
Documents.
C. Interpretation of Contract Documents
Questions regarding documents, discrepancies, omissions, or intent of the Specifications
or drawings shall be submitted in writing to the City of Fayetteville through the Engineer,
at least three working days prior to opening of bids to provide time for issuing and
forwarding an addendum. Any interpretation of the Contract Documents will be made
only by addendum duly issued or delivered by the City of Fayetteville to each person
receiving a set of documents. The City of Fayetteville will not be responsible for any
other explanations or interpretations of the Contract Documents.
D. Material Substitution
Each Bidder shall base his Bid upon the materials and equipment as described in the
Bidding Documents. The successful Contractor will not be allowed to make any
substitutions on his own initiative, but in each instance will be required to obtain
authorization from the City of Fayetteville before installing any work in variance with
requirements of the Contract Documents.
1
Instructions to Bidders
City of Fayetteville
Sanitary Sewer Improvements
E Approximate Quantities
On all items on which Bids are to be received on a unit price basis the quantities stated in
the Bid will not be used in establishing final payment due the Contractor. The quantities
stated, on which unit prices are invited, are approximate only. Bids will be compared on
the basis of number of units stated in the Bidding Schedule. Payment on the Contract on
unit price items will be based on the actual number of units installed in the completed
work.
F. Preparation of Bid
All prospective bidders and proposed subcontractors on this contract must demonstrate
that they have comparable experience in this type of work for their bid to be considered
responsive. Each bidder and subcontractor must show evidence of having successfully
completed a minimum of three manhole rehabilitation contracts with construction cost of
at least $100,000 each during the last three years. The Contractors may use
subcontractors that do not have the three previous manhole rehabilitation project
experience for construction of new manholes only.
Bids submitted by prospective bidders who do not show demonstrated qualifications will
be considered nonresponsive and will be rejected:
Only bids which are made out on the Bid Form included in this document will be
considered. The Bid Form must not be separated from this document. Amounts are to be
shown in both words and figures where indicated In case of discrepancy between words
and figures the words shall prevail, unless it clearly appears in City of Fayetteville's
opinion that the words rather than the figures are in error. If any portion of the Bid is
required to be given in unit prices and totals and a discrepancy exists between the unit
price and totals, the unit prices shall prevail, unless it clearly appears in City of
Fayetteville's opinion that the unit prices rather than the total are in error. If a discrepancy
exists between the total Bid and the true sum of the individual Bid items, the true sum
shall prevail. A Bid will be rejected if it does not contain a price for each and every item
named in the bidding schedule. Bidders are warned against making any erasures or
alterations of any kind, and Bids which contain omissions, erasures, conditions,
alterations, or additions not called for may be rejected. If a deficiently prepared bid is not
rejected, the City of Fayetteville may demand correction of any deficiency and award the
contract to the bidder upon satisfactory compliance with the Instructions.
Instructions to Bidders
City of Fayetteville
Sanitary Sewer Improvements
2
G. Signing of Bid
If the Bidder is a corporation, the legal name of the corporation shall be set forth together
with the signature of the officer or officers authorized to sign contracts on behalf of the
corporation. If Bidder is a co -partnership, the true name of the firm shall be set forth
together with the signatures of all the partners. If Bidder is an individual, his signature
shall be inscribed. If signature is by an agent, other than an officer of a corporation or a
member of a partnership, a power of attorney must be on file with the City of Fayetteville
prior to opening Bids or submitting Bids; otherwise, the Bid may be regarded as irregular.
H. Bid Security
No Bid will be considered unless accompanied by a Bid security as defined in the
Invitation to Bid, as a guarantee that if the Bid is accepted the Bidder will execute the
Agreement and file bonds and insurance as required by the Contract Documents within 10
days from the date of the award of the Contract. For the bid bond to be acceptable, the
name of the surety company issuing said bond shall be licensed to do business in the State
of Arkansas and shall be included on the current U.S. Treasury list of acceptable sureties
("A" rated or better), and the amount of the bond written by any one acceptable company
shall not exceed the amount shown on the Treasury list for that company. The Bidder
shall submit with Bid the Bonding Company Information Sheet as part of the Bid
Proposal.
Retum of Bid Securities
The security of the two lowest Bidders will be returned after the execution of the
agreement with the successful Bidder and the approval of his bonds and insurance. The
security of all other Bidders will be returned promptly after the Bids have been opened
and reviewed by the City of Fayetteville. If all Bids are rejected the securities wjll be
returned at the time of rejection.
J. Agreement, Bonds, Insurance
The attention of Bidders is specifically directed to the forms of agreement and bonds to
be executed and types of insurance to be taken out in the event a contract award is made.
3
Instructions to Bidders
City of Fayetteville
Sanitary Sewer Improvements
K. Designation of Subcontractors
Each bidder shall list on the form included in these documents the names and addresses
of all subcontractors who will perform work or labor or render service to the Bidder
on or about the construction site in an amount in excess of five percent of the Bidder's
total Bid. Each Bidder shall show on the form the portion of the work to be done by each
subcontractor. The Contractor shall be required to perform a minimum of thirty (30)
percent of the contract amount with his own crews.
L. Bid Submittal
1. Each Bid, properly signed, together with the Bid security and all documents bound
herewith, shall be enclosed in a sealed envelope addressed and entitled as
specified in the Invitation to Bid and delivered to the office designated in the
Invitation to Bid.
2. Each Bidder shall submit with his Bid one copy of the Contract Documents with
all Addendum and the "Subcontractors" form contained in this document. All
Subcontractors who will be doing manhole rehabilitation work must be pre-
qualified.
M. Withdrawal of Bid
Any Bid may be withdrawn at any time prior to the hour fixed in the Invitation to Bid for
the opening of Bids, provided that a request in writing, executed by the Bidder, or his
duly authorized representative, for the withdrawal of such Bid is filed with the City of
Fayetteville prior to the time specified for opening of Bids. The withdrawal of a Bid will
not prejudice the right of a Bidder to file a new Bid.
N. Qualification of Bidders
1. It is the intention of the City of Fayetteville to award a Contract only to a Bidder
who furnishes satisfactory evidence that he has the requisite experience and ability
and that he has sufficient capital, facilities, and plant to enable him to prosecute
the work successfully and promptly, and to complete the work within the time
specified in the Contract Documents.
Instructions to Bidders
City of Fayetteville
Sanitary Sewer Improvements
4
Each Bidder shall submit with his Bid the executed Bidder's "Statement of
Experience" form and "Statement of Commitment" form contained in this
document. Each bidder shall also submit documented evidence that he has, with
his own forces, completed a minimum of three manhole rehabilitation projects
with a construction cost of at least $100,000 each during the past three years.
3. The City of Fayetteville reserves the right to require the three lowest Bidders to
file proof within seven (7) calendar days of the Bid opening of their ability to
finance and execute the project. This proof shall include, but not be limited to, a
financial statement certified by a CPA for the last three years, a list of equipment
owned by Bidder, a backlog of jobs under contract and amounts, and a record of
successful completion of similar projects.
4. The successful Bidder shall conform to the Rules and Regulations of Arkansas
Department of Finance and Administration concerning nonresident contractor's
notice and bond requirements.
The successful Bidder must meet the statutorily prescribed requirements before
Award of Contract by the City of Fayetteville.
6. In order to perform public work, the successful Bidder shall, as applicable, hold or
obtain such Contractor's and Busincss Licenses as required by State statutes and
the Rules and Regulations of the Arkansas Contractor's Licensing Board.
7. All contracts shall be interpreted under Arkansas Law.
0. Disqualification of Bidders
More than one Bid for the same work described in this documcnt from an individual, firm
or partnership, a corporation or an association under the same or different names, will not
be considered. Reasonable grounds for believing that any bidder is interested in more
than one Bid for the work contemplated will cause the rejection of all Bids in which such
Bidder is interested. If there is reasonable grounds for believing that collusion exists
among the Bidders, the Bids of the participants in such collusion will not be considered.
Penalty for Collusion
If at any time it shall be found that the person, firm, or corporation to whom the contract
has been awarded has, in presenting any Bid or Bids, colluded with any other party or
parties, then the Contract so awarded shall be null and void, and the Contractor and his
sureties shall be liable to the City of Fayetteville for all loss or damage which the City of
Fayetteville may suffer thereby, and the City of Fayetteville may advertise for new Bids
for said work.
5
Instructions to Bidders
City of Fayetteville
Sanitary Sewer Improvements
License
Each Bidder shall possess state and local licenses as are required by law, and shall famish
satisfactory proof to the City of Fayetteville upon request that the licenses are in effect
during the entire period of the Contract.
R. Preconstruction Conference
A preconstruction conference shall be held after the time of the Contract award and
before the Notice to Proceed to discuss the responsibility of each party in the project and
to clarify any questions. Representatives of the Contractor shall be required to attend the
conference.
S. Bid Opening
Bids will be opened and the prices bid will be read aloud publicly at the time and place
indicated in the Invitation to Bid. Bidders or their agents are invited to be present.
T. Award of Contract
1. The City of Fayetteville shall award a contract to the Bidder whom, in the City of
Fayetteville's judgement, is the lowest responsive, responsible Bidder. The City
of Fayetteville reserves the right to reject all Bids, to waive informalities, and to
reject nonconforming, nonresponsive, or conditional Bids
In evaluating Bids, City of Fayetteville shall consider the qualifications of the
Bidders, whether or not the Bids comply with the prescribed requirements, and
alternatives and unit prices if requested in the Bid Form. City of Fayetteville may
consider the qualifications and experience of subcontractors and other persons and
organizations (including those who are to furnish the principal items of material or
equipment), and may reject the Bid of any Bidder who does not pass any such
evaluation to City of Fayetteville's satisfaction.
3. A responsive Bidder shall be one who has responded accurately to all
requirements of these Contract Documents including pre -qualifying in the
preparation and submission of his Bid. If any alterations, erasures or changes are
made to the printed Bid Form, the Bid shall be considered nonresponsive
4. The City of Fayetteville reserves the right to accept and incorporate corrections,
clarifications or modifications following bid opening when to do so would not, in
Instructions to Bidders
City of Fayetteville
Sanitary Sewer Improvements
6
the City of Fayetteville's opinion, prejudice the bidding process or create any
improper advantage to any bidder; and to waive irregularities and informalities in
any proposal submitted or in the bidding process; provided, however, that the
waiver of any prior defect or informality shall not be considered a waiver of any
future or similar defects or informalities and bidders should not rely upon, or
anticipate, such waivers in submitting their proposals.
If the Contract is awarded, City of Fayetteville shall give the apparent successful
Bidder a Notice of Award within 90 days after date of the Bid Opening.
Effective Date of Award
If a Contract is awarded by the City of Fayetteville, such award shall be effective when
formal notice of such award, signed by the authorized representative of the City of
Fayetteville, has been delivered to the intended awardee, by some officer or agent of the
City of Fayetteville duly authorized to give such notice or received by mail at the main
business address shown on his Bid.
Execution of Agreement
Contractor shall deliver a signed contract to the City of Fayetteville within seven (7) days
of bid opening. Contractor must submit required bonds and insurance within ten (10)
days of Notice of Award by the City. Effective date of bonds shall be the same or later
than the date of the Agreement. The City of Fayetteville has ten (10) days from receipt of
acceptable performance bonds and Agreement (signed by the Contractor) to sign the
Agreement and return to the Contractor an executed duplicate of the Agreement.
W. Failure to Execute Agreement and File Bonds and Insurance
•
Failure of a successful Bidder to execute the Agreement and file required bonds and
insurance within the required time shall be just cause for the annulment of the awards
On failure of a successful Bidder to execute the Agreement and file the required bonds
and insurance within the required time, he shall forfeit his Bid security as agreed
hereinbefore. Upon annulment of an award as aforesaid, the City of Fayetteville may then
award a Contract to the next lowest responsible Bidder.
7
Instructions to Bidders
City of Fayetteville
Sanitary Sewer Improvements
X. Payment for Excess Costs and Liquidated Damages
The successful Contractor will be required to pay for excess cost of field engineering and
inspection and liquidated damages as defined in the General Conditions of the Contract, if
extensions of time are granted by City of Fayetteville because of avoidable delays or if the
Contractor elects to work overtime hours as defined in the General Conditions of the
Contract.
Commencement and Completion of Work
The Notice to Proceed for the Schedule of work shall be issued within thirty days of the
execution of the Agreement by the City of Fayetteville.
The successful Bidder shall commence work within ten calendar days from and after the
issuance by the City of Fayetteville of a written Notice to Proceed, shall substantially
complete all work in accordance with the terms and conditions of the Contract
Documents no later than 90 calendar days, and shall complete all work to the point of
final acceptance by the City of Fayetteville no later than 110 calendar days. The Notice to
Proceed will be issued after receipt of acceptable insurance, bonds, and other required
items.
Z Information Not Guaranteed
I. All information given on the Drawings or in the other Contract Documents
relating to subsurface and other conditions, natural phenomena, existing pipes,
and other structures is from the best sources at present available to the City of
Fayetteville. All such information is furnished only for the information and
convenience of bidders and is not guaranteed.
2. It is agreed and understood that the City of Fayetteville does not warrant or
guarantee that the subsurface or other conditions, natural phenomena, existing
pipes or other structures encountered during construction will be the same as those
indicated on the Drawings or in the other Contract Documents.
3. It is agreed further and understood that no bidders or contractor shall use or be
entitled to use any of the information made available to him or obtained in any
examination made by him in any manner as a basis of or ground for any claim or
demand against the City of Fayetteville or the Engineer, arising from or by reason
of any variance which may exist between the information made available and the
actual subsurface or other conditions, natural phenomena, existing pipes or other
structures actually encountered during the construction work, except as may
otherwise be expressly provided for in the Contract Documents.
Instructions to Bidders
City of Fayetteville
Sanitary Sewer Improvements
8
AA. Covenant Against Contingent Fees
The contractor warrants that no person or selling agency has been employed or retained to
solicit or secure this contract upon an agreement or understanding for a commission,
percentage, brokerage, or contingent fee. For breach or
violation of this warranty the City of Fayetteville shall have the right to annul this
contract without liability or in its discretion to deduct from the contract price or
consideration, or otherwise recover, the full amount of such commission, percentage,
brokerage, or contingent fee.
BB. Gratuities
1. The City of Fayetteville may, by written notice to the contractor, terminate the
right of the contractor to proceed under this contract if it is found, after notice and
hearing, by the City of Fayetteville that gratuities (in the form of entertainment,
gifts, or otherwise) were offered or given by the contractor or any agent or
representative of contractor, to any official or employee of the City of Fayetteville
with a view toward securing a contract or securing favorable treatment with
respect to the awarding or amending, or the making of any determinations with
respect to the performance of this contract
?.
In the event this contract is terminated as provided in the paragraph (1) above, the
City of Fayetteville shall be entitled:
a) to pursue the same remedies against the contractor as it could pursue in the
event of a breach of the contract by the contractor, and
b) as a penalty in addition to any other damages to which it may be entitled
by law, to exemplary damages in an amount (as determined by the City of
Fayetteville) which shall be not less than three nor more than ten times the
costs incurred by the contractor of providing any such gratuities to any
such officer or employee.
The rights and remedies of the City of Fayetteville provided in this clause shall
not be exclusive and are in additions to any rights and remedies provided by law
or under this contract.
9
Instructions to Bidders
City of Fayetteville
Sanitary Sewer Improvements
CC. Subcontracts Under Construction Contracts
The award or execution of all subcontracts by a prime contractor and the procurement and
negotiation procedures used by such prime contractor in awarding or executing such
subcontracts shall comply with.
1. All provisions of State and local law;
2. All provisions of these General Conditions with respect to fraud and other
unlawful or corrupt practices; and
3. All provisions of these General Conditions with respect to access to facilities and
records and audit of records.
DD. Prevailing Wage Determination
Arkansas Prevailing Wage Determination Number 02-060 establishes the minimum wage
rates to be paid on this project. This Determination is included in these Contract
Documents and is a part thereof. These rates were established pursuant to the Arkansas
Prevailing Wage Law, Arkansas Code Ann. SS22-9-301 to 22-9-315 (1987) and the
administrative regulations promulgated thereunder. The Contractor shall post this
Determination at the fob site in a prominent and easily accessible place.
EE. Freedom of Information Act
City contracts and documents prepared while performing city contractual work are subject
to the Arkansas Freedom of Information Act. If a Freedom of Information Act is
presented to the City of Fayetteville, the (contractor) will do everything possible to
provide the documents in a prompt and timely manner as prescribed in the Arkansas
Freedom of Information Act (A.C.A. §25-19-101 et. seq.). Only legally authorized
photocopying costs pursuant to the FOIA may be assessed for this compliance.
END OF INSTRUCTIONS TO BIDDERS SECTION