RESOLUTION NO. 105-05
A RESOLUTION APPROVING A LUMP SUM
ALLOCATION IN THE AMOUNT OF $170,005.00 FOR THE
PURCHASE OF EASEMENTS REQUIRED FOR THE
FARMINGTON WATERLINE PROJECT; AND
APPROVING A 10% PROJECT CONTINGENCY IN THE
AMOUNT OF $17,001.00.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1. That the City Council of the City of Fayetteville, Arkansas, hereby
approves a lump sum allocation in the amount of $170,005.00 for the purchase of
easements required for the Farmington Waterline Project.
Section 2. That the City Council of the City of Fayetteville, Arkansas, hereby
approves a 10% project contingency in the amount of $17,001.00.
PASSED and APPROVED this 7th day of June, 2005.
ATTEST:
ati-k: G • ce4
_U• 'per
F. .
FAY Err EVILLE'F.
Sit 9:QKANSP'Jam~
.uuuw...
By:
SONDRA SMITH, City Clerk
APPROVED:
By:
DAN COODY, Mayor
• •
•9T
ail
mm4
zee
•a 3q4a
gg
33c
cc,
ti
0
m
a
z
5
41
y
z;
'o
iy1
31 fti Y FemiN Trust No.1
30 Farmmcron Church cl Ctvlet
3°
p
x•
n
TBIOaunherN Trutt
1
velSd,m.Anee Real Relate lnc.I
i
N
MITE
Q
2
s
g
0.
®4-altI
5
MITUa
a
I telfniri Femi MUM No. 1 1
DQ022pin
ggo
u
'
o-m;Day
flgg%
rR
0
ROW I PERM. ESMT TEMP ESMT
(FT') (FT') (FP)
am
e
110
m$
$.:N
'aHois
§
§H
mMningSJFA
HRggilErclE
mimsgma
s«Wrx««Nrrrrrrrrsrr«resrsrrrr
s«
r«««
8
8
8
88
o
UgGO
888
C
m.
88
88
mco
80008
NN
op
§
8
§§��=i0
888888
-4
0
8
»2rm.
S0
888888888888888888888888888888
.0.0000
2s
rs2grE2
Sb",1a
bbbo
000ol'nYnd
SS&'b'
i
s'o
888888
ittan
8
8
0rm
§sggioN
888888888888888888888888888888888888888£
m-4„
gUooIELIII
r„germ.
ogou€�
i§$tMsm
;
Ur0-'
1
GD
0
REMINDER
LETTER
(
NOTIFICATION
LETTER
DATE
ACQUIRED
0
m
S-
• • G %p5
City Council Meeting of May 3, 2005 r rm /1<dh
CITY COUNCIL AGENDA MEMO ghd-itriDW
0011 -6 -1. -
To: Mayor and City Council
From: Bob Davis, P.E., Water & Wastewater Director
Date: May 20, 2005
Subject: Approval of a lump sum plus 10% contingency to purchase easements
based on completed appraisals for the Farmington Waterline Project.
RECOMMENDATION : Staff recommends approval of purchase of the easements for
the Farmington Waterline Project. This recommendation was preceeded by a thorough
review of alternate routing and/or alignment of the subject wastewater conveyances.
BACKGROUND: This waterline relocation work is being done due to widening of
Highway 62 by the Arkansas Department of Transportation.
DISCUSSION:
BUDGET IMPACT: Payment for easements will be from the Water & Sewer Fund.
The $187,006.00 requested for these services is 18% of the $1,019,616.00 budget
allocated for the Farmington Waterline Relocation Project.
• •
RESOLUTION NO.
A RESOLUTION APPROVING A LUMP SUM ALLOCATION IN
THE AMOUNT OF $170,005.00 FOR THE PURCHASE OF
EASEMENTS REQUIRED FOR THE FARMINGTON WATERLINE
PROJECT; AND APPROVING A 10% PROJECT CONTINGENCY
IN THE AMOUNT OF $17,001.00.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1. That the City Council of the City of Fayetteville, Arkansas,
hereby approves a lump sum allocation in the amount of $170,005.00 for the
purchase of easements required for the Farmington Waterline Project.
Section 2. That the City Council of the City of Fayetteville, Arkansas,
hereby approves a 10% project contingency in the amount of $17,001.00.
PASSED and APPROVED this 7th day of June, 2005.
ATTEST:
B
APPROVED
r►
f
DAN COODY, Mayor
• •
ARKANSAS
WATER AND WASTEWATER
VOTE TAB
WATER & SEWER COMMITTEE
MAY 9, 2005
FARMINGTON WATERLINE EASEMENT ACQUISITION IN THE AMOUNT OF
$187,006.00
CERTIFIED:
Kyle Cook
Lioneld Jordan
Bobby Ferrell
Robert Reynolds
Kyle Cook
Lioneld Jordan
Bobby Ferrell
Robert
Reynolds
FOR
/
V
/
/
N ha
AGAINST
CERTIFIED:
Kyle Cook
Lioneld Jordan
Bobby Ferrell
Robert Reynolds
Bob Davis
Submitted By
•
City of Fayetteville
Staff Rev{pw Fgrjp
City Council Agenda Items
or
Contracts
7 -Jun -05
City Council Meeting Date
Water & Wastewater
Division
Action Required:
i
Director
Department
Approval of a lump sum plus 10% contingency to purchase easements based on completed appraisals for the
Farmington Waterline.
$187,006.00
Cost of this request
5400.5600.5810.00
Account Number
4034
Project Number
Budgeted Item
x
1,019,616
Category/Project Budget
33,625.81
Funds Used to Date
985,990.19
Remaining Balance
Budget Adjustment Attached
Hwy. 62 Waterline Relocation -
Farmington
Program Category / Project Name
Water/Sewer Imp.
Program / Project Category Name
Water/Sewer Fund
Fund Name
Department Director
(City Attorney
OS -2 e --o5
Date
Finan a and Internal Service Director Date
Mayor
Date
Previous Ordinance or Resolution # N/A
Original Contract Date:
Original Contract Number:
N/A
N/A
Received in Mayor's Office
E$IIAFD
1
(Comments:
Clarice Pearman - Res. 105-05, 106-05 & " -05 Page 1
From: Clarice Pearman
To: Davis, Bob
Date: 6/13/05 1:43PM
Subject: Res. 105-05, 106-05 & 107-05
Bob,
Attached are the above resolutions regarding various easements passed by the City Council, June 7,
2005.
Thanks.
Clarice
CC: Deaton, Vicki