HomeMy WebLinkAbout66-04 RESOLUTION0 0 RESOLUTION NO. 66-04 A RESOLUTION TO INCREASE THE PROJECT CONTINGENCY FOR THE FAYETTEVILLE PUBLIC LIBRARY CONSTRUCTION BY $999,691.00 FROM SETTLEMENT AND BUDGETED ITEMS BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS: Section 1: The City Council of the City of Fayetteville, Arkansas hereby increases the project contingency amount for the Fayetteville Public Library construction by $999,691.00. These additional funds come from a settlement and from the budget. PASSED and APPROVED this the 20th day of April, 2004. ;FAYETTEVILLE' ATTEST: SMITH, City Clerk 0 NAME OF FILE: Resolution No. 66-04 CROSS REFERENCE: Item # Date Document 0. 1 04/05/04 memo to mayor & city council 2 draft resolution 3 04/05/04 Revised memo to aldermen 4 04/07/04 Staff Review Form 5 04/23/04 memo to Louise Schaper NOTES: • CITY COUNCIL AGENDA MEMO • City Council Meeting of April 20, 2004 1 Agenda Item Number PFJ"I &V/1 feel To: Mayor and City Council Thru: Hugh Earnest, Chief Administrative Officer From: Louise Schaper, Executive Director -Library Date: April 5, 2004 Subject: Increase in project contingency RECOMMENDATION Approve a resolution adding the funds received from Grubbs, Hoskins and monies programmed for technology improvements, final off-site improvements, moving expenses associated with moving into the new facility and the remaining deferred items into the project contingency. BACKGROUND This project is on budget and on schedule. Approval of this request is necessary to maintain the project's momentum to ensure that the new library will be completed on time and within budget. The project is in the final phases of completion, so it is necessary to be able to respond rapidly to changes needed in order to meet the public expectations of project completion. The technology purchases will be made from state/GSA contracts. The deferred items are being completed within budget. Funds received to be added to general contingency: • $105,000 from Grubbs, Hoskins settlement Budgeted amounts to be transferred from other line items to project contingency for expenditure: $375,344 for deferred items and moving of the library. This includes moving the library, finishing the low voltage and security systems, and landscape work. $470,000 for technology items including computers, servers, printers, software and phone system. $49,347 for the final offsite improvements including burying telephone and cable lines and a contingency in case rock is hit. DISCUSSION This change is to allow deferred items to be paid for as they are incurred, many of which are in increments smaller than $20,000. It will also replace $105,000 of contingency funds paid for rock removal at the start of the project. In addition, this will allow the technology items on GSA/State contract to be purchased more timely. BUDGET IlVRACT No impact on the project budget. All of these items are in the new main library building project budget. 0 0 RESOLUTION NO, A RESOLUTION TO INCREASE THE PROJECT CONTINGENCY IN THE LIBRARY CONSTRUCTION CONTRACT BY $9999691.00 FROM SETTLEMENT AND BUDGETED ITEMS NOT FULLY NEEDED FOR THEIR DESIGNATED PURPOSE BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS: Section 1: The City Council of the City of Fayetteville, Arkansas hereby increases the project contingency amount in the library construction contract authorization by $999,691.00. These additional funds come from a settlement and from budgeted items that were accomplished without fully depleting the allotted funds. PASSED and APPROVED this the 201h day of April, 2004. ATTEST: By: SONDRA SMITH, City Clerk By: APPROVED: pR DAN COODY, Mayor Date: December 11, 2002, rev. 1/16/03, 1/23/03, 5/5/03, 9/29/03; 11/12/03; 3/25/04; 4/5/04 To: Fayetteville City Council Aldermen From: Louise Schaper, Executive Director, Fayetteville Public Library Subject: Blair Library Project Budget and Contract Approvals This table identifies those requests related to the construction of the Blair Library that Council has approved, as well as forthcoming requests. Our intent is to ensure that Council is aware of all requests that are within our $23,341,655 budget for the project as approved by the FPL Board on May 2, 2002, as well as those items that are outside of this budget. Some items will be funded and/or procured by the FPL Foundation including most furnishings, some plant materials, and some technology items. Blair Library Construction, Furnishing and Equipping Item Within Source(s) Budget Est. date Date Amount Notes budget? approval Approved Crossland Yes sales tax+ 5/21/02 $17,633,931. Includes $221,995for contract for private off-site improvements construction from CIP funds Contingency Yes sales tax + $830,000 4/20/04 5/21/02 $700,000 $167,676 remaining of private remainder approved contingency Exterior Yes sales tax+ 11/02 11/19/02 $402,896 APC at entrance and cladding: APC private $949,658 brick will clad lintels + replacement stairwell towers. Added to Crossland contract. Low voltage Yes sales tax+ 10/21/03 $206,701 Added to Crossland equipment rivate contract. Low voltage Yes sales tax + 4/20/04 '.$24,077 Deferred from contract conduit private(pending) Landscape Yes sales tax + 4/20/04 $54,377 Deferred from contract private(pending) Interior Yes sales tax + 4/20/04 Deferred from contract signage private AV Equipment Yes sales tax + 4/20/04 Deferred from contract rivate Meeting room Yes sales tax + 4/20/04 Deferred from contract enhancements private Technology Yes $470,000 4/20/04 related items private Furnishings Yes $980,000 3/16/04 $151,185 Shelving; remainder by private funds Smart library, Yes ksalestaxx $659,751 5/03 5/03 ;' $395,632 Conveyor e.g. conveyor, RFID self -check, RFID Self -check Moving costs Yes $30,000 4/20/04 private This page identifies those items related to off-site improvements (utility burial, drainage, sidewalks etc.) approved in CIP ($671,995). Because additional off-site improvements have been requested by City departments and will be funded by these departments we list them here as well. We will, as those items come up, list any additional CIP items approved in 2003 for use in 2004, i.e. signage and landscape. CIP Approved Off -Site Improvements Related to Blair Library Item Within Source(s) Budget Est. date Date Amount Notes budget? approval Approved Off-site Yes Off-site $221,995 5/21/02. $221,995 In Crossland Contract, improvements CIP but funded from CIP site (see first item improvements project. above Includes sidewalks etc. West Avenue Yes Off-site $101,806 10121/03. $101,806 West Ave underground underground CIP utility permanent power. utilities Vendor is AEP/SW EPCO. West Avenue Yes Off-site $110,117 11/18103.'`: $110,117 Addition to Crossland underground CIP contract for installation of utilities to underground utilities to residences seven housing structures adjacent to Blair Library Additional Improvements to Blair Library Item Within Source(s) Budget Est. date Date- Amount Notes budget? approval Approved - Not in Water and $41,342 11/18/03 11/18/03 $41;342 Improvements to water CIP Approved library Sewer and sewer that were Improvements budget. In Funds identified after the Related to Water 8 contract was signed with Blair Library Sewer Crossland. Includes Funds new 6" waterlines in Mountain; 8' waterline in School; 8" sanitary sewer in Rock and 12" waterline in Rock. These improvements are requested to correct on west side of West Avenue. School Street Yes Off -Site $186,395. 3/16/04 - - $186,395 Utility burial utility burial CIP AEP/SWEPCO; there is a "rock clause" in the contract. Additional Improvements to Blair Library Item Within Source(s) Budget Est. date Date- Amount Notes budget? approval Approved - Not in Water and $41,342 11/18/03 11/18/03 $41;342 Improvements to water CIP Approved library Sewer and sewer that were Improvements budget. In Funds identified after the Related to Water 8 contract was signed with Blair Library Sewer Crossland. Includes Funds new 6" waterlines in Mountain; 8' waterline in School; 8" sanitary sewer in Rock and 12" waterline in Rock. These improvements are requested to correct leaking, deteriorated and undersized old water and sewer lines in the streets adjacent to Blair Libra • STAFF REVIEW FORM • X AGENDA REQUEST CONTRACT REVIEW GRANT REVIEW For the Fayetteville City Council Meeting of: April 20, 2004 FROM: Louise Schaper Fayetteville Public Library General Government Name Division Department ACTION REQUIRED: Approve an increase in project contingency for the new main library of $999,691. This covers the final deferred items, technology items, final offsite improvement items, technology purchases, restoring the recovered funds from Grubbs, Hoskins and moving of thenew library. COST TO CITY: $ 999,691.00 Cost of this request 4150-9150-580400 Account Number 99073-1 Project Number $ 8,950,917 Category/Project Budget $ 6,491,365 Funds Used to Date $ 2,459,552 Remaining Balance New Library Program Category / Project Name New Library Program / Project Category Name Library Construction Fund Fund Name BUDCMT REVIER• X Budgeted Item Budget Adjustment Attached �GY� ys,��, Budget Manager Date CONTRACT/CR3ANT/LEASE REVIEW: ISb4-Is/ott Date Internal A itor Date Date Purchasing Manager Date Division Head Date Department Director Financ & Internal Services Dir. Date -b-�7 Date Cross Reference New Item: Yes No Previous Ord/Res#: Orig. Contract Date Orig. Contract Number F7J/ Data Dsb FAYETTEV&LE S THE CITY OF FAYETTEVILLE, ARKANSAS DEPARTMENTAL CORRESPONDE To: Louise Schaper Fayetteville Public Library From: Clarice Buffalohead-Pearman City Clerk Division Date: April 23, 2004 Re: Resolution No. 66-04 Attached is a copy of the above resolution passed by the City Council April 20, 2004, to increase the project contingency amount for the new library. This resolution with attachments will be recorded in the city clerk's office and microfilmed. If anything else is needed please let the clerk's office know. /cbp attachments cc: Nancy Smith, Internal Auditor STAFF REVIEW FORM X AGENDA REQUEST X CONTRACT REVIEW GRANT REVIEW For the Fayetteville City Council Meeting,of: FROM: , Louise Schaper Fayetteville Public Library General Government Name Division Department ACTION REQUIRED: Approve a contract adjustment in the amount of $53,577 with Crossland Construction Company Inc. for Change Order #20 which covers low voltage and electrical work,elevator door changes, an air compressor and bollards. Amount requested is covered by project contingency. COST TO CITY: $ 53,577.00 $ 1,492,559 Cost of this request Category/Project Budget 4150-9150-580400 Account Number $ 221,650 Funds Used to Date New Library Program Category / Project Name New Library Program / Project Category Name 99073-1 $ 1,270,909 Library Construction Fund Project Number Remaining Balance Fund Name BUDGET REVIEW: X Budgeted Item Budget Adjustment Attached Budget Manager CONTRACT/GRANT/LEASE REVIEW: Accounting Manager City Atto ney STAFF Date Date Day// Internal Auditor Purchasing Manager Cross Reference Division Head Date New Item: Yes Gaffe jj yn L�u� Department Director 57 q /o.5Previous Ord/Res#: Jam_ O —pt' Orig. Contract Date Fina c d Internal Services Dir. Date Orig. Contract Number No Chief Atinistr ive Officer Date �� / '' ENTERED Mayor Date Date Date Staff Review Form - Page 2 Description t adjustment will be billed to the Fayetteville Public Library Four Meeting Date Comments: Budget Manager Accounting Manager City Attorney Purchasing Manager Internal Auditor Finance & Internal Services Director Chief Administrative Officer Reference Comments: Tavelevi le ARKANSAS The City of Fayetteville, Arkansas City Council Agenda Memo City Council Meeting Date: June 7, 2005 To: Mayor and City Council Thru: Steve Davis, Finance and Internal Services Director From: Louise Schaper, Executive Director, Fayetteville Public Library Date: May 5, 2005 Subject: Contract adjustment in the amount of $53,577 with Crossland Construction Company Inc. for Change Order # 20. Recommendation: We recommend approval of a contract adjustment in the amount of $53,577 with Crossland Construction Company, Inc. for Change Order #20 which covers final CCD's for electricals, revision to elevator doors, air compressor for the conveyor, bollards for the front of the library, increased cooling capacity for the Server Room, and a reduction in the signage allowance. Background: All low voltage and added electrical needs were preformed on a time and materials basis through CCD to contain the costs. Discussion: Electrical costs were higher than CCD's issued. All items are within the project contingency fund. Budget Impact: These items are within the new library project budget. 113 WEST MOUNTAIN 72701 479-575-8330 479-575-8257 (Fax) Contract Administration G701 Change Order (Instructions on the reverse side) Distribution List: Owner Architect Contractor — Field Other PROJECT (Name and address): CHANGE ORDER NUMBER: Y0 FAYETTEVILLE PUBLIC LIBRARY 401 WEST MOUNTAIN STREET DATE: 25 APR 2005 FAYETTEVILLE ARKANSAS 72701 TO CONTRACTOR (Name and address): ARCHITECT'S PROJECT NUMBER2000073-00 CROSSLAND CONSTRUCTION COMPANY INC CONTRACT DATE: 21MAY 2002 ATTENTION: JOHN PRIEST — PROJECT MANAGER 14149 E. Admiral Place Tulsa, OK 74116 CONTRACT FOR: GENERAL Cl THE CONTRACT IS CHANGED AS FOLLOWS: (Include, where applicable, any undisputed amount attributable to previously executed Construction Change Directives) \ I A. Provide the work as itemized in ATTACHMENT TO FAYETTEVILLE PUBLIC LI P The original (Contract Sum) (Guaranteed Maximum Price) was The net change by previously authorized Change Orders The (Contract Sum) (Guaranteed Maximum Price) prior to this Change Order was The (Contract Sum) (Guaranteed Maximum Price) will be (increased) (decreased) (unchanged) by this Change Order in the amount of The new (Contract Sum) (Guaranteed Maximum Price) including this Change Order will be The Contract Time will be (increased) (decreased) (unchanged) by The date of Substantial Completion as of the date of this Change Order therefore is n\ /� NOTE: This Change Order does not include changes in the Contract Sum, Contract Time or Guaranteed Maximu\Pnce which have been autharizt Construction Change Directive until the cost and time have been agreed upon by both the Owner and Contractor , in -which case a -Change Order is to supersede the Construction Change Directive. O NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACTOR AND OWNER. Q VQ ARCHITECT (Firm name) Associate Architect ADDReYV ARCHITECTS rr, Su . r• r CONTRACTOR (Firm name) OWNER.(Firm CROSSLAND CONST. CO. INC. CITY OF F ADDRESS ADDRESS / PC BOA 907 1i4fl51 ROGERS, AR 72756 F Y TTF BY i B (Typed name) (Typed name) JOHN PRIEST MAYOR O DATE DATES 72701 CAUTION: You should sign an original AIA Contract Document, on which this text appears in RED. An original assures changes will AQt 4b obscured. AIA Document G701 Change Order O 2001 The American Institute of Architects • Washington, DC • www.aia.org • WARNING: Reproduction, unlicensed photocopying or substantial quotation of the material herein without written permission of the AIA violates the copyright laws of the United States and will subject the violator to legal prosecution. To report copyright violations of AIA Contract Documents, e-mail The American Institute of Architectslegal counsel, copyright@aia.org. `AIA Contract Administration -'- G701 Change Order Instructions 'GENERA NFORMATION k Document G701 is for implementing changes in the Work agreed to by the Owner, Contractor and Architect. a completed G701 indicates agreement upon all the terms of the change, including any changes in the Contract anteed Maximum Price) and Contract Time. . . _ , .. . 19 Prior to using any AIA Contract Document, users should consult the AIA Contract. Documents or visit a local AIA chapter to be certain they are using current document editions. AIA Document G701 is a copyrighted work and may not be reproduced or excerpted from without the express 'fission of the AIA./G701 is intended for use as a consumable —that is, the original document purchased is to be the course of its use. There is no implied permission to reproduce this document, nor does membership in The ;titute/of Architects confer any further rights to reproduce G701. y for of, w ETIN by OF to end users to reproduce a maximum of ten copies of a completed or executed G701, a particular project. Further reproductions are prohibited without application for, and e AIA. AIAIContract Documents, e-mail The American Institute of Architects' legal counsel, G701'D.O'CUMENT IN THE CONTRACT )f the change or reference specific exhibits describing, in detail, the change to be made in the er. Include any drawings, specifications, documents, or other supporting data that clarify the scope Ihse^the blanks provided, br,strike-out'the terms in parentheses that do not apply, the original Contract Sum or Guaranteed M ximum-Pnce; the thnet change.by previously authorized Change Orders (note that this does not include changes authorized by Construction Change -Directive unless such changes were subsequently agreed to by the Contractor and recorded as a Change Order);'the Contract -Sum or Guaranteed Maximum Price prior to this Change Order; the amount of increase or decrease, if any, in the Contract Sum.or Guaranteed Maximum Price; and the new Contract Sum or Guaranteed Maximum Price as adjusted by DD(/ CHANGE-INCONTRACT TIME LlInsernt the blanks provide the'Contract TimeOrder and strikeout the unused terms in parentheses, the amount (in days) of the increase or decrease, Uso insert the date of Substantial Completion, including any adjustment effected by this EXECUTION OF THE 0701 DOCUMENT - I i.,.♦,, . `� �..\ When the Owner and Contractor, in concurrence with the Architect, have reached agreement on the change to be made'in the Contract, including any adjustments -in the Contract Sum (or Guaranteed Maximum Price) and Contract Time, the G701 document should be ekecuted in triplicate by the two parties and the Architect, each retaining an original. ' • e - �,• -.- rs Instructions for AIA Document G701 Change Order O2001 The American Institute of Architects • Washington, DC • www.aia.org • WARNING: Reproduction, unlicensed photocopying or substantial quotation of the material herein without written permission of the AIA violates the copyright laws of the United States and will subject the violator to legal prosecution. To report copyright violations of AIA Contract Documents, e-mail The American Institute of Architectslegal counsel, copyright®aia.org. ��AIAContract Administration G701 Change Order Instructions 'GENERAL INFORMATION PURPOSE. AIA Document 0701 is for implementing changes in the Work agreed to by the Owner. Contractor and Architect. Execution -of a completed 0701 indicates agreement upon all the terms of the change. including any changes in the Contract Sum (or Guaranteed Maximum Price) and Contract Time. USE OF CURRENT AIA DOCUMENTS. Prior to using any AIA Contract Document, users should consult the AIA Contract Documents Web'sitc, u'1vn:nia.org/rlucitmetits, or visit a local AIA chapter to be certain they are using current document editions. COPYRIGHT. AIA Document G701 is a copyrighted work and may not be reproduced or excerpted from without the express • written permission of the AIA:oG701 is intended for use as a consumable —that is, the original document purchased is to be consumed in the course of its use.'There is no implied permission to reproduce this document, nor does membership in The American Institute of Architects confer any further rights to reproduce G70 1. A limited license is hereby granted to end users to reproduce a maximum of ten copies of a completed or executed G701, • but only for use in connection with a particular project. Further reproductions are prohibited without application for, and receipt of, written permission from the AIA. To report.copyright violations of AIA Contract Documents, e-mail The American Institute of Architects' legal counsel. cbpyrig/t@nia,crg. COMPLETING THE G701'DOCUMENT DESCRIPTION OF THE CHANGE IN THE CONTRACT Insert a detailed description ofthe change or reference specific exhibits describing, in detail, the change to be made in the Contract by this Change Order: Include any drawings, specifications. documents, or other supporting data that clarify the scope • ofithe changer DETERMINATION'OF COSTS Inseh in the blanks provided;, or.strike•out the terms in parentheses that do not apply, the original Contract Sum or Guaranteed Maximo h -Price; the net change by previously authorized Change Orders (note that this does not include changes authorized by • Construction Change- Directive unless such'changes were subsequently agreed to by the Contractor and recorded as a Change Order); theContractSam or Guaranteed Maximum Price prior to this Change Order; the amount of increase or decrease, if any, . in: the'Contract Sum'or Guaranteed Maximum Price; and the new Contract Sum or Guaranteed Maximum Price as adjusted by this Change Order. CHANGE.IN CONTRACT TIME -Insert in the blanks provided, and strikeout the unused terms in parentheses, the amount (in days) of the increase or decrease, if any, in the Contract Time. Also insert the date of Substantial Completion, including any adjustment effected by this Change Order:• EXECUTION OF THE G701 DOCUMENT When the Owner and Contractor, in concurrence with the Architect, have reached agreement on the change to be made in the Contract, including any adjustments in the Contract Sum (or Guaranteed Maximum Price) and Contract Time, the G701 document shouldbe executed in triplicate by the two parties and the Architect, each retaining an original. Instructions for AIA Document G701 Change Order O2001 The American Institute of Architects • Washington, DC • wwwaia.org • WARNING: Reproduction, unlicensed photocopying or substantial quotation of the material herein without written permission of the AIA violates the copyright laws of the United States and will subject the violator to legal prosecution. To report copyright violations of AIA Contract Documents, e-mail The American Institute of Architects' legal counsel, copyright ®aia.org. ATTACHMENT TO FAYETTEVILLE PUBLIC LIBRARY CHANGE ORDER #20 1. To comply with directive from Elevator Inspector, revise equipment room doors to swing outward for an increase in Contract Sum of $3,168.58 2. Provide air compressor for Book Conveyor as requested by Owner Representative for an increase in Contract Sum of $7,022.88 3. Provide cherry veneer to aluminum angles supporting K-1 light fixtures per request from Owner Representative for an increase in Contract Sum of $1,794.91 4. Increase cooling capacity for Server Room due to increased number of servers consistent with Proposal Request 61 as reduced by sharing of cost by Green Anderson Engineers for an increase in Contract Sum of $1,000.00 5. Install three bollards to discourage' parking on entry walkway in accord with Proposal Request 63 except painting to be by Owner for an increase in Contract Sum of $4,823.80 6. Delete roof over entry canopy and add composite metal panel to roof of drive up book deposit as requested by Owner and priced in PCO 108 for a decrease in Contract Sum of ($739.28) 7. Provide for added electrical work performed under Construction Change Directives and added electrical work beyond the limit of electrical CCD's with time and materials documented by PCO's 80, 94, 95, 99, 100, 101, 102, 103 & 107 for an increase in Contract Sum of $57,318.09 8. Reduce signage allowance established under Change Order 15 by a decrease in Contract Sum of ($20,812.16) 9. Extend required Substantial Completion Date for sitework by an additional 28 calendar days for no change in Contract Sum $0.00 Summary of Change Order 20 changes to Contract Sum, an Increase of $53,576.82 AminnoezFosterHaileyJohnson MEMORANDUM April 28, 2005 Architects & Planners To: Mayor Dan Coody Copy: Cathy Rew Sean Wagner Bill Browner From: Jim Fost V1 I Reference: fayettevill�ublic Library, Change Order #20 Chan Order ,signed by the Contractor and Architect, is attached for Owner signatur . items were previously authorized by Owner and have been completed. Please advise if you have questions. The original is for City records. Please return three copies to me for distribution. Post Office Box 790. 100 West Center, Suite 302 • Fayetteville, AR 72702.479-442-5565 • FAX 479-442-8849 STAFF REVIEW FORM AGENDA REQUEST X CONTRACT REVIEW GRANT REVIEW For the Fayetteville City Council Meeting of: _..o FROM: Louise Schaper Fayetteville Public Library General Government Name Division Department ACTION REQUIRED: Approve a contract adjustment in the amount of $53,577 with Crossland Construction Company Inc. for Change Order #20 which covers low voltage and electrical work,elevator door changes, an air compressor and bollards. Amount requested is covered in project contingency that was authorized by Resolution No. 66-04, attached. COST TO CITY: $ 53,577.00 $ 1,492,559 New Library Cost of this request Category/Project Budget Program Category / Project Name 4150-9150-580400 Account Number 99073-1 Project Number BUDGET REVIEW: Budget Manager $ 221,650 New Library Funds Used to Date Program / Project Category Name $ 1,270,909 Library Construction Fund Remaining Balance Fund Name X Budgeted Item Budget Adjustment Attached CONTRACT/GRANT/LEASE REVIEW: Accounting Manager City Attorney Date Date Internal Auditor Date Purchasing Manager STAFF RECOMMENDATION: Division Head Date Department Director Finance & Internal Services Dir. Chief Administrative Officer Mayor Date Date Date Date Cross Reference New Item: Yes No Previous Ord/Res#: Orig. Contract Date Orig. Contract Number Date Date Staff Review Form - Page 2 Description t adjustment will be billed to the Fayetteville Public Library FourMeeting Date Comments: Budget Manager Accounting Manager City Attorney Purchasing Manager Internal Auditor Finance & Internal Services Director Chief Administrative Officer Reference Comments: RESOLUTION NO. 66-04 A RESOLUTION TO INCREASE THE PROJECT CONTINGENCY FOR THE FAYETTEVILLE PUBLIC LIBRARY CONSTRUCTION BY $999,691.00 FROM SETTLEMENT AND BUDGETED ITEMS BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS: Section 1: The City Council of the City of Fayetteville, Arkansas hereby increases the project contingency amount for the Fayetteville Public Library construction by $999,691.00. These additional funds come from a settlement and from the budget. PASSED and APPROVED this the 20th day of April, 2004. ATTEST: FAYETTEVILLE: City Clerk From: Clarice Pearman To: Schaper, Louise Subject: Crossland Attached is a copy of Change Order #20 for Crossland Construction. I am returning via interoffice mail three of the four originals of the change order. CC: Deaton, Vicki