HomeMy WebLinkAbout101-04 RESOLUTIONRESOLUTION NO. 101- o 4
A RESOLUTION APPROVING THE IMPROVEMENT SCHEDULE
FOR SCHOOL AVENUE FROM ARCHIBALD YELL BOULEVARD
TO THE INTERSECTION WITH MOUNTAIN STREET; AND
APPROVING A BUDGET ADJUSTMENT IN THE AMOUNT OF
$278,000.00 FOR SAME.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1. That the City Council of the City of Fayetteville, Arkansas
hereby approves the Improvement Schedule for School Avenue from Archibald
Yell Boulevard to the intersection with Mountain Street.
Section 2. That the City Council of the City of Fayetteville, Arkansas
hereby approves a budget adjustment in the amount of $278,000.00 for same.
PASSED and APPROVED this 13± day of July 2004.
�..``�R,WTRf .....
me..$5".•61Y O,c•�G�
CU• •-P-
;FAYETTEVILLE;
%Via, •9/CANSP�GOJ'i
ATTEST: �'e.,NtA5N .•
By
•..411111111%1 •
SONDRA SMITH, City Clerk
APPROVED:
By:
DAN COODY, Mayor
NAME OF FILE:
CROSS REFERENCE:
Item #
Date
•
Resolution No. 101-04
Document
1
07/02/04
memo to mayor & City Council
2
draft resolution
3
copy of budget adjustment
4
Staff Review Form
5
memo to Gary Dumas
6
7
8
9
10
11
12
13
14
15
16
NOTES:
•
•
City Council Agenda Item
e6.5 J/17
/ot_ 0 5e
-l0D/r
�yrhprev 't r 5
To: Mayor and City Council
From: Gary Dumas
Date: July 2, 2004
Subject: Resolution Approving Improvement Schedule for Archibald Yell/School
Intersection, School/Mountain Intersection and School Street
Improvement and Budget Adjustment
Recommendation: Staff recommends approval of the attached resolution regarding the
schedule of improvements and budget adjustment for the Archibald Yell/School
Intersection, School/Mountain Intersection and School Street Improvements.
Background: The community has invested over $23,000,000 in the creation of a new
icon representing Fayetteville, the Blair Library, Fayetteville Public Library. Discussions
prior to 2002 concerning the library's cost and budget revealed that some off-site
improvements were to be undertaken and funded by Departments other than the Library.
In June 2002, the Council's Street Committee gave their unanimous endorsement to the
need for an analysis of the School Street/Archibald Yell Blvd. intersection and
recommended that the Mayor authorize the activity at a cost of $13,600 through contract
with Garver Engineers. The purpose of the study was an evaluation of alternative
improved layouts of the intersection.
Subsequently in the fall of 2003 the City Council included in the 2004 Capital
Improvement Program the School and Archibald Yell Intersection Improvement at a
project cost of $100,000. Early this year the City's Engineering Division finalized plans
for this intersection improvement and forwarded them o the Arkansas Highway and
Transportation Department. That approval was received April 13, 2004.
In order to accomplish the basic improvement within the budget the city's Transportation
Division scheduled the project within their work program and within the time constraints
of the Water and Sewer Division improvements in the area and the construction schedule
of the various Library contractors. Intersection improvements are scheduled to be
complete by the end of July.
Somewhat coincident and overlapping the Library construction, the Dickson Street
Improvement Project, and the Library opening, the Dover/Kohl Downtown Plan
occurred. It enumerated many ideas for consideration and refinement. One of those
involved the School/Archibald Yell intersection and a reconfiguration of Archibald Yell
Blvd. These two potential improvements are very substantial and will require years if not
decades to gain approval, design, fund and build. The purpose of the immediate project
is to complete the entry to the new Library in a contextual manner that ties three special
places together, the new Library, Dickson Street and the Square.
Discussion: In order to take advantage of and to begin a process which will showcase
the community's investments made in the new Library and in the Dickson Street
enhancements, improvements beyond the basic intersection design are necessary.
These additional improvements include the use of material and lighting consistent with
the Library and Dickson Street and the creation of a linkage or pathway between these
destinations and the Square This means that additional funds are necessary for
1 of 1 7/8/2004 8:21:32 AM
•
City Council Agenda Item
appropriate signage, lighting, and intersection enhancements that will continue the theme
created by Dickson Street.
Please refer to the attached slides for the options available to create this contextual
linkage.
The street lights should be purchased from the manufacturer of the Dickson St. lights.
There are two different light standards, the shorter street lights and the taller intersection
lights. A bid waiver for these manufacturers will be forwarded to city council at a later
date.
The recommended improvement options:
• Complete enhancements at
School and Archibald Yell $ 19,000
• Improve School and Mountain
With asphalt intersection and
brick crosswalks with pedestrian bump outs $ 35,530
• School and Mountain traffic control
(4 -way stop) $ 0
• Complete repair and overlay of School $ 32,089
• Purchase and install street lights along School $165,953
Budget Impact: Funding for the project will be denved from the existing
School/Archibald Yell CIP ($100,000), programmed School St. overlay ($34,778), and
the remainder from unencumbered funds from Old Missouri Road Improvements -
Rolling Hills to Old Wire and the portion from Mud Creek to Joyce Boulevard. The
following is the fund information for this project:
• Number: 4470-9470-5809.00
• Project Numbers: 03007 & 03008
• Project Funds: $1,330,000.00
• Funds Encumbered: $886,586.00
• Remaining Funds: $443,414.00
Funds in Budget Adjustment - $278,000
2 of 2 7/8/2004 8:21:32 AM
RESOLUTION NO.
A RESOLUTION APPROVING THE IMPROVEMENT SCHEDULE
FOR SCHOOL AVENUE FROM ARCHIBALD YELL BOULEVARD
TO THE INTERSECTION WITH MOUNTAIN STREET; AND
APPROVING A BUDGET ADJUSTMENT IN THE AMOUNT OF
$278,000.00 FOR SAME
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1. That the City Council of the City of Fayetteville, Arkansas
hereby approves the Improvement Schedule for School Avenue from Archibald
Yell Boulevard to the intersection with Mountain Street.
Section 2. That the City Council of the City of Fayetteville, Arkansas
hereby approves a budget adjustment in the amount of $278,000.00 for sames
PASSED and APPROVED this 20th day of July 2004.
ATTEST:
ONDR
APPROVE
ODY, Mayo
S
•City of Fayetteville, Arkansas
Budget Adjustment Form
Budget Year
2004
Department: Sales Tax Capital Improvements
Division:
Program:
Date Requested
Adjustment Number.
Project or Item Requested:
$278,000 is requested in the School & Archibald Yell -
Intersection project.
Project or Item Deleted:
$278,000 from the Old Missouri Improvements capital
project.
Justification of this Increase:
Project funds are needed.
Justification of this Decrease:
Project funds remain.
Account Name
Street improvements
Account Name
Street improvements
Increase Budget (Decrease Revenue)
Account Number
4470 9470 5809 00
Decrease Budget (Increase Revenue)
Account Number
4470 9470 5809 00
Amount
Project Number
278,000 04015 1
Amount
Project Number
278,000 03007 1'
Approval Signatures
Requested By-
Budget
y
Budg� gaf�
Department Director
Finance & Internal Services Director
Mayor
Date
Date
Date
Date
Date
Type. A
Budget Office Use Only
B C E
Date of Approval
Posted to General Ledger
Posted to Project Accounting
Entered in Category Log
Initial
Initial
Initial
Date
Date
Date
Initial Date
STAFFIIIVIEW FORM - FINANCIAL OBLIGATI,
XXX AGENDA REQUEST
CONTRACT REVIEW
GRANT REVIEW
For the Fayetteville City Council Meeting of:
July 20, 2004
FROM:
Gary Dumas
Name
Operations Department
Division Department
ACTION REQUIRED: Resolution Approving Improvement Schedule for Archibald Yell/School Intersection,
School/Mountain Intersection and School Street Improvements and Budget Adjustment
COST TO CITY:
$278,000.00 $
4470-9470-5809.00
Account Number
04015
Project Number
100,000.00 School/Archibald Yell Intersection
Category/Project Budget • Program Category / Project Name
$10,572 Street Improvements
Funds Used to Date Program / Project Category Name
$ 89,428.00 Sales Tax Capital
Remaining Balance Fund Name
BUDGET REVIEW:
xxxx Budgeted Item xxxxx Budget Adjustment Attached
udget Manager
—G'° %
Date
CONTRACT/GRANT/LEASE REVIEW:
Accounting Manager J/ Date
City Attorney
Date
Internal Auditor Date
Purchasing Manager Date
STAFF RECOMMENDATION:
ivision Head
Department irector
Finance &(Internal Services Dir.
SA AIIP
Chief `, ministrative Officer
Mayor
Date
Date
9'71 --01
Date
7470Lf
Date
Received in Mayor's Office
Cross Reference:
Previous Ord/Res#:
Orig. Contract Date:
Orig. Contract Number:
New Item:
Date
Yes
No
FAYETTEIILLE
THE CITY OF FAYETTEVILLE, ARKANSAS
City Clerk Division
DEPARTMENTAL CORRESPONDENCE
113 West Mountain
Fayetteville, AR 72701
Telephone: (479) 575-8323
To: Gary Dumas
Operations Director
From: Clarice Buffalohead-Pearman
City Clerk Division
Date: July 19, 2004
Re: Resolution No. 101-04
The City Council passed a resolution at a special council meeting, July 13, 2004, approving the
improvement schedule for School Avenue. Attached is a copy of the resolution and budget adjustment.
The resolution with attachments will be recorded in the city clerk's office and microfilmed. If anything
else is needed please let the clerk's office know.
/cbp
attachments
cc: Nancy Smith, Internal Auditor
Barbara Fell, Budget & Research