HomeMy WebLinkAbout169-03 RESOLUTION• • • RESOLUTION NO.169-03 A RESOLUTION APPROVING CHANGE ORDER # 12 TO THE CONTRACT WITH CROSSLAND CONSTRUCTION COMPANY, INC. IN THE AMOUNT OF ONE HUNDRED TEN THOUSAND ONE HUNDRED SEVENTEEN DOLLARS ($110,117.00) TO INSTALL UNDERGROUND UTILITIES TO SEVEN (7) RESIDENCES ADJACENT TO THE NEW FAYETTEVILLE PUBLIC LIBRARY. BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS: Section 1. That the City Council of the City of Fayetteville, Arkansas, hereby approves Change Order # 12 to the contract with Crossland Construction Company, Inc. in the amount of One Hundred Ten Thousand One Hundred Seventeen Dollars ($110,117.00) to install underground utilities to seven (7) residences adjacent to the new Fayetteville Public Library. A copy of Change Order # 12, marked Exhibit "A" is attached hereto and made a part hereof. PASSED and APPROVED this 18th day of November, 2003. plETre?. et' tfik- TES1': By: Anikkal SONDRA SMITH; City Clerk fvtlizt, APPROVED: By DAN COODY, Ma • Change Order (In -inn -lions on reverse side) PROJECT: (Name and addTn) FAYETTEVILLE PUBLIC LIBRARY 401 WEST MOUNTAIN STREET FAYETTEVILLE ARKANSAS 72701 TO CONTRACTOR: (Name and address) CROSSLAND CONSTRUCTION COMPANY INC ATTENTION: JOHN PRIEST— PROJECT MANAGER 2510 WEST HUDSON ROAD ROGERS ARKANSAS 72756 2 0 0 011110 I T I O N AIA DOCUMENT CHANGE ORDER NUMBER: DATE: ARCHITECT'S PROJECT NUMBER CONTRACT DATE: CONTRACT FOR: THE CONTRACT IS CHANGED AS FOLLOWS: (Include. nhcre aryrhrable, any undupdcd armums attributable to prolong)? needed Conuunum Change Uvrrn srs.i 12 27 October, 2003 2000073-00 21 MAY 2002 GENERAL CONSTRUCTION G701-2000 OWNER ARCHITECT CONTRACTOR 0 FIELD 0 OTHER 0 Provide for West Avenue Utilities not included in the AEP/SWEP proposal as described in Proposal Request 23 for an increase in Contract Sum of $110,117.00. The original (Contract Sum) was $ 17,633,931.00 The net change by previously authorized Change Orders $ The (Contract Sum) prior to this Change Order was s 18,839,796.70 The (Contract Sum) (Cee.easWn^-Q9 s ill be (increased) (Jacreaa"d) (.-IVJn^gee{; by this Change Order in the amount of s 110,117.00 The new (Contract Sum) including this Change Order will be $ 18,949,913.70 The Contract Time will bei (unchanged) by _' ( 0 ) days. The date of Substantial Completion as of the date of this Change Order therefore is 31 JULY 2004 1,205,865.70 NOTE: This Change Order does not include changes in the Contract Su m.Contract Time or Guaranteed Maximum Price which have been authorized by Construction Change Directive for which the cent or time are in dispute as described in Subparagraph 7.3.8 of AIA Document A101. Not valid until signed by the Architect, Contractor and Owner. AFHJ ARCHITECTS PO BOX 790 FAYETTEVILLE, AR 72702 AREIIITLCT (Typed name) Associate .c ite CROSSLAND CONST. CO. INC. PO BOX 907 ROGERS, AR 72756 CONTRACTOR (Typed name) JA. S FOSTER BY 21 oetc* DATE trema) JOHN PRIEST BY /Op, -' %3 DATE CITY OF FAYETTEVILLE 113 WEST MOUNTAIN ST FAYETTEVILLE, AR 72701 OWN ' R (Typed (Signamrci MAYOR DAN COODY BY ? 02000 The American Institute of Architects. Reproduction of the material herein or substantial quotation of in provisions without written permission of the AIA violates the copyright laws of the united States and will subject the violator to legal prosecution. WARNING: Unlicensed photocopying violates U.5. copyright laws and will subject the violator to NO prosecution. Stabeis 01000 AIA® AIA DOCUMENT G701-2000 CHANGE ORDER The American Institute of Architects 1735 New York Avenue, N.W. Washington, D.C. 20006-5292 02000 AIA® AIA DOCUMENT G701-2000 INSTRUCTIONS The American Institute of Architects 1735 New York Avenue, N.W. Washington, D.C. 20006-5292 2 • • Instructions GENERAL INFORMATION PURPOSE. This document is intended for use in implementing changes in the Work agreed to by the Owner, Contractor and Architect. Execution of a completed G7os form indicates agreement upon all the terms of the change, including any changes in the Contract Sum (or Guaranteed Maximum Price) and Contract Time. RELATED DOCUMENTS. This document was prepared for use under the terms of AIA general conditions, including AIA Document Azot, General Conditions of the Contract for Construction, and the general conditions contained in AIA Document Any, Abbreviated Owner -Contractor Agreement Form for Construction Projects of Limited Scope—Stipulated Sum. USE OF CURRENT DOCUMENTS. Prior to using any AIA document, the user should consult the AIA, an AIA component chapter or a current AIA Documents Price List to determine the current edition of each document. REPRODUCTIONS. AIA Document G7os is a copyrighted work and may not be: reproduced or excerpted from in substantial part without the express written permission of the AIA. The G7os document is intend- ed to be used as a consumable—that is, the original document purchased by the user is intended to be con- sumed in the course of being used. There is no implied permission to reproduce this document, nor does membership in The American Institute of Architects confer any further rights to reproduce G701 in whole or in part. A limited license is hereby granted to retail purchasers to reproduce a maximum of TEN copies of a com- pleted or executed G7os, but only for use in connection with a particular project. COMPLETING THE G701 FORM DESCRIPTION OF CHANGE IN THE CONTRACT Insert a detailed description of the change or reference specific exhibits describing in detail the change to be made in the Contract by this Change Order, including any Drawings, Specifications, documents or other supporting data to clarify the scope of the change. DETERMINATION OF COSTS Insert the following information in the blanks provided, and strike out the terms in parentheses that do not apply: • the original Contract Sum or Guaranteed Maximum Price; • the net change by previously authorized Change Orders (note that this does not include changes authorized by Construction Change Directive unless such a change was subsequently agreed to by the Contractor and recorded as a Change Order); • the Contract Sum or Guaranteed Maximum Price prior to this Change Order; • the amount of increase or decrease, if any, in the Contract Sum or Guaranteed Maximum •Pfice; and • the new Contract Sum or Guaranteed Maximum Price as adjusted by this -Change Order. CHANGE IN CONTRACT TIME Insert the following information in the blanks provided, and strike out the terms in parentheses that do not apply: • the amount in days of the increase or decrease, if any, in the Contract Time; and • the date of Substantial Completion, including any adjustment effected by this Change Order. EXECUTION OF THIS DOCUMENT When the Owner and Contractor, in concurrence with the Architect, have reached agreement on the change to be made in the Contract, including any adjustments in the Contract Sum (or Guaranteed Maximum Price) and Contract Time, the G7ot document should be executed in triplicate by the two par- ties and the Architect, each of whom retains an original. WARNING: Unlicensed photocopying violates US. copyright laws and will subject the violator to legal prosecution. NAME OF FILE: CROSS REFERENCE: m# Date Resolution No. 169-03 Document 1 11.15.03 Res. 169-03 w/change order 2 10.29.03 memo to mayor & city council draft resolution copy of memo to Bob Kohler copy of Crossland potential change orders copy of proposed change order copy of potential change order request copy of Beaver Electric Itr copy of Fayette Tree & Trench, Inc. invoice staff review form memo to city council 1/ . 3a . 03 memo to Louise Schaper NOTES: • • For City Council Agenda November 18, 2003 To: Mayor Dan Coody and City Council From: Louise Schaper, Library and Bob Kohler, Owner's Representative Date: October 29, 2003 2 ////8103 /6? Gr055/01d frJ Subject: Approve a contract adjustment to the original contract dated May 21, 2002 in the amount of $110,117 with Crossland Construction Company for the installation of underground utilities to seven housing structures adjacent to the library along the west side of West Avenue. Recommendations We recommend the City Council approve the contract adjustment in the amount of $110,117 to install underground utilities to the seven residences along West Avenue and a spare conduit that allow connectivity from the new building to the City computer network. Background On October 21, 2003 the Fayetteville City Council approved a resolution allowing AEP/SWEPCO to begin work on underground utility installation for primary power to the new library building and for primary and low voltage power to pedestals that serve the seven residences adjacent to the library site. Code -related library construction requirements include the removal of overhead utility lines and poles that currently exist along the east side of West Avenue. These lines serve the residences facing the new building on the west side of West Ave. This contract adjustment includes all remaining work not included in the October 21 action that will provide permanent electric power, phone and TV cable to the residences that are otherwise deprived of these services as a direct result of library construction and the removal of the existing poles. Included in this work is the trenching, removal and replacement of all concrete, provide and install all conduit from AEP/SWEPCO pedestals, install new meters provided by AEP/SWEPCO, provide and install conduit and wire from new meter to the existing panels or newly provided panels. The scope of work extends to the final termination at an exterior electrical panel of each residence. Also included in this request is the installation of a 2" conduit for future library use to connect to City computer network from an existing pole north of Mountain St. to an existing pull box. DISCUSSION Crossland Construction Company has bid this work through the electrical subcontractor for the project, Beaver Electric, which has in turn bid the trenching work through the approved bidding process to the winning bidder, Fayette Tree and Trench. The architects, MS&R, and the consultant for associated engineering services, Green Anderson, have reviewed and recommend approval of the proposal. BUDGET IMPACT While this project was not in the original contract with Crossland Construction, it was budgeted in the CIP for site improvements. • • RESOLUTION NO. A RESOLUTION APPROVING CHANGE ORDER # 12 TO THE CONTRACT WITH CROSSLAND CONSTRUCTION COMPANY, INC. IN THE AMOUNT OF ONE HUNDRED TEN THOUSAND ONE HUNDRED SEVENTEEN DOLLARS (5110,117.00) TO INSTALL UNDERGROUND UTILITIES TO SEVEN (7) RESIDENCES ADJACENT TO THE NEW FAYETTEVILLE PUBLIC LIBRARY. BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS: Section 1. That the City Council of the City of Fayetteville, Arkansas, hereby approves Change Order # 12 to the contract with Crossland Construction Company, Inc. in the amount of One Hundred Ten Thousand One Hundred Seventeen Dollars (5110,117.00) to install underground utilities to ses (' ) residences adjacent to the new Fayetteville Public Library. A. cop roof Change Order # 12, marked Exhibit "A" is attached hereto and madepAit hereof PASSED and APPROVED this 18th day of November 200003. APPROVED: \ AFIEST: 1 By: SONDRA gIVIFIH, Gity Clerk GOODY, Mayor • AmirmoezFosterHaileyJohnson 'Mil Architects & Planners MEMORANDUM October 27, 2003 To: Bob Kohler Copy: John Priest Sean Wagner Mike Green Kip Guthrie From: Jim Fo The engineers an• architects recommend approval of Crossland Construction Company's ..sal for providing underground utilities to residents adjoining the library along the west side of West Avenue The attached Potential Change Order 35 covers work described in Proposal Request 23, also attached. Documents also include a breakdown of pricing by Beaver Electric and their subcontractor, Fayette Tree and Trench. Sheet U 101 A was revised to cover work by AEP and their subcontractor, as well as work by a separate Electrical Contractor. The scope of work covered by this price is both work indicated to be by Electrical Contractor and to provide for items excluded by the AEP proposal. Conduit for SBC and Cox cable are included as well as a separate conduit for future library use to connect to the City's computer network. • If approved, the total change would be $110,117.00. Ninety percent of this amount was never in the Library budget. That is the portion related to reconnecting these residents with buried utilities. Providing overhead service to these residents would been somewhat Tess costly but it would have caused conflicts between required easements and existing homes as well as severe surgery on existing trees. Time is critical to have this work approved and we advocate that it be on the November 18 Council agenda. Some of the aspects relate to AEPs work to bring permanent power to the Library since SBC and Cox cable conduits would be placed at the same time. It would also be in the best interest of the City to have the trenches for residential service provided concurrently by the AEP subcontractor. Their larger excavating equipment would probably be more effective in the subgrade of West Avenue than the rubber tired backhoe that Beaver Electric has available. Reference: yetteville bbc Library, Proposal Request 23 Post Office Box 790. 100 West Center, Suite 302 • Fayetteville, AR 72702.479-442-5565 • FAX 479-442-£3849 Potsial Change Orders I • • Crossland Construction Company Fayetteville Public Library 2A07Z0 401 West Mountain Street Fayetteville, AR 72701 Detailed Report Date Range: All Dates Pnnted on: 10/17/03 0043 PCO #35 - PR #23 Permanent Power for Residents on West Ave. Date: 10/17/03 n Category , Reason U'• IRefa. renclt,y:"‘"777:7;--77-7n. Pending ser..Deflnedneldl`; f ---r7 "'" Architect Directive Days Raq,d Day1i.'Apprd 'DatelReq'd;Data D ne : � ,Closed' ;�_Nottiy' �,;:Total'Orig EsY�. ;Total Prop'd.�::. TotahApprd; 0 00 o.00 No No 0.00 110,117.00 0.001 COR.No-JPCCO:No`Y: Reference;Document-�;::=; ;'.;,;Notes:z�.'i',° =,r';; -i • item:No i rcompanyr'-i`<."_':"-:' Budpet•Allocatio 0001 Deso etient>•t :++..�,i�: 's , , <.i...k Approximate Changes Permanent Power for West Ave n �"`I:Budget Code 'ItemrNo[es- • — r •Prop Amtl 'ApprAmf CO NOii_s' r 110,117.001 0.001 1 C:1P R O L O G 4\PROJECTS\L I B RAR Y. P M D Page 1 *AAA Contra Administration G709 Work Changes Proposal Request • (Instructions on the rev rse side) PROJECT (Name and address): FAYETTEVILLE PUBLIC LIBRARY 401 WEST MOUNTAIN STREET FAYETTEVILLE, ARKANSAS 72701 OWNER (Name and address): CITY OF FAYETTEVILLE 113 WEST MOUNTAIN STREET FAYETTEVILLE, ARKANSAS 72701 FROM 143OtlaRIOMCGOOMXXXPASSOCiATE ARCHITECT AMIRMOEZ FOSTER HAILEY JOHNSON PO BOX 790 FAYETTEVILLE, ARKANSAS 72702-0790 TO CONTRACTOR (Name and aadress): CROSSLAND CONSTRUCTION COMPANY INC. ATTN: JOHN PRIEST, PROJECT MANAGER PO BOX 907 ROGERS, ARKANSAS 72756 Please submit an itemized proposal fur changes in the Contract Sum and Contract Time for proposed modifications to the Contract Documents described herein. Within _TEN ( 10 ) oays. the Contractor must submit this proposal or notify the Architect. in writing. of the date on which proposal submission is anticipated. THIS IS NOT A CHANGE ORDER. A CONSTRUCTION CHANCE DIRECTIVE OR A DIRECTION TO PROCEED WITH THE WORK DESCRIBED IN THE PROPOSED MODIFICATIONS. PROPOSAL REQUEST NUMBER DATE OF ISSUANCE: CONTRACT FOR: CONTRACT DATE: ARCHITECTS PROJECT Distribution List: Owner Architect Consultant Contractor Field Other Twenty Three (23) October 8, 2003 GENERAL CONSTRUCTION MAY 21, 2002 NUMBER: 2000073-00 DESCRIPTION (Insert a written description or the Work): 1. Provide for West Avenue utilities indicated on Sheet U101A indicated to be by Electrical Contractor as well as work excluded by the proposal from AEP/SWEP including conduit and pull rope for SBC and Cox Communication to be installed by Fayette Tree and Trench. Sheets C106 and C108 indicate changes in curb and sidewalk to accommodate utilities. 2. Provide 1 additional 2" conduit for future Library use to connect to City computer network from the existing pole north of Mountain Street to a pull box connected to the 2" spare conduit included in the Library contract. Arrange with Fayette Tree and Trench to install this added conduit along with others for Cox Cable. ATTACHMENTS (List attached documents that support description): See Drawing Sheets previously reissued: U101A sealed by Michael Green 8/18/03, and C106, C108 signed by Kip Guthrie 8/14/03. Letter proposal from AEP/SWEP Floyd Homaday dated 9/18/03. REQUESTED BY TH .�,+ • XXX ASSOCIATE ARCHITECT James R. Foster, FAIA BY—r/.eriewie 2a7. (Sig . ture) (Printed name and title) CAUT10 .. u snould sign an original AIA Contract Document. an wnich this text appears in RED. An original assures changes will not be obscured. AIA Document G709 Work Changes Proposal Reouosl O 2001 Tho American Institute of Architects • Wasn•nglon, DC • lvww.aa otg WARNING: Reproduction. unlicensed pnotocopying or substantial quotation of the Inatenal herein witnout written permission of the AIA violates the copyright laws of the United States and will subldn the violator to legal prosecution. To report copyright vidalions et AIA Contract Documents. e-mail The American Insttule el Architects' legal counsel. cppynghrOara.org. • • GRAND TOTAL FOR CHANGE n 0 x -o CCC Overhead @ 15.00% CCC Bond @ 1 00% CCC Insurance @ 0.15% Subcontractor Total Labor Direct Cost Material Direct Cost Totals 'Beaver Electric Z d 3 A Subcontractor Pricing unit cost will be charged. If rock in encountered the originally agreed Conduit and pull rope for SBC and Cox Repair home puddy and paint Repair homes_ replace roof, siding, & paint_' Description 0 N Q N !drawings issued on August 18. 2003. [include rock Trenching or rock removal. Pricing bases on SWEPCO pedestals. install new meter provided by SWEP( and replace all concrete, provide and install conduit from 1119. and 127 West Avenue. Price includes trenching. remove Providing underground service to 101, 10! Description of Work N 0 C O CO 0 > w' n 0 0 �w r o $ 4,578.001 $ 1,823.30 +A $ 153.801 MEN*A M o e — c E Quantity _ O in 01 O N Cn Co CA CD O1 D I-- CII LA LD UDN O .-- Acn CA CA Cn VD O ID VD • - O c a F m - m, MATERIAL SU TAX AS APPLICABLE MATERIAI In IK — N — N N C w Days Req manent Power for Residents on We meter to the Price does not -4 O Di -1 O s r -- IA MMMMM N 01 S $ 7,500.00 $ 75.00 $ 200.00 t7 " d qnS I N .TOTAL 3TOTAL 8.375% Unit M IAIA M IAM IA M :3? .- co d C CD C •-• " -. Apprc 559.90 8 A MMIA IA IA M MM IA MM M IA Material Cost _ CU 734.91 DuI 2 3 C7 ID G D CO - cn pN O V in 8 O O 1,200.00 of Fayetteville, Arkansas oez•Foster Hailey Johnson Carpenter & (2) Laborer Layout Eng. & (1) Laborer Carpenter & (1) Laborer Concrete Finisher Laborer Carpenter Operator w/ Equipment Description CCC Crew Type LABOR SUB' LABOR BURDEN LABOR J hr hr hr hr hr hr hr Is hr L 0 = N hrl hrl hr hr hr hr hr hr W J -' B hr Crew Type cpmmOC/W Dm y m NIA IA MMM IAM $ 75.00 IA N O g Labor Cost MIN M IAIAMI4 0 O N_ \ S N v't s l IAM N pp O 888 V O OD 25.00 20.00 30.00 50.00 C Pi qui — V N aznvcR CLGLIKIL LU. • • BEAVER ELECTRIC CORPORATION 208 N. Block P.O. Box 1071 Fayetteville, Arkansas 72702 Phone: (479) 442-8755 Fax: (479) 442 0938 PROPOSAL CONTRACT Date: 10-16-03 Crossland Construction 3015 East Skelly Drive Tulsa, Ok 74105 Ph.479-571-2322 Fax 479-571-3748 Ph.620-429-1414 Fax. 620-429-8948 Att. John Priest, Subject: Request for Pricing ASI # 23, Re• ASI # 23 breakdown, Dear Mr. Priest, P.01/02 Change Order Num. 0017 Be advised of the following changes to the Fayetteville Public Library job, per ASI request number 23. Scope of Work: Provide all new electrical services, conduit, wire, and electrical devices as directed in Architects Supplemental Instructions No. 23. Scope of Work Matenal Tax Labor Sub Con. 08P Total ASI # 15 $29,281 $ 1,582 $ 16,113 535,750 stews $ 95,549 14 g332 - Total Pnce $l1p5i979O Allow 3-6 weeks for deliveryof �al approval. equipment atter written release and equipment submittal approval. Prices quoted are subject to cancellation or escalation if not accepted within 30 days. Terms are Net 30 days. Please review the following inclusions: 1) Rigid conduit will be installed from below grade to 5 feet above grade. 2) Emt conduit will be used 5 feet above grade. 3) All fittings for Emt conduit will be die cast. 4) Nema 3R boxes to be mounted 18 inches above grade for SBC and Cox cable use. 5) Provide all pull - strings for SBC and Cox cable in underground conduits. 6) Beaver Electric will provide new cable from power company transformer to new or existing meter bases. 7) The following residences will receive new service panels 101, 105 and 115. 8) The following residences will reuse existing meter bases and panels 107, 111, 119 and 127. • • • • OCwCM1 ❑LCL i K I L LU. • • P.02/02 9) Residence 115 will be reconnected with only 2 circuits since this home only has 2 power circuits. 10) Repair of street crossings. Please review the following exclusions: 1) Overtime. (Our price is based on a continuous work schedule with normal working hours from 7:00am. To 3:30 Monday thnx Friday. 2) Painting. 3) Repairing of existing roofs. 4) Permits. 5) All SSC and Cox pedestals. 6) All Transformers and pads by others. 7) Removal of existing overhead wire. 8) Repairing of siding. 9) Asbestos testing and abatement. 10) Any wiring for SBC and Cox cable by others. 11) All power company terminations by others. This includes transformer and meter base terminations. 12) Temporary power for residences. 13) Rock excavation extra. Please forward Jo green Anderson for approval ASAP. / ohn Williams Project Manager TOTAL P.02 10/27/03 11:01 FAX 316 429 1412 CHUSSLANI CUNSTHCC1IUN OCT -27-2003 09.07 • 9ERUER ELECTRIC CO Fayette Tree & Trench, Inc. P. 0. Box 471 Fayetteville, AR 72702-0471 NAME/ADDRESS BEAVER ELECTRIC 208 N. BLOCK STREET FAYETTEVILLE, ARKANSAS ATTENTION: CHUCK • igl UU2 P.02/02 BID PROPOSAL DATE 9/19/2003 DESCRIPTION QTY COST TOTAL RE: FAYETTEVILLE PUBLIC LIBRARY WEST STREET SERVICE LINES TO EXISTING HOUSES INSTALLATION OF CONDUITS ACROSS WEST STREET & TO METER LOCATION INSTALLATION OF 7 STREET CROSSINGS (CONDUIT NOT INCLUDED EN PRICE) REPADIING CROSSLNGS TO CITY OF FAYETTEVILLE CODES RESTORING YARDS AS NEEDED PULL ROPES IN CONDUIT PUT TOGETHER CONDUIT NOTE, PRICE DOES NOT INCLUDE CONDUIT OR MATERIALS RELATED TO WIRING UP HOUSES ROCK EXCAVATION EXTRA 35,750.00 35750.00 TOTAL 535,750.00 TOTAL P.02 • STAFF REVIEW FORM • X AGENDA REQUEST CONTRACT REVIEW GRANT REVIEW For the Fayetteville City Council Meeting of: November 18, 2003 FROM: Louise Schaper Library General govemment Name Division Department ACTION REQUIRED: Approve a contract adjustment to the original contract dated May 21, 2002 in the amount of $110,117 with Crossland Construction Company for the installation of underground utilities to seven housing structures adjacent to the library along the west side of West Avenue . COST TO CITY: $110,117 $ 211891,640 New Main Library Cost of this request Category/Project Budget Program Category / Project Name 4470-9470-5804-00 $ 16,315,177 New Main Library Account Number Funds Used to Date Program / Project Category Name 99073 $ 5,5761463 Capital Improvements Project Project Number Remaining Balance Fund Name BUDGET REVIEW: Budget Manager X Budgeted Item eS 2d C.J Date Budget Adjustment Attached CONTRACT/GRANT/LEASE REVIEW: % atd-ct tit /OIdB%4s �� i - 101750iO3Accounting Manager Date Internal A itor Date CL" 10/31 i City Attorne Purchasing Manager Date STAFF RECOMMENDATION: Division Head Department Director Date Date II rnal Services Dir. Date Chief nistrat ue Officer Cross Reference New Item: Yes No Previous Ord/Res#: Orig. Contract Date Orig. Contract Number li/37 i • //-/�,a /993 01205,49 Date: December 11, 2002, rev. 1/16/03, 1/23/03, 5/5/03, 9/29/03; 11/12/03 To: Fayetteville City Council Aldermen From: Louise Schaper, Executive Director, Fayetteville Public Library Subject: Blair Library Project Budget and Contract Approvals This table identifies those requests related to the construction of the Blair Library that Council has approved, as well as forthcoming requests. Our intent is to ensure that Council is aware of all requests that are within our $23,341,655 budget for the turnkey project as approved by the FPL Board on May 2, 2002 and those items that are outside of this budget. Some of the forthcoming items, i.e. furnishings, may be procured directly by the FPL Foundation. The second page identifies those items related to off-site improvements (utility burial, drainage, sidewalks etc.) approved in CIP ($671,995). Because additional off-site improvements have been requested by City departments and will be funded by these departments we list them here as well. hem Within budget? Source(s) Budget Est. date approval Date Approved Notes Amount Blair Library Construction, Furnishing and Equipping Crossland contract for construction Yes sales tax + private 5/21'/02 j7j33l Includes site improvements funds $221,995 for off - from CIP Contingency Yes sales tax + private $830,000 5721%02 $7007,000 lintels $167,676 approved Deferred will planned remaining of contingency from contract. APC be at entrance as and brick will clad + stairwell towers. Exterior cladding: APC replacement Yes sales tax + private $949.658 $470,000 $980,000 11/02 S jj2jj Low voltage equipment Yes sales tax + private 10721%03 $206)701 Deferred from contract. Low voltage conduit Yes sales tax + private 4Q03 Deferred from contract Landscape Yes sales tax + private 1004 Deferred from contract Interior signage Yes sales tax + private 2004 Deferred from contract AV Equipment Yes sales tax + private 2004 Deferred from contract Meeting room enhancements Yes sales tax + private sales tax + private private 2004 2003-04 2003-04 _ _ _ Deferred from contract Includes shelving, seating, work stations etc. Technology related items Yes Fumishings Yes Smart e.g. conveyor, self -check, RFID library, Yes sales tax + private $659,751 5/03 5/03 $395T632 Conveyor RFID -- Self -check Moving costs Yes sales tax + private $30,000 $0 2004 N/A _ _ _ .... Such as staff lockers, full signage package, meeting room divider, .fano. Unfunded and cut items. No • '/g'03 4 3 dwss od arm"' Czt C+ou(aok Item Within budget? Source(s) Budget Est. date approval Date Approved Amount Notes Off -Site Improvements Related to Blair Library Off-site improvements (see first item above) Yes Off-site CIP $221,995 5/21702 $2214995 In Crossland Contract. but funded from CIP site improvements project. Includes sidewalks etc. West Avenue underground utilities Yes Off-site CIP $101,806 10/21703 $101!806 West Ave underground utility permanent power. Vendor is AEP/SWEPCO. West Avenue underground utilities to residences Yes Off-site CIP $110.117 11/18/03 ' $1'10,117 Addition to Crossland contract for installation of underground utilities to seven housing structures adjacent to Blair Library on west side of West Avenue. Water and sewer improvements in the streets adjacent to Blair Library Not in library budget. In Water & Sewer Funds Water and Sewer Funds $41,342 11/18/03 ' $41342 .. Improvements to water and sewer that were identified after contract was signed with Crossland. Includes new 6- waterlines in Mountain; 8- waterline in School- 8' sanitary sewer in Rock and 1T waterline in Rock. These improvements are requested to correct leaking, deteriorated and undersized old water and sewer lines in the streets adjacent to Blair Library. FAYETTEVA,LE THE CITY OF FAYETTEVIllC ARKANSAS DEPARTMENTAL CORRESPONDENCE • To: Louise Schaper Fayetteville Public Library From: Clarice Buffalohead-Pearman City Clerk Division Date: November 21, 2003 Re: Res. No. 169-03 Attached is an executed copy of the above resolution, approved by the City Council on November 18, 2003, authorizing Change Order No. 12 to the contract, with Crossland Construction Company, Inc. to install underground utilities to seven residences adjacent to the new library. Also I am retuming to you five additional original change orders signed by the mayor. This resolution and change order will be recorded in the city clerk's office and microfilmed. If anything else is needed please let the clerk's office know. /cbp attachments cc Nancy Smith, Internal Auditor