HomeMy WebLinkAbout86-02 RESOLUTION• • • RESOLUTION NO. 86-02 A RESOLUTION TO APPROVE A CHANGE ORDER IN A DECREASED AMOUNT OF $102,205.00 WITH APAC- ARKANSAS, INC. FOR THE TAXIWAY STRENGTHENING AND WIDENING PROJECT BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS: Section 1. That the City Council of the City of Fayetteville, Arkansas hereby approves the Change Order for the taxiway strengthening and widening project including parking ramp expansion performed by APAC-Arkansas, Inc. which will result in a cost reduction of $102,205.00. The Mayor is authorized to sign said Change Order (attached as Exhibit A). PASSED and APPROVED this the 4th day of June, 2002. •J R • t�lll�ijrpt, ather Woodruff, City C 1 APPROVED: By: DAN COODY, May • NAME OF FILE: CROSS REFERENCE: Resolution No. 86-02 • 06/04/02 Resolution No. 86-02 05/15/02 Change Order No. 2 (Agreement Date is 09/04/01) with APAC- Arkansas, Inc., McClinton Anchor Division, for airfield pavement rehab. & taxiway widening & strengthening - Drake Field 06/04/02 Copy of the Budget Adjustment Form 05/17/02 Memo to Mayor Coody & City Council Committee from Ray M. Boudreaux, Director, #2 - Airfield Pavement Rehabilitation/Taxiway Members thio Staff Review regarding Change Order Widening 06/04/02 Staff Review Form 06/05/02 Memo to Ray Boudreaux, Fayetteville Municipal Airport, from Heather Woodruff, City Clerk NOTES: • • Res. 86-02 CHANGE ORDER Order No. 2 Date: May 15. 2002 Agreement Date: September 4 . 2001 NAME OF PROJECT: Airfield Pavement Rehab. & Taxiway Widening and Strengthening - Drake Field OWNER: City of Fayetteville (Airport Department) CONTRACTOR: APAC-Arkansas Inc.. McClinton Anchor Division The following changes are hereby made to the CONTRACT DOCUMENTS: 1. Revise the Quantity for Bid Item No. 3 for Unclassified Excavation for the East Apron due to existing Select Material under the Apron Expansion Area Reduce the Quantity for 18,400 Cy to 13,100 CY at $10.40/cy. Deduct cost of $ 55,120.00 from contract. 2. Revise the Quantity for Bid Item No. 5 for Select Borrow Embankment for the East Apron due to existing Select Material under the Apron Expansion Area. Reduce the Quantity for 16,600 Cy to 13,200 CY at $18.80/cy. Deduct cost of $ 63,920.00 from contract. 3. Relocate the taxiway widening and strengthening from Taxiway "F" to Taxiway "D" between the Runway and Taxiway "B". Adjust the quantities and cost per the attached page 3 of 3 of this Change Order. Add cost of $ 12,475.50 to contract. 4. Add Bid Item No. 56 for the 1" Conduit to relocate Runway Light cable in radii for 400 LF at $1.95 per LF. Add cost of $ 780.00 to contract. 5. Add Bid Item No. 57 for Underdrain connection to existing Pipe or Inlet Structure for 2 each at $ 515.00 per each. Add cost of $ 1,030.00 to contract. 6. Add Bid Item No. 58 for Stone Backfill of subgrade stabilization for 75 Tons at $ 34.00 per Ton. Add cost of $ 2,550.00 to contract. Justification: 1 82 The east Apron Expansion area, when previously expanded, had select borrow material placed 60plus feet east of the east edge of the apron. This select borrow material is three (3) to five (5) thick and therefore the need to excavate this material per the plans is not required and the quantity of borrow material required is therefore less. The excavation quantity saved is 5300 CY and the Borrow material quantity saved is 3400 CY. 3. The Federal Funding for the east parallel taxiway is not available to extend to Taxiway "F. Therefore the Forest Service Fire Fighting Aircraft will need to use Taxiway "D" to return the their base n the east side of the Airport. 4. The radii extensions on Taxiway "D° each side of the Runway require the relocation of two runway lights, lighting cable and the 1" conduit for the cable between the runway light bases. 5. The underdrain in two locations needs to be connected to existing storm drainage facilities. The original planned underdrain was to drain to daylight from the East Apron. 6. The subgrade in several locations have water seepage that continues to saturate the select embankment. J:1200010021051G1ange-Orderslc-order-2.wpd Page 1 of 3 r • • Res. 86-02 The installation of an 18" layer of Stone Backfill (3" to 5") wrapped with filter fabric will allow for completion of the embankment material. The underdrains also serve to drain these areas. CONTRACT PRICE prior to this Change Order: Decrease in Contract Price. Revised CONTRACT PRICE Including this Change Order: Final Completion Time Prior to This Change Order: Net Time Change Resulting From This Change Order: Current Contract Completion Dates Including This Change Order: Completion Date: Change to CONTRACT TIME: The CONTRACT TIME will be (increased) (decreased) by 0 calendar days. $ 2,560,744.25 ($ 102,205.00) $ 2,458,539.25 150 Calendar Days 0 Calendar Days July 1. 2001 Approvals Required: To be effective this Order must be approved by the Owner if it changes the scope or objective or the PROJECT, or as may otherwise be required�Ge rbybythe GENERAL CONDITIONS. A Requested by: ri rnai &. APAC- Arkansas, Inc., McClinton Anchor Division Recommended by: Approved by: Vl� (land Con City of Fayetteville J:120001002105Change-Orders\o-ofter-2.wpd Page 2 o/ 3 05//4/az Date 5-45^-02 Date Da e • • • Change Order #2 Fayetteville Municipal Airport (Drake Field) Airfield Paving Rehab & Taxiway Widening & Strengthening May 1, 2002 Work to be Added to Protect Res. 86-02 Bid Item No. Description Unit Unit Price Unit Price Plan $ Taxiway "F" Plan Qty Plan $ Taxiway "D" (Runway to Taxiway "B") 2 Topsoil Removal (Plan Quantity) CY 59.40 250 $2,350.00 3 Unclassified Excavation (Plan Quantity) CY $10.40 2 Topsoil Removal (Plan Quantity) CY 4 $9.40 Quantity) CY 250 $2,350.00 3 Unclassified Excavation (Plan Quantity) CY Select Borrow Embankment $10.40 CY $18.80 500 675 $7,020.00 4 Embankment from Excavation (Plan Quantity) CY 100 $1,625.00 56.55 8 Soil Stabilization 175 51,146.25 $1.30 5 Select Borrow Embankment (Plan Quantity) CY 9 518.80 Milling SY 450 100 58,460.00 12 6 Topsoil Replacement (Plan Quantity) CY 650 $16.25 $12,740.00 200 13 53,250.00 8 Soil Stabilization Fabric SY 300 515,600.00 $1.30 Asphalt Leveling 900 $11170.00 559.25 9 Asphalt 15 Milling TON SY 390 521,391.50 56.45 Bituminous Prime Coat GAL 52.40 100 5645.00 17 12 Crushed Aggregate Base Course TON 200 $19.60 18 Crack Cleaning & Sealing GAL 600 $11,760.00 500 13 Asphalt Binder Course TON Control $52.00 GAL $1 55 369 290 $15,080.00 35 Seeding, Fertilizing & Mulching 14 Asphalt Leveling or Strengthening Course TON $471.00 $59.25 Taxiway Light Relocation including Base EA $405.00 410 $24,292.50 15 Asphalt Surface Course TON $101.50 $54.85 8 5812.00 270 $14,809.50 16 Bituminous Prime Coat GAL 51,520.00 52.40 56,080.00 42 210 LF $504.00 700 17 Bituminous Tack Coat GAL LF 51.05 $2.05 650 380 539900 44 18 Crack Cleaning & Sealing GAL 40 $0.71 450 5319.50 35 Seeding, Fertilizing & Mulching AC $1,570.00 0.32 5502.40 37 Taxiway Light Relocation including Base EA $405.00 16 56,480.00 39 Taxiway Light Base Removal EA $101.50 _16 $1624.00 41 Relocate Taxiway Sign EA $1,520.00 3 $4,560.00 42 Lighting Cable, Counter & Cable Trench LF $5.08 950 $4,826.00 43 2" Condiut for Lighting Cable LF $2.05 900 $1,845.00 44 2 -way, 4* Electrical Duct LF 576.10 40 $3,044.00 Total for Items Work to be Deleted from Project 5114,087.15 Bid Item No. Description Unit Unit Price Plan Qty Plan $ Taxiway "F" ( Runway to Taxiway "B" ) 2 Topsoil Removal (Plan Quantity) CY 59.40 250 $2,350.00 3 Unclassified Excavation (Plan Quantity) CY $10.40 800 $8,320.00 4 Embankment from Excavation (Plan Quantity) CY 56.55 150 5982.50 5 Select Borrow Embankment (Plan Quantity) CY $18.80 500 59,400.00 6 Topsoil Replacement (Plan Quantity) CY $16.25 100 $1,625.00 8 Soil Stabilization Fabric SY $1.30 950 $1,235.00 9 Asphalt Milling SY 56.45 100 5645.00 12 Crushed Aggregate Base Course TON $19.60 650 $12,740.00 13 Asphalt Binder Course TON $52.00 300 515,600.00 14 Asphalt Leveling or Strengthening Course TON 559.25 120 $7,110.00 15 Asphalt Surface Course TON 554.85 390 521,391.50 16 Bituminous Prime Coat GAL 52.40 225 5540.00 17 Bituminous Tack Coat GAL $1.05 200 $210.00 18 Crack Cleaning & Sealing GAL 50.71 500 5355.00 19 Crack Control Fabric GAL $1 55 369 $571.95 35 Seeding, Fertilizing & Mulching AC 51,570.00 0.3 $471.00 37 Taxiway Light Relocation including Base EA $405.00 8 $3,240.00 39 Taxiway Light Base Removal EA $101.50 8 5812.00 41 Relocate Taxiway Sign EA 51,520.00 4 56,080.00 42 Lighting Cable, Counter & Cable Trench LF $5.08 700 $3,556.00 43 2' Condiut for Lighting Cable LF $2.05 650 $1,332.50 44 2 -way, 4' Electrical Duct LF 576.10 40 53,044.00 Total for Items $101,611.45 Total Addition Project Cost $12,475.70 J:1200010021051Change-Orderslchangeorde2.wb3 Page 3 of 3 • City of Fayetteville, Arkansas Budget Adjustment Form • Res, 86-02 Budget Year Department: Aviation & Economic Development 2002 ivision: Airport gram Capital Date Requested 06/04/2002 Adjustment # Project or Item Requested. To recognize $91,982 reduction in Fed. Grant Revenue To recognize $ 5,110 reduction in State Grant Revenue Increase Use of Fund Balance $5,110 Project or Item Deleted: $102,202 reduction to Pavement Rehabilitation & Maint. Capital Project CC ?Y, Justification of this Increase: APAC/ McClinton Anchor Change Order #2 will reduce the project cost, thus reducing associated grant revenues which are based on percent of project cost as follows: Federal - FAA 90% State - Dept of Aero 5% Local - Airport Fund 5% Justification of this Decrease: APAC/ McClinton Anchor Change Order #2 will reduce the project cost. Sufficient funding remains to comply with City Policy. Account Name Federal Grant #29 State Grants on Federal Projects Increase Expense (Decrease Revenue) Amount 91,982 5,110 Use of Fund Balance 5110 Account Name Pavement Maint 8 Rehab Account Number 5550 0955 6820 5550 0955 6803 29 00 5550 0955 4999 99 Decrease Expense (Increase Revenue) Amount 102,202 Account Number 5550 3960 7820 Project Number 00029 1 • Project Number 29 00029 1 Approval Signatures Requested By Date Admin. Servj4s Director Mayor Budget Office Use Only Type: A B Date of Approval Posted to General Ledger Posted to Project Accounting Entered in Category Log Blue Copy. Budget & Research / Yellow Copy: Requester C D E FAYETTEVILLE THE CITY OF FAYETTEVILLE, ARKANSAS DAN COODY, MAYOR AVIATION AND ECONOMIC DEVELOPMENT RAY M. BOUDREAUX, DIRECTOR TO: THRU: FROM: DATE SUBJECT: Dan Coody, Mayor City Council Member Staff Review Com Ray M. Boudreau May 17, 2002 Change Order # 2 — Airfield Pav-ment Rehabilitation /Taxiway Widening 11 • 4500 School Ave., Suite F Fayetteville, AR 72701 501.718.7542 Background: APAC Inc., McClinton Anchor Division began construction on the Airfield Pavement Rehabilitation and Taxiway Widening project in September, 2001. The project consists of taxiway strengthening and widening, and includes parking ramp expansion of the east -side general aviation ramp. Purpose: APAC Inc., McClinton Anchor Division has submitted Change Order #2 which represents a net reduction of $102,202 to the Contract amount. The Change Order is the result of a reduction to the quantity of select fill materials due to the existing presence of materials in the work area, plus additional conduit for Runway lighting electrical, underdrain connection pipe, and stone backfill materials. Budget Considerations: The Change Order represents a reduction to the project cost. A Budget Adjustment reflecting the budget changes is attached. Requested Action: Staff recommends approval by the City Council of Change Order #2 to APAC Inc., McClinton Anchor Division, and the associated Budget Adjustment. RMB/jn Attachments: /4/ Budget Adjustment Form McClelland Consulting Engineers, Inc.; letter 4 originals; Change Order #2 Project expense summary Protect Name: AIP #: State Aero Grant: AS400 Project #: Vendor: Bid #: Contract #: Contract Amount: Change Order #1: Contract Total: Date: 21 -Nov -01 07 -Jan -01 15 -Feb -02 15 -May -02 Totals Check # 286131 287720 289384 submitted • Pavement Rehabilitation & Apron AIP3-05-0020-2901 1853-01 00029 APAC - McClinton Anchor 01-46 814 $2,713,912.65 $5,321.60 $2,719,234.25 Expense Retainage Subtotal 135,638.20 329,948.96 168,295.53 65,428.65 699,311.34 Retainage Payment (12,924.37)122,713.83 (32,994.90) 296,954.06 (16,829.55)151,465.98 (6,542.87) 58,885.78 0.00 0.00 (69,291.69) 630,019.65 Cloocuments and SettingsljniUwlsai My DocumentsUameslproLtrackWroj_#29_Construction. 123 • Project Balance 2,596,520.42 2,299,566.36 2,148,100.38 2,089,214.60 2,089,214.60 2,089,214.60 • NZEMcCL 11 LA CONSLJL TING I DESIGNED E0 SERVE I ENGINEERS, INC. May 15, 2002 • P.O. Box 1229 Fayetteville, Arkansas 72702-1229 501-443-2377 FAX 501-443-9241 Mr. Ray Bourd = - ux Airport Depa ent City of Faye evi le 113 West ountain Fayettev e AR 72701 RE: Airfield Pavement Rehabilitation & Taxiway Widening and Strengthening Drake Field AIP 3-05-0020-2901 Dear Mr. Boudreaux: Enclosed please find four (4) copies of Change Order No. 2 for the reduction in the excavation and select borrow material quantities for the east apron expansion, the relocation of the widening of Taxiway "F" to Taxiway "D", and the addition of 1" conduit for the relocated runway lighting circuit, underdrain connection to storm drainage, and stone backfill in wet areas to stabilize select embankment. This Change Order decreases the Contract amount by $102,202.00. Please return one copy to our office and one copy to the Contractor. If there are any questions regarding this change order, please contact us. Sincerely, MQGkELLAND CO c LTING ENGINEERS, INC. Enclosure: Change Order No. 2 (4 copies) JA2000N02105\coacspondawe\Boudreau-516.wpd: • • • CHANGE ORDER Order No. 2 Date: May 15, 2002 Agreement Date: September 4 . 2001 NAME OF PROJECT: Airfield Pavement Rehab. & Taxiway Widening and Strengthening - Drake Field OWNER: City of Fayetteville (Airport Department) CONTRACTOR: APAC-Arkansas Inc.. McClinton Anchor Division The following changes are hereby made to the CONTRACT DOCUMENTS: 1. Revise the Quantity for Bid Item No. 3 for Unclassified Excavation for the East Apron due to existing Select Material under the Apron Expansion Area. Reduce the Quantity for 18,400 Cy to 13,100 CY at $10.40/cy. Deduct cost of $ 55,120.00 from contract. 2. Revise the Quantity for Bid Item No. 5 for Select Borrow Embankment for the East Apron due to existing Select Material under the Apron Expansion Area. Reduce the Quantity for 16,600 Cy to 13,200 CY at $18.80lcy. Deduct cost of $ 63,920.00 from contract. 3. Relocate the taxiway widening and strengthening from Taxiway "F" to Taxiway "D" between the Runway and Taxiway 'B". Adjust the quantities and cost per the attached page 3 of 3 of this Change Order. Add cost of $ 12,475.50 to contract. 4. Add Bid Item No. 56 for the 1" Conduit to relocate Runway Light cable in radii for 400 LF at $1.95 per LF. Add cost of $ 780.00 to contract. 5. Add Bid Item No. 57 for Underdrain connection to existing Pipe or Inlet Structure for 2 each at $ 515.00 per each. Add cost of $ 1,030.00 to contract. 6. Add Bid Item No. 58 for Stone Backfill of subgrade stabilization for 75 Tons at $ 34.00 per Ton. Add cost of $ 2,550.00 to contract. Justification: 1 &2. The east Apron Expansion area, when previously expanded, had select borrow material placed 60plus feet east of the east edge of the apron. This select borrow material is three (3) to five (5) thick and therefore the need to excavate this material per the plans is not required and the quantity of borrow material required is therefore less. The excavation quantity saved is 5300 CY and the Borrow material quantity saved is 3400 CY. The Federal Funding for the east parallel taxiway is not available to extend to Taxiway 'F. Therefore the Forest Service Fire Fighting Aircraft will need to use Taxiway "D" to retum the their base n the east side of the Airport. 4. The radii extensions on Taxiway "D" each side of the Runway require the relocation of two runway lights, lighting cable and the 1" conduit for the cable between the runway light bases. 5. The underdrain in two locations needs to be connected to existing storm drainage facilities. The original planned underdrain was to drain to daylight from the East Apron. 6. The subgrade in several locations have water seepage that continues to saturate the select embankment. J:1200010021051Cnange-Ordersborder-2.wpd Page 1 of 3 • • • The installation of an 18" layer of Stone Backfill (3" to 5") wrapped with filter fabric will allow for completion of the embankment material. The underdrains also serve to drain these areas. CONTRACT PRICE prior to this Change Order $ 2,560,744.25 Decrease in Contract Price: ($ 102,205.00) Revised CONTRACT PRICE Including this Change Order: $ 2.458,539.25 Final Completion Time Prior to This Change Order: 150 Calendar Days Net Time Change Resulting From This Change Order: 0 Calendar Days Current Contract Completion Dates Including This Change Order: Completion Date: July 1, 2001 Change to CONTRACT TIME: The CONTRACT TIME will be (increased) (decreased) by 0 calendar days. Approvals Required: To be effective this Order must be approved by the Owner if it changes the scope or objective or the PROJECT, or as may otherwise be required by the GENERAL CONDITIONS. Requested by: Recommended by: Approved by: as//Wan APAC- Arkansas, Inc., M $ Iinton Anchor Division Date Engineers, Inc. r -/5-0z Date City of Fayetteville Date J:\200310021051Charpe-Order&[ .ceder-2.wpd Page 2 o/ 625(007 (0'f. aS /0 2,2,0J OD X45%556 2.5 B 1 • • Change Order #2 Fayetteville Municipal Airport (Drake Field) Airfield Paving Rehab & Taxiway Widening & Strengthening May 1, 2002 Work to be Added to Protect BM Item No. Unit Description Unit Price Unit Plan Qty Plan $ Unit Price Pian Qty ( Runway to Taxiway Plan S Taxiway "D" (Runway to Taxiway "B") 2 Topsoil Removal (Plan Quantity) CY 59.40 250 52,350.00 2 Topsoil Removal (Plan Quantity) 800 58,320.00 CY 4 Embankment from Excavation (Plan Quantity) 59.40 250 56.55 150 52,350.00 5982.50 3 Unclassified Excavation (Plan Quantity) CY CY $18.80 500 59,400.00 510.40 675 Topsoil Replacement (Plan Quantity) 57,020.00 4 Embankment from Excavation (Plan Quantity) 51625.00 CY 8 Soil Stabilization 56.55 SY 175 $1.30 $1,146.25 51,235.00 5 Select Borrow Embankment (Plan Quantity) SY CY S6.45 100 $18.80 450 12 58,460.00 Aggregate Base Course 6 Topsoil Replacement (Plan Quantity) 519.60 650 CY 516.25 200 Binder Course TON 53,250.00 8 Soil Stabilization Fabric SY Asphalt Leveling or Strengthening Coursc TON $1.30 900 559.25 120 $1,170.00 9 Asphalt Milling Asphalt Surface Course TON SY 554.85 390 521,391.50 56.45 100 16 Bituminous Prime Coat GAL 5645.00 12 Crushed Aggregate Base Course TON Bituminous Tack Coat GAL 519.60 600 511,760.00 18 13 Asphalt Binder Course 50.71 TON 5355.00 19 Crack Control Fabric 552.00 290 $15,080.00 369 14 Asphalt Leveling or Strengthening Course Seeding, Fertilizing & Mulching AC TON 51,570.00 0.3 5471.00 559.25 410 Taxiway Light Relocation including Base 524,292.50 5405.00 15 Asphalt Surface Course 53,240.00 TON 39 Taxiway Light Base Removal EA 554.85 270 8 514,809.50 5812.00 16 Bituminous Prime Com GAL 4 56 $2.40 210 42 Lighting Cable, Counter & Cable Trench 5504.00 LF 17 Bituminous Tack Coat 700 GAL 53,556.00 43 $1.05 380 5399.00 650 18 Crack Cleaning & Sealing GAL 2 -way, 4" Electrical Duct LF 576.10 50.71 40 450 53,044.00 $319.50 35 Seeding, Fertilizing & Mulching AC $1,570.00 0.32 5502.40 37 Taxiway Light Relocation including Base EA 5405.00 16 56,480.00 39 Taxiway Light Base Removal EA $101.50 16 S 1,624.00 41 Relocate Taxiway Sign EA 51,520.00 3 54,560.00 42 Lighting Cable, Counter & Cable Trench LF 55.08 950 54,826.00 43 r Condiut for Lighting Cable LF 52.05 900 51,845.00 44 2 -way, 4• Electrical Duct LF 576.10 40 53,044.00 Total for Items Work to be Deleted from Protect 5114,087.15 Bid Item No. Description Unit Unit Price Plan Qty Plan $ Taxiway "F" ( Runway to Taxiway "B" ) 2 Topsoil Removal (Plan Quantity) CY 59.40 250 52,350.00 3 Unclassified Excavation (Plan Quantity) CY $10.40 800 58,320.00 4 Embankment from Excavation (Plan Quantity) CY 56.55 150 5982.50 5 Select Bonow Embankment (Plan Quantity) CY $18.80 500 59,400.00 6 Topsoil Replacement (Plan Quantity) CY 516.25 100 51625.00 8 Soil Stabilization Fabric SY $1.30 950 51,235.00 9 Asphalt Milling SY S6.45 100 5645.00 12 Crushed Aggregate Base Course TON 519.60 650 512,740.00 13 Asphalt Binder Course TON 552.00 300 515,600.00 14 Asphalt Leveling or Strengthening Coursc TON 559.25 120 57,110.00 15 Asphalt Surface Course TON 554.85 390 521,391.50 16 Bituminous Prime Coat GAL 52.40 225 5540.00 17 Bituminous Tack Coat GAL 51.05 200 $210.00 18 Crack Cleaning & Sealing GAL. 50.71 500 5355.00 19 Crack Control Fabric GAL 51.55 369 5571.95 35 Seeding, Fertilizing & Mulching AC 51,570.00 0.3 5471.00 37 Taxiway Light Relocation including Base EA 5405.00 8 53,240.00 39 Taxiway Light Base Removal EA 5101.50 8 5812.00 41 Relocate Taxiway Sign EA 51,520.00 4 56 080.00 42 Lighting Cable, Counter & Cable Trench LF 55.08 700 53,556.00 43 2 Condiut for Lighting Cable LF 52.05 650 $1,332.50 44 2 -way, 4" Electrical Duct LF 576.10 40 53,044.00 Total for Items 5101 611.45 Total Addition Project Cost $12,475 70 J:1200010021051Change-Orderslchangeorde2.wb3 Page 3 of 3 • FAYETTEAPI.LE THE CITY OF FAYETTEVILLE, ARKANSAS DAN GOODY, MAYOR AVIATION AND ECONOMIC DEVELOPMENT RAY M. BOUDREAUX, DIRECTOR • • 4500 School Ave., Suite F Fayetteville, AR 72701 501.718.7642 TO: Dan Goody, Mayor City Council Members THRU: Staff Review Committee FROM: Ray M. Boudreaux, Director DATE' May 17, 2002 SUBJECT: Change Order # 2 — Airfield Pavement Rehabilitation /Taxiway Widening Background: APAC Inc., McClinton Anchor Division began construction on the Airfield Pavement Rehabilitation and Taxiway Widening project in September, 2001. The project consists of taxiway strengthening and widening, and includes parking ramp expansion of the east -side general aviation ramp. Purpose: APAC Inc., McClinton Anchor Division has submitted Change Order #2 which represents a net reduction of $102,202 to the Contract amount. The Change Order is the result of a reduction to the quantity of select fill materials due to the existing presence of materials in the work area, plus additional conduit for Runway lighting electrical, underdrain connection pipe, and stone backfill materials. Budget Considerations: The Change Order represents a reduction to the project cost. A Budget Adjustment reflecting the budget changes is attached. Requested Action: Staff recommends approval by the City Council of Change Order #2 to APAC Inc., McClinton Anchor Division, and the associated Budget Adjustment. RMB/fin Attachments: /4/ Budget Adjustment Form McClelland Consulting Engineers, Inc.; letter 4 originals; Change Order #2 Project expense summary • •. City of Fayetteville, Arkansas •Budget Adjustment Form • Budget Year: 2002 , i•. Department: Aviation & Economid Development• Division: • ; Airport : afY' i :. Program: •'' Capital •• Date Requested 06/04/2002 Adjustment # Project or Item Requested: .Y SY. .. To recognize $91,982 reduction in Fed. Grant Revenue To recognize $ 5,110 reduction in State Grant Revenue. .Increase Use of Fund Balance $5,110 • e • ':t ai1,. Project or Item Deleted: $102,202 reduction to Pavement Rehabilitation & Maint. Capital Project • '.;.• Justification of this Increase: • APAC/ McClinton Anchor Change Order #2 will reduce the project cost, thus reducing associated grant revenues which are based on percent of project cost as follows: Federal - FAA 90% State - Dept of Aero 5% Local - Airport Fund 5% Justification of this Decrease: APAC/ McClinton Anchor Change Order #2 will reduce the project cost. Sufficient funding remains to comply with City Policy. Account Name Federal Grant #29 State Grants on Federal Projects Use of Fund Balance Account Name Increase Expen e (Decrease Revenue) Amount 91,982 5,110 . 5,110 Account Number 5550 0955 6820 Project Number 29 00029 1 5550 0955 6803 00 • 5550. 0955 4999 99 Decrease Expense (Increase Revenue) Amount Paveinent Maint & Rehab •',l, • ,,156 . • 102,202• Account Number • 5550 • e • Project Number 3960 7820. ,B!,.: 29 00029 ; 1 • $• • Requested By •Approval Signatures • Budgetts�Manager .31: • :•. • Dejiaitment Director ,s4: •1 • Admin. Services Director Mayor • Date Date Date Date Type: A Budget Office Use Only • Date of Approval _ 1 Posted to General Ledger ; •Posted to Project Accounting Date Entered in Category Log • Blue Copy: Budget & Research / Yellow Copy: Requester • D Project Name: AIP #: State Aero Grant: AS400 Project #: Vendor: Bid #: Contract #: Contract Amount: Change Order #1: Contract Total: Date: 21 -Nov -01 07 -Jan -01 15 -Feb -02 15 -May -02 Totals Check # 286131 287720 289384 submitted • Pavement Rehabilitation & Apron AIP3-05-0020-2901 1853-01 00029 APAC - McClinton Anchor 01-46 814 $2,713,912.65 $5,321.60 $2,719,234.25 Expense 135,638.20 329,948.96 168,295.53 65,428.65 Retainage Payment (12,924.37)122,713.83 (32,994.90) 296,954.06 (16,829.55)151,465.98 (6,542.87) 58,885.78 0.00 0.00 Retainage Subtotal (69,291.69) 699,311.34 630,019.65 C:1Doarments and SeningsynitolsansMy DocumentsUamesVroi_trackProLa29_ConsauUbn. 123 • Project Balance 2,596,520.42 2,299,566.36 2,148,100.38 2,089,214.60 2,089,214.60 2,089,214.60 • • • • McCLELLAND CONSULTING 1 DESIGNED To SERVE 1 ENGINEERS, INC. May 15, 2002 Mr. Ray Bourd Airport Depa City of Faye 113 West Fayettev ux ent eville ountain AR 72701 • P.O. Box 1229 Fayetteville, Arkansas 72702-1229 501-443-2377 FAX 501-443-9241 RE: Airfield Pavement Rehabilitation & Taxiway Widening and Strengthening Drake Field AIP 3-05-0020-2901 Dear Mr. Boudreaux: Enclosed please find four (4) copies of Change Order No. 2 for the reduction in the excavation and select borrow material quantities for the east apron expansion, the relocation of the widening of Taxiway "F" to Taxiway "D", and the addition of 1" conduit for the relocated runway lighting circuit, underdrain connection to storm drainage, and stone backfill in wet areas to stabilize select embankment. This Change Order decreases the Contract amount by $102,202.00. Please return one copy to our office and one copy to the Contractor. If there are any questions regarding this change order, please contact us. Sincerely, MELLAND COLTING ENGINEERS, INC. Enclosure: Change Order No. 2 (4 copies) .132OwoO21OSc«.espwwenceWaadreawcs16.wpd: • • r - XX AGENDA REQUEST CONTRACT REVIEW GRANT REVIEW For the Fayetteville City Council meeting of FROM: Ray M. Boudreaux Name • • STAFF REVIEW FORM Aviation & Economic Development Airport Division Department ACTION REQUIRED: Review and approve Change Order #2 to APAC-Arkansas Inc., McClinton Anchor Division. Signature of the Mayor required COST TO CITY: $ (102,202) - Reduction to Contract Cost of Uls Request 5550.3960.7820.29 Account Number $ 2,719,234 Airfield Pavement Rehab / Taxiway Category/Project Budget Category/Project Name 699,311 Capital Funds Used to Date Program Name 00029 2,019,923 Airport Project Number Remaining Balance Fund BUDGET REVIEW: XX Budget Manager Budgeted Item Budget Adjustment Attached Administrative Services Director CONTRACT/GRANT/LEASE REVIEW: Plats -Aa Q 44? v/oa Acco ndng ManagA/W- eer �/y Date temal • udder City Attorney Date ADA Coordinator A:N.) stg. 5Iaale a -- Purchasing Officer Date GRANTING AGENCY: 5:4_4(2( te Date STAFF RECOMMENDATION: icPine-oV ?� -,•r a),40.41,_ DUc,_ 4 7 i le1p y yr/ ar" Division Head Department rector Administrate ervices Director Mayor 4 Date Date 57S�J2 Date Cross Reference New Item: Yes Prev Ord/Res #: 123-01 Orig Contract Date: 09/04/2001 Orig Contract Number. #814 • Description: • • STAFF REVIEW FORM r Page 2 Oke -t& �� flt k2.3 2— - at(tt radrat. Ce4 (t-K4L Comments: Budget Coordinator: Accounting Manager: c if -8 caeo anderat. City Attorney: Purchasing Officer: ADA Coordinator: Internal Auditor: - 4nenn .1/Q0A U14#. Iod,ao)-G 0)3 a2 CZt. OnChA- n04- .I aficicro4 Ceitikac9 Reference Comments: • xx AGENDA REQUEST CONTRACT REVIEW GRANT REVIEW For the Fayetteville City Council meeting of FROM: Ray M. Boudreaux Name i STAFF REVIEW FORM • RECEIVED `•.sY 0 „I CITY OF FAYETTEVILLE CITY CLERK'S OFFICE Aviation & Economic Development Airport Division Department ACTION REQUIRED: Review and approve Change Order #2 to APAC-Arkansas Inc McClinton Anchor Division. Signature of the Mayor required. COST TO CITY: $ (102,202) - Reduction to Contract Cost of this Request 5550.3960.7820.29 Account Number $ 2,719,234 Airfield Pavement Rehab / Taxiway Category/Project Budget Category/Project Name 699,311 Capital Funds Used to Date Program Name 00029 2,019,923 Airport Project Number Remaining Balance Fund BUDGET REVIEW: xx Budget Manager Budgeted Item Budget Adjustment Attached Administrative Services Director CONTRACT/GRANT/LEASE REVIEW: GRANTING AGENCY: Accounting Manager Date Internal Auditor Date City Attorney Date ADA Coordinator Date Purchasing Officer Date STAFF RECOMMENDATION: /t etgen '9 ��sqc DMsion Head Date Administrative Services Director Mayor Date Date Cross Reference New Item: Yes Prev Ord/Res #: 123-01 Orig Contract Date: 09/04/2001 Orig Contract Number. # 814 05-20-02A07:25 RCVD Description: STAFF REVIEW FORM Page 2 • laxtwz W tien Comments: Reference Comments: Budget Coordinator: Accounting Manager: City Attorney: Purchasing Officer: ADA Coordinator: Internal Auditor: •