HomeMy WebLinkAbout22-02 RESOLUTION•
A.
RESOLUTION NO, 22-02
A RESOLUTION TO APPROVE CONTRACT AMENDMENT
NO.1 WITH MCGOODWIN, WILLIAMS, AND YATES, INC.
IN THE AMOUNT OF $580,296.00
WHEREAS, the City of Fayetteville, Arkansas after a public hearing
determined that the 5% fixed fee should be deducted from the previously
requested amount of the proposed contract amendment for that portion
applicable to the cost overruns of Hanifin Associates, and ECO, Inc. prior to
approval of the City Council; and
WHEREAS, representatives of McGoodwin, Williams, and Yates, Inc.
agreed to such reduction which resulted in a total reduction of $15,495.00.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF
THE CITY OF FAYETTEVILLE, ARKANSAS:
Section 1. That the City Council of the City of Fayetteville, Arkansas
hereby approves Contract Amendment No. 1 with McGoodwin, Williams, and
Yates, Inc. in the amount of $580,296.00 (attached as Exhibit A); and authorizes
the Mayor to execute said contract amendment.
PASSED and APPROVED this the 5th day of February, 2002.
11 14
Woodruff, City C - k
APPROVED:
•
NAME OF FILE:
CROSS REFERENCE:
Resolution No. 22-02
•
02/05/02
Resolution No. 22-02
Amendment No. 1 to City of Fayetteville Contract Agreement for
Engineering Services Westside Wastewater Treatment Facility with
McGoodwin, Williams, and Yates, Inc.
01/15/02
Copy of the Budget Adjustment Form
02/11/02
Letter to Greg Boettcher, PW Director, from James C. Ulmer, Vice
President, McGoodwin, Williams and Yates, Inc.
02/11/02
Memo to Mayor Coody from Greg Boettcher, PW Director, CC: Kit
Williams, Steve Davis, Jim Beavers, Heather Woodruff, regarding
Engineering Contract Amendment No. 1
02/05/02
Staff Review Form
02/26/02
Memo to Greg Boettcher, Public Works Director, from Heather
Woodruff, City Clerk
News Release from Greg Boettcher regarding Historical/Archaeo-
logical Field Study
NOTES:
•
ORIGffiAL V az
AMENDMENT NO. 1 TO
CITY OF FAYETTEVILLE
AGREEMENT FOR ENGINEERING SERVICES
WESTSIDE WASTEWATER TREATMENT FACILITY
WHEREAS, on March 21, 2000, the City of Fayetteville (the Owner) and McGoodwin,
Williams and Yates, Inc. (the Engineer) entercd into an Agreement for Engineering Services in
connection with the construction of the new Westside Wastewater Treatment Plant to serve the
Illinois River Basin. The scope of these services included preliminary studies and preliminary
design, resulting in a Preliminary Engineering Report setting forth the findings; and
WHEREAS, the Engineer has completed those services required under the original scope
including preparation and submittal of the Preliminary Design Report; and
WHEREAS, the overall prQlect (hereinafter referred to as "the Overall Project") being
developed by the Owner includes an upgrade of the existing Paul Noland Wastewater Treatment
Plant on the cast side of the city and the sewer system collection and transmission facilities work
for both the east and west sides. This work is being accomplished by three other engineering
consultants; and
WHEREAS, the Owner requested that the Engineer's and its subconsultants' original
scopc be expanded to include services relating to the Overall Project; and
WHEREAS, the Engineer agrees to provide the requested services;
NOW THEREFORE, in consideration of the mutual covenants and agreements herein
contained, the Owner and the Engineer, the parties hereto, stipulate and agree that the Agreement
for Engineering Services dated March 21, 2000, is hereby amended in the following particulars:
Section IV. Services to be Furnished by the Engineer During Design Phase
1. Section A - Study, Preliminary Desibm and Report, is amended by adding the
following paragraphs under Section IV -A.
Environmental Permitting. The environmental work in the original scope
being provided by subconsultant ECO, Inc. shall be expanded from only the
Westside Treatment Plant to include all four elements of the Overall
Project, thus allowing continuity of activities and eliminating duplicated
efforts by the other engineering consultants. This work includes:
• Corps of Engineers 404 permitting;
• Initiating the work on the NPDES storm water permit;
• Participating in the public information program including attendance at
public meetings; providing environmental information justification for
the Overall Project and assisting in the dissemination of accurate
environmental information about the Overall Project;
Amend 1 to Fy-296 - 1 of 5
A
R
• 411
• Assisting in the evaluation of and development of Candidate
Conservation Agreement (CCA) to address prospective and endangered
species concerns;
• Providing specialized environmental guidance regarding the
environmental issues surrounding the planned Westside sewer line
construction at the former Research and Technology Park to include
preliminary evaluation of site conditions, site issues, and possible
mitigation measures.
The Engineer shall coordinate the work between ECO and the other
engineering consultants for the Overall Project, and provide specific data
regarding the Westside Treatment Plant.
Public Education and Involvement. The public education and information
work being conducted by Hanifin Associates for the Westside Treatment
Plant shall be expanded to include all four elements of the Overall Project,
thus allowing continuity of activities and eliminating duplicated efforts by
the other engineering consultants. This additional work includes:
• Increasing the public informational meetings from three to 16;
• Formalizing the public involvement program to meet specific
requirements for Facility Planning/State Revolving Loan Fund under
the regulations of the Arkansas Soil & Water Conservation
Commission;
• Providing written information/graphics/handouts to inform the public
on the proposed work;
• Expanding the scope of the public information program to include the
use of web -site and media mediums;
• Development of communication resources, tools, and criteria to
improve the effectiveness and clarity of the information presented to the
public;
• Assist in the conduct of a Public Hearing regarding the final selected
alternative in the Facility Plan and Environmental Information
Document.
The Engineer shall coordinate the work between Hanifin Associates and the
other engineering consultants, and provide specific data regarding the
Westside Treatment Plant.
3. Wastewater System Improvement Project Facility Plan. The Engineer will
prepare an amendment to the Facility Plan for the Overall Project
previously prepared by another consultant and presented in February of
1997. The plan will utilize the preliminary engineering work completed by
each of the four engineering consultants. The plan will be completed in
accordance with requirements as set out by the State of Arkansas for
projects utilizing the Revolving Loan Fund. This Facility Plan will be
submitted to ASWCC in the final version (following the September 20,
2001 public hearing) in November, 2001. The Engineer will coordinate the
review of the Facility Plan by the state and federal agencies until final
approval.
Amend 1 to Fy-296 - 2 of 5
• •
4. Environmental Information Document. The Engineer will prepare an
Environmental Information Document for the Overall Project to accompany
the Facility Plan which evaluates and presents the environmental issues and
program documents required to reflect work proposed by the four project
consultants. The Engineer will work with ECO, Inc. to produce this
document and coordinate the review of the EID until final approval.
5. Revolving Loan Fund Coordination. The Engineer shall assist the Owner
by providing project coordination, preparation of Revolving Loan Fund
documents, and necessary engineering services as required to complete the
RLF program requirements.
6. Biosolids Management System Coordination. The Engineer shall expand
investigations into the biosolids management planning for the Overall
Project, including investigations of additional alternatives and the
coordination of a recommended strategy.
7. Industrial Loadings. The Engineer shall provide the necessary services to
determine the impact of a prospective industrial plant on the Westside
Treatment Plant.
8. Broyles Road Extension. The Engineer shall develop and implement
preliminary planning for the Broyles Road extension in Farmington. This
extension, if constructed, would provide access to the new Westside
Treatment Plant. The study shall be conducted jointly for the Owner and
the City of Farmington.
9. Additional Services. The Engineer shall conduct other studies and analyses
as required to facilitate the production and approval of the Facility Plan,
environmental permitting, and public involvement as required.
These services to be furnished by the Engineer shall be subject to the agreed cost ceiling
set out in Section XII.5 as amended.
Section X. Subcontracting
Add the following paragraph: "The Engineer shall furnish copies of all sub -agreements if
requested by the Owner."
Section XII. Fees and Payments
I. Section A is amended as follows: The fixed fee set out in this section is increased
to $130,505.
Amend 1 to Fy-296 - 3 of 5
• •
2. Section A is amended by adding the following: Compensation for the Broyles
Road Extension Study shall be a lump sum amount of $12,900. The cost of this study is to be
shared equally with the City of Farmington. Thus, the Owner's portion is $6,450.
3. Scction B, the estimate of cost for ECO, Inc., shall be increased to $343,868,
including expenses.
4. Scction C, the estimate of cost for Hanifin Associates, Inc., shall be increased to
$187,166, including expenses.
5. Section D, second paragraph, first line, is amended to read as follows: ' The
estimated total compensation for the services set out under Section IV.A as amended is
$1,535,598, including the fixed fee of $130,505 and reimbursable expenses, and Fayetteville's
share of the lump sum fee for the Broyles Road Extension Study."
6. Attachment A to this Amendment sets out a summary of the original budget and
requested changes.
7. After the last paragraph under Section D, add the following: "The Engineer shall
furnish copies of invoices, billing information, and other materials as the Owner may request, to
verify the accuracy of invoices and the nature of the work being performed."
Section XVI. Miscellaneous Provisions
Add paragraph H as follows:
H. Arkansas Freedom of Information Act. The Engineer agrees that it will provide to
the Owner, at a cost to be agreed upon, all documents in its possession that are,
under this Agreement, the property of the Owner and which the Owner believes to
be subject to an Arkansas Freedom of Information Act request made to it, or, in
anticipation of such a request, which it believes necessary for it to possess. The
Engineer further agrees that it will request of all subconsultants, retained by the
Engineer to perform services under this Agreement, to provide to the Owner, at a
cost to be agrecd upon, all documents in the possession of such subconsultants that
are, under this Agreement, the property of the Owner and which the Owner
believes to be subject to an Arkansas Freedom of Information Act request made to
the Owner, or, in anticipation of such a request, which it believes necessary for the
Owner to possess. The Engineer will produce all documents or material in the
format that are kept by the Engineer, or at the option of the Engineer, in some other
format. If a specialized format is requested by the Owner, the cost of conversion,
if that additional responsibility is accepted by the Engineer, will be borne by the
Owner at the then prevailing rates for the parties actually performing the
conversion. Production of requested items will be done with reasonable diligence,
but cannot in some circumstances be within the time frame established by the Act.
Amend 1 to Fy-296 - 4 of 5
•
• •
The above and foregoing provisions apply only to work performed from this date
forward and does not apply retroactively.
Nothing in this Agreement shall constitute an acceptance of the Engineer or its
subconsultants to the application of the Arkansas Freedom of Information Act to
the Engineer or its subconsultants or to the Engineer's or subconsultant's books,
records, drawings, or other items not constituting the property of the Owner under
this Agreement, nor a waiver of its rights to object to any requests made to it
pursuant to the Arkansas Freedom of Information Act by any person or entity not a
party to this Agreement.
All other provisions of the original agreement remain in full force and effect.
IN WITNESS WHEREOF, the parties hereto have caused this Amendment to be duly
executed this day of 74
, 2002.
CITY OF FAYETTEVILLE, ARKANSAS McGOODWIN, WILLIAMS AND YATES,
INC.
By:
By
Dan Coody, Mayor
ATTE
arl Yates, Pre
ATTEST:
rk
del CO\•
oodruff, City Cle
s C. Ulmer, Vi 'resident
Amend 1 to Fy-296 - 5 of 5
NOTE: All cost figures include expenses.
o o v •= CO `� m
..-
T<'22o m -( d 0 F-• ?55Q0
,2338 m o(7om =4
m 3
nm CD
CD 3
a m O O S 03co Cr
a 3 m 3 3 0 n C C n f) y
0 > > m Qo
(D Cn a • m
0 •
(n
3 0
S
(A EA
01 �COCO
CP CO 0)
W
N (071 -
EA
01 C0 O▪ CO—sCAO
CO CO V CO -I V
O —
. N C00 CR
b cn tP Co co CO A
O N CP0C)A
m
2a6png lew6u0
E0
R EA CD
X) 1N -S N CA O CCD 0
A.A Co CCO00) ON(0l1 Cr = 3 N v
6M(7)O) Of -•(A0 N ry m
NAcoWd0
OO CoCA C)t0
EA
-4
CO
(0
O
Co
EA
W 0000 a))a)coo 000
NA A A -co
'
000 N co W
000)v v N
EA EA
oA
O NCO r
co 0. O 0A O' 0 0
Co 0 Co 0 0
EA EA EA
(n 01 W-•
CoCR
N co tAT CO 03 COOTCA 0N) Cr
CO 0 CO 00IV A ID -4). -Co CO CO Co
O
0) O CO 00°A ACIN(0
u
W
(D N_ 0.
0 73 3
CD CD N A
C
(7 N n
as 9 co
n (^
f0
CO
C
a
(0
o •0 2
z m a m cn
O. N CCD
n 3a
CO
EA EA (,. EA
W co o A Apo AODW N O -I W
V1 O (J1 W W CO v O N W W 13
C O_ C O
N (P O O N 0 O) - (b W n 0 co 0
CO (P CO O 0 0a) � U1 CO W a fn` (^ .0..
SUMMARY OF REQUESTED BUDGET
V1N3WHOVlld
•
City of Fayetteville, Arkansas
Budget Adjustment Form
•
Budget Year
2002
Department:
Division:
'Program:
Public Works
Sewer Construction
Date Requested
January 15, 2002
45.22 oz
Project or Item Requested:
$579,000 in the Professional Services
account in the Wastewater Treatment Plant
- Expansion capital project.
Project or Item Deleted:
$579,000 from the Use of Fund Balance
account in Water & Sewer Fund.
Justification of this Increase.
The funding is needed for the City to
contract with McGoodwin, Williams, and
Yates Inc. for consultant services as
related to the construction of the
Wastewater Treatment Plant Expansion.
Justification of this Decrease:
The fund balance is from remaining funds
not spent in 2001.
Increase Expense (Decrease Revenue)
Account Name Amount
Professional Services 579,000
Account Name
Use of Fund Balance
Account Number
5400 5700
Decrease Expense (Increase Revenge)
Amount
579,000
Project Number
5314 00 98047 10
Account Number
5400 0940
4999 99
Project Number
Approval Signatures
Requ ed By
B getaX
6146(
t Director
Date
OZ
JfieoZ
Utile
0/7o 2..
Date
ky%
Date
Budget Office Use Only
Type: A B C
Date of Approval
Posted to Genual Ledger
Posted to Project Accounting
Entered in Category Log
RJ.., r.....,- n..ana. x. Ra..s...r. r V n,.... �,...... o__.....,
E
• •
McGoodwin, Williams and Yates, Inc.
Consulting Engineers
909 Rolling Hills Drive
Fayetteville. Arkansas 72703
Telephone 501/443.3404 FAX 501/4434340
February 11, 2002
Re: Contract Amendment No. 1
Westside Wastewater Treatment Plant
Fayetteville, Arkansas
MWY Project No. Fy-296
Mr Greg Boettcher, P E
Public Works Director
City of Fayetteville
113 West Mountain
Fayetteville, Arkansas 72701
Dear Greg:
Enclosed herewith are three copies of executed Amendment No. 1 to the
Agreement for Engineering Services for the Westside Wastewater Treatment Facility.
We trust you will find this document in order and can forward it to the Mayor and
City Clerk for a date and signatures. If you will notify our office when the signatures
are complete, we will send someone to pick up one copy for our files.
We appreciate very much the city's willingness to go forward with this contract
amendment, and look forward to continued service to the city in this very important
wastewater treatment facilities project.
JCU:sc
Enclosure
Cordially yours,
/mes C. Ulmer, P. E.
ce-President
2-12
2 :✓ &o0&EOJnfl
TD 7716 &#J4/, it-
zSc21 j/.t/lo ,Z € ?m
43cDS—
ZE /LJe Att t ratnis
Tom' Pes,G,tc C'cwniliMT-
1
c
• •
FAYETTEVILLE
THE CITY OF FAYETTEVILLE, ARKANSAS
DEPARTMENTAL CORRESPONDENCE
TO: Mayor Coody
COPY: Kit Williams, Steve Davis, Jim Beavers, Heather W
FROM: Greg Boettcher, Public Works Director
DATE: February 11, 2002
RE•
Engineering Contract Amendment No. 1
McGoodwin, Williams and Yates, Inc.
Wastewater system Improvement Project
West Side Wastewater Plant
Attached please find a copy of the professional fee calculations that have
been developed by McGoodwin, Williams and Yates, Inc. (Memorandum
dated February 8, 2002). This communication outlines the methodology for
the elimination of professional fees on the labor costs for ECO and Hannifin
and Associates. The Fayetteville City Council, at its February 5, 2002
meeting, approved this contract amendment provided that the 5% fixed fee
estimated at $15,000.00 to $17,000.00, be deducted from the amount
requested. I have reviewed the information presented, that computes a fixed
fee reduction of $15,495.00, and find said amount to be both in order and in
accordance with City Council approval. The resulting value of Contract
Amendment No. 1 is $580,296.00, bringing the not -to -exceed total contract
value to $1,535,598.00.
A revised contract amendment shall be provided for signature on Monday,
February 11,2002
GB:ks
2- S-02;,i:48AM;MC000OWIN WILLIAMS
;479.443.4340 0 1/ 2
• •
McGoodwin, Williams and Yates, Inc.
Consulting Engineers
909 Rolling Hills Drive
Fayetteville, Arkansas 72703
Telephone 479/443-3404 FAX 479/443-4340
MEMORANDUM
To: Mr. Greg Boettcher, P E , Public Works Director
City of Fayetteville, Arkansas
From: James C. Ulmer, P. E., Vice -President
Date: February 8, 2002
Re: Wastewater System Improvement Project
Contract Amendment No. 1
Fayetteville, Arkansas
MWY Project No. Fy-296
Attached is a table showing the labor cost and expense calculations for ECO, Inc. and
Hanifin Associates through December 9, 2001, as shown on our original cost figures
presented to you as a part of the worksheets accompanying Contract Amendment
No. 1. At the bottom of this table, we have calculated our allowable fee for labor for
both ECO and Hanifin Associates in order to determine the amount of fee reduction as
required by the Council at their meeting of February 5, 2002.
The original fee request for Contract Amendment No. 1 was to increase the fee to
$146,000. However, the fee reduction requested by the City Council on February 5 was
$15,495, which represents five percent of the ECO and Hanifin costs (over and above
the original scope) through December 9, 2001. Therefore, our revised total fee to be
reflected in Contract Amendment No. 1 shall be $130,505, as shown on the attached
table.
We trust you will find this explanation acceptable for the purposes of establishing the
amount of fee in Contract Amendment No. 1.
Attachment
Post -n• Fax Note 7671
-1
O
E
pT
0
a
0
M
M
N
4
elD9
a
• •
2
5
N
$ 9L'OEY'BiZ
s
a
Ul
N
Z /Z • OpEr•EIVeSLt1
M M
P
A co
m O
N
suonhIn,lp pd
co
CO
co
0
mmm(m�flcmiclOOq c
acg
m
o spm
�c3 -4
a ma
m a.
8
w
V
0
m
O
mm b A a O Q
-• A+ N N V Al
N 0m N N mNm
V O N N O N
O bY
O +
•
0
pqA n
+ o t{�m a M u
-saoI A N+ca o O
N N N V OqI tpl1l m • o
,iowwa(a-- 4§
8
a
2m
3 t7
O
3
D
3
J
2y
3
3
3
0
$WYI1 IM NIMOOOOOrl tVIVO? . t!ZO-6 -Z
• •
McGoodwin, Williams and Yates, Inc.
Consulting Engineers
909 Rolling Hills Drive MIC OIFELPID
Fayetteville, Arkansas 72703
Telephone 501/443-3404 FAX 501/443-4340
January 25, 2002
Re: Wastewater System Improvement Project
Proposed Contract Amendment between City and Engineer
Fayetteville, Arkansas
MWY Project No. Fy-296
Mr. Greg Boettcher, P E
Director of Public Works
City of Fayetteville
113 West Mountain
Fayetteville, Arkansas 72701
Dear Greg:
Thanks for your letter of November 13 requesting a contract amendment. We're
pleased to answer your questions and provide whatever detail you require to move our
work forward. I've summarized relevant information below and attached a more
comprehensive memorandum to this letter.
Project History
Our original contract with the City was executed March 21, 2000. It called for
MWY to complete the Preliminary Engineering Design for the proposed Westside
WWTF, including a written Preliminary Design Report. We completed this report in May
2001 and enlisted the services of subconsultants whose special expertise was critical to
complete the work. They are listed in the attached memorandum. MWY successfully
completed contract scope requirements approximately $200,000 below budget.
Along the way, the City made several decisions which resulted in the expansion
of MWY's role in work related to the wastewater system improvement project. They are
summarized as follows:
Revolving Loan Fund
Concurrent with the preliminary design process, the City elected to pursue
Arkansas' Revolving Loan Fund program. This was an excellent decision, because it
would provide a low-cost source of capital for all facets of the total project. In Apnl 2000,
at the City's request, Don Bunn, Assistant Public Works Director and Jim Ulmer, Vice -
President of MWY, met with officials of the Arkansas Department of Environmental
Quality to assess the program requirements to enter the RLF program and learned:
Mr. Greg Boettcher
January 25, 2002
Page 2
• •
1. The 1997 Facility Plan created by CH2M Hill did not meet ADEQ
requirements and the City would be required to produce a new Facility
Plan Amendment. Later, at the City's direction, in May through November
2001, MWY created a new Facility Plan Amendment which required
approximately 2,800 manhours to complete.
A new Environmental Information Document (EID) was required that
would address all known environmental issues and program requirements.
3. A formal public hearing on the selected plan was also required. This
meeting was supplemental to the numerous public meetings conducted
during the preliminary design process. As you are aware, planning,
organizing, facilitating and following-up a formal public hearing that
conforms to state requirements is a time -intensive process. MWY also
assumed responsibility for this activity.
Environmental Permitting
1. Early in this process, consultation with environmental regulatory agencies
determined that the project would require one 404 and NPDES storm
water permit rather than one for each part of the project. At this point, the
project team agreed that ECO would develop the single 404 and NDPES
storm water permit for the total project, a less cumbersome way to
proceed. While this decision reduced work for each of the subconsultants,
it significantly increased ECO's work, which accounts in large part for its
higher billing.
2. ECO participated in nearly all public meetings to provide environmental
overview, requirements and to answer public concerns regarding
environmental issues. ECO also prepared the EID required for the Facility
Planning process. In an attempt to reduce costs, much of the information
developed during the 404 permitting process was used to develop the
EID This also allowed us to address the difficult environmental issues the
City would have to overcome to successfully complete the projects.
Public Education
1. The City's decision to pursue RLF financing intensified the need to
develop clear and effective information for voters who would be asked to
approve a %-percent sales tax on November 6, 2001. And it resulted in
significant additional support from our public information consultant,
Hanifin and Associates. Instead of the planned three public meetings,
sixteen were held before the election. Hanifin and Associates planned,
coordinated and followed-up on all sixteen of these meetings.
Mr. Greg Boettcher
January 25, 2002
Page 3
• •
2. In a public opinion survey, Hanifin and Associates learned a significant
number of voters felt they had insufficient information about the overall
wastewater treatment system improvements. This was a major concern,
as voters won't approve issues they don't understand. As work moved
forward, odor control issues at Noland, property value concerns and
environmental matters took on paramount importance. Public education
took on new importance and resulted in additional cost from our public
information consultant.
Expanded Responsibilities
As you know, the RLF application process is complex and time-consuming. In
the absence of clearly defined project leadership responsibility, the dearth of long-term
experience with RLF as well as numerous regulatory agencies, and the absolute
necessity of voters approving the 'As -percent sales tax, MWY became the de facto
project manager. We did so with the implicit consent of the City to help ensure the
compatibility of each project aspect and success of the total project.
While the choice resulted in significant additional responsibility, we saw a
significant benefit to the City. MWY and its consultants helped the people of
Fayetteville save over $38 million in interest costs related to these projects by
successfully completing the RLF Program requirements to qualify for the 3 percent RLF
loan.
In an August 8, 2001 memo, Don Bunn informed the public works director, the
mayor and city council that MWY was:
...currently in the process of Facility Plan revision and EID preparation, working with
ADEQ and the Arkansas Soil and Water Conservation Commission in connection with
securing RLF funding and has attended several city related public meetings on the
protect. In addition, they have been working with the City in the investigation of the
possible construction of a fertilizer plant in the Northwest Arkansas area which would
utilize sewage sludge from the area cities and poultry litter. Contract Amendment No. 1
for the above activities will be presented to the Council for review and approval at a
later date.
Unquestionably, these activities went beyond the scope of work in our original
contract and we accept responsibility for our decisions. We made them with the City's
best interests at heart and the interests of the project we have an obligation to complete
in a timely manner and at the lowest possible cost.
At the same time, we fully understand the importance of keeping clients informed
about our activities and the cost of services that exceed the scope of our contract. As
this letter is written, we are reviewing internal processes to identify what changes we
can make to better accomplish this objective. Prior to their implementation, we will
discuss these changes with you to ensure they meet the City's objectives.
Mr. Greg Boettcher
January 25, 2002
Page 4
• •
The attached memorandum provides detail and explanation of costs incurred by
us and our subconsultants in the performance of our contract responsibilities. We trust
you will find this information adequate and that you will forward our request for payment
to the Council with your recommendation for approval.
If you have any questions or need any additional information, please do not
hesitate to call us. We are at your disposal.
LCY:sc
Attachment
cc: Mayor Dan Coody
Board of Aldermen
Cordially yours,
L. Carl Yates
McGoodwin, Williams and Yates, Inc.
Consulting Engineers
909 Rolling Hills Drive
Fayetteville, Arkansas 72703
Telephone 501/443-3404 FAX 501/443-4340
MEMORANDUM
To: Mayor Dan Goody
Mr. Greg Boettcher, Public Works Director
Fayetteville City Council
From: McGoodwin, Williams and Yates, Inc.
Date: January 25, 2002
Re: Wastewater System Improvement Protect
Proposed Contract Amendment between City and Engineer
Fayetteville, Arkansas
MWY Project No. Fy-296
On March 21, 2000, McGoodwin, Williams and Yates (MWY) entered into a
contract with the City of Fayetteville to provide engineering services through preliminary
design, final design, and the construction of facilities for the Westside Wastewater
Treatment Facility. The contract provided for fees through the necessary studies,
preliminary design and completion of a preliminary design report, with the fees for
subsequent work to be negotiated at a later, unspecified date. At about the same time,
the City entered into engineering contracts with the RJN Group for collection and
transmission system engineering for the west side, with Garver Engineers for the same
type of services on the east side, and with Black & Veatch to provide the required
services for necessary upgrades to the existing Paul Noland Plant.
We completed our work under our original scope in May, 2001, at a cost
approximately $200,000 below the estimated cost set out in the contract.
Our contract provides for the utilization of several subconsultants to assist us in
our work. Two of these subconsultants and their scope of work are as follows:
1. ECO, Inc. — ECO's original scope provides for general environmental
guidance to us as we developed the project and to provide services
required for the filing of a Section 404 permit based on the assumption
that the treatment facility could be permitted under the Nationwide permit
rather than filing for an Individual 404 permit. The services proposed to
be provided were for the Westside Treatment Plant only.
Hanifin Associates, Inc. — Hanifin Associates' charge was to develop a
strategic communications program to inform the general public about
January 21, 2002
Page 2
• •
issues concerning the new proposed Westside Plant. Because of known
opposition to constructing this facility, it was believed that a compre-
hensive program to inform the public about the issues related to their
concerns was critical to the success of the project.
Soon after the work commenced on the project, the City decided that the
services ECO, Inc. and Hanifin Associates, Inc. were providing for the Westside
Treatment Plant should be expanded to include the total project, and in the case of
ECO, Inc., to provide services necessary to obtain a 404 permit for the total project
(including both plants and all line work). This decision was based on regulatory
mandates that a single Individual 404 permit would be required. ECO was further
directed to work closely with all project consultants and Hanifin Associates in the public
involvement processes. Although these two subconsultants would then be working with
the City and all consultants, we agreed that these expanded services would be invoiced
to our firm and then passed on to the City for reimbursement.
The 400 -page 404 permit application with documentation has been completed in
draft format and will be finalized shortly after work has been re -authorized on the
project. It is anticipated that once the final application is submitted it will take
approximately six months for completion of review by the Corps of Engineers and the
issuance of the permit. Consequently, in order to avoid delay of construction, when
plans and specifications have been completed, environmental permitting work should
proceed with all due haste. The cost to -date for the environmental management and
permitting (over and above that accomplished under the original scope) is
approximately $160,000, of which $154,000 is for work accomplished by ECO, Inc. and
$6,000 by us. Please note that approximately 75 percent of the cost for work
accomplished by ECO is for line work projects on both the east and west sides of the
City and not part of our contract for the Westside Facilities. A brief summary of the
404 permit work elements is shown in Attachment A.
The cost of the additional work performed by Hanifin Associates, Inc. was due to
its involvement in the entire project rather than just the Westside Treatment Facility,
and for educational assistance during the development of the Facility Plan and the
AutumnFest exposition in early October. Additional costs involved relate to odor
problems at the existing Noland Plant, i.e., several meetings with attendant preparation
were held to discuss this matter. The added cost for Hanifin Associates over the
original budget is $88,426. Hanifin's original budget assumed three public meetings,
whereas 16 were finally held. The need for additional public education was noted in
Hanifin's summary of written comment presented in the Public Opinion Survey
(Attachment B). A summary of Hanifin's work is shown in an October 15, 2001, letter
included as Attachment C.
From the very beginning of the project, the City began evaluating the best
method of funding for the project. At the City's request, we provided assistance in this
evaluation. By May of 2001, the City had decided to utilize the State of Arkansas
Revolving Loan Fund and at that time asked us to provide the necessary services to
January 21, 2002
Page 3
• •
amend the Facility Plan which had been prepared in 1997 by CH2M Hill. This work was
not included in our original contract. The Draft Facility Plan Amendment (including the
required Environmental Information Document) was completed in August. A summary
of significant meetings conducted relevant to the total project effort is presented in
Attachment D. The entire Draft Facility Plan Amendment includes 10 separate volumes
and was submitted to the Arkansas Sod & Water Conservation Commission in August
for review and approval. The Draft Facility Plan was revised and has become the Final
Facility Plan and incorporates the comments of the public at the formal public hearing
and reviewing agency comments, and was resubmitted for final review and approval on
November 2, 2001. By letters dated December 3 and 4 (Attachments E and F) to
Mayor Goody from the ASWCC, they indicate that the Facility Plan had been reviewed
and it appears to be "approvable." However, they cannot give final approval until
certain programmatic events have occurred. Specifically, the City of Fayetteville must
have officially entered into the Revolving Loan Fund program and environmental review
processes must have been completed with closure on several environmental issues
which should be resolved with the completion of the 404 permit process. Final Facility
Plan and Environmental Information Document approval will come in the form of the
issuance of a Finding Of No Significant Impact (FONSI) for the project. Thus, final
approval may take some period of time, as all agencies having interest in the project
must be given opportunity to comment on the draft 404 permit. Consequently, the City
is "ahead of the curve" on receiving facility plan approval so that it will not delay start of
construction. Additionally, the environmental issues that affect the design will have
been identified and resolved early in the design process, so that costly redesigns will be
avoided. The cost to -date on this facility planning part of the work (including RLF
coordination) is approximately $245,000, with $190,000 being for work performed by us
and approximately $55,000 for work performed by ECO, Inc. in the development of the
Environmental Information Document. A graph showing the dates of our effort in
manhours by payroll date is shown in Attachment G.
In addition to extra services detailed above, the City requested that we assist in
the following tasks: 1) Broyles Road Extension study; 2) preliminary work on the
Candidate Conservation Agreement involving not only the "Westside line protect" but
also the research and technology park; 3) evaluating the possible impact of potential
industry on the Westside Plant; and 4) coordination of the effort to utilize the "waste -to -
energy -to -fertilizer" process for the biosolids (DukeSolutions/Harmony).
There is still work to be completed in the facility planning process and securing
approvals of preliminary environmental issues. This work will basically be completed by
us, ECO, Inc., and by the Arkansas Archeological Survey, with some consultation with
the other three engineering consultants on the project. Our work will include working
with ECO, Inc. in the environmental permitting (including a wetlands mitigation plan, if
required), coordinating final review and making any changes required in the Facility
Plan Amendment, RLF coordination, and coordination of the effort to finalizing the
definitive contract between the City and DukeSolutions/Harmony for the utilization of the
waste -to -energy -to -fertilizer process for biosolids treatment and disposal. We estimate
the cost of our effort to be approximately $57,500.
January 21, 2002 • •
Page 4
ECO's work will involve the completion of the environmental permitting process
with some possible work revising the Environmental Information Document. It is
estimated the cost of ECO's work to complete these tasks will be approximately
$58,000. A summary of ECO's total project cost separated by work elements is
presented as Attachment H.
A cultural resources survey will be required for those areas impacted by the
project. We propose to utilize the Sponsored Research Program of the Arkansas
Archeological Survey for this work, with an estimated cost of $45,000.
A summary of our requested contract scope is included in tabular form as
Attachment Ito this Memorandum.
We certainly understand the City's desire to execute contract amendments prior
to completing the work. In this instance, we acknowledge that we were in error in not
working with City staff to prepare and present the appropriate amendments to the
Council for consideration prior to starting the work under the increased scope. We are
implementing in-house procedures to assure that this doesn't happen with future work.
Once these have been fully developed, we will share them with you.
It was not until July, 2001, that our cost actually began exceeding the original
budget amount, and we notified the City. At that time, with the urgency of completing
the Facility Plan to keep the project moving, we felt that the best interests of the project
would be served by concentrating our efforts on completing the work so that the City
could complete the program requirements to qualify for the 3 percent RLF loan, rather
than stopping to amend our contract. We believe that the City's intent is evidenced in
Don Bunn's memorandum of August 7, 2001 (Attachment J), which accompanied the
contract amendments for the other project consultants on the Council meeting of
September 18, 2001. Actually, we put the interests of the City and the project above
our own.
We work in an atmosphere of trust. As clients have asked us to do additional
work, we have bent over backwards to get that work done, with the understanding that
formal contract amendments would be executed at a later date.
Attachments
January 25, 2002
McGoodwin, Williams and Yates, Inc.
Consulting Engineers
909 Rolling Hills Drive
Fayetteville, Arkansas 72703
ATTACHMENT A
Summary of 404 Work Elements
• Illinois River Watershed Sewer Lines (20 miles)
- 40 stream crossings
- 11 wetlands totaling 10.82 acres
• Westside Plant Outfall
- I stream crossing
• Westside Plant Effluent Line (2.78 miles)
- 1 stream crossing
- I wetland totaling 1.47 acres
• Westside WWTP Site
- 2 wetlands totaling 7.0 acres
• Broyles Road Reroute (0.40 miles)
- 2 stream crossings
- 2 wetlands totaling 1.5 acres
• West Fork of the White River Watershed Sewer Lines (14.84 miles)
- 28 stream crossings
- 4 wetlands totaling 2.35 acres
PROJECT TOTALS
72 stream crossings
20 wetlands totaling 23.14 acres
38.02 miles for linear portions of project
• ATTACHMENT B •
PUBLIC OPINION SURVEY COMMENT SUMMARY
I"
I,
II
I'
C
IN
Question
Comments
NO
When this survey first arrived, we lacked knowledge and information. It was during a meeting
with the "Candidates for Mayor' that we heard discussion of this matter. We plan to be alert to
future information from any source.
We didn't return the first survey because we did not believe we were informed enough to give
t
you opinions that we could substantiate with facts. We hope this survey is helpful despite our
lack of knowledge regarding the treatment of wastewater.
We are new to the area and not very informed about this topic.
;This is certainly an important issue and I appreciate your efforts to seek citizen input. It asks
about respondent's self -assessed level of information, and then, at times assumes quite a lot of
:information and understanding about Fayetteville's current waste matter situation. To rally
'support for the new facility, you might have provided a quick summary of the current situation
!and future options. Just a paragraph. and then ask more esoteric questions. Just a
suggestion!!
Since I don't know anything about the subject I do not feel that I can make any kind of an
opinion. Thanks anyway.
Obviously, I need to be more informed
Not sufficient information to have an informed opinion.
Need to know more information
: Need more knowledge about how existing funds are used. Another area where consumer is last
;to know facts —true story?
re info
here since 6/98 and know there is a debate about waste but have never read a good
n or learned an hin from media. NEED MORE INFO!!t
alexianation
all of these issues should be presented in a public forum to educate the citizens so
1 ht make more informed decisions on these matters.
't know anything about this problem. Either way.
1
it don't know enough about fair pricing, need for improvement of water treatment, or need for tax
increases to make an informed decision on this matter. Does most of the public?
t
; I don't feel that I have enough knowledge about water treatment to answer these questions
do not feel that I am informed enough to property answer the above questions (questions 9b -e).
it
'I can't answer any of these questions without knowing something about deficiencies and
strengths of current system.
' I not well informed about water quality systems or waste treatment. But if a new facility is
am
I think it should be of a quality that will last and meet all the city's needs. I would
necessary,
rather pay for it on my bill (those who use more, pay more), than with a sales tax.
1
!IGo`dd'luck: Your department is asking questions that require more information in order to
'develop an intelligent response.
1
Do not understand any of this!!!
'Being to Arkansas and the Fayetteville area, were not knowledgeable about the
new residents
water problems
Water Quality 2000 Program
Public Information Program
t
1u:6U1-??6-7409
0CT 17'01
15:05 No.014 P.0;
•
I;ujt7cj
■N■■N■ATTACHMENT C
• j I � I • • (;n IIIIYIIfj' Ulil@V('h "Soar nn,n, 1LhJC(i1M - C J'rvr un*-.nllf,,
I $f/Ul$I IK'
A S S O C I A T E S 632 Mainsheet - laurel, MD 20707 - 301 •776.7407 - lax; 301 •7 I NC.
October 15, 2001
James Ulmer, P.E.
Vice President
McGoodwin, Williams & Yates
909 Rolling Hills Drive
Fayetteville, AR. 72703
RE: Public Information and Communications Program
City of Fayetteville, AR. — Wastewater System
Improvement Project
Dear Jim:
The following information provides the sequence and circumstances affecting the
additional program efforts required for the City's wastewater system improvement
project. This work was primarily performed to comply with the public participation
program efforts of the City's amendment to its 201 facilities planning process. The
additional work that occurred, primarily in 2001, was not identified in the original scope of
work for Hanifin Associates, Inc (March 2000 — Attachment 1), inasmuch as the overall
technical efforts and final regulatory requirements were not clearly defined for the City's
Proposed amendment to its Wastewater Management Facility Plan.
The City's initial objective in February 2000 was to provide a public information program
that addressed the project's overall objective. However, changes in the direction in which
this program would continue into a second phase was acknowledged by the project
leaders in January 2001. At that time, it was determined that an increased level of public
education was needed as a result of the analysis derived from the public information and
opinion survey (October/November 2000). This analysis confirmed that low levels of
public knowledge existed about the project, the methods in which it would be financed,
and the overall affects to water quality if the project did not materialize.
Subsequently, the project leaders agreed in January 2001 that an aggressive
public education effort would be initiated over the next several months (Attachment 2).
This decision was also reinforced by the City's newly -elected public officials. The City's
new leaders recognized the importance of customer education in order to secure
approval by State DEQ officials for the facility plan amendment.
In summary, the additional work tasks and out of scope costs incorporated the following
level of effort.
1. Redesigning the information program to comply with the Facility Plan
Amendment Update requirements, based on the survey analysis and public
official's requests.
2. Additional (bi-monthly) trips to provide essential program support and produce
the work required for the Facility Plan Amendment update.
3. Development and production of a comprehensive public information project
summary mailed to over 2500 residents and distributed through numerous
ID:301-776-7409
C
0CT 17'01 15:06 No.014 P.02
•
meetings; an information report about the costs of the wastewater system and
needed improvements, and one about the environmental regulations that guided
the overall technical development of the facility plan amendment.
4. Providing additional survey and socio-economic analysis on property owner
issues and establishing a significant database of citizen questions and
responses.
5. Developing special graphics and information for the City's web site.
6. Design, management and facilitation and documentation services for additional
public information meetings, the amendment public hearing and educational
workshops about the project.
7. Production of project graphic materials to support the City's public information
presentations and activities about the project, and additional mailings to
wastewater system customers and property owners.
8. Developing the framework and script for the City's public information video.
9. Providing additional communication services and public official updates.
10. Establishing for the City a framework for a long-range public information program
about the relationship of clean water and the value of wastewater treatment
technology.
Should you desire additional information, please let me know.
Sincerely,
,.
da 44c1Hanifin Bonner, Ph.D
ID:301-776-7409
0
0CT 17'01
0
15:06 No.014 P.03
�.
�� _■. m,.
| �| §�� .! #4! =r| §!|
■� t4- §;. 2,� 2
!$ 22t !` t3 �| || R||
J Q- e
;■# 2.■ 88. ,E! ..- ].s#
§� �! 2 \!| §�k■! kk,!
- - "` ; ` §■a�
oe! � ... ;■| ■B! P.�#
§ f §
,■7 !� _� §- *-§-
U . • I!!
;- - �. -;k _` k|
-
. ,; |E fl.- '!, )i4 ,,. dqv
§|| 1.
2° 3 .|
@
a* ;_S. -, ■E,
S.
| ;!■■; ;;; ��- ., --
.. rm,
.��.
| k
7§| DI (§| � | | %§§|
! | |
/ | | | | | §
| 0 | | § § t • § 2
• ID:301-776-7409 0CT 17'01 15:07 No.014 P.04
• •
Summary of Out of Scope Tasks Costs
Public Information Program • City of Fayetteville, AR
Wastewater System Improvement Project
October 15. 2001
.....
�Ctls1aT�. `.:.._„ ..,....:iTsa lama:" .: __. ; " ^;:-• '.': Di➢lilptloh � ..:
OUT OF SCOPE WORK TASKS
,
Special Information maelings and large scale public
2000 turn
Public and community meetings
workshop to prosom program approach
Conducting 30C10-ournumic analysis on properly
2000 Sep
Database Developmont
owner Issues & values: establishing database
2000 Oct
Information Survey
Printing, postage end mailing fees
Travel
Survey management
RedeslgnIng program to comply with
overall program development. Additional trips (2) for
Fsclily Plan Amendment; Travel &
project meetings associated with program
2000 Mar
Survey Production
development and survey presentation
Newsletter development for clllr ens which
7AJxPubllc
Iransitionod Into an overall 'layman• summary of
the facility plan: Spacial graphics for clllrens
2001
Education & graphics
summary report and war) page development
Additional travel to auppon program reschoduling
2001 - Msy
Travel & Moelings
and facility plan amendment needs
Web site davolopinenl to support City needs.
2001 - Jun
Public Education Materiels & travel
education project summary 6 special graphics
Public education (finance) fact sheet, workshop,
2001 - July
Meetings, Materials & Travel
meetings & travel (2) trips
(3) flips. workshop b material production. meetings,
2001 -Aug
Meetings, Materials & Travel
and printing 8 displays
(1) trlp. public hearing materials 8 producion
2001 . Sep
Mcot;ngs, Materials & Travel
displays 8 printing
Invoice Information:
Date
Invoice No.
Amt
4/3/2000
961348
2461.65
513/2000
961350
5804.3
6/1/2000
961350
3409.59
7/6/2000
961365
18118.3
811/2000
961370
18391.04
9/7/2000
961372
6772.75
10/4/2000
981376
5393.
12/4/2000
961383
14308.48
2/1612001
961393
4575.4 5
1/8/2001
961386
2883.9
_6
_
3/14/2001 ..._...
961397 _. ___ --
2750.1
4/4/2001 —. ._.__..
961405 -_- —-_—_6624.8
5/2/2001
-
961409
7456.09
—
6/4/2001
.. _. —.
. -
_
961412 .-
4195.9
17/512001
__. .. -
961415
5789.93
_ _
8/6/2001
-
9G1418 -
, 15063.2
-
8/4/2001
901420-�_
- 28288.97
26288.97
Total layette;:
162787.92
ATTACHMENT D
Fayetteville Wastewater System Improvements Project
MEETING SUMMARY
April
19, 2000
Partners meeting at MWY.
April
26, 2000
Jim Ulmer and Don Bunn to Little Rock — ADEQ/RLF meeting.
May
5, 2000
Meeting at MWY.
June
6, 2000
Neighborhood meeting — West Side.
June
7, 2000
Media briefing.
June
8, 2000
Neighborhood meeting — East Side.
June
14-15, 2000
Meetings; sludge meeting in p.m. on 15th. Meet with Greg Boettcher
and Ted Webber re project update.
June
15, 2000
Major public meeting at Hilton.
June
28, 2000
Partners meeting — Linda H. Bonner insisted that we initiate meetings
with ODEQ and OSRC.
June
29, 2000
Sludge Workshop at Fayetteville Room 326.
July 20, 2000
Partners meeting.
August 24, 2000
Partners meeting;Odor Control Seminar at Drake 5:30-8:00 p.m.
Sept.
11, 2000
ADEQ at Fayetteville.
Sept.
21, 2000
Partners meeting — RLF process.
Oct.
12, 2000
Meeting w/Don Bunn at 10:00 a.m. re Facility Planning schedule.
Oct.
13, 2000
Conference call w/Murray Flemming re effluent limits.
Oct.
16, 2000
Meet with ODEQ/OSRC at Tahlequah.
Oct.
19, 2000
Partners meeting and Citizens project update.
Oct.
25, 2000
Meeting with Thone & Scott Carr at 8:30 a.m. re biosolids disposal.
Nov.
8, 2000
Biosolids meeting at Don Bunn's office.
Nov.
16, 2000
Partners meeting and Citizens project update.
Dec.
28, 2000
Meet with Don Bunn re Farmington report of overflows.
Jan.
11, 2001
Meeting with Mayor Coody at 10:00 a.m.
Jan.
25, 2001
Meet with Kim Hesse and Bruce Shackleford re perimeter screening.
Jan.
25, 2001
Meet with Mayor Coody in Room 313 re odor.
Feb.
15, 2001
Meet with Mark Bradley re ADEQ permits.
Feb.
20, 2001
Meet with Don Bunn at 1:15 p.m.
Feb.
22, 2001
Partners meeting.
March 7, 2001
Don Bunn at 9:00 a.m.; Mayor Coody at 1:30 p.m.
March 15, 2001
Mayor Coody at 3:00 p.m. — prepare for Water & Sewer
Committee.
March 27, 2001
Water & Sewer Committee.
March
28, 2001
Duke Solutions conference call.
April
3-4, 2001
Charlotte, N.C. & Harrisburg, VA to Duke -Harmony plant tour. (Jim
Ulmer, Jeff Richards, Don Bunn, and other NWA city officials.)
April
19, 2001
Murray Flemming 9:30 a.m.; Rogers Tour 2:00 p.m.; Public Mtg. p.m.
April
23, 2001
Conference call 10:00 a.m., Springdale/Fayetteville Biosolids.
Bold signifies meeting about RLF or where RLF discussed.
2
May 9, 2001
Meet with Alderman Lionel Jordan at 4:30 p.m. — briefing on
project.
May 23, 2001
ADEQ at Fayetteville — agenda and sign -in sheet available.
May 24, 2001
Partners meeting at 1:00 p.m.
June 5, 2001
Odor presentation 8:30 a.m.; Review Appl. WWAC 1:30 p.m.
June 21, 2001
Partners meeting.
July 6, 2001
Meet with Greg Boettcher and Don Bunn at 8:30 a.m.
July 9, 2001
Fayetteville Water & Sewer Committee 7:00 p.m.
July 10, 2001
Meet with Don Bunn at 8:30 a.m.
July 10, 2001
Fayetteville Council Agenda Meeting.
July 11, 2001
WWAC at Little Rock with Don Bunn.
July 17, 2001
Fayetteville Council, call for Sales Tax election.
July 26, 2001
Meet with Don Bunn, Bruce Shackleford, et.al. 10:00 a.m.
re environmental permitting.
July 26, 2001
Financing seminar.
August 1, 2001
2nd trip to WWAC (Little Rock) with Don Bunn & Lane Crider.
August 2, 2001
Sierra Club tour and meeting (6:00 p.m. to midnight).
August 5, 2001
Advertise Public Hearing.
August 7, 2001
Council meeting setting Sales Tax election.
Aug. 13-14, 2001
AutumnFest educational booth.
August 16, 2001
Draft Facility Plan to Depositories.
August 23, 2001
Partners meeting.
August 23, 2001
Environmental Workshop at Continuing Ed. Center 6:30-9:00 p.m.
August 28, 2001
West Side neighborhood meeting.
August 30, 2001
East Side neighborhood meeting.
Sept. 20, 2001
Facility Plan/EID Public Hearing at Continuing Ed. Center.
Sept. 24, 2001
Review RLF application and re ASWCC meeting.
Oct. 12-13, 2001
AutumnFest booth & display about Project and Environmental Issues.
Oct. 16, 2001
Fayetteville Staff meeting re Project.
Oct. 16, 2001
Meeting at Oklahoma Scenic Rivers Commission re ProjecUBiosolids.
Oct. 18, 2001
Meeting/Conf. Call re Mayor's Town Hall meeting. (Greg Boettcher,
Don Bunn, Maureen Hoover, Linda Bonner, Jim Ulmer.)
Oct. 29, 2001
Mayor's Town Hall meeting.
Oct. 30, 2001
Meeting with cities re Biosolids Disposal.
Nov. 20, 2001
Meeting with Greg Boettcher and Don Bunn.
Nov. 20, 2001
Meeting with Oklahoma Scenic Rivers Commission.
Dec. 4, 2001
Meet with Greg Boettcher re MOA dates.
Dec. 11, 2001
Meeting w/USFWS, Corps, AG&F, ASWCC, Mayor Coody,
Greg Boettcher, Don Bunn, Ted Webber & Gary Dumas
re. Environmental Coordination.
Jan. 3, 2002
Okla. Scenic Rivers Commission Select Committee w/Mayor Coody
and Greg Boettcher.
Jan. 28, 2002
Mayors' meeting at Fayetteville re Biosolids.
Bold signifies meeting about RLF or where RLF discussed.
12/04/2001 11:46
501-60561 ASWCC • PAGE 02 Fy
J. RanOy Young. P.E.
E*ocullva Director
December 3, 2001
Honorable Dan Coody
Mayor, City of Fayetteville
113 West Mountain
Fayetteville, Arkansas 72701
Re: CS -050803-03
Fayetteville, Arkansas
Dear Mayor Coody:
�4rkansas
Soil and cWater
Conservation Commission
101 EAST CAPITOL
SUITE 350
LITTLE ROCK, ARKANSAS 72201
ATTACHMENT
PHONE 501.662.1611
FAX 501.662.3991
The Water Resources Development Division (WRDD) of the Arkansas Soil and Water
Conservation Commission (ASWCC) has reviewed the Final Environmental Information
Document and offers the following comments. It appears every effort has been made to
notify every agency, organization, citizen group, and citizen that may have an interest in
this proposed project. The attention given to the Environmental Review Process (ERP) is
greatly appreciated.
Prior to the production and publication of a required Finding of No Significant Impact
(Fonsi) and Environmental Assessment (EA) that meets the ERP requirements t`..c_e are a
few things that must take place. A couple of these reviewing agencies have made
comments requesting clarity so they may make a better determination of their position on
the proposed project. The U.S. Fish and Wildlife Service and the Arkansas Historic
Preservation Program are two of the agencies requesting more information. The U.S.
Corps' of Engineers will also be involved with the permitting of stream crossings and
construction within "waters of the United States." These issues are being addressed with
diligence and coordination is taking place at the time of this letter to satisfy the above
reviewing agencies.
Once again, we appreciate the attention given to the environmental aspects of this project
and please call me if you have any questions.
Sincerely,
Keith enders
Environmental Program Manager
Cc: Lane Crider, P.E.; McGoodwin, Williams and Yates, Inc.
An Equal DppoINry Ernooyar
12/04/2001 13:51 501-682-6561 ASWCC • PAGE 01
y Z9(a
-,••'�; �'"�. ^ Arkansas
Soil and cWater
J. RanOy Young. P.E.
Executive Oiraclor
Conservation Commission
101 EAST CAPITOL
SUITE 350 PHONE 501-682-1611
LITTLE ROCK. ARKANSAS 72201 FAX 501.662.3001
December 4, 2001
The Honorable Dan Coody
Mayor, City of Fayetteville
113 West Mountain Street
Fayetteville, AR 72701
Re: CS -050803-03
Wastewater Systems Improvement Project
Fayetteville, Arkansas
ATTACHMENT F
Dear Mayor Coody:
As stated in my October 15, 2001 letter, I bad no particular comments regarding the "draft
facility plan"; other than the need to address the comments received from all other interested
parties. It does appear that that mission was accomplished.
The "final facility plan" has been reviewed, and it appears to be approvable. I would like to
emphasize that final approval cannot be given until certain programmatic events have occurred.
Specifically, the City of Fayetteville must have officially entered the RLF program; or have
signed the Memorandum of Agreement (MOA). Next, the EID process must have been
completed, with the issuance of a FONSI (Finding of No Significant Impact).
At such time that these two key steps have been completed, official approval may be given. Any
changes resulting from the EID or other activities (water quality modeling, etc.) may require the
amendment of the facility plan. This would not pose that great of a problem.
This is not a totally unique situation; as many communities at this stage authorize thc?:
consultants to proceed with the development of plans and specifications.
Please contact me at 501-682-0556, if there arc any questions.
Sincerely,
Michael L. Core, P.E.
Project Engineer
cc: James C. Ulmer, P.E., McGoodwin, Williams and Yates, Inc.
Greg Boettcher, Public Works Director, City of Fayetteville
Pa Egret Oppaaaary Employer
I
V
It
2
,q
d 4
a
d4
LL
ag
N p
dO
N O
O
A
Jg
a
�pQpQpQpQoQ
OO O O p OO
O OO O O O OO
O OO O O O OO
it.O
O VI
m m N N
sjq-ueyy
ATTACHMENT H
ECO's Total Project Cost Summary
Section
Description
Total Cost
169-01
General Regulatory Compliance
$ 46,511.51
169-01A
Regulatory Compliance Westside WWTP/MWY
2,423.48
169-01B
Regulatory Compliance Westside Linework/RJN
412.87
169-01C
Regulatory Compliance Eastside WWTP/B&V
246.43
169-01 D
Regulatory Compliance Eastside Linework/Garver
929.72
169-02
404 Permit General Services
27,159.21
169-02A
404 Permit Westside WWTP/MWY
27,655.65
169-02B
404 Permit Westside Linework/RJN
52,471.09
169-02D
404 Permit Eastside Linework/Garver
26,829.88
169-03
Storm Water Permit General Services
55.76
169-03C
Storm Water Permit Eastside WWTP/B&V
.90
169-04
EID Review/Revision
55,591.20
169-04A
EID Westside WWTP/MWY
13.69
169-04C
EID Eastside WWTP/B&V
42.50
169-05
Public Participation Process
34,565.59
169-06
Candidate Conservation Agreement
9,642.80
169-07
ART Park
1,315.77
Total---------------------------------------------------------------------------------- $ 285,868.05
q
m
8
O
C
a
CD
co
x
CD
N
CD
CD
CA
T
?PBT
o
a
im
o
�m�
T
J
o
o
m
0
O
3
co
O
y
CA
O
y
m
3
3
T
O
Pe
N
J
N
3+
W
<Da.
Q
Op
a
C
(
Cm
T
N
a
CD
y
(D
a)
-,
C
m
m
c
m
Q
axC
33o
o
0
0
y
o
N
N
L
m
N
W
3
n
O
Q
rD
CD
O)
I
N
(D
O
m
A
O
J
N
.-.
m
O)
V
O)
V
V
N
m
V
Q�
N
a(OO0J,
N
N
CD
Oo
coA
a
1O
CO
I
O
N
N
O
m
A
cc
No
'Cl
(D
O
O n
N
-
N
N
O
O
C
a
coA
A0o
0ocD
C
3
to
a
w
f D
C)
O
N
N
N
-
0N0)
O)
O)-Oo
co
0CD
N
N
N
OO0Vo
O
A0
)O
)
n
O
D
N
auw
O
o
rn
ww_°Jw
rnrnmm
CD
X
>
'
Nt?p
A
ppo'
(D
w
-
w
m
m
C/)
z
6nI
`^
a
n
C
J
IA
NN
1
0770
^
W
m m
C
a0
b000O
8 C
W
ao
OOO
O
3 co
co
G7
w
OO
c
n
m
m
-1
Co
^
C
^
o.
Cr
I
O1
I
.-.0c,
(Wl1
V
(AJ1
CO
O)
O)
O
.1
O
^
N
m
00-D
O
fD
wm
N d�
N
tVD
CA
coo
N
O)
000Avvp)w
(�Op
ay�Ny
m
3
a
CD
a)
I
v)
a'
(N71
A
O
A
A
Co
A
W
o)
W
0
C
0 W
a
N
N
N
W)D
V
ON
W
O
1O
O
OO-.
O)
aO]w
a
CO
O
CO
(D
y N...
W
O
W
I0000)0100
W
d
r
ATTACHMENT J
•
1tv of _
DEPARTMENTAL CORRESPONDENC•
To: Fayetteville City Council
From: Don Bunn, Assistant Public Works Director
Thru: Greg Boettcher, Public Works Director
Mayor Dan Coody
Subject: Contract Amendments
Wastewater Improvements Project
Date: August 7, 2001
In March and April of 2000 the City entered into contracts with Black and Veatch
Engineers of Kansas City, Garver Engineers of Fayetteville, McGoodwin, Williams,
and Yates Engineers of Fayetteville, and RJN Group of Dallas. The contracts were
for the purpose of developing Preliminary Design Reports connected with the
Fayetteville Wastewater Improvements Project. The contract amounts and the
responsibilities of each engineer are:
Black & Veatch Renovation, Existing Noland Plant $ 359,720.00
Garver Engineers East Side Lines and Pump Stations $ 429,392.00*
McGoodwin Westside Treatment Plant $ 955,302.00
RJN Group Westside Lines and Pump Stations $ 638,267.00.
and Development of Design Flows
Total of All Contracts $ 2.382.681.00
* Includes Amendment No. 1 approved Feb 6, 2001
1
\J
L
Iv
I0
Since the execution of thoucontracts in February and March2000, there have
been several developments which has necessitated a change in the scope of the work
and justifies increases in each of the contracts:
1. In the summer of 2000 the City of Fayetteville made the decision to
participate in the State's Revolving Loan Fund (RLF) Program as the primary
source of funding for the project. By participating in the RLF Program the
City obligated itself to a) Revise the Facility Plan of 1997 to the satisfaction of
the Arkansas Department of Environmental Quality, b) Prepare a revised
Environmental Information Document (EID), and c) Hold a Public Hearing.
2. In early December it became apparent from preliminary data developed at
that time that the cost of the project, based on established design criteria,
would run well over $150,000,000.00. At that time the consultants were asked
to revise their cost estimates and make the other changes necessary based on
some revised design criteria*.
Three (3) contract amendments are being presented for the Council's review and
approval. The contract amendments are with Black and Veatch, RJN Group, and
Garver Engineers. Explanations of each are:
Garver Engineers: On February 6, 2001 the Council approved Amendment No. 1
with Garver Engineers in the amount of $37,860.00. This amendment was for the
extra work in connection with the change in design criteria. Attached for your review
and approval is Amendment No.2 in the amount of $37,218. The specific work
included in Amendment No. 2 is:
1. Revision of the Preliminary Design Report as a result of the design flow
changes.
2. Coordination with McGoodwin on Facility Plan and EID Revisions.
3. Additional Monthly Coordination Meetings.
4. Additional meetings with the Council, the public, and with the Health
Department, ADEQ, and other regulatory agencies.
* Two changes in the design criteria were made in order to reduce costs on the project. The ori&inal
criteria called for the 2025 design flows to be met in sewer pipes flowing 2/3 full with no surcharge of
sewers under ultimate flow conditions. This was changed so that sewerpipes would carry 2025 design
flows flowing full and ultimate flows would be carried under a surcharged condition. In addition,
man credit was taken for flow reductions as a result of future sewer rehabilitation efforts than
onginalf planned
•
•
•
2
This work is intended to ry through the Public Hearing tob celd in September
and also cover any incidental work until such time as an amendment for the
preparation of Detailed Plans and Specifications is approved. The amount of this •
• amendment is $37,218, bringing the total not -to -exceed contract amount to $466,610.
Black and Veatch: Attached for the Council's review and approval is proposed
Contract Amendment No. 1 with Black and Veatch in the amount of $38.809.
The work specifically included under this proposed amendment is:
1. Preparation and attendance at the Public Meeting to be held September 20.
2. Additional public information meetings (4).
3. Attendance at six (6) additional coordination meetings.
4. Provide coordination and assistance in the preparation of the Revised Facility
Plan.
This amendment is intended to carry through the Public Hearing to be held in
September and provide for miscellaneous assistance until such time as an amendment
for the preparation of Detailed Plans and Specifications is approved. The not -to -
exceed figure would be increased to a total of $398,529 with approval of this
amendment •
RJN Group:
Attached
for the
Council's
review and approval is proposed Contract
Amendment
No,_ I with
the RTN
Groun
in the amount of $124.903.03. This
amendment is to provide compensation for additional work incurred in connection
with the change in design criteria, additional public meetings, and coordination and
assistance in connection with the Revised Facility Plan and EID. Generally, the work
includes:
1. Work involved in revising flow projections for both east and west sewer lines,
the existing Noland Plant, and the proposed Westside Treatment Plant
2. Additional public meetings and coordination meetings required until such time
as an amendment is approved for the preparation of detailed Plans and
Specifications.
3. Provide assistance in the preparation of the Revised Facility Plan and the EID.
Exhibit A of the proposed Contract Amendment No. 1 gives a more detailed listing
• of the additional work items required. The not -to -exceed Contract Amount would be
increased to $763,170.88 with the approval of this amendment.
•
RI
I.
McGoodwin Williams, armed Yates: The engineering firm oilolcGoodwin, Williams,
and Yates is currently in the process of Facility Plan Revision, EID preparation,
working with ADEQ and the Arkansas Soil and Water Conservation Commission in
connection with securing RLF Funding, and has attended several city related public
meetings on the project.
In addition, they have been working with the City in the investigation of the possible
construction of a fertilizer plant in the Northwest Arkansas area which would utilize
sewage sludge from the area cities and poultry litter.
Contract Amendment No. 1 for the above activities will be presented to the Council
for review and approval at a later date.
It is the recommendation of the Staff that Contract Amendment No. 2 with Garver
Engineers, and Contract Amendment No. I with Black and Veatch and RJN Group
be approved. A summary of the proposed amendments is:
•
l=
Engineering Firm Cost of Amendment Revised Contract Amount
Black and Veatch $ 38,809 $ 398,529.00
Garver Engineers 37,218 466,610.()0
RJN Group 124.903 763.170.88 •
Totals $200,930 $1,628,309
Staff also recommends the
approval of a project budget adjustment of
$236,572.00 to
fund this request as well as
provide funding for
the additional financial
services to be
performed by Stephens, Inc
and rate studies to
be performed by Black
& Veatch.
4
STAFF REVIEW FORM • •
X Agenda Request
Contract Review
Grant Review f�/(i�n ��Zr*
1vi1 1� l�i''.� A f�rl-J1ED
For the Fayetteville City Council meeting of Ee--e 5, 2002
FROM:
Greg Boettcher Water and Sewer Public Works
Name Division Department
ACTION REQUIRED:
Approval of a Consultant Contract Amendment No. I (original contract dated March 21, 2000) for Wastewater
System Improvement Project in the amount of not more than $578,918.24 to address: ( I) Additional engineering
services, outside original contract scope, by McGoodwin, Williams and Yates, Inc. - $115,100.06, (2) Expanded
sub -consultant services by Environmental Consulting Operations for environmental permitting for the Project -
$326,782.05, (3) Additional technical services by Hanifin Associates for public involvement program for the Project
-$88,836.13, (4) Land appraisal services by Reed and Associates, not included in the original Project scope, to
assess the Project's potential impacts upon neighboring land values - S2,600.00, (5) Cultural Resource Survey by
Sponsored Research, not included in the original Project scope, to assess the Project's potential impacts upon
historical and archaeological resources - $45,000.00 and (6) Flood elevation analysis services, not included in the
original Project scope, to define 100 -year flood elevation for the West Side Treatment Plant site - $600.00. Current
contract amount is $955,302.00, with the requested increase raising the contract value to $1,534,220.24. Approval
of a budget adjustment is requested. The funding of a budget adjustment for the approved contract increase is from
the proceeds of the Series 2000 Water and Sewer Revenue Bond Issue.
COS E 1'O CITY:
(Subject to Negotiations)
$578,517.52
Cost of this Request
5400-5700-5314-00
Account Number
98047-10
Project Number
Budget Manager
73.099
Category/Project Budget
$ 73.099
Funds Used to Date
$ -0-
Remaining Balance
X Budgeted Item
Administrative Services Director
CONTRACI'IGI N I7LEASE REVIEW: GRANTING AGENCY:
Accounting Ma ager J Date
ice Co..vu �f _
City Attorney Date
Purchasing Officer ,
Professional
Category/Project Name
Wastewater Improvements
Program Name
Water and Sewer Bonds- Series 2000
Fund
X_ Budget Adjustment Attached
ADA Coordinator - Date
_sJc�.
In emal dnor Date
STAFFREVIEW: Cos{S s"L,ec.f ♦o Ct4-t Cot.+c.tf 4-PPre"(
Date Cross Reference
OL
Date New Item: Yes No
,//I/oZ
ate Prev Ord/Rcs /I 34 -00
B- 1 SO
t c Orig Contract Date: 3/ )-O
S .•
STAFF REVIEW FORM
X Agenda Request
Contract Review
Grant Review
For the Fayetteville City Council meeting of January 5, 2002
FROM:
tree Boettcher Water and Sewer Public Works
Name Division Department
ACTION REQUIRED:
Approval of a Consultant Contract Amendment No. I (original contract dated March 21, 2000) for Wastewater System
Improvement Project in the amount of not more than $578,918.24 to address: (I) Additional engineering services, outside
original contract scope, by McGoodwin, Williams and Yates, Inc. -$115,100.06, (2) Expanded sub -consultant services
by Environmental Consulting Operations for environmental permitting for the Project - $326,782.05, (3) Additional
technical services by Haniftn Associates for public involvement program for the Project - $88,836.13, (4) Land appraisal
services by Reed and Associates, not included in the original Project scope, to assess the Project's potential impacts upon
neighboring land values - $2,600.00, (5) Cultural Resource Survey by Sponsored Research, not included in the original
Project scope, to assess the Project's potential impacts upon historical and archaeological resources -$45,000.00 and (6)
Flood elevation analysis services, not included in the original Project scope, to define 100 -year flood elevation for the
West Side Treatment Plant site - $600.00. Current contract amount is $955,302.00, with the requested increase raising
the contract value to S 1,534,220.24. Approval of a budget adjustment is requested. The funding of a budget adjustment
for the approved contract increase is from the proceeds of the Series 2000 Water and Sewer Revenue Bond Issue
COST TO CITY:
(Subject to Negotiations)
S578.517.52 $73,099 Professional
Cost of this Request Category/Project Budget Category/Project Name
5400-5700-5314-00
Account Number
98047-10
Project Number
BUDGET REVIEW:
$73,099
Funds Used to Date
Remaining Balance
X Budgeted Item
Wastewater Improvements
Program Name
Water and Sewer Bonds- Series 2000
Fund
Budget Adjustment Attached
Budget Manager Administrative Services Director
CONTRACT/GRANT/LEASE REVIEW: GRANTING AGENCY:
Accounting Manager Date ADA Coordinator Date
City Attorney Date Internal Auditor Date
Purchasing Officer Date
STAFF REVIEW: Costs subject to City Council approval
Division Head Date Cross Reference
Department Director Date New Item: Yes No
Administrative Services Director Date Prev Ord/Rcs#:39-00
Mayor Date Orig Contract Date: prX�
Page 2
STAFF REVIEW FORM
Description Meeting Date
Comments: Reference Continents:
Budget Coordinator
Accounting Manager
City Attorney
Purchasing Officer
ADA Coordinator
Internal Auditor
FAYETTEVILLE, ARKANSAS
PUBLIC WORKS DEPARTMENT
ADMINISTRATIVE CORRESPONDENCE
TO: Mayor Dan Coody and City Council
City of Fayetteville, Arkansas
FROM: Greg Boettcher, Public Works Director
DATE: January 3, 2002
RE: Wastewater System Improvement Project
McGoodwin, Williams and Yates, Inc.
Engineering Contract Amendment
**********************************************************************
BACKGROUND
The City of Fayetteville (OWNER) and McGoodwin, Williams and Yates, Inc. (ENGINEER)
entered into an agreement for engineering services (New Westside Treatment Facility -Study, Preliminary
Design and Report) on March 21, 2000, the contract's total compensation for authorized services being
$955,302.00. This contract covers two phases of Engineering Services, the first being the aforementioned
"Study, Preliminary Design and Report -Section IV. (A) and the second phase being the "Detailed Design
and Preparation of Construction Plans and Specifications -Section IV. (B). Only the first phase services
were negotiated and authorized by the City of Fayetteville. The engineering contract terms specifically
noted that the compensation set forth in the agreement did not include costs for services associated with the
requirements of the State Revolving Loan Funding Program. In addition, the agreement's terms
specifically required all changes, modifications or amendments in scope, price or fees to he addressed by a
formal contract amendment that is approved by the Mayor and City Council in advance of the change in
scope, cost or fees.
The ENGINEER, in the performance of the authorized services, subcontracted with other engineering and
technical consultants to fulfill the scope of work. The listing of subcontract parties and their subcontract
values are as follows:
Boyle Engineering
S
99,985.00
Webster Environmental
S
83,820.00
Hanifin Associates
S
98,252.00
Environmental Consulting
S
17,086.00
Grubs and hloskyn
$
14,000.00
M.J. Harden
510,980.00
Environmental Services
533,170.00
A copy of the Engineering Cost Summary and the Detailed Scope of Work, as set out with the engineering
S
agreement of March 21, 2000 are included as Exhibit "A".
This engineering services contract was one of four contracts covering a comprehensive wastewater system
improvement project (PROJECT) for the City of Fayetteville. Other consultants and PROJECT sub -
elements included: RJN Engineers -West Side Collection System, Black and Veatch Engineers -Paul
Noland Wastewater Treatment Plant and Garver Engineers- East Side Collection System. The City of
Fayetteville did elect to finance the Wastewater System Improvement Project using the State Revolving
Loan Fund as administered by the Arkansas Soil and Water Conservation Commission. This funding
program does impose additional engineering, environmental and administrative burdens upon both the
OWNER and ENGINEER. The ENGINEER has recently submitted a request for a contract amendment to
cover the alleged changes, modifications and amendments in scope, price and fees. The requested contract
amendment represents an increase of 5578,5 17.52, changing the contract amount from $955,302.00 to
51,533,819.52.
DISCUSSION
The information submitted by the ENGINEER has been summarized in the spreadsheet included herewith
as Exhibit "B". This spreadsheet includes the original contract budget amounts, the current costs in each
category as of December 2001 and the anticipated final costs to complete the facility
planning/permitting/administrative tasks now underway or needed to complete the facility planning
process. Following is a brief description of each cost category as 10 (1). nature of services provided, (2).
scope of original services and (3). alleged additional services for which extra compensation is requested
I. McGoodwin. Williams and Yates, Inc. -The authorized scope of engineering services
related to the development of a preliminary design report for a new west side wastewater
treatment plant, coordinating the plant's preliminary design with the other engineering
consultants already retained by the OWNER for associated elements of the PROJECT.
The engineering services scope was detailed in the agreement (Exhibit "C") and consisted
of preliminary design activities including submission of a preliminary design report. The
scope of services was reportedly expanded to include the following items, greatly
increasing the level of effort: (a) Served as central coordinator for the PROJECT, (b)
Expanded scope of engineering report from only the West Side Treatment Plant to include
all four elements of the PROJECT including conformance with the requirements set by the
Arkansas Soil and Water Conservation Commission for a (Wastewater Facility Plan,
Preliminary Design Report, and Environmental Informational Document), (c) Assisted in
the coordination of and preparation of applications for funding from the State Revolving
Loan Fund, (d) Developed and implemented planning for the Broyles Road Extension, (e)
Administration of the expanded environmental permitting for the PROJECT, (f) Expanded
investigations into the biosolids management planning for the PROJECT, including
investigation of additional alternatives and coordination of recommended strategy, and (g)
Special investigations into West Side Industrial loadings. The costs for those services are
above the approved amount.
2. Boyle Engineering- The services of this sub -consultant related to the provision of
specialized technical assistance of wastewater process evaluations, (selection and
preliminary design). Due to the increased use of in-house resources of McGoodwin,
Williams and Yates, Inc. the costs for sub -consultant services was below budgeted levels,
with the unused budget amount being transferred to the services of the prime consultant.
3. Webster Environmental -The services of this sub -consultant related to the provision of
4
0
specialized technical assistance for odor control at the proposed West Side Treatment
Plant, including assessment of odor potentials, evaluation of odor control alternatives and
furnishing preliminary design recommendations for the selected odor control system. The
costs for these sub -consultant services were below budgeted levels, with the unused
budgetamount being transferred to the services of the prime consultant. -
4. Environmental Consulting Operations (ECOJ-The original scope of services of this sub -
consultant related to the provision of specialized environmental assistance for the
permitting of the proposed West Side Wastewater Treatment Plant. The scope of this sub -
consultant's work was reportedly expanded, greatly increasing the level of effort, including
the following activities: (a) Expanded environmental permitting scope from the West Side
Treatment Plant to include all four elements of the PROJECT, (b) Increased the scope of
the Corps of Engineers 404 permitting from only the West Side Treatment Plant to include
permitting for all four elements of the PROJECT, allowing continuity of activities and
eliminating duplicated efforts by the other consultants, (c) Initiated work on the NPDES
Storm Water Permit for the PROJECT, (d) Added the development of an Environmental
Information Document (EID) to the scope of work, said EID addressing the entire
PROJECT; the development of the EID being a specific requirement of the Revolving
Loan Fund under the Arkansas Soil and Water Conservation Commission, (e) Participated
in the public information program for the PROJECT funding, including attendance at
public meetings, providing environmental information and justifications for the PROJECT
and assisting in the dissemination of accurate environmental information about the
PROJECT, (f) Assisted in the evaluation of and development of Candidate Conservation
Agreement (CCA) for the PROJECT, to address prospective endangered species concerns,
(g) Provided specialized environmental guidance regarding the environmental issues
surrounding the planned construction at the former Research and Technology Park along
Highway 540, including preliminary evaluations of site conditions, site issues and possible
mitigation measures. A more detailed description of the services provided by ECO is
detailed in the correspondence dated November 27, 2001, a copy of which is included as
Exhibit "D". The costs for these sub -consultant services are above the approved amount.
5. M.J. I larden-The services of this sub -consultant related to the provision of current aerial
photography for the West Side Treatment Plant Site, to support the preliminary
engineering activities. The costs for these sub -consultant services were at budgeted level.
6. Gruhhs-Hoskvn- The original scope services of this sub -consultant related to the
performance of geotechnical services associated with the preliminary design of the West
Side Wastewater Treatment Plant. The costs for these sub -consultant services were below
budgeted levels, with the unused budget amount being transferred to the services of the
prime consultant
7. Hanifin Associates- The services of this sub -consultant related to the provision of
professional guidance in the development of a public information program for the proposed
West Side Wastewater Treatment Plant, including development of a methodology for the
public involvement, arranging three public meetings to discuss the proposed new treatment
plant and coordination of the program with others concerned. The scope of work by this
sub -consultant was allegedly expanded to include such areas of additional work as: (a)
Expansion of the public information scope from the West Side Wastewater Treatment Plant
to include the entire PROJECT, (b) Increasing the extent of public informational meetings
from the initially planned three meetings to approximately sixteen public information
meetings, (c) Expanding and formalizing the public involvement program to meet the
specific requirements for Facility Planning/State Revolving Loan under the regulations of
the Arkansas Soil and Water Conservation Commission, (d) Expanding the scope of the
0
public information program to include the provision of written
information/graphics/handouts to inform the public on the proposed Sales Tax Bond Issue
held in November of 2001, (e) Expanding the scope of the public information program to
include the use of video and web site mediums, and (f) Development of communication
resources/tools/criterion to improve the effectiveness and clarity of the information
presented to the public on the PROJECT. A more detailed description of the services
provided by Hanifin Associates is detailed in the correspondence dated October 15, 2001, a
copy of which is included as Exhibit "E".
8. Environmental Services Company -The services of this sub -consultant relate to the
laboratory testing to provide background data for the preliminary design of the West Side
Wastewater Treatment Plant. This work included water testing, sludge testing and sub-
system raw wastewater testing. The costs for these sub -consultant services were below
budgeted levels, with the unused budget amount being transferred to the services of the
prime consultant.
9. Reed and Associates -The services of this sub -consultant were not included in the original
scope of work of engineering consultant. This sub -consultant provided a detailed land
appraisal report that evaluated the effects of wastewater treatment plants upon the values of
surrounding properties. The appraisal firm researched the values of specific properties,
comparing their value prior to and after the construction of a wastewater treatment plant in
their immediate vicinity. '[he analysis found no loss of land value when a wastewater plant
was constructed near a private property. This analysis was not included in the original
scope of work.
10. Sponsored Research (Arkansas Archaeological Survey)- l'he services of this sub -consultant
were not included in the original scope of work of engineering consultant. This sub -
consultant's services are now needed to survey the PROJECT construction areas for the
presence of historical and archaeological resources. The Arkansas State Historic
Preservation Officer has required that the PROJECT include a Cultural Resources Survey,
hence, the need for this sub -consultant. This sub -consultant utilizes local resources from
the University of Arkansas and is an approved provider of Cultural Resource Survey
Services. This survey was not included in the original scope of work.
II. TWH-The services of this sub -consultant were required to assess the flooding potentials of
the proposed West Side Wastewater Treatment Plant. The flood mapping for the proposed
plant site did not have specific 100 -year flood elevations, as required for the design of
wastewater treatment facilities. The new facilities must be able to withstand a 100 -year
flood without damages to equipment and structures. This sub -consultant performed a
detailed hydrologic study of the site and established the design 100 -year flood elevation.
This analysis was not included in the original scope of work.
ASSESSMENT
The final decision regarding any proposed contract amendment rests with the Fayetteville City Council.
The terms and conditions of the agreement obligated the ENGINEER to secure prior approval from the
OWNER for all changes in scope, costs or fees, said approval being issued by the Mayor and City Council.
From a more liberal perspective, however, it is recognized that the scope of the PROJECT has changed
including the decision to use the Revolving Loan Fund to finance the PROJECT, increasing the levels of
effort by the ENGINEER. It is also noted that the agreement specifically exempted the work associated
with the Revolving Loan Fund as a component of the original scope, said condition being further
confirmed in the letter of transmittal for the contracts dated February 29. 2000 (enclosed as Exhibit "F").
Certain elements for which additional compensation arc requested do relate to the exemption for Revolving
Loan Funding, however, other elements of the requested additional compensation relate only to changes in
0
scope for which no authorization was granted by the Mayor and City Council. This deviation from
contract terms eliminated the OWNER's opportunity to review the changes in scope, fees and costs prior to
their performance, and prevented negotiation of approvable terms, conditions and compensations. Actions
of the ENGINEER have compromised the OWNER's ability to evaluate scope, assess costs, to investigate
alternative methods and to adhere to proper procedures for the expenditure of public funds. The fault lies
with the ENGINEER, who had sole control over his work and that of the sub -consultants.
The ENGINEER's contract administration is not acceptable performance and should not be rewarded. In
the request for a contract amendment, the ENGINEER has requested additional compensation to cover
additional past and future costs associated with the PROJECT. The costs being claimed are at normal
billing rates and include fixed fees (profit). In the agreement, the fixed fee for the prime consultant was
established at 10.15%, said fixed fee being applied to the services of sub -consultants, direct labor, indirect
labor and expenses. As a beginning point for the negotiation of the contract amendment, the OWNER may
consider the removal of profit (10.15% fixed fee) from all claimed costs performed without prior approval,
said discounting of the requested additional compensation being computed as follows:
A. McGoodwin, Williams and Yates, Inc. - For actual services provided by the staff of the
ENGINEER, an increase in costs of $140,819.19 has been requested, which is offset in part by a
$81,819.85 under run of certain sub -consultants (Boyle (-$66,494.43), Webster (-S6,835.07),
Grubbs (-$5,795.50), and ESC (-$2,694.85). Accordingly, the net increase requested becomes
$58,999.34, of which, 542,500.00 represents work yet to be performed. In addition to the direct
labor, indirect labor and expenses requested under the proposed contract amendment, the
ENGINEER is requesting that the fixed fee (profit at 10.15%) also be increased by $55,700.00,
raising the current agreement's fixed fee from $88,105.00 to $143,805.00. It is proposed that the
fixed fee (profit at 10.15%) he limited only to the actual increase in the ENGINEER's costs, or
10.15% of the $58,999.34 or a fixed fee increase of $6,000.00. Accordingly, the $196,919.91
increase request is proposed to be reduced to $64,999.34 ($58,999.34 for direct labor, indirect
labor and expenses plus $6,000.00 for fixed fee increase).
B. Environmental Consulting Operations - For environmental consulting services, ECO is requesting
a total contract amount of $343,868.05, increasing the original $ 17,086.00 contract by
5326,782.05. While this sub -consultant has identified certain tasks that were not in the original
scope of services and has attributed cost to each category, the resultant costs are deemed excessive.
Of the $326,782.05 contract increase, approximately $58,000.00 relates to work that remains to
be completed and $251,696.05 represents work already performed without authorization. It is
recommended that the OWNER consider discounting the invoice for work performed without prior
authorization by a factor of 10.15%, reducing the contract increase by $25,500.00. Accordingly,
the $326,782.05 increase request is proposed to be reduced to an increase of $301,282.05,
bringing the total contract value to $318,368.05 for all work. This approach to the cost overrun
should address the hard costs of the consultant, but will remove profit from the work performed
without prior authorization.
C. Hanifin and Associates - For development of a public information program for the PROJECT,
Hanifin and Associates is requesting a total contract amount of S187,088.13, increasing the
original $98,252.00 contract by $88,836.13. While this sub -consultant has identified certain tasks
and services that were not in the original scope of services, and has identified certain activities that
exceeded the original levels of involvement, the resultant costs are deemed excessive. All of the
requested $88,836.13 in increased contract compensations relates to activities already completed
without prior authorization. It is recommended that the OWNER consider discounting the invoice
for services performed without prior authorization by a factor of 10.15%, reducing the increase by
$9,000.00. Accordingly, the $88,836.13 increase request is proposed to be reduced to an increase
of $79,836.13, bringing the total contract value to $178,088.13 for all work performed.
D. Reed and Associates - For the land appraisal services, not included in the prime consultant's
original contract scope, it is recommended that the engineering contract be increased by $2,600.00.
Since this work was not approved in advance, the 10.15% fixed fee should be denied, making the
increase a total of $2,600.00.
E. Sponsored Research - For the performance of a Cultural Resource Survey, not included in the
prime consultant's original contract scope, it is recommended that the engineering contract he
increased by $49,567.00. Since this work is to he approved in advance of the authorization, the
increase to the contract should include the cost of the cultural resources survey ($45,000.00) and a
10.15% fixed fee ($4,567.00), making the increase a total of $49,567.00.
F. TW Fi - For the performance of a 100 -year flood level analysis, not included in the prime
consultant's original contract scope, it is recommended that the engineering contract be increased
by $600.00. Since this work was not approved in advance, the 10.15% fixed fee should be denied,
making the increase a total of $600.00.
The following table includes a comparison of the original contract values, the contract values proposed by
the ENGINEER, and the contract values that would result from the discounting of all work performed
without prior approval by the OWNER:
COST CATEGORY
PRIME/SUBS
ECO
HANNIFIN ASSOC.
REED AND ASSOC.
SPONSORED RESEARCH
TWH
"I'Ol'AI.
ORIGINAL VALUE
$ 839,964.00
$ 17,086.00
$ 98,252.00
$ 0.00
$ 0.00
$ 0.00
S 955,302.00
REOUESTED VALUE
$ 954,663.34
S 343,868.05
$ 187,088.13
S 2,600.00
S 45,000.00
$ 600.00
$1,533,819.52
ALTERNATE VALUE
$ 904,963.34
S 318,368.05
S 178,088.13
S 2,600.00
S 49,567.00
S 600.00
$1,454,186.52
It was the responsibility of the ENGINEER to communicate the need for a contract amendment to the
OWNER, affording an opportunity for review and evaluation in advance of the work. The decision
regarding this contract amendment does rest with the Mayor and City Council, with the range of actions
possible including approval, denial or negotiation.
PRELIMINARY DRAFT COP
AMENDMENT NO I
TO
THE AGREEMENT FOR CONSULTING SERVICES
WEST SIDE WASTEWATER TREATMENT PLANT
PROJECT: West Side Wastewater Treatment Plant
CONSULTANT: McGoodwin, Williams and Yates, Inc.,
909 Rolling Hills Drive
Fayetteville, Arkansas 72701
OWNER: City of Fayetteville, 113 West Mountain,
Fayetteville, AR 72701
WHEREAS, McGoodwin, Williams and Yates, Inc. (ENGINEER) and the City of
Fayetteville, Arkansas (CLIENT) entered into an agreement for Consulting Services dated
March 21, 2000, and,
WHEREAS, the scope of the March 21, 2000 agreement set out a specific scope of services,
and additional items of work, outside the initial scope of services have been required to
complete the study, preliminary design and report phase of the West Side Wastewater
Treatment Plant (PROJECT), including the following items by the prime consultant,
McGoodwin, Williams and Yates, Inc.:
• Served as central coordinator for the PROJECT
• Expanded scope of engineering report from only the West Side Treatment Plant to
include all four elements of the PROJECT including conformance with the
requirements set by the Arkansas Soil and Water Conservation Commission for a
Wastewater Facility Plan, Preliminary Design Report, and Environmental
Informational Document
• Assisted in the coordination of and preparation of applications for funding from the
State Revolving Loan Fund
• Developed and implemented planning for the Broyles Road Extension
• Administration of the expanded environmental permitting for the PROJECT
• Expanded investigations into the biosolids management planning for the PROJECT,
including investigation of additional alternatives and coordination of recommended
strategy
• Special investigations into West Side Industrial loadings and,
WHEREAS, the scope of the March 21, 2000 agreement set out a specific scope of services
for the various sub -consultants and additional items of work, outside the initial scope of
services have been required to complete the study, preliminary design and report phase of
the West Side Wastewater Treatment Plant (PROJECT), including the following items of
work by designated sub -consultants:
12. Boyle Engineering -No change in scope
13. Webster Environmental -No Change in scope
14. Environmental Consulting Onerations (ECU'
*Expanded environmental permitting scope from the West Side Treatment
Plant to include all four elements of the PROJECT
*Increased the scope of the Corps of Engineers 404 permitting from only
the West Side Treatment Plant to include permitting for all four elements
of the PROJECT, allowing continuity of activities and eliminating
duplicated efforts by the other consultants
*Initiated work on the NPDES Storm Water Permit for the PROJECT
*Added the development of an Environmental Information Document
(EID) to the scope of work, said EID addressing the entire PROJECT; the
development of the EID being a specific requirement of the Revolving
Loan Fund under the Arkansas Soil and Water Conservation Commission
*Participated in the public information program for the PROJECT
funding, including attendance at public meetings, providing environmental
information and justifications for the PROJECT and assisting in the
dissemination of accurate environmental information about the PROJECT
*Assisted in the evaluation of and development of Candidate Conservation
Agreement (CCA) for the PROJECT, to address prospective endangered
species concerns
*Provided specialized environmental guidance regarding the
environmental issues surrounding the planned construction at the former
Research and Technology Park along Highway 540, including preliminary
evaluations of site conditions, site issues and possible mitigation measures
I5. M.J. Harden -No change in scope
16. Grubbs-Hoskvn-No Change in scope
17. Hanifin Associates -
*Expansion of the public information scope from the West Side
Wastewater Treatment Plant to include the entire PROJECT
*increasing the extent of public informational meetings from the initially
planned three meetings to approximately sixteen public information
meetings
*Expanding and formalizing the public involvement program to meet the
specific requirements for Facility Planning/State Revolving Loan under the
regulations of the Arkansas Soil and Water Conservation Commission
*Expanding the scope of the public information program to include the
provision of written in formation/graphics/handouts to inform the public on
the proposed Sales Tax Bond Issue held in November of 2001
*Expanding the scope of the public information program to include the use
of video and web site mediums
*Development of communication resources/tools/criterion to improve the
effectiveness and clarity of the information presented to the public on the
PROJECT
18. Environmental Services Company -No change in scope
10
19. Reed and As0•
.ates-
*Performance of a detailed land appraisal report to evaluate the effects of
wastewater treatment plants upon the values of surrounding properties
20. Sponsored Research (Arkansas Archaeological Survey) -
*Cultural resource survey of the PROJECT construction areas for the
presence of historical and archaeological resources, as required by the
Arkansas State Historic Preservation Officer
21. TWH-
*Calculation of the 100 -year flood elevation for the proposed West Side
Wastewater Treatment Plant site and,
NOW THEREFORE be it resolved between the ENGINEER and OWNER, that the above
referenced items of additional work, when authorized in writing by the OWNER, shall be
completed for the following additional compensation, with the agreement to be amended in the
following particulars:
A. Breakdown of Fees: "TO BE INSERTED WHEN APPROVED"
B. Section XII. Fees and Payments is amended as follows:
For the original and amended scope of services as set out in agreement and attachments
hereto (Administrative Correspondence dated January 3, 2002), compensation shall be
based upon actual salary cost for employees doing the work plus overhead at not more
than 1.55 times the actual salary cost (said overhead rate to be based upon an independent
certified public accountant's certified copy of "Overhead Computation" conforming to
Fomi RLF-155, latest revision, as issued by the Arkansas Soil and Water Conservation
Commission. The ENGINEER shall furnish copies of completed RLF-155 forms for
each fiscal year that work is performed on the PROJECT, with the rate to be adjusted
retroactively for any fiscal year in which deviations result), plus a fixed fee in the amount
of S
The estimated total compensation for the authorized services is S , including a
fixed fee of $__________ and S for direct labor, indirect labor, sub -consultant
services and reimbursable expenses.
C. Section XVI. Miscellaneous Provisions is amended to include the following:
H. The ENGINEER and all sub -consultants providing services under this agreement
shall be required to comply with the Arkansas Freedom of Information Act, latest
provisions, with regard to records and information associated with the PROJECT.
The ENGINEER shall comply with all requirements, including placement of identical
disclosure requirements in agreements with all sub -consultants, and shall meet the
obligations of the law regarding such items as electronic copies, time frame for
responses, reasonable charges for information and similar conditions to those placed
upon the City of Fayetteville.
1. The ENGINEER, in the performance of the authorized services, shall comply with
11
applicable schedules and conditions of the approved Memorandum of Agreement
with the Arkansas Soil and Water Conservation Commission, including amendments
to said agreement.
The ENGINEER shall furnish copies of all sub -agreements, invoices, billing
information, correspondence and other materials as the OWNER may request to
verify the accuracy of invoices and the nature of the work being performed.
K. The ENGINEER shall comply with the applicable provisions of the approved
Memorandum of Agreement (copy attached), shall comply with the applicable rules,
regulations and guidelines of the Arkansas Soil and Water Conservation Commission -
Revolving Loan Fund, including Regulation 10 provisions relating to nonperformance
or negligence of the consulting engineering firm. These provisions are incorporated
into the agreement by this reference.
IN WITNESS WHEREOF to the acceptance of the terms and conditions as set forth in the
Amendment No I to the March 21, 2000 agreement for Engineering Services, McGoodwin,
Williams and Yates, Inc. and the City of Fayetteville, Arkansas have executed this amendment to
agreement effective the date set forth below. All other terms and conditions of said Agreement
not in conflict with or not amended herewith remain in full force and effect.
Signed this day of , 2002.
CITY OF FAYETTEVILLE McGOODWIN, WILLIAMS AND YATES, INC.
FAYETTEVILLE, AR FAYETTEVILLE, AR
Dan Coody
Mayor of Fayetteville
ATTEST — City Clerk
L. CARL YATES
President
ATTEST- Vice -President
12
ATTACHMENT 6
ENGINEERING COST SUMMARY
WEST SIDE WASTEWATER TREATMENT PLANT
FAYETTEVILLE,ARKANSAS
MWY Project Number Fy-296
Engineering
McGoodwin, Williams and Yates
Direct Labor
$183,635
Overhead on direct Labor (1.55)
284,634
Subtotal MWY Direct Labor+ Overhead
$468,269
Engineering Subcontracts
Boyle Engineering
$99,985
Webster Environmental Associates
83,820
Subtotal Engineering Subcontracts
$183,805
Total Engineering
$652,074
Technical Support Services
Environmental Consulting Operations, Inc
$17,088
Geotechnical Services
14,000
Laboratory Sampling andTesting (3 Weeks)
33,170
Photogrammetry
10,980
Subtotal Technical Support Services
$75,236
Public Involvement
Hanifin Associates, Inc.
$98,252
Reimbursable Expenses
AirTravel
Car Rental
Lodging
Meals
GPS EguiF
Subtotal F
Rental
$28,800
2,820
4,425
4,590
1,000
Total Estimated Project Costs $867,197
Professional Fee 88,105
Exhibit "A"
Engineering Cost Summary
Pagel of 2
••
s
TRAVEL COST SUMMARY
WEST SIDE WASTEWATER TREATMENT PLANT
_ FoYETTEVILLE, ARKANSAS-- -
Project No. Fy-296
Air Travel
Site Visits $21,000
WEA 3,000
Boyle 4.800
$28,800
Car Rental
Site Visits $ 1,500
WEA 720
Boyle _ 66
$ 2,820
Lodging
Site Visits $ 2,625
WEA 900
Boyle 900
$ 4,425
Meals
Site Visits $ 3,150
WEA 540
Boyle 900
$ 4,590
Exhibit "A"
Engineering Cost Summary
Page 2 of 2
C
0
■#8;829■
j@R;;§#;
,
\k�k��
k■
■|
B§
7
82!82@
q
R
7
i§
!
2§
§
�
&
o
§
■
2
a
2
&e
z
|
cn
I-
■
<a
88
888
§
\
f
`
2<zB
M
o.
!8@9!888
q
,3=
!
/
§|
=a,;.
4.
cok3
§
-•
S
§
's
8888888
a'■
■A##§mf`
N
7
w
z
§
!
w
`�;s88888888
C,
;
!
\
a
§
�
888888,n
n
8
°
#a!!#K/laaa
2
&±!z!a
,»
4.
a
§
/
}||
2-!|1111k
-!|
f!!
7111
2
e
;
��
Exhibit "B"
West Side Wastewater Treatment Plant Attachment 1
Fayetteville, Arkansas MWY Job No. Fy-296
SCOPE OF WORK
1. DEVELOPMENT OF SCOPE OF WORK
2. CONTRACT DEVELOPMENT
3. PRELIMINARY
DESIGN
.. , ..,., I ..Iw u•:
.• .• 1 .
Ij
Ii/. I •. I I.. _. ..
'•
• 1 1• 1 •'.•1
,L_1, ••_I • 1\11 N\ 1•'p''• 1. 1sits, :1•II
Pt 1 1 1 1 1•' 1 I. 1 ..l !II 1 •1 • •II
ij
\• + 11 1' 1 +.1 •'1'JII 11 1 • 1.• 11 • II •• +111 II•_.1.•
.• I ,I%it.nl •.' 'JI I. I • • 11 I 1_.Y'11 I .•1 I.
1• 1 I.I.!tII 1 1 sic • I
rt.IDetermine11
\•• 11 I. 1•I• • 1 •: .• po •1 • ...
I
Determine11 \•• .111 • • _• .1.
I. t-, •1
•
••
Ill
Y 1 • I I •• • I.
11 1conditions1 _ I 1 1 I I 1 1 1 1 I. w I K 1 1 ✓. 1\ 1 • 1 11 4111:
I. 11AlternativesIj41jijt
fll
• 11 • 1 1 • 1 i• 11 \ 11 •11 1 + 1 1 .n 1 I .1 •1.� l
1: I• .\ 1 1 1 1 u. 1:1
1 • 111 +I 1• 1•' II I.v I•.w1
• I • 11removal4 1•.
••.1 .11 ulfacilities
• i 1 54.: 111 11 u • esse
•gt
III
1
. 1 I. • 4 11 1._• • 1 J 1 _4
Clarifiers
I.Y
:1.
1 _M• • 1
' I 1n : 1 • • •11• • ' •: 11 .
1 r •• .• 1 1 1 1 • 1 4 •.
q 1 1 I ' 11 \ • 1 1• I • 1_
1
• 1.-. equipment• I • 11 II 1 1 11 1 ..M +1:
• 1 1'A • •,
• 1 1 1• 1 1 I • 1 1•.• 1 1 • i • 1 + I 1 •
•
• 1 • • • .. : 1 • • 1 ' .. 1 ..1 1 • (monetary . I 1 non -monetary)
Exhibt "C"
Scope o Work
Page I of 3
,!.U,,1 . O • ' . • •. u 1 1 1 • . I • . 1. t4I u . • ..nv 1 1 UI•.A I r
/ lI 11,7
' 1 . I1 • 1 • 1 -.
I.1 I ✓. w w 1. . V _ I
• . . . II I • I 'ItL.!1'r'
' I I • .. .
• I .n\ 1 1 _ _. +1.+1 II
1 . •
• 4i','t
. I. +1 11 , ••I. •1 • -. _ • • 1 II II • •. •• ✓.•I II II IC• 11
• I I • _• • 1 I I I •'ill••. 1 . I i i I
• • _.•II II+. -• +I I ,•I I. III IIIIY WIIt Ii,:
J.• I I
.. • I I . I •IA: ••I•I I. IIJ , .. 1 II¼iit!c.!lI
I w I ' 1• •1 Y.
: . • .. I • 1 1 ! . • n w
I• . I • 1 iii
.. .. ., •
. • • I . I r . • • n • 1..
I •rI •. • I_ • • .d•1-• U I -
-fljr liii
p Hr • I.w I 111+1 -« •I II I,1 II •
. 1 '.:
1 .• . - 1 . 11 . 1 I:. II
Ii
1 . r r.• -.. 1.11 J. .r -. w 1 I -� IL• . ✓. L. 1 . I II • jr-hi
\ ip I r ✓. n • . ,, • ..• n . .: I I 1 •. • I • • • ii I 1 • I. • . . . • :n • 1 .. ij • •.-: r: -. • I 1. -.- .. ..I •
1:
•. • I : ..• . I � I : :II 1 �ty,tLA'. II -. • u II Il • 1 1 1.1 1
1 i 1 1 1 1 1. --- I
Iir.. . u I I I - 1 1 1 i s .. 1• u w. • I I '
. . I •.1
. u .. :.,. • m . I v.. a ..
I Y: I.I I .. II.YI •: I • 1
• • 1t':'j!_
.I II 11�+1 1 F .1 + 1 -- III I.w1: 1 I I I , II . 1
1 — 1 •:Y.
*%V
I ✓. I I : I• I I I I I:: M. 1. I I : 1 I -.I I 111 I• •' • 1. w: •/me
I I • • ,•
/ II �.I In1. �-.. ••1 I1
�. v . • 1 �: u • .. I I I • rt . -. I I I 1 ✓ . +. • I 1 I . • • .. • • . A w
I.. -}I nw • u.0 lul I I ..I C II I•II.1 ii.1
v. I I 1 1:. 1. «r 1 I .• 1 I
•. • l 1..
•
• .-\ .I 11 I .t.)ijt1I1 • 11I I I I 1 I I. I Y. • I ., 11 •1 •I 1 • ••.• 1II II, .1• • •I1 • :Vj • • I I I I • .•rt I .II .n
1• I • I 1 •• 1. I •
• 1 1 1 • •
1 1• I -n • • 1 110! ✓. I .n ,flit.) . 1 I[.)t&)' 1• 1/ + ''I • I ,v iaJ
fltIN 1
1 I I 1 1 MI: .. I1 A
•. 1. I v w. l••. 11' I.1 • MI. I . I•n• . 1 .••: r1•
. .I.
..n\ .I • I I - • 1 1. 111 I I I 1 11 1 •1 I w
• • n I . • • • I • 1 I 1. 411
• • • •1 •11 .•11• vl '' • 1
•. .!,j. • 1 I : I • . • .1 1
• • . • • • • �: 1 . • 1 • I I . I . • I Y. N • Hn .nom 111 . 11 • 111 11 •
I III 1 1 •- • I• 11 1 1 L w I
M 1111 ' • w I
• .: I v. 1 I. I: 1 Vr •• I
• •. 1 v -n : 1 I . 1 • 1 . r: 1 • 1 • . • . I • wK 'D) I .:I -
lt
.I .• • 1 1 . • 1 II • 1 11 • I II 1
•• •I• •.•.• • I. 1: ••KI •_tP.. • r: I• . . •.n. • 1 I:.•w
•I 11 •. .. 1. .I ...u...I•I LI ..•. .1 I •I••I•. u1•.:•.I jI .n 1 I .• O•• I 1 .n• I
(ii
I 1 . i 1 . .• I i.. • .. •I N 1.•
••: v I I •• 1.• • I I I 11 I .P 1.
• I.I • • �. I+u P1
• + lu up I • • II I 11 1 .I 1
• • I .. L.+1 I . 1 'w :.ot.It I 'w
Y.!J. . 1•: I• `Y: •
'• .VI IIK . . ••.I ••v 1 II 1.1 • V 1 1.1 . Y. 1-
• • •+I II -I 'I I1j4I Y•I'
ri... y I •1 •• I 11-+1 ..
• ••• I: 1: 1'11. 1: .• 1 1. . IT.. +I lIIjj
1'_ • 114 IIj ph ji Ii • • 1 I'I I- 1' •. • ., • • .1 • -. I
• -. 111 11 • . • I • • .1 • 1 • 1 I 1 1 • 11 1 \Y I I
•• 1 .
NOV-28-01 WED 05:22 PM
•
•
P.02
ENVIRONMENTAL
III i,'COTI
OPERATIONS NS
November 27, 2001
ECO, INC.
1nle8rating ECOnomy and ECOlogy"
Jim Ulmer, P.E.
McGoodwin, Williams, & Yates, Inc.
909 Rolling Hills Drive
Fayetteville, AR 72703
1313 Highway 229-5A
Benton. Arkansas 72015
Phone (501) 315-9009
FAX (501) 315.9035
e-mail: eco@aristotle.net
Re: ECO, Inc. projected costs for Section 404 permit for City of Fayetteville
Wastewater Improvements: MWY project # FY 296
Dear Jim,
As requested, I am providing information regarding projected costs for completion
of the Section 404 permit application for the City of Fayetteville Wastewater
Improvement Project. The City's decision -makers that are reviewing the projected
costs should be aware that the Section 404 permit application for a project of this
magnitude is a complex process that goes way beyond simply filling out
applications forms. It will be important to develop the application in a
comprehensive manner that provides the Corps with all of the required
information. To date, we have printed a very rough draft of the 404 appl+.ration.
The introduction, narrative descriptions of the 76 stream crossings (including
photos of streams) narrative descriptions of the 21 linework wetlands and 50
wetland data points (including photos of wetlands) comprise approximately 140
pages.
As required by the Corps, a Wetland Mitigation Plan, which details the
compensatory mitigation to offset the wetlands that will be permanently altered at
the Westside Wastewater Treatment Plant site, is to be submitted with the
application. Currently, our rough draft Mitigation Plan totals approximately 170
pages (including 56 wetland data points and wetland photos) and will involve
further development. By the time we complete the Section 404 permit, the
document will be in the neighborhood of 350 to 400 pages, excluding appendices
and attachments.
Although
the Candidate Conservation
Agreement (CCA) is
coupled to the. 404
permit, it
will be outside the scope of
the actual 404 permit
application.
Exhibit "D"
NOV-28-01 WED 05:23 PM P.03
• •
Consequently, I have not included the actual development of the CCA in the
projected costs for the 404 application.
Below are descriptions of the tasks that remain to complete the 404 application:
1. Completion of COE Wetland Data Forms for Wetland Data Points
We have completed approximately 98% of the work for this task, contingent upon
the lack of wetlands on the site selected for the mitigation wetland. This has been
the most labor-intensive portion of the 404 application. It involved field
identifications of potential wetland areas, soil characterizations, hydrological
evaluations, identification of plant specimens to the species level, and completion
of the Corps' wetland data forms. On, the average, it takes about 8 man-Lurs per
data point, depending on the location and number of plant species. With a total of
106 data points, a lot of labor was required.
As required by the Corps, additional fieldwork by ECO, Inc. will be necessary to
mark the delineated wetlands in the field. I will attempt to get the Corps to agree
to allow us to complete this after submittal of the permit application.
2. Compensatory Wetland Mitigation Plan
The site selection process for the mitigation site will be a joint effort by ECO, Inc.
and MWY. Many variables must be evaluated in order to choose the location of
the 17 -acre constructed wetland. Building a functional wetland is much more
involved than simply constructing a few berms to hold water. The design criteria
will be developed as a part of the site selection process. ECO, Inc. will provide
this information to MWY for the design work.
A water budget/hydroperiod analysis must be modeled to determine the source and
volume of input during the growing season to provide for hydrologic support of the
proposed structure and functions in order to determine the amount of water needed
to support a wetland plant community. Calculations with major input and output
components of a hydrologic budget will form the basis for the wetland design. The
calculations will need to represent a variety of years of rainfall data, which include
median conditions and typical variations from those conditions. We will have to
conduct an evaluation of potential water sources, which will provide the flexibility
to regulate inputs to achieve a minimum level, and the output to limit the
maximum level. We must answer such questions as: Is it possible to select a site
with the input source to be provided solely from runoff? Is it feasible to construct
a well as the primary (or supplemental) input source? Can an input source for the
wetland be developed that will also provide irrigation water for the propr...c,d tree
farm?
2 Exhibit "D"
NOV-20-01 WED 05:23 PM
All of the issues described above, along with others, must be discussed in the
Mitigation Plan. For example, what depths of inundation are to be achieved, and
what plant species can survive in these conditions? What will construction of the
wetland cost, including the planting of wetland vegetation? We have found a
source of wetland vegetation that sells clumps of sedges for $2.50 a bunch. Will
this be cost-effective to the City, or will the use of wetland soils as a source of
plant propagules better achieve the desired results? Furthermore, if the depth of
inundation is not relatively uniform, there will be hydrologic zonation, whereby
plant species adapted for specific depth ranges must be planted within the zones in
which they can survive.
We may evaluate the possibility of using treated effluent as an input source. To
avoid having an additional permitted outfall, any excess water that is removed
from the wetland could be pumped back to the wastewater treatment system to co -
mingle with the effluent just prior to disinfection. The relatively small volume of
excess wetland water would make up a very small portion of the total effluent
volume. Pumping, as a means to rid the system of any excess water, however,
would require a greater expenditure of resources and energy than the conventional
weir discharge. The cost-effectiveness of this will need to be evaluated.
Another issue that we may face is the possibility of having to conduct more
wetland delineations. If the site we select has existing wetlands that will be altered
during the construction of the mitigated wetland, additional delineations will need
to be done.
3) Meetings/Additional Field Work
Before the Mitigation Plan can be fully developed, ECO, Inc. and MWY will need
to have meetings and site visits to evaluated the suitability of the selected site. I
suggest that we also have a meeting with the Corps at the time we submit the
application. Presenting the nature of the proposed project to the Corps should
provide them with a better understanding of the project timelines and goals. We
should also receive feedback from the Corps, regarding permit requirements, and
time frame for the permit issue date. This will be an important consideration that
will be associated with the detailed design work completed by the engineering
firms. It will be more cost-effective for the City if the engineers have an
understanding of the permit restrictions prior to completion of the design work.
For instance, I anticipate seasonal restrictions to be in the permit, whereby
construction activities across streams will be limited to a six month period during
the calendar year. This will have a great bearing on project phasing for
3 Exhibit °D"
NOv-20-01 WED 05:24 PM
P.05
construction activities. Additionally, having an issued 404 permit in hand will be
vital in the development of the construction contract language (environmental
requirements) further down the road.
As previously mentioned, the final development of the CCA will not be included
within the scope of work for the 404 permit application. However, because the
CCA will be closely associated with maintaining the 404 permit after it is issued, it
will be essential to include the USFWS in some of the planning meetings. As I
have mentioned before, Susan Rogers (USFWS Biologist) has requested a meeting
with the City before the end of this year. We need a response from the City
regarding this issue, because the USFWS will be among the regulatory agencies
that will provide comments to the Corps after review of the draft 404 permit.
Consequently, it would be prudent to have at least one meeting with USFWS
before submittal of the 404 application. The final CCA can be developed at a later
date. Susan Rogers has agreed to approach the CCA as a working, evolving
document. Her primary goal at this point is to see some demonstration of
reasonable assurances that the City will eventually execute the CCA.
It will also be advisable to schedule meetings with the City administrators in order
to provide project updates, general design and operation/maintenance strategy, and
potential site location(s) for the mitigation wetland. They will need to be aware
that the selected site will be required to be deed -restricted in perpetuity, only one
of several decisions that will also have to go before the City Council.
4) Division of Labor
As the 404 permit application process evolves, we will better define which tasks
will be completed by MWY, and those to be performed by ECO, Inc. We will
provide you with a general narrative of the mitigation wetland design cri►Pria, and
the models to analyze the hydrologic budget. ECO, Inc. will also accompany
MWY personnel during site visits in the site selection process. Additional input
will be provided by ECO, Inc. regarding the most feasible approach to establishing
wetland vegetation.
At this point, we will need the following information to be provided by MWY:
Drpwins
• Aerial photograph/site location map indicating location of wetland mitigation
site
• Cross-sectional drawings of berms/wetland design drawings
4 Exhibit "D"
"OV-28-01 WED 05:25 PM P.06
• •
• The complete "marked" set of drawings for the RJN work, showing wetlands
and stream crossings, based on our field work (sent to Lane). Garver has
completed marking their drawings.
• Drawing or aerial of delineated wetlands on Westside WWTP site
• Cross sectional drawings for the entire Westside access road, with the stream
crossings.
• A "Typical Stream Crossing" diagram for Fayetteville similar to one completed
for previous pipeline projects.
• The cross sectional drawings of the effluent line, specifically for the single stream
crossing (Station 16+25), and the Goose Creek outfall structure.
Additional Informa tion/Documentation
• Completed calculations/models for constructed hydrologic budget for
constructed wetland
• An explanation of what will be done with the existing Mud Creek outfall
structure
• Floodplain maps for areas within floodplalns where construction activities will
occur
• List of property owners along specific project scope areas within jurisdictional
waters of the U.S. Refer to marked RJN and Garver drawings for station
numbers of stream crossings and wetlands.
• Archaeological Study — This does not have to be completed prior to submittal of
the 404 application to the Corps, however, the Corps will require a letter from
the SHPO which states that the project will have no anticipated adverse impacts
to cultural or historical resources before the final 404 permit can be Issued.
5) Projected Costs
Based upon the information available to us at this time, I am providing projected
cost estimates (in the attached tables) for completion and submittal of the ection
404 permit application to the Corps. This does not include tasks which will be
necessary after the submittal of the application, such as annual wetland function
and value monitoring (a standard requirement by the Corp), wetland construction
oversight, or review/negotiation of the draft 404 permit. We do have a good
general understanding of the necessary information to be provided in the permit
application. However, it should be understood that the final regulatory
requirements will be subject to the opinion and subjectivity of regulatory agency
personnel.
I understand the concerns expressed by some, regarding the costs of the 404
permit. However, our experience has proven many times that compliance is
always the most cost-effective approach to our environmental projects. The
5 Exhibit "D"
NOV-20-01 WED 05:26 PM
P.07
importance of the 404 permit should not be under -estimated. It will have an
impact on virtually every phase of this project. The first shovel -full of d;r? will not
be moved until we have a permit that will have reasonable requirements, as
provided by current environmental regulations.
As you can see from reviewing the information provided in this correspondence,
additional work will be necessary (primarily constructed wetland issues) before the
404 application is at a stage that is suitable for submittal to the Corps. It is vital
that we maintain our inertia, in order to continue with the goal of obtaining the 404
permit before final detailed designs are developed.
We appreciate the opportunity to work with you on this project. Should you need
additional information, please contact me at (501) 315-9009.
Sincerely,
Bruce Shackleford, M.S., REM, REPA
President
6 Exhibit "D'
•QY 4IQi�Il •
H A
O
3 33-• PC _�3 o' r
Q
= m e° 0 3 =° 1 m °: o api 3. E P,
•
•
,'.=c p p., .:•ue 3 A o 'J _ CD 3. .7
V w ^• N 1_I i ^• A f 0^• �•! ^• rr° 1 ♦D• c' •••
w d `' p 'o
_ y
fo p m �,'U1 '�_ 7 1 'fl O. A ; �• N a
.t ro O.
^ C n A A -.O
a
n. C. a flre.. C. _. A oo -' n ii to
° a
n Q+
d a !p ..r; d O
8 G d '�9 f y p H m y y N y •_
m p
^ O .•3y C: A s c ap
d
a z
m ^- a a o d
,- i
tp 7 0 0Vf 6n H Vi 6A fn S r' f ° () hil
- A O. ... to oo .... ... 2 a fD -A,. ?:
°y °•'� ^ `� N to O to p C' 7' a -
7 =, O. 'OO ao W ... ao J d Vi N o
d ^• 'fig c 3 f ap A 00 - ,, w
o o dpi C r:
f7 r•
C 7 a 6'9 d9 Vf iA Vl 6H ' 1 O 'r
p fD N ^ -. A
- . 7 00 N �+ fD; O d •..
• w 'O to O J w ; ? .• ,... (�
< r•
VI
a a•� 00 'V 0•
d (A fA fA fA (/f H {ya w �'•
c tnJ - tnsp�c o a
^ OI - - 00 A O p' ci, C C
ut O% J O -` J . '7 CD ••
Qa CD y '
� � O
o r•
N ^
N
O r
C fD
n Q. r • B
�• 7 3
.»
N S
.O
O
ID:301-776-7409 0CT 17'01 15:05 No.014 P.01
• •
hI Crwnrnlnlry OuryKVcn - t•wromxnrnlfiWernhn - Comnunhnfn,n $Mnfp,r,e•,
ASSOCIATES 632 Main Street - laurel, MD 20207- 301.776.7407 - tax 301.776.7409
I NC.
October 15, 2001
James Ulmer, P.E.
Vice President
McGoodwin, Williams & Yates
909 Rolling Hills Drive
Fayetteville, AR. 72703
RE: Public Information and Communications Program
City of Fayetteville, AR. — Wastewater System
Improvement Project
Dear Jim:
The following information provides the sequence and circumstances affecting the
additional program efforts required for the City's wastewater system improvement
project. This work was primarily performed to comply with the public participation
program efforts of the City's amendment to its 201 facilities planning process. The
additional work that occurred, primarily in 2001, was not identified in the original scope of
work for Hanifin Associates, Inc (March 2000 — Attachment 1), inasmuch as the overall
technical efforts and final regulatory requirements were not clearly defined for the City's
proposed amendment to its Wastewater Management Facility Plan,
The City's initial objective in February 2000 was to provide a public information program
that addressed the project's overall objective. However, changes in the direction in which
this program would continue into a second phase was acknowledged by the project
leaders in January 2001. At that time, it was determined that an increased level of public
education was needed as a result of the analysis derived from the public information and
opinion survey (October/November 2000). This analysis confirmed that low levels of
public knowledge existed about the project, the methods in which it would be financed,
and the overall affects to water quality if the project did not materialize.
Subsequently, the project leaders agreed in January 2001 that an aggressive
public education effort would be initiated over the next several months (Attachment 2).
This decision was also reinforced by the City's newly -elected public officials. The City's
new leaders recognized the importance of customer education in order to secure
approval by State DEQ officials for the facility plan amendment.
In summary, the additional work tasks and out of scope costs incorporated the following
level of effort.
1. Redesigning the information program to comply with the Facility Plan
Amendment Update requirements, based on the survey analysis and public
official's requests.
2. Additional (bi-monthly) trips to provide essential program support and produce
the work required for the Facility Plan Amendment update.
3. Development and production of a comprehensive public information project
summary mailed to over 2500 residents and distributed through numerous
Exhibit "E"
Y Y
Y Y
S
Gtl
Cat
9
,
M
A
I
i
£0'd V1000N 90:Si 10.21 170 60DL-9LL-i0£:QI
ID:301-776-7409 OCT 17'01 15 07 No.014 P.04
Summary of Out of Scope Tasks Costs
Public Information Program - City of Fayetteville, AR
Wastewater System Improvement Project
October 15, 2001
p D ? 'rDiidilptlon n
OUT OF SCOPE WORK TASKS
Special infdrmadon meetings and largo scale public
200O Jun
Public and community meetings
workshop to prosont program approach
Conducting soelo-oeonvmie analysis on property
2000 Sep
Databa6e Development
owner Issues & values: estaullehing database
2O00 Oct
Information Survey
Printing, pwtege and mailing tees
Travel
Survey management
Redesigning program to comply wtth
overall program development: Additional trips (2) for
Feafly Plan Amendment; Travel &
project meetings associated with program
2000 Mar
Survey Production
development and survey presentation
Newslotlw development for cdzens which
Iransitionod Into an overall •layman' summery of
the facility plan; Special graphics (or citlrens
2001 - Apr
Public Education & graphics
summary report and web page development
Additional travel to support program reschoduling
2001 - May
Travel & Moetings
and facility plan amendment needs
Web site development to supPat Cily needs,
2001 - Jun
Public Education Materiels & travel
education project summary 6 spodal graphics
Public education (6nanco) fact sheet, workshop,
2001 - July
Meetings, Materials & Travol
meetings & travel (2) trips
(3) trips. workshop & material production, meetings.
2001 -Aug
Meetings. Materials & Travel
and printing A displays
(1)14. public hearing materials & production,
2001 - Sep
Mcotings, Materials & Travel
displays & printing
Invoice Information:
Date
Invoice No.
Amt
4/3/2000
961346
2461,
5/3/2000
961350
5604.3
6/1/2000
961358
3409.59
7/6/2000
961365
811/2000
961370
9/7/2000
981372
10/4/2000
961376
12/4/2000
961383
M4575.4
2/16/2001
861393
1/8/2001
961386
3/14/2001 -
BBt397
•
4/4/2001
961405
-
5/2/2001
961408
7456.09
6/4/2001
961412
4195.95
7/5/2001
961415
5789.93
8/5/2001
881118
15063.2
-_
9/4/2001 —
961420 —
26286.8
Total Invoices:
-
152287.9
Exhibit "E"
THE CITY OF EAYETTEVIEEL ARKANSAS
DEPARTMENTAL CORRESPONDENCE
February 29, 2000
To: Fayetteville City Council
From: Don Bunn, Assistant Public Works Director 42
Thru: Charles Venable, Public Works Director
Mayor Fred Hanna
Subject: Contracts for Preliminary Engineering Services
Fayetteville Wastewater Improvements Project
The following three (3) items totaling $1,706,554.00 are proposed contracts for engineering
services related to the Fayetteville Wastewater Improvements Project. The proposed
contracts are with (1) Black & Veatch for services relating to improvements to the Noland
Wastewater Treatment Plant, $359,720.00, (2) Garver Engineers for services related to
sewer collection system improvements within the White River Watershed, $391,532.00, and
(3) McGuodwin, Williams, and Yates for services relating to the new west side wastewater
treatment facility, $955,302.00. The Council approved a contract with RJN for services in
connection with the project in the amount of $638,267.00. All of the contracts authorize the
development of a preliminary engineering report as a first phase of the engineering work
and provide for future phases as the work progresses.
Attached to this memorandum is an outline of the procedure that the Staff followed in
selecting the above named consultants. The process began last May immediately following
the approval by the Council for the purchase of land west of Fayetteville for the purpose of
siting a new treatment facility.
The Design Reports are due to be completed by November of this year. The Preliminary
Design Reports will serve several purposes. The Reports will serve to update and revise the
Facility Plan where needed to account for changes In conditions and costs since the Facility
Plan was prepared (1995-1997). The basic conclusions of the Facility Plan will not change
since those conclusions were based on comparative costs, however, the location and sizing
of sewers and interceptors may change as well as the type of treatment considered, and the
economics of various sludge alternatives.
Also, enough detail will be generated by the studies to determine the size and location of
new facilities and to establish reasonably accurate cost estimates of the work. The work
program and cost estimates will be used to plan the financing of the improvements and will
serve as a basis for the scope of work and cost of preparing the detailed plans and
specifications.
Exhibit UFe
t. • 0 %
We are considering utilizing the State's Revolving Loan Fund as the major source of funds
for this project. The loan fund is managed by the Arkansas Department of Environmental
Quality and is backed by grants from the Environmental Protection Agency. They have
indicated that a total of $60,000,000 would be available to Fayetteville over a two or three
year construction period. The current lending rate is 3.75 percent.
We have submitted materials to the State to determine the areas where we are already in
compliance with their conditions and regulations, and how much additional work may be
required to come into compliance. Areas that will be examined include our engineering
selection process, form of engineering contracts, public involvement, sewer system
evaluations as it relates to infiltration and inflow control, sewer rates, and accounting
procedures.
If we make the decision to participate In the program there will have to be amendments to
these contracts to account for whatever extra effort that may be required to comply with
ADEQ regulations. However, it is expected that the savings in interest costs over the life of
the ADEQ loan will more than offset whatever additional costs that we incur because of our
participation in the program.
Exhibit "F'
FAYETTEV&LE
THE CITY OF FAYETTEVILLE. ARKANSAS
DEPARTMENTAL CORRESPONDENCE
To: Greg Boettcher, Public Works Director
From: Heather Woodruff, City Clerk
Date: February 26, 2002
•
MICROFILMED
Please find attached a copy of Resolution No. 22-02 approving contract Amendment No. l with
McGoodwin, Williams and Yates, Inc. I am returning one original contract to you and mailing
one original contract to McGoodwin, Williams, and Yates, Inc. The third original will be
microfilmed and filed with the City Clerk.
Your Budget Adjustment Form has been forwarded to the Budget & Research Division.
cc: Nancy Smith, Internal Audit
Steve Davis, Budget & Research
010 03 City of Fayetteville 2/27/2002
Update Index Maintenance • 13:47:12
Document Item Action
Reference Date Ref. Taken Brief Description
RES 2052002 22-02 MCGOODWIN, WILLIAMS, AND YATES INC
- - - - - - - - - - - - - - - - - - - - - - - - -
Enter Keywords.. .....: RES. 22-02
CONThACT
AMEND MENT
MCOOOD, WILLIAMS AND YATES
File Reference # ......: MICROFILM
Security Class........: Retention Type:
Expiration Date.......: **** Active
Date for Cont/Referred:
Name Referred to......:
Cmdl-Return Cmd8-Retention Cmd4-Delete Cmd3-End Press 'ENTER' to Continue
Cmd5-Abstract Yes No (c) 1986-1992 Munimetrix Systems Corp.
City of Fayetteville, Arkansas
113 W. Mountain
Fayetteville, AR 72701
NEWS RELEASE
Contact: Greg Boettcher (470) 575-8330
HISTORICAUARCHAEOLOGICAL FIELD STUDY STARTED
The Sponsored Research Program of the Arkansas Archeological Survey, a research unit
of the University of Arkansas System, has commenced the cultural resources survey for
Fayetteville's $120 million Wastewater System Improvement Project. Under the
direction of Dr. Robert C. Mainfort, Jr., archaeologists will inspect all project
construction areas, including proposed pipeline routes, new pump station sites, new
treatment plant sites and all other areas that could be disturbed as a result of the planned
construction. These investigations serve to locate and define resources of a historical,
archaeological or cultural nature that could be affected by the planned work. Field
identification of such resources allows appropriate mitigation measures to be taken to
protect or avoid valuable cultural resources prior to construction activities. Resources of
a significant nature are discovered as part of the proactive process, enabling: (1)
amendment of planned construction to avoid the resource; (2) archiving of the resource,
(3) protection of the resource or (4) other appropriate measures.
The findings of the cultural resource survey will be consolidated into a technical report
that will be submitted to the State Historic Preservation Officer in Little Rock, Arkansas,
for review and approval. Any identified threats to significant cultural resources will need
to be resolved prior to the issuance of an approval by the State Historic Preservation
Officer. This evaluation and approval process must be completed prior to the start of any
ground disruption activities (construction), but for publicly funded infrastructure projects,
approval is secured during the preliminary design phase.
The process of identifying cultural resources is most effective during the preliminary
planning of a project. At this stage of project development, changes are easily
incorporated into design to protect such resources and very little design effort is wasted
on layouts that are in conflict with cultural resources. These responsible planning efforts
provide even greater benefits during the project's construction phase by minimizing risks
of cultural resource conflicts. Under the current federal and state regulations, the
discovery of significant cultural resources during construction requires all work to be
stopped until the significance of said resources is assessed by professional archaeologists,
and approval to proceed granted by the State Historic Preservation Officer. The cultural
resources survey now being performed avoids these types of costly delays and project
complications.
The City of Fayetteville has authorized the Arkansas Archeological Survey to proceed
with the cultural resource survey work. The archaeologists conducting the survey will
make every effort to contact property owners for permission to evaluate lands that could
be affected by the proposed construction, but many of the proposed wastewater lines will
be located along existing City easements. There will be no damage to the properties and
when requested, the findings will be reported to all interested participating property
owners.
The cultural resource survey is scheduled to commence immediately, with the field
assessment to be completed in approximately one month (weather permitting). A report
on the findings is expected to be completed within 6— 8 weeks after completion of the
field investigation. Hence, the report should be submitted to the State Historic
Preservation Officer in August of 2002. The review and approval by the Historic
Preservation Officer will depend upon backlogs and report findings, with
comments/approvals expected in September of 2002. The cost of the cultural resource
survey activities for the project is approximately $47,500.00
Mayor Dan Coody encourages all property owners to grant permission to the cultural
resource surveyors, as it is important for these historical and archaeological resources to
be located, cataloged and preserved for the future. The extent of the survey work includes
approximately 30 miles of pipeline routes, 9 lift station improvements , the southern
extension of the Broyles Road from the plant site to Farmington and the 300 acre west
side plant site.
015 04 City of Fayetteville
n aintenance/inquiry •
Document IteAction
Reference Date Ref. Taken Brief Description
RES 2/05/2002 22-02 MCGOODWIN, WILLIAMS,
Keywords ...............
RES. 22-02 - - -
CONTRACT
AMENDMENT
NO. 1
MCGOOD, WILLIAMS AND YATES
$580,296.00
mcgoodwin
File Reference #......: ORD CC OFC/02
Security Class........: Retention Type:
Expiration Date.......: **** Active ****
Date for Cont/Referred:
Name Referred to......:
Press Cmd 6 to update
Cmdl-Return Cmd2-Check Out Cmd8-Retention Cmd3-End Press 'ENTER' to Continue
Cmd5-Abstract Yes No (c) 1986-1992 Munimetrix Systems Corp.
8/12/2002
11:47:37
AND YATES INC