HomeMy WebLinkAbout22-02 RESOLUTION•
A.
RESOLUTION NO, 22-02
A RESOLUTION TO APPROVE CONTRACT AMENDMENT
NO.1 WITH MCGOODWIN, WILLIAMS, AND YATES, INC.
IN THE AMOUNT OF $580,296.00
WHEREAS, the City of Fayetteville, Arkansas after a public hearing
determined that the 5% fixed fee should be deducted from the previously
requested amount of the proposed contract amendment for that portion
applicable to the cost overruns of Hanifin Associates, and ECO, Inc. prior to
approval of the City Council; and
WHEREAS, representatives of McGoodwin, Williams, and Yates, Inc.
agreed to such reduction which resulted in a total reduction of $15,495.00.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF
THE CITY OF FAYETTEVILLE, ARKANSAS:
Section 1. That the City Council of the City of Fayetteville, Arkansas
hereby approves Contract Amendment No. 1 with McGoodwin, Williams, and
Yates, Inc. in the amount of $580,296.00 (attached as Exhibit A); and authorizes
the Mayor to execute said contract amendment.
PASSED and APPROVED this the 5th day of February, 2002.
11 14
Woodruff, City C - k
APPROVED:
•
NAME OF FILE:
CROSS REFERENCE:
Resolution No. 22-02
•
02/05/02
Resolution No. 22-02
Amendment No. 1 to City of Fayetteville Contract Agreement for
Engineering Services Westside Wastewater Treatment Facility with
McGoodwin, Williams, and Yates, Inc.
01/15/02
Copy of the Budget Adjustment Form
02/11/02
Letter to Greg Boettcher, PW Director, from James C. Ulmer, Vice
President, McGoodwin, Williams and Yates, Inc.
02/11/02
Memo to Mayor Coody from Greg Boettcher, PW Director, CC: Kit
Williams, Steve Davis, Jim Beavers, Heather Woodruff, regarding
Engineering Contract Amendment No. 1
02/05/02
Staff Review Form
02/26/02
Memo to Greg Boettcher, Public Works Director, from Heather
Woodruff, City Clerk
News Release from Greg Boettcher regarding Historical/Archaeo-
logical Field Study
NOTES:
•
ORIGffiAL V az
AMENDMENT NO. 1 TO
CITY OF FAYETTEVILLE
AGREEMENT FOR ENGINEERING SERVICES
WESTSIDE WASTEWATER TREATMENT FACILITY
WHEREAS, on March 21, 2000, the City of Fayetteville (the Owner) and McGoodwin,
Williams and Yates, Inc. (the Engineer) entercd into an Agreement for Engineering Services in
connection with the construction of the new Westside Wastewater Treatment Plant to serve the
Illinois River Basin. The scope of these services included preliminary studies and preliminary
design, resulting in a Preliminary Engineering Report setting forth the findings; and
WHEREAS, the Engineer has completed those services required under the original scope
including preparation and submittal of the Preliminary Design Report; and
WHEREAS, the overall prQlect (hereinafter referred to as "the Overall Project") being
developed by the Owner includes an upgrade of the existing Paul Noland Wastewater Treatment
Plant on the cast side of the city and the sewer system collection and transmission facilities work
for both the east and west sides. This work is being accomplished by three other engineering
consultants; and
WHEREAS, the Owner requested that the Engineer's and its subconsultants' original
scopc be expanded to include services relating to the Overall Project; and
WHEREAS, the Engineer agrees to provide the requested services;
NOW THEREFORE, in consideration of the mutual covenants and agreements herein
contained, the Owner and the Engineer, the parties hereto, stipulate and agree that the Agreement
for Engineering Services dated March 21, 2000, is hereby amended in the following particulars:
Section IV. Services to be Furnished by the Engineer During Design Phase
1. Section A - Study, Preliminary Desibm and Report, is amended by adding the
following paragraphs under Section IV -A.
Environmental Permitting. The environmental work in the original scope
being provided by subconsultant ECO, Inc. shall be expanded from only the
Westside Treatment Plant to include all four elements of the Overall
Project, thus allowing continuity of activities and eliminating duplicated
efforts by the other engineering consultants. This work includes:
• Corps of Engineers 404 permitting;
• Initiating the work on the NPDES storm water permit;
• Participating in the public information program including attendance at
public meetings; providing environmental information justification for
the Overall Project and assisting in the dissemination of accurate
environmental information about the Overall Project;
Amend 1 to Fy-296 - 1 of 5
A
R
• 411
• Assisting in the evaluation of and development of Candidate
Conservation Agreement (CCA) to address prospective and endangered
species concerns;
• Providing specialized environmental guidance regarding the
environmental issues surrounding the planned Westside sewer line
construction at the former Research and Technology Park to include
preliminary evaluation of site conditions, site issues, and possible
mitigation measures.
The Engineer shall coordinate the work between ECO and the other
engineering consultants for the Overall Project, and provide specific data
regarding the Westside Treatment Plant.
Public Education and Involvement. The public education and information
work being conducted by Hanifin Associates for the Westside Treatment
Plant shall be expanded to include all four elements of the Overall Project,
thus allowing continuity of activities and eliminating duplicated efforts by
the other engineering consultants. This additional work includes:
• Increasing the public informational meetings from three to 16;
• Formalizing the public involvement program to meet specific
requirements for Facility Planning/State Revolving Loan Fund under
the regulations of the Arkansas Soil & Water Conservation
Commission;
• Providing written information/graphics/handouts to inform the public
on the proposed work;
• Expanding the scope of the public information program to include the
use of web -site and media mediums;
• Development of communication resources, tools, and criteria to
improve the effectiveness and clarity of the information presented to the
public;
• Assist in the conduct of a Public Hearing regarding the final selected
alternative in the Facility Plan and Environmental Information
Document.
The Engineer shall coordinate the work between Hanifin Associates and the
other engineering consultants, and provide specific data regarding the
Westside Treatment Plant.
3. Wastewater System Improvement Project Facility Plan. The Engineer will
prepare an amendment to the Facility Plan for the Overall Project
previously prepared by another consultant and presented in February of
1997. The plan will utilize the preliminary engineering work completed by
each of the four engineering consultants. The plan will be completed in
accordance with requirements as set out by the State of Arkansas for
projects utilizing the Revolving Loan Fund. This Facility Plan will be
submitted to ASWCC in the final version (following the September 20,
2001 public hearing) in November, 2001. The Engineer will coordinate the
review of the Facility Plan by the state and federal agencies until final
approval.
Amend 1 to Fy-296 - 2 of 5
• •
4. Environmental Information Document. The Engineer will prepare an
Environmental Information Document for the Overall Project to accompany
the Facility Plan which evaluates and presents the environmental issues and
program documents required to reflect work proposed by the four project
consultants. The Engineer will work with ECO, Inc. to produce this
document and coordinate the review of the EID until final approval.
5. Revolving Loan Fund Coordination. The Engineer shall assist the Owner
by providing project coordination, preparation of Revolving Loan Fund
documents, and necessary engineering services as required to complete the
RLF program requirements.
6. Biosolids Management System Coordination. The Engineer shall expand
investigations into the biosolids management planning for the Overall
Project, including investigations of additional alternatives and the
coordination of a recommended strategy.
7. Industrial Loadings. The Engineer shall provide the necessary services to
determine the impact of a prospective industrial plant on the Westside
Treatment Plant.
8. Broyles Road Extension. The Engineer shall develop and implement
preliminary planning for the Broyles Road extension in Farmington. This
extension, if constructed, would provide access to the new Westside
Treatment Plant. The study shall be conducted jointly for the Owner and
the City of Farmington.
9. Additional Services. The Engineer shall conduct other studies and analyses
as required to facilitate the production and approval of the Facility Plan,
environmental permitting, and public involvement as required.
These services to be furnished by the Engineer shall be subject to the agreed cost ceiling
set out in Section XII.5 as amended.
Section X. Subcontracting
Add the following paragraph: "The Engineer shall furnish copies of all sub -agreements if
requested by the Owner."
Section XII. Fees and Payments
I. Section A is amended as follows: The fixed fee set out in this section is increased
to $130,505.
Amend 1 to Fy-296 - 3 of 5
• •
2. Section A is amended by adding the following: Compensation for the Broyles
Road Extension Study shall be a lump sum amount of $12,900. The cost of this study is to be
shared equally with the City of Farmington. Thus, the Owner's portion is $6,450.
3. Scction B, the estimate of cost for ECO, Inc., shall be increased to $343,868,
including expenses.
4. Scction C, the estimate of cost for Hanifin Associates, Inc., shall be increased to
$187,166, including expenses.
5. Section D, second paragraph, first line, is amended to read as follows: ' The
estimated total compensation for the services set out under Section IV.A as amended is
$1,535,598, including the fixed fee of $130,505 and reimbursable expenses, and Fayetteville's
share of the lump sum fee for the Broyles Road Extension Study."
6. Attachment A to this Amendment sets out a summary of the original budget and
requested changes.
7. After the last paragraph under Section D, add the following: "The Engineer shall
furnish copies of invoices, billing information, and other materials as the Owner may request, to
verify the accuracy of invoices and the nature of the work being performed."
Section XVI. Miscellaneous Provisions
Add paragraph H as follows:
H. Arkansas Freedom of Information Act. The Engineer agrees that it will provide to
the Owner, at a cost to be agreed upon, all documents in its possession that are,
under this Agreement, the property of the Owner and which the Owner believes to
be subject to an Arkansas Freedom of Information Act request made to it, or, in
anticipation of such a request, which it believes necessary for it to possess. The
Engineer further agrees that it will request of all subconsultants, retained by the
Engineer to perform services under this Agreement, to provide to the Owner, at a
cost to be agrecd upon, all documents in the possession of such subconsultants that
are, under this Agreement, the property of the Owner and which the Owner
believes to be subject to an Arkansas Freedom of Information Act request made to
the Owner, or, in anticipation of such a request, which it believes necessary for the
Owner to possess. The Engineer will produce all documents or material in the
format that are kept by the Engineer, or at the option of the Engineer, in some other
format. If a specialized format is requested by the Owner, the cost of conversion,
if that additional responsibility is accepted by the Engineer, will be borne by the
Owner at the then prevailing rates for the parties actually performing the
conversion. Production of requested items will be done with reasonable diligence,
but cannot in some circumstances be within the time frame established by the Act.
Amend 1 to Fy-296 - 4 of 5
•
• •
The above and foregoing provisions apply only to work performed from this date
forward and does not apply retroactively.
Nothing in this Agreement shall constitute an acceptance of the Engineer or its
subconsultants to the application of the Arkansas Freedom of Information Act to
the Engineer or its subconsultants or to the Engineer's or subconsultant's books,
records, drawings, or other items not constituting the property of the Owner under
this Agreement, nor a waiver of its rights to object to any requests made to it
pursuant to the Arkansas Freedom of Information Act by any person or entity not a
party to this Agreement.
All other provisions of the original agreement remain in full force and effect.
IN WITNESS WHEREOF, the parties hereto have caused this Amendment to be duly
executed this day of 74
, 2002.
CITY OF FAYETTEVILLE, ARKANSAS McGOODWIN, WILLIAMS AND YATES,
INC.
By:
By
Dan Coody, Mayor
ATTE
arl Yates, Pre
ATTEST:
rk
del CO\•
oodruff, City Cle
s C. Ulmer, Vi 'resident
Amend 1 to Fy-296 - 5 of 5
NOTE: All cost figures include expenses.
o o v •= CO `� m
..-
T<'22o m -( d 0 F-• ?55Q0
,2338 m o(7om =4
m 3
nm CD
CD 3
a m O O S 03co Cr
a 3 m 3 3 0 n C C n f) y
0 > > m Qo
(D Cn a • m
0 •
(n
3 0
S
(A EA
01 �COCO
CP CO 0)
W
N (071 -
EA
01 C0 O▪ CO—sCAO
CO CO V CO -I V
O —
. N C00 CR
b cn tP Co co CO A
O N CP0C)A
m
2a6png lew6u0
E0
R EA CD
X) 1N -S N CA O CCD 0
A.A Co CCO00) ON(0l1 Cr = 3 N v
6M(7)O) Of -•(A0 N ry m
NAcoWd0
OO CoCA C)t0
EA
-4
CO
(0
O
Co
EA
W 0000 a))a)coo 000
NA A A -co
'
000 N co W
000)v v N
EA EA
oA
O NCO r
co 0. O 0A O' 0 0
Co 0 Co 0 0
EA EA EA
(n 01 W-•
CoCR
N co tAT CO 03 COOTCA 0N) Cr
CO 0 CO 00IV A ID -4). -Co CO CO Co
O
0) O CO 00°A ACIN(0
u
W
(D N_ 0.
0 73 3
CD CD N A
C
(7 N n
as 9 co
n (^
f0
CO
C
a
(0
o •0 2
z m a m cn
O. N CCD
n 3a
CO
EA EA (,. EA
W co o A Apo AODW N O -I W
V1 O (J1 W W CO v O N W W 13
C O_ C O
N (P O O N 0 O) - (b W n 0 co 0
CO (P CO O 0 0a) � U1 CO W a fn` (^ .0..
SUMMARY OF REQUESTED BUDGET
V1N3WHOVlld
•
City of Fayetteville, Arkansas
Budget Adjustment Form
•
Budget Year
2002
Department:
Division:
'Program:
Public Works
Sewer Construction
Date Requested
January 15, 2002
45.22 oz
Project or Item Requested:
$579,000 in the Professional Services
account in the Wastewater Treatment Plant
- Expansion capital project.
Project or Item Deleted:
$579,000 from the Use of Fund Balance
account in Water & Sewer Fund.
Justification of this Increase.
The funding is needed for the City to
contract with McGoodwin, Williams, and
Yates Inc. for consultant services as
related to the construction of the
Wastewater Treatment Plant Expansion.
Justification of this Decrease:
The fund balance is from remaining funds
not spent in 2001.
Increase Expense (Decrease Revenue)
Account Name Amount
Professional Services 579,000
Account Name
Use of Fund Balance
Account Number
5400 5700
Decrease Expense (Increase Revenge)
Amount
579,000
Project Number
5314 00 98047 10
Account Number
5400 0940
4999 99
Project Number
Approval Signatures
Requ ed By
B getaX
6146(
t Director
Date
OZ
JfieoZ
Utile
0/7o 2..
Date
ky%
Date
Budget Office Use Only
Type: A B C
Date of Approval
Posted to Genual Ledger
Posted to Project Accounting
Entered in Category Log
RJ.., r.....,- n..ana. x. Ra..s...r. r V n,.... �,...... o__.....,
E
• •
McGoodwin, Williams and Yates, Inc.
Consulting Engineers
909 Rolling Hills Drive
Fayetteville. Arkansas 72703
Telephone 501/443.3404 FAX 501/4434340
February 11, 2002
Re: Contract Amendment No. 1
Westside Wastewater Treatment Plant
Fayetteville, Arkansas
MWY Project No. Fy-296
Mr Greg Boettcher, P E
Public Works Director
City of Fayetteville
113 West Mountain
Fayetteville, Arkansas 72701
Dear Greg:
Enclosed herewith are three copies of executed Amendment No. 1 to the
Agreement for Engineering Services for the Westside Wastewater Treatment Facility.
We trust you will find this document in order and can forward it to the Mayor and
City Clerk for a date and signatures. If you will notify our office when the signatures
are complete, we will send someone to pick up one copy for our files.
We appreciate very much the city's willingness to go forward with this contract
amendment, and look forward to continued service to the city in this very important
wastewater treatment facilities project.
JCU:sc
Enclosure
Cordially yours,
/mes C. Ulmer, P. E.
ce-President
2-12
2 :✓ &o0&EOJnfl
TD 7716 &#J4/, it-
zSc21 j/.t/lo ,Z € ?m
43cDS—
ZE /LJe Att t ratnis
Tom' Pes,G,tc C'cwniliMT-
1
c
• •
FAYETTEVILLE
THE CITY OF FAYETTEVILLE, ARKANSAS
DEPARTMENTAL CORRESPONDENCE
TO: Mayor Coody
COPY: Kit Williams, Steve Davis, Jim Beavers, Heather W
FROM: Greg Boettcher, Public Works Director
DATE: February 11, 2002
RE•
Engineering Contract Amendment No. 1
McGoodwin, Williams and Yates, Inc.
Wastewater system Improvement Project
West Side Wastewater Plant
Attached please find a copy of the professional fee calculations that have
been developed by McGoodwin, Williams and Yates, Inc. (Memorandum
dated February 8, 2002). This communication outlines the methodology for
the elimination of professional fees on the labor costs for ECO and Hannifin
and Associates. The Fayetteville City Council, at its February 5, 2002
meeting, approved this contract amendment provided that the 5% fixed fee
estimated at $15,000.00 to $17,000.00, be deducted from the amount
requested. I have reviewed the information presented, that computes a fixed
fee reduction of $15,495.00, and find said amount to be both in order and in
accordance with City Council approval. The resulting value of Contract
Amendment No. 1 is $580,296.00, bringing the not -to -exceed total contract
value to $1,535,598.00.
A revised contract amendment shall be provided for signature on Monday,
February 11,2002
GB:ks
2- S-02;,i:48AM;MC000OWIN WILLIAMS
;479.443.4340 0 1/ 2
• •
McGoodwin, Williams and Yates, Inc.
Consulting Engineers
909 Rolling Hills Drive
Fayetteville, Arkansas 72703
Telephone 479/443-3404 FAX 479/443-4340
MEMORANDUM
To: Mr. Greg Boettcher, P E , Public Works Director
City of Fayetteville, Arkansas
From: James C. Ulmer, P. E., Vice -President
Date: February 8, 2002
Re: Wastewater System Improvement Project
Contract Amendment No. 1
Fayetteville, Arkansas
MWY Project No. Fy-296
Attached is a table showing the labor cost and expense calculations for ECO, Inc. and
Hanifin Associates through December 9, 2001, as shown on our original cost figures
presented to you as a part of the worksheets accompanying Contract Amendment
No. 1. At the bottom of this table, we have calculated our allowable fee for labor for
both ECO and Hanifin Associates in order to determine the amount of fee reduction as
required by the Council at their meeting of February 5, 2002.
The original fee request for Contract Amendment No. 1 was to increase the fee to
$146,000. However, the fee reduction requested by the City Council on February 5 was
$15,495, which represents five percent of the ECO and Hanifin costs (over and above
the original scope) through December 9, 2001. Therefore, our revised total fee to be
reflected in Contract Amendment No. 1 shall be $130,505, as shown on the attached
table.
We trust you will find this explanation acceptable for the purposes of establishing the
amount of fee in Contract Amendment No. 1.
Attachment
Post -n• Fax Note 7671
-1
O
E
pT
0
a
0
M
M
N
4
elD9
a
• •
2
5
N
$ 9L'OEY'BiZ
s
a
Ul
N
Z /Z • OpEr•EIVeSLt1
M M
P
A co
m O
N
suonhIn,lp pd
co
CO
co
0
mmm(m�flcmiclOOq c
acg
m
o spm
�c3 -4
a ma
m a.
8
w
V
0
m
O
mm b A a O Q
-• A+ N N V Al
N 0m N N mNm
V O N N O N
O bY
O +
•
0
pqA n
+ o t{�m a M u
-saoI A N+ca o O
N N N V OqI tpl1l m • o
,iowwa(a-- 4§
8
a
2m
3 t7
O
3
D
3
J
2y
3
3
3
0
$WYI1 IM NIMOOOOOrl tVIVO? . t!ZO-6 -Z
• •
McGoodwin, Williams and Yates, Inc.
Consulting Engineers
909 Rolling Hills Drive MIC OIFELPID
Fayetteville, Arkansas 72703
Telephone 501/443-3404 FAX 501/443-4340
January 25, 2002
Re: Wastewater System Improvement Project
Proposed Contract Amendment between City and Engineer
Fayetteville, Arkansas
MWY Project No. Fy-296
Mr. Greg Boettcher, P E
Director of Public Works
City of Fayetteville
113 West Mountain
Fayetteville, Arkansas 72701
Dear Greg:
Thanks for your letter of November 13 requesting a contract amendment. We're
pleased to answer your questions and provide whatever detail you require to move our
work forward. I've summarized relevant information below and attached a more
comprehensive memorandum to this letter.
Project History
Our original contract with the City was executed March 21, 2000. It called for
MWY to complete the Preliminary Engineering Design for the proposed Westside
WWTF, including a written Preliminary Design Report. We completed this report in May
2001 and enlisted the services of subconsultants whose special expertise was critical to
complete the work. They are listed in the attached memorandum. MWY successfully
completed contract scope requirements approximately $200,000 below budget.
Along the way, the City made several decisions which resulted in the expansion
of MWY's role in work related to the wastewater system improvement project. They are
summarized as follows:
Revolving Loan Fund
Concurrent with the preliminary design process, the City elected to pursue
Arkansas' Revolving Loan Fund program. This was an excellent decision, because it
would provide a low-cost source of capital for all facets of the total project. In Apnl 2000,
at the City's request, Don Bunn, Assistant Public Works Director and Jim Ulmer, Vice -
President of MWY, met with officials of the Arkansas Department of Environmental
Quality to assess the program requirements to enter the RLF program and learned:
Mr. Greg Boettcher
January 25, 2002
Page 2
• •
1. The 1997 Facility Plan created by CH2M Hill did not meet ADEQ
requirements and the City would be required to produce a new Facility
Plan Amendment. Later, at the City's direction, in May through November
2001, MWY created a new Facility Plan Amendment which required
approximately 2,800 manhours to complete.
A new Environmental Information Document (EID) was required that
would address all known environmental issues and program requirements.
3. A formal public hearing on the selected plan was also required. This
meeting was supplemental to the numerous public meetings conducted
during the preliminary design process. As you are aware, planning,
organizing, facilitating and following-up a formal public hearing that
conforms to state requirements is a time -intensive process. MWY also
assumed responsibility for this activity.
Environmental Permitting
1. Early in this process, consultation with environmental regulatory agencies
determined that the project would require one 404 and NPDES storm
water permit rather than one for each part of the project. At this point, the
project team agreed that ECO would develop the single 404 and NDPES
storm water permit for the total project, a less cumbersome way to
proceed. While this decision reduced work for each of the subconsultants,
it significantly increased ECO's work, which accounts in large part for its
higher billing.
2. ECO participated in nearly all public meetings to provide environmental
overview, requirements and to answer public concerns regarding
environmental issues. ECO also prepared the EID required for the Facility
Planning process. In an attempt to reduce costs, much of the information
developed during the 404 permitting process was used to develop the
EID This also allowed us to address the difficult environmental issues the
City would have to overcome to successfully complete the projects.
Public Education
1. The City's decision to pursue RLF financing intensified the need to
develop clear and effective information for voters who would be asked to
approve a %-percent sales tax on November 6, 2001. And it resulted in
significant additional support from our public information consultant,
Hanifin and Associates. Instead of the planned three public meetings,
sixteen were held before the election. Hanifin and Associates planned,
coordinated and followed-up on all sixteen of these meetings.
Mr. Greg Boettcher
January 25, 2002
Page 3
• •
2. In a public opinion survey, Hanifin and Associates learned a significant
number of voters felt they had insufficient information about the overall
wastewater treatment system improvements. This was a major concern,
as voters won't approve issues they don't understand. As work moved
forward, odor control issues at Noland, property value concerns and
environmental matters took on paramount importance. Public education
took on new importance and resulted in additional cost from our public
information consultant.
Expanded Responsibilities
As you know, the RLF application process is complex and time-consuming. In
the absence of clearly defined project leadership responsibility, the dearth of long-term
experience with RLF as well as numerous regulatory agencies, and the absolute
necessity of voters approving the 'As -percent sales tax, MWY became the de facto
project manager. We did so with the implicit consent of the City to help ensure the
compatibility of each project aspect and success of the total project.
While the choice resulted in significant additional responsibility, we saw a
significant benefit to the City. MWY and its consultants helped the people of
Fayetteville save over $38 million in interest costs related to these projects by
successfully completing the RLF Program requirements to qualify for the 3 percent RLF
loan.
In an August 8, 2001 memo, Don Bunn informed the public works director, the
mayor and city council that MWY was:
...currently in the process of Facility Plan revision and EID preparation, working with
ADEQ and the Arkansas Soil and Water Conservation Commission in connection with
securing RLF funding and has attended several city related public meetings on the
protect. In addition, they have been working with the City in the investigation of the
possible construction of a fertilizer plant in the Northwest Arkansas area which would
utilize sewage sludge from the area cities and poultry litter. Contract Amendment No. 1
for the above activities will be presented to the Council for review and approval at a
later date.
Unquestionably, these activities went beyond the scope of work in our original
contract and we accept responsibility for our decisions. We made them with the City's
best interests at heart and the interests of the project we have an obligation to complete
in a timely manner and at the lowest possible cost.
At the same time, we fully understand the importance of keeping clients informed
about our activities and the cost of services that exceed the scope of our contract. As
this letter is written, we are reviewing internal processes to identify what changes we
can make to better accomplish this objective. Prior to their implementation, we will
discuss these changes with you to ensure they meet the City's objectives.
Mr. Greg Boettcher
January 25, 2002
Page 4
• •
The attached memorandum provides detail and explanation of costs incurred by
us and our subconsultants in the performance of our contract responsibilities. We trust
you will find this information adequate and that you will forward our request for payment
to the Council with your recommendation for approval.
If you have any questions or need any additional information, please do not
hesitate to call us. We are at your disposal.
LCY:sc
Attachment
cc: Mayor Dan Coody
Board of Aldermen
Cordially yours,
L. Carl Yates
McGoodwin, Williams and Yates, Inc.
Consulting Engineers
909 Rolling Hills Drive
Fayetteville, Arkansas 72703
Telephone 501/443-3404 FAX 501/443-4340
MEMORANDUM
To: Mayor Dan Goody
Mr. Greg Boettcher, Public Works Director
Fayetteville City Council
From: McGoodwin, Williams and Yates, Inc.
Date: January 25, 2002
Re: Wastewater System Improvement Protect
Proposed Contract Amendment between City and Engineer
Fayetteville, Arkansas
MWY Project No. Fy-296
On March 21, 2000, McGoodwin, Williams and Yates (MWY) entered into a
contract with the City of Fayetteville to provide engineering services through preliminary
design, final design, and the construction of facilities for the Westside Wastewater
Treatment Facility. The contract provided for fees through the necessary studies,
preliminary design and completion of a preliminary design report, with the fees for
subsequent work to be negotiated at a later, unspecified date. At about the same time,
the City entered into engineering contracts with the RJN Group for collection and
transmission system engineering for the west side, with Garver Engineers for the same
type of services on the east side, and with Black & Veatch to provide the required
services for necessary upgrades to the existing Paul Noland Plant.
We completed our work under our original scope in May, 2001, at a cost
approximately $200,000 below the estimated cost set out in the contract.
Our contract provides for the utilization of several subconsultants to assist us in
our work. Two of these subconsultants and their scope of work are as follows:
1. ECO, Inc. — ECO's original scope provides for general environmental
guidance to us as we developed the project and to provide services
required for the filing of a Section 404 permit based on the assumption
that the treatment facility could be permitted under the Nationwide permit
rather than filing for an Individual 404 permit. The services proposed to
be provided were for the Westside Treatment Plant only.
Hanifin Associates, Inc. — Hanifin Associates' charge was to develop a
strategic communications program to inform the general public about
January 21, 2002
Page 2
• •
issues concerning the new proposed Westside Plant. Because of known
opposition to constructing this facility, it was believed that a compre-
hensive program to inform the public about the issues related to their
concerns was critical to the success of the project.
Soon after the work commenced on the project, the City decided that the
services ECO, Inc. and Hanifin Associates, Inc. were providing for the Westside
Treatment Plant should be expanded to include the total project, and in the case of
ECO, Inc., to provide services necessary to obtain a 404 permit for the total project
(including both plants and all line work). This decision was based on regulatory
mandates that a single Individual 404 permit would be required. ECO was further
directed to work closely with all project consultants and Hanifin Associates in the public
involvement processes. Although these two subconsultants would then be working with
the City and all consultants, we agreed that these expanded services would be invoiced
to our firm and then passed on to the City for reimbursement.
The 400 -page 404 permit application with documentation has been completed in
draft format and will be finalized shortly after work has been re -authorized on the
project. It is anticipated that once the final application is submitted it will take
approximately six months for completion of review by the Corps of Engineers and the
issuance of the permit. Consequently, in order to avoid delay of construction, when
plans and specifications have been completed, environmental permitting work should
proceed with all due haste. The cost to -date for the environmental management and
permitting (over and above that accomplished under the original scope) is
approximately $160,000, of which $154,000 is for work accomplished by ECO, Inc. and
$6,000 by us. Please note that approximately 75 percent of the cost for work
accomplished by ECO is for line work projects on both the east and west sides of the
City and not part of our contract for the Westside Facilities. A brief summary of the
404 permit work elements is shown in Attachment A.
The cost of the additional work performed by Hanifin Associates, Inc. was due to
its involvement in the entire project rather than just the Westside Treatment Facility,
and for educational assistance during the development of the Facility Plan and the
AutumnFest exposition in early October. Additional costs involved relate to odor
problems at the existing Noland Plant, i.e., several meetings with attendant preparation
were held to discuss this matter. The added cost for Hanifin Associates over the
original budget is $88,426. Hanifin's original budget assumed three public meetings,
whereas 16 were finally held. The need for additional public education was noted in
Hanifin's summary of written comment presented in the Public Opinion Survey
(Attachment B). A summary of Hanifin's work is shown in an October 15, 2001, letter
included as Attachment C.
From the very beginning of the project, the City began evaluating the best
method of funding for the project. At the City's request, we provided assistance in this
evaluation. By May of 2001, the City had decided to utilize the State of Arkansas
Revolving Loan Fund and at that time asked us to provide the necessary services to
January 21, 2002
Page 3
• •
amend the Facility Plan which had been prepared in 1997 by CH2M Hill. This work was
not included in our original contract. The Draft Facility Plan Amendment (including the
required Environmental Information Document) was completed in August. A summary
of significant meetings conducted relevant to the total project effort is presented in
Attachment D. The entire Draft Facility Plan Amendment includes 10 separate volumes
and was submitted to the Arkansas Sod & Water Conservation Commission in August
for review and approval. The Draft Facility Plan was revised and has become the Final
Facility Plan and incorporates the comments of the public at the formal public hearing
and reviewing agency comments, and was resubmitted for final review and approval on
November 2, 2001. By letters dated December 3 and 4 (Attachments E and F) to
Mayor Goody from the ASWCC, they indicate that the Facility Plan had been reviewed
and it appears to be "approvable." However, they cannot give final approval until
certain programmatic events have occurred. Specifically, the City of Fayetteville must
have officially entered into the Revolving Loan Fund program and environmental review
processes must have been completed with closure on several environmental issues
which should be resolved with the completion of the 404 permit process. Final Facility
Plan and Environmental Information Document approval will come in the form of the
issuance of a Finding Of No Significant Impact (FONSI) for the project. Thus, final
approval may take some period of time, as all agencies having interest in the project
must be given opportunity to comment on the draft 404 permit. Consequently, the City
is "ahead of the curve" on receiving facility plan approval so that it will not delay start of
construction. Additionally, the environmental issues that affect the design will have
been identified and resolved early in the design process, so that costly redesigns will be
avoided. The cost to -date on this facility planning part of the work (including RLF
coordination) is approximately $245,000, with $190,000 being for work performed by us
and approximately $55,000 for work performed by ECO, Inc. in the development of the
Environmental Information Document. A graph showing the dates of our effort in
manhours by payroll date is shown in Attachment G.
In addition to extra services detailed above, the City requested that we assist in
the following tasks: 1) Broyles Road Extension study; 2) preliminary work on the
Candidate Conservation Agreement involving not only the "Westside line protect" but
also the research and technology park; 3) evaluating the possible impact of potential
industry on the Westside Plant; and 4) coordination of the effort to utilize the "waste -to -
energy -to -fertilizer" process for the biosolids (DukeSolutions/Harmony).
There is still work to be completed in the facility planning process and securing
approvals of preliminary environmental issues. This work will basically be completed by
us, ECO, Inc., and by the Arkansas Archeological Survey, with some consultation with
the other three engineering consultants on the project. Our work will include working
with ECO, Inc. in the environmental permitting (including a wetlands mitigation plan, if
required), coordinating final review and making any changes required in the Facility
Plan Amendment, RLF coordination, and coordination of the effort to finalizing the
definitive contract between the City and DukeSolutions/Harmony for the utilization of the
waste -to -energy -to -fertilizer process for biosolids treatment and disposal. We estimate
the cost of our effort to be approximately $57,500.