HomeMy WebLinkAbout81-01 RESOLUTION• •
RESOLUTION NO. 81-01
A RESOLUTION TO APPROVE PAYMENT OF THE CITY'S
20% SHARE OF THE CONSTRUCTION COSTS FOR THE
DOUBLE SPRINGS ROAD BRIDGE REPLACEMENT WHICH
ARE NOW ESTIMATED TO BE $249,119.45, PLUS A PROJECT
CONTINGENT AMOUNT OF $37,367.00 AND APPROVE A
RELATED BUDGET ADJUSTMENT
• WHEREAS, the City of Fayetteville has agreed by adopted Resolution
138-92 in September of 1992 to pay 20% of the cost to replace the Double Springs
Bridge over Owl Creek; and
WHEREAS, the City of Fayetteville reaffirms its commitment to pay its
20% share by Resolution 53-01 on April 17, 2001; and
WHEREAS, the bids submitted to the Arkansas Highway Department
exceed its cost estimate so that the City's share of the costs increased by
$47,882.00.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF
THE CITY OF FAYETTEVILLE, ARKANSAS.
Section 1. That the City Council authorizes the Mayor to pay the City's
20% share of the cost of the Double Springs Road bridge project in the amount of
$249,119.45, plus a contingent amount of up to $37,367.00.
Section 2. That the City Council approves a budget adjustment in the
amount of $85,249.45 which is attached as Exhibit "A".
PASSED and APPROVED this the 19th day of June, 2001.
By: Heather
, %�
Bather Woodruff, City Clerk
APPROVED:
By: , �I_J/►�
DAN COODY, Mayor/
City of Fayetteville, Arkansas
Budget Adjustment Form
EXHIBIT A
. Budget Year
2001
Department:
Division:
Program:
Public Works
Engineering
Sales Tax Capital
Date Requested
March 19, 2001
Adjustment #
Project or Item Requested:
$85,249 is requested in the Double Springs
Road Bridge capital project.
Project or Item Deleted:
$85,249 from the Miscellaneous
Drainage Improvements Project.
Justification of this Increase:
The additional funding is to cover the
City's 20% cost share match of the revised
actual bids of the project.
Justification of this Decrease:
Sufficient funding remains in
project to meet objectives.
•
Increase Expen e (Decrease Revenue)
Account Name Amount Account Number Project Number
Bridge & Drainage Imprvs
85,249 4470 9470
5817 00 98036 20
Decrease Expense (Increase Revenue)
Account Name Amount Account Number Project Number
Bridge & Drainage Imprvs
85,249 4470 9470
5817 00 97041 40
Reaueste
B
Approval Signatures
2Zte T 4,— `f D/
Budge
Afr
ager
Date
Date
Mayor
Date
Budget Office Use Only
Type: A B C D
Date of Approval
Posted to General Ledger
Posted to Project Accounting
Entered in Category Log
rn
Blue Copy: Budget & Research / yellow Copy: Requester CADArA'FORMS.BA-AW MA o/o22.WKJ
E.
st
Ac
•
NAME OF FILE: Resolution No. 81-01
•
CROSS REFERENCE: Resolution 53-01; Resolution No. 138-92
06/19/01
Resolution No. 81-01
03/19/01
Exhibit "A" (Budget Adjustment Form)
03/27/01
Departmental Correspondence to Fayetteville City Council thru Dan
Coody, Mayor, Don Bunn, Assistant PWD, Jim Beavers, City Engineer,
from Side Norbash, Staff Engineer regarding Double Springs Road
Bridge (AHTD Project) 20% Cost Sharing with the Highway Department
05/23/01
Letter to Mayor Coody from Robert Walters, Chief Engineer AHTD,
regarding Owl Creek Str. & Apprs. Job 040152
04/17/01
Resolution No. 53-01 (cross reference)
09/15/01
Resolution No. 138-92 (cross reference)
06/19/01
Staff Review Form
06/21/01
Departmental Correspondence to Sid Norbash, Engineering, from
Heather Woodruff, City Clerk
NOTES:
FAYETTEVILE
THE CITY OF FAYETTEVILLE, ARKANSAS
DEPARTMENTAL CORRESPONDENCE
To: Fayetteville City Council
Thru: Dan coody, Mayor
Don Bunn, Assistant PWD
Jim Beavers, City Enginee
From: Sid Norbash, Staff Engineer
Date: March 27, 2001
Re: Double Springs Rd. Bridge (ABM Project)
20% Cost Sharing with the Highway Department
Per attached Resolution 53-01, the above referenced project is a
Highway Department Project with 80%-20% cost share with the City of
Fayetteville,
This project includes a new bridge to replace the existing bridge
over the Owl Creek, and some street improvements as well.
On 10-19-2000, based on interim estimates, the Highway Department
estimated the City's share for 20% to be $229,537 (see attached
documents). On May 16, 2001 the Highway Department opened bids for
this project, and the bid was over the Highway Department's
estimate, which increases the City's share to $277,419.45 or
$47,882 higher than the previous estimate. The City has made a
deposit of $28,300 to the Highway Department to date.
The Staff is requesting that the Council approve the following:
(1) funding of this project in the estimated amount of $249,119.45
(2) the related budget adjustment in the amount of $85,249.45.
(3) A project Contingency amount of $37,367 (15%).
Please be advised that the actual final cost to the City could vary
higher or lower, depending on the actual construction costs.
SN/sn
attachments
ARIIINSAS STATE HIGHWS ,KCCE4egirt--I
AND
TRANSPORTATION DEPARTMENT CITY OF FAYETTEVILLE
MAYOR'S OFFICE
MAY 2 9 2001
Dan Flowers
Director
Telephone (501) 569-2000
The Honorable Dan Coody
Mayor of Fayetteville
113 West Mountain
Fayetteville, AR 72701
Dear Mayor Coody:
May 23, 2001
P.O. Box 2261
Little Rock, Arkansas 72203-2261
Telefax (501) 569-2400
Re: Job 040152
F.A.P BRN-9142(1)
Owl Creek Str. & Apprs.
(Fayetteville) (S)
Washington County
Mobley Contractors, Inc. of Morrilton, Arkansas submitted the low bid of $1,017,174.25
for the referenced project at the Department's May 16, 2001 letting. The Arkansas State
Highway Commission has tentatively accepted their proposal and will execute the
contract upon receipt of the City's matching funds.
The City's estimated share of costs for this project is calculated below.
Preliminary Engineering (AHTD) $
Utilities
Right -of -Way
Construction
Construction Engineering
Totals
Less Deposits Received
City Share Remaining
Total Cost
116,847.06
33,000.00
67,500.00
1,017,174.25
152,576.14
$ 1,387,097.45
Federal Share
$ 93,478.00
26,400.00
54,000.00
813,739.00
122 061.00
$ 1,109,678.00
City Share
$ 23,369.06
6,600.00
13,500.00
203,435.25
30,515.14
$ 277,419.45
28,300.00
$ 249,119.45
•
• •
The Honorable Dan Coody
May 23, 2001
Page Two
Your check for $249,119.45 (made payable to the Arkansas State Highway and
Transportation Department) should be forwarded to this office as soon as possible. The
contract will not be executed, and construction cannot begin, until your check is
received. Submittal of these funds to the Department will be considered as your
concurrence in the award of this contract.
The Department will make every effort to assure the project is constructed in accordance
with the plans and specifications, thereby minimizing the possibility of items being
declared non -participating for federal funds. However, should any of the items be
declared non -participating, the City would be responsible for 100% of their cost. Upon
completion of the project, a statement will be prepared reflecting the final cost and
respective matching shares. At that time, the City will be returned funds remaining over
the deposit or billed for additional funds required.
We look forward to working with the City to complete the proposed improvements.
Should you have any questions or comments, please advise.
Robert L. Walters
Chief Engineer
AB -27-2001 10:45 AHTD
• •
Job 040152, Owl Creek Str. & Apprs. (Fayetteville) (S)
F.A.P. BRN-9142-(1)
Cost Estimate Based on Revised Interim Estimate dated 02/09/01
(Project now includes a 100' X 28' Temporary Bridge
and a 143' X 7' Retaining Wall at the City's pump station)
Actual PE charges (thru 01/06/01)
Estimated ROW
Estimated Utilities
Estimated Construction
Estimated CENG (15%)
Less Deposits by City
Estimated Amount Due From City
Iota(
$ 106,437
42,000
62,000
815,000
122,250
$ 1,147,687
915015692b2i r.ua/ui
Federal (80%1
$ 85,150
33,600
49,600
652,000
97,800
$ 918,150
City (20%1
21,287
8,400
12,400
163,000
24,450
$ 229,537
(28,300)
$ 201,237
Bridge Length: 116 ft.
Cross Section: 2 -11 ft. lanes, 8 ft. shoulders (38 ft. total width)
New bridge will be raised approximately 8' from lowest point of the existing roadway
Total length of bridge and approaches -1,500 ft.
raw eait wtcl At
bleu) ti)Ittewl (IA fie
Yoyuxvt
'oat -it' Fax
Nob 7671
�.� a7��llp�..�/
FT" . tth2„
�� Fes^ 4r " ""
ro
' &ttttdJ
),Dopa
co.
maw •
Kron. 569- a1'7-$5
-018 tit ., 40A 01
Fail
•
AHS 0
reeptaNls Coctac s
Mg, F''raesk Vo-e.l
{.a• 51x da•xec
k• -•R 7a7 -b1 — a- aCI
TOTAL P.01
•SOLUTION NO. 53-01
•
A RESOLUTION TO APPROVE THE 20% COST SHARING OF
THE DOUBLE SPRINGS ROAD BRIDGE OVER OWL CREEK
AND TO APPROVE A BUDGE ADJUSTMENT OF $72,037.00
WHEREAS, the Board of Directors of Fayetteville agreed to pay its 20%
share of the cost of construction of the Double Springs Road bridge over Owl
Creek and designated this as its top priority bridge project by Resolution #138-92
on September 15,1992; and
WHEREAS, the State Highway Department is now prepared to move
forward and let contracts for the bridge at an estimated cost to the City of
Fayetteville of $229,537.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF
THE CITY OF FAYEITEVILLE, ARKANSAS:
Section 1. The City Council hereby reaffirms its agreement to pay 20%_
of the construction costs for the Double Springs Road bridge over Owl Creek and
authorizes the Mayor to pay such cost share to the Arkansas Highway
Department.
Section 2. The City Council hereby approves the Budget Adjustment in
the amount of $72,037.00 for this project. The Budget Adjustment is attached
hereto as Exhibit A.
c:' . i
iv?Neigiii AND APPROVED this /7 day of April, 2001.
f•
•<•J
ATTEST:
By:
Heather Woodruff, City erk
APPROVED:
By
/L% /.
DAN COODY, gor
if
Rc
•
• •
RESOLUTION NO. 138-92
A RESOLUTION EXPRESSING THE WILLINGNESS OF THE
CITY OF FAYETTEVILLE, ARKANSAS TO MATCH
FEDERAL -AID BRIDGE REPLACEMENT AND
REHABILITATION MONIES FOR THE BRIDGE ON DOUBLE
SPRINGS ROAD OVER OWL CREEK.
WHEREAS, the City of Fayetteville understands Federal -Aid
Bridge Replacement and Rehabilitation funds are available for
replacement or rehabilitation of eligible structures; and
WHEREAS, the City has determined that the top priority bridge
is on Double Springs Road over Owl Creek; and
WHEREAS, the City understands that their matching portion of
this project will be 20% of the total cost, and should the escrowed
City matching funds be inadequate to cover the City's obligation,
the Department may cause this deficiency to be withheld from the
allotment of gasoline tax returnable to the City;
NOW THEREFORE, BE IT RESOLVED BY THE BOARD OF DIRECTORS OF THE
CITY OF FAYETTEVILLE, ARKANSAS:
Section 1. That the City of.Fayetteville will participate
in accordance with its designated responsibility in this project.
Section 2. The Mayor and City Clerk are hereby authorized
and directed to execute all appropriate agreements and contracts
necessary to expedite the construction of this bridge improvements
on city streets. A copy of the agreement is attached hereto and
made a part hereof.
Section 3. The City of Fayetteville pledges its full
support and hereby authorizes the Arkansas State Highway and
Transportation Department to initiate action to construct this
project.
PASSED AND APPROVED this 15th day of September , 1992.
APPROVED:
B
ATTEST:
By
Mayor
c
R
• •
STAFF REVIEW FORM
_X_ AGENDA REQUEST
CONTRACT REVIEW
GRANT REVIEW
For the Fayetteville City Council meeting of June 19. 2001
FROM: ' /
Sid Norbash .KLr✓ Engineering Public Works
Name
Division Department
ACTION REQUIRED: Doubie Springs Rd. Bridge Replacement Project. Approval of:
(1) 20% funding of this AHTD project in the estimated amount of $249,119.45
(2) The related budget adjustment. (3) Project Contingency of $37,367 (15%).
COST TO CITY:
Double Springs Rd.
$85.249.45 $201_..237 Bridge Replacement
Cost of this Request Category/Project Budget Category/Project Name
4470-9470-5817-00
Account Number
98036
Project Number
-0- Bridge and Drainage_Imprvts.
Funds Used To Date Program Name
$201.237 Sales Tax
Remaining Balance Fund
�7 : X Budgeted Item _X.. Budget Adjustment Attached
Budget C dins r
CEO
Administrative Services Director
CT/
EREVIEW:
Accounting Manager
GRANTING AGENCY:
Date ADA Coordinator Date
Cpty ttorney
UQ
Purchasing Officer
0
Date Internal Auditor Date
6 o
Date
STAFF RECOMMENDATION: Approval of funding, budget adjustment & Contingency.
ision Head
i.ula•V
4
Mayor
a9-09-0/
Date
Date'
Cross ReferenrA
New Item: Yes_ No X
Prev Ord/Res #: 53-01
Orig Contract Date: 9-15-1992
6y4iu1Orig Contract#
Date
s
• •
Staff Review Form
Description/ Double Springs Rd. Bridge Meeting Date 6-19-2001
Project Name 20% Funding for AHTD's Project
Comments: Reference Comments:
Budget Director
Accounting Manager
City Attorney
Purchasing Officer
ADA Coordinator
Internal Auditor
FAYETTEVI!LE
THE CITY OF FAYETTEVILLE. ARKANSAS
DEPARTMENTAL CORRESPONDENCE
To: Sid Norbash, Engineering
From: Heather Woodruff, City Clerk
Date: June 21, 2001
Attached is a copy of the resolution approving the cost share agreement with the Arkansas
Highway Department for the Double Springs Road Bridge Replacement. The original will be
microfilmed and filed with the City Clerk.
cc: Nancy Smith, Internal Audit
Steve Davis, Budget and Research