HomeMy WebLinkAbout25-98 RESOLUTION1
RESOLUTION NO 25-98
A RESOLUTION APPROVING AMENDMENT NO. 1 TO THE
ENGINEERING CONTRACT WITH MILHOLLAND COMPANY
IN THE AMOUNT OF $4,425 FOR THE ADDITION OF RIGHT
OF WAY AND EASEMENT PLAT PREPARATION FOR THE
POPLAR STREET IMPROVEMENTS PROJECT.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section 1. That the City Council hereby approve Amendment No. 1 to the engineering
contract with Milholland Company in the amount of $4,425 for the addition of right of way and
easement plat preparation for the Poplar Street Improvements Project; and authorizes the Mayor and
City Clerk to execute said contract amendment. A copy of Amendment No. 1 is attached hereto
marked Exhibit "A" and made a part hereof.
--PASSED AND APPROVED this 3rd day of March , 1998.
foot,/
"l �� s,' • ;.4 APPROVED:
if L;'{l; ItIA" i4*y Y..r, B
Fred Hanna, Mayor
s".
I": _._'` *
ATTEST:
By:
7-4756
44
Heather Woodruff, Citi Clerk
EXHIBIT A
POPLAR STREET ENGINEERING CONTRAC'I
MILHOLLAND COMPANY
CONTRACT AMENDMENT NO. 1
The engineering contract between the City of Fayetteville and Milholland
Company for work related to the reconstruction of Poplar Street is hereby
amended in accordance with Section 3, Paragraph D.
The Contract is amended to add the preparation of 13 easement and right of
way documents and tract maps at a cost of 325.00 each for a total of $4,425.00.
•
Original Contract Amount -
Cost of This Amendment-
$ 60,350.00
4,425.00
Revised Contract Amount- $ 64,775.00
Fre i-Ia nna, Mayor
City of Fayetteville
4Se Y/i
Date
c2 -0)--9Y
Mel Milholland Date
Milholland Company
it9MU 7w
iUot�.
RESOLUTION NO 92-99
A RESOLUTION APPROVING A CONTRACT AMENDMENT
FOR ENGINEERING SERVICES WITH MILHOLLAND
COMPANY TO ADD BIDDING AND CONSTRUCTION
MANAGEMENT FOR THE POPULAR STREET
IMPROVEMENTS IN THE AMOUNT OF $71,601.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section 1 That the City Council hereby approves a contract amendment for engineering
services with Milholland Company to add bidding and construction management for the Popular
Street improvements in the amount of$71,601. A copy of the amendment is attached hereto marked
Exhibit "A" and made a part hereof.
PASSED AND APPROVED this Si. day of July , 1999.
-`t
•
x- i , I A:1: v �0'
`et,
•
�,:
, .yf l 4.
AT1Ei r �`��
!�/o4�
By atther Woodruff, City lerk
APPROVE
By
Fred Hanna, Mayor
AGENDA REQUEST
X CONTRACT REVIEW
GRANT REVIEW
For the Fayetteville
STAFF REVIEW FORM
City Council meeting of
MICROFILMED
Mayor's Approval,
FROM:
Sid Norbash
Name
Engineering
Division
Public Works
Department
ACTION REQUIRED: Approval of the Amendment fl to the Engineering Contract
with Milholland Company for Poplar Street and Drainage Impvts. Project, in
the amount of $18,833.50.
COST TO CITY:
$18,833.50
Cost of this Request
4470-9470-5809-00
Account Number
97023-0010
Project Number
$922,889
Category/Project Budget
$877.796
Funds Used To Date
$45,183
Remaining Balance
BUDGET REVIEW:
X Budgeted Item
Bu gordinator
Poplar St. Impvts.
Category/Project Name
Street Impvts.
Program Name
Sales Tax
Fund
Budget Adjustment Attached
Administrative Services Director
CONTRACT/G /LEASE REVIEW:
counting Manag
Ci Attorney
GRANTING AGENCY:
Date ADA Coordinator.
/- f 3r)0.A4
Date Interna
Purchasing Officer Date
Auditor
Date
Date
STAFF RECOMMENDATION: Approval of the
Contract with Milholland Company.
da. -t
irk/1/o/
Divon Head Dhte
.'it..� / Zz _c i
# kJ.Depar ent Director Date1
•
Y .1.0(tll t
istrative rvices Director Date
ayor
I
Date
Amendment #1 to the Engineering
Cross Reference
New Item: Yes_ No.S
Prev Ord/ S s #: 92-99
tL zs-99
Orig Contract #610
Orig Contract Date: 7-6-99
Staff Review Form
Description/ -Poplar Street Imprvts. Meeting Date N/A
Project Name Amendment. #1 to Eng. Contract
Comments: Reference Comments:
Budget Director
Accounting Manager
City Attorney
Purchasing Officer
ADA Coordinator
Internal Auditor
CONTRACT AMENDMENT NO. 3
FOR
ENGINEERING SERVICES
PROJECT:
POPLAR STREET IMPROVEMENTS
E-541
THE ORIGINAL CONTRACT was made and entered into on August 19, 1997, AND THIS
CONTRACT AMENDMENT NO. 3, made and entered into on this 1 day of ,
2001, by and between the CITY OF FAYETTEVILLE, Arkansas, hereinafter ref ed to asCtIke
"OWNER", and MILHOLLAND COMPANY, Engineering and Surveying, Consulting Engineers
of Fayetteville, Arkansas, hereinafter referred to as the "ENGINEER",
WITNESSED THAT:
WHEREAS, the OWNER Originally desired to Re -Construct POPLAR STREET 28 feet in width
from LEVERETT AVENUE East to GREGG AVENUE centered in a Right -Of -Way fifty varying
from forty (40') to feet (50') in width, AND
WHEREAS, the OWNER has AMENDED its desires several times previously, AND
WHEREAS, the OWNER has added into "PHASE IV: CONTRACT AMENDMENT,"
Amendment No. 1 and Amendment No. 2, as follows:
Amendment No. 1: C.O. No. 1 by Resolution No. 25-98 in the amount of $ 4,425.00;
Amendment No. 2: - C.O. No. 2 by Resolution No. 92-99 in the amount of $71,601.00;
AND,
WHEREAS, the OWNER desires to add Amendment No. 3 to said PHASE IV to provide for the
following items:
ITEM No. 1: S-2196: Field Stake Poplar Street Right -of -Way for Relocation
of Various Utilities out of the Existing and New Street Right -of -Ways
$ 1,776.50
ITEM No. 2:
Design 377 LF of a new 18" SDR -26 Sanitary Sewer Main to replace
old clay pipe and laterals under Poplar Street;
AND Re -Design Poplar Street intersection with Gregg Avenue and
the Arkansas -Missouri Railroad Crossing $ 9,857.00
1
Amendment No. 3; PHASE IV; POPLAR STREET IMPROVEMENTS, Cont.
Page Two (2)
ITEM No. 3: Design a "Traffic Control Plan" with Detours and Construction
Signage for use to provide control for "One -Way" Traffic during
Construction of said street $ 1,700.00
ITEM No.4: Additional Engineering Services resulting from delayed Construction
and Additional Items $ 5,500.00
THEREFORE, the OWNER desires the ENGINEER to provide said services in C.O. No. 3 for a
Total Fee Amount of $18,833.50
THEREFORE, the ADJUSTED TOTAL PHASE IV CONTRACT Price Equals .... $94,859.50
WHEREAS, the OWNER deemed it essential to delay and modify its original plans, and Amend,
AND,
WHEREAS, the ENGINEER has sufficient experienced personnel and equipment to perform the
work described in this Agreement, as Amended,
NOW THEREFORE, in consideration of the mutual covenants and agreements herein contained, the
OWNER and the ENGINEER, the parties hereto, stipulate and agree that the OWNER does hereby
employ the ENGINEER to perform the required engineering services as herein above set out; AND
the ENGINEER agrees to provide said ADDITIONAL SERVICES.
IN WITNESS WHEREOF, the OWNER has caused these presents to be executed in its behalf by
its duly authorized representatives, and the said ENGINEER by it duly authorized representatives,
and the parties hereto have set their hands and seals on the date heretofore set out.
Attest:
zt c �G✓oatis�s
(City Clerk /o
Atte t:
Secretary
2
CITY OF FAYETTEVILLE, ARKANSAS
1-14.4 d_CeD
Dan Coody, Mayor
MILHO NND C MP Y
cyz
elvin L Milholland, Engineer, Surveyor
FAYETTEVILLE
THE CITY OF FAYETTEVILLE, ARKANSAS
DEPARTMENTAL CORRESPONDENCE
To: Dan Coody, Mayor
Thru: Don Bunn, Assistant Public Works Director
Jim Beavers, City Engineers
From: Sid Norbash, Staff Engineer .0124^/
Date: January 17, 2001 ,J zz
Re: Poplar Street Improvements - Engineering Amendment..#'i#/
Engineering Contract with Milholland Company
The attached Amendment #1 to the above referenced contract has been
necessitated because of certain field adjustments and necessities.
The justifications for the addition of these changes are as follows:
Item #1 Was added per request of the City Staff for accommodating utility
companies that needed adjustments to their lines. Mainly to establish the
required locations and elevations.
Item #2 was added to this contract per request of the City Staff for all
the Engineering work necessary to design and relocate a very old 18" clay
sewer main which did not withstand the construction and started to fail.
Item #3 was added to this contract per Mr. Venable's request and to avoid
any liability to the City, and in order to address the contractor's
concerns.
Item #4 was added to this contract because two additional water line
adjustments were needed, also the construction of the 18" sewer main took
longer than anticipated, therefore, lengthening the construction period.
Per attached resolutions 25-98, and 92-99, the Council has approved
$76,026 for this portion of the contract.
Since the over -run for this contract is $18,833.50, and is within the
$20,000 Mayor's authorization, the Staff request that this amendment be
approved by the Mayor. Also, since the construction of this project is
completed, this amendment will close out this contract.
SN/sn
attachments
FAYETTEVILLE
THE CITY OF FAYETTEVIIIE. ARKANSAS
DEPARTMENTAL CORRESPONDENCE
•
To: Sid Norbash, Engineering
From: Heather Woodruff, City Clerk
Date: January 23, 2001
Attached is a copy of amendment no. 3 to the Engineering Contract with Milholland Company
for Poplar Street and drainage improvements. I am also returning one original to you. The
original will be microfilmed and filed with the City Clerk.
cc: Nancy Smith, Internal Audit