HomeMy WebLinkAbout124-94 RESOLUTION•
1MICROFILMED)
RESOLUTION NO. 124-94
A RESOLUTION AWARDING BID NO. 94-65 IN THE
AMOUNT OF $24,462.00 AND AUTHORIZING THE MAYOR
AND CITY CLERK TO EXECUTE A CONTRACT WITH
WHITFIELD CONSTRUCTION FOR CONSTRUCTION OF A
VISITING AREA AT THE CITY JAIL.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section I. That Bid No. 94-65 in the amount of $24,462.00 is hereby awarded and
the Mayro and City Clerk are authorized to execute contract with Whitfield Construction for
construction of a visiting area at the city jail. A copy of the contract is attached hereto marked
Exhibit "A" and made a part hereof.
PASSED AND APPROVED this 18th day of October , 1994.
ATTEST:
By: C]/C.C. �J
Traci Paul, City Clerk
APPROVED:
By:
1, //.�oZb+z-
ed Hanna, Mayor
CITY OF FAYETTEVILLE
113 W MOUNTAIN
FAYETTEVILLE, AR
BID: 94-65
DATE: 9/14/94
TIME: 11:30 AM
DESCRIPTION: CONSTRUCTION OF CITY JAIL VISITING AREA
NOH
BIDDER
1 HECKATHORN CONSTRUCTION
2 MARINONI CONSTRUCTION
3 HARRISON-DAVIS CONSTRUCTION
4 BILL WHITFIELD CONSTRUCTION
CERTIFIED BY:
SObN
PURCHASING MANAGER
AL.,4 tA91A41191A-
WITNESS
T
BID
$29,863.00
$24,800.00
$35,970.00
$24,462.00
9b47,74
DATE
EXHIBIT A
BILL WHITFIELD CONSTRUCTION CO., INC.
909 SOUTH POWELL STREET
SPRINGDALE, AR 72765
CONTRACT
TO
CITY OF FAYETTEVILLE
113 WEST MOUNTAIN
FAYETTEVILLE, AR 72701
FOR
PROJECT #94-65
CITY JAIL VISITING AREA
-1-
=�`SRP.03
CONTRACT
This contract executed this I PaT4 day of C;C'T[Z___ 1994,
between theCity of.Fay ttevi le, Arkansas,,hereinafter called the
City, and Vdc1hrhlUifi (RShUC 1CV'. ,The .
hereina ter called,.,the Contracto , and having an address at
1U t :)wwt1,� > irll ; v2iru}1(i . kg_ At-ra0b
In consideration of the mutual covenants contained herein, the
parties agree as follows:
4.
The Contractor at his own cost and expense shall furnish all
labor, materials, supplies, machinery, equipment, tools,
supervision, bonds, insurance, tax permits, and all other
accessories and services necessary to complete iters bid per
bid 54-66 as stated in CONTRACTOR'S PROPOSAL, and in
accordance with specifications attached hereto and nade a part
hereof under Bid c94-65, all included herein as if spelled out
word for word.
The City shall pay the Contractor based on prices indicated in
Contractor's Proposal. Progress payments will be nade after
approval and acceptance of work and submission of invoice.
Paycients will be made approximately 30 days gfte re eipt of
invoice. Amount of contract not to exceed S,,,Q,c(oa,..
The Contract documents which corp:ise the contract be_tWe.en the
C.Z.y dflCi the Contractor conrh=t o_` this Contract r_nd the
r o_ d;. _....ants attachcr. hereto, and :;aac part :.creo` .
Bi? for -1 ide;.ted a::; Invitation to Bid 94-65 with the
specifications and conditions typed thereon.
The Contractor's proposal.
C. The Notice to Prospective Bidders and the Bid Tabulation.
These Contract documents constitute the entire agreement
between. the City and the Contractor and may be modified only
by a duly executed written instrument signed by the City and
the Contractor.
contractor shall not assign his duties under the terms of this
agreement.
6. Contractor agrees to hold the City harmless and indemnify the
City, against any and all claims for property damage, personal
injury or death, arising from Contractor's performance of this
contract. This clause shall not in any form or manner be
construed to waive that tort immunity set forth under Arkansas
Law
7. The Contractor shall furnish a certificate of insurance
addressed to the Owner, showing that he carries the following
insurance which shall be maintained throughout the term of the
Contract. Any work sublet, the contractor shall require the
subcontractor similarly to provide worker's compensation
insurance. In case any employee engaged in work on the
project under this contract is not protected under Worker's
Compensation Insurance, the Contractor shall provide and shall
cause each Subcontractor to provide adequate employer's
liability insurance for the protection of such of his
employees as are not otherwise protected.
c.
Workmen's Compensation Statutory Amount
Compre pensive Q n rat
Automobile Insurance
Bodily Injury Liability
Property Damage Liability
$500,000 for each person
injured.
$1,000,000 for each
accident.
$250,000 for
accident.
$500,000 aggregate.
each
'emi._._, for insuranCC and the bond reauired herein shall
iC: Dv rhe Con raptor.
Tr: contract exceeds $20,000, Contractor agrees to furnish a
Performance_ Bend, approved by the City, guaranteeing the
pc Eornance of this contract, for not less than one hundred
percent of the amount of this contract. Said performance bond
shall be conditioned on fulJ and complete performance of this
contract and acceptance by the City of Fayetteville for the
payment of all labor and materials entering into or incident
to the proposed improvements. The Contractor agrees to
furnish proof of licensure as required under the terms of Act
50 of the 1965 Acts of the Arkansas Legislature
Contractor agrees to begin work within five (5) days of notice
to proceed and complete the work within 30 calendar days
thereafter. Liquidated damages of $100 per day shall be
assessed at the option of the City, not as a penalty,
beginning on the first day following the completion time to
cover additional costs.
10. All work, called for herein shall be coordinated directly with
Operations Management International's designated project
manager.
1
'i-1ti =ti
P. 05
This contract may be terminated by the City with 30 days
written notice.
12. Construction must meet all ADAAG requirements of American
Disabilities Accessibility Guidelines.
WITNESS OUR HANDS THIS 1O7N DAY OF 0CTnRF-R , 1994 .
CITY OF FAYETTEVILLE,
FAYETTEVITS.F, ARKANSAS
BY
MAYOR
1 i la.i tc\c lCA CoKst-tikcILoa.\ Co., c
HANE
DC:NAMEA2iIS TITLE
BY
St
Bt3. TRESS ADDRESS
City of Fayetteville; Arkansas
Budget Adjustment Form
Budget Year
1994
Department: General Government
Division: Miscellaneous
Program:
Date Requested
Oct 18, 1994
Adjustment #
Project or Item Requested: Additional funding is requested for jail
modifications.
Project or Item Deleted: None. Reallocation of project 94070,
Police/Court Improvements. to fund th jail modifications.
Justification of this Increase: Bid for jail modifications carne above
the budgeted amount.
Justification of this Decrease: Project 94070 is for a variety of
improvements associated with the PoliceiCourt Building - the jail
modification project is consistent with the intent of the funding. This
adjustment formalizes the reallocation of funds.
Account Name
Building Costs
Increase
Amount Account Number Project Number
5,930 1010 6600 5804 00 94015
Decrease
Account Name Amount Account Number Project Number
Building Costs
5.930 1010 6600
5804 00 94070
��//�/ Approval Signatures
/r, /61z
-(/ s---..-/ -9rg1
•
Requested By
Binet ordinator `
Department Director
Admin. Services it for
Mayor
N /A
Type: A
Budget Office Use Only
C D E F
Date of Approval
Posted to General Ledger
Entered in Category Log
Budget Office Copy