HomeMy WebLinkAbout86-93 RESOLUTIONCity of Fayetteville, Arkansas
Budget Adjustment Form
3.30
Budget Year
1993
Department
Division:
Program:
Public Works
Engineering
Sewer Mains Construction
Date Requested
8-9-93
Adjustment
1
Prosect or Item Requested:
24" Sewer Main crossing on Highway 180
at Gregg Avenue Intersection
Project or Item Deleted:
None
JugWwatmn ni this Increase:
As part of our Sewer Rehab Program, a 24'
Sewer crossing is scheduled for the
future. However, since this portion of
6th Street is under construction, it is
less expensive to do this Highway Cross-
ing at this time.
Justification of this Decrease:
The funds for this project are
shifted from the Sewer Rehab to
this contract; however, the Sewer
Rehab Project is being served.
Account Name Amount
Increase
Account Number
Sewer Mains Const. $21,511.00 5400 5700 5815. 00
(Hwy. 180 W&S Reloc.)
Account Name
Sewer Mains Const.
(Sewer Rehab)
Amount
$21,511.00
Decrease
Project Numba
92066 0020
Aunt Number Project Number
5400 5700 5815 00
Approval Signaturm
8-9-93
Requ ed :
Age ai
Bwg d'•. or
►!. 11 • Visas.
De
•
•
art
n Director
Admin. erviccs
146
Mayor
S-53
Ovc93
Budget Office Use Only
Type: A BCDEF
Date of Approval
Posted to General Ledger
Entered in Category Log
Budget Office Copy
•
OWNER:
PROJECT:
City of Fayetteville
113 West Mountain
Fayetteville, AR 72701
Water and Sewer Relocations
6th Street, Hwy 180
Fayetteville, Arkansas
CONTRACTOR: Goodwin & Goodwin
8009 Texas Road
Fort Smith, Arkansas 72901
Change Order No. 2
Date: July 29, 1993
Project No: FY912165
Contract
Date: May 18, 1993
The following changes to the Contract are hereby ordered:
1. The Owner wishes to add a 24 -inch sewer crossing with 36 -inch bored
casing across 6th Street at Gregg Street to serve a planned future
24 -inch gravity relief sewer line.
A. Add Bid Item No. 64 for 90 LF of 36"
Bored Casing at $250/LF
Add $ 22,500.00
B . Add Bid Item No. 65 for 95 LF of
24" PVC, SDR 35 Sewer Pipe at $113/LF
Add
$ 10,735.00
C. Add Bid Item No. 66 for 6 LF External
Drop Pipe for Drop Manhole at $125/LF
Add $ 750.00
D . Increase Bid Item No. 51 by 2 EA Manholes
0' - 8' at $900/EA
Add $ 1,800.00
E . Increase Bid Item No. 52 by 4 EA Manholes
Additional 2' Increments at $200/EA
Add $ 800.00
F. Increase Bid Item No. 2 by 23 LF of 12"
PVC, C-900 Water Line at $21/LF
Add $ 483.00
G . Increase Bid Item No. 31 by 23 LF Flowable
Fill Trench Backfill at $5/LF
Add
$ 115.00
Total Additional cost for 24 -inch Sewer Line Crossing
Original Contract Amount
Previouse Change Order Amount
Change Order Will Increase
Contract Amount By
Revised Contract Amount
Contract Time
Increase in Contract Time
Revised Contract Time
CONTRACTOR:
Goodwin & Goodwin
By:
ENGINEER:
ryan Goodwin
McClelland Consulting Engineers, Inc.
By:
OWNER:
R. Way%e Jo1`tes
City of gayetteville
By:
Fred Hanna, Mayor
ADD
120
20
140
$ 37,183.00
$371,384.00
$ 25,880.00
$ 37,183.00
$434,447.00
calendar days
calendar days
calendar days
D to
7 -2? -93
Date
Date
•
• •
RESOLUTION NO. 86-93
A RESOLUTION AUTHORIZING A CHANGE ORDER IN THE
AMOUNT OF $37,183 TO THE CONSTRUCTION CONTRACT
WITH GOODWIN & GOODWIN CONSTRUCTION COMPANY
FOR THE HIGHWAY 180 WATER AND SEWER
RELOCATION PROJECT AND APPROVAL OF A BUDGET
ADJUSTMENT.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1. That the a change order in the amount of $37,183 to die construction
contract with Goodwin & Goodwin Construction Company for the Highway 180 Water and
Sewer Relocation Project. A copy of the change order is attached hereto marked Exhibit "A" and
made a part hereof.
Section 2. The Council hereby approves a budget adjustment decreasing Sewer Mains
Construction (Sewer Rehab), Acct. No. 5400 5700 5815 00 increasing Sewer Mains Construction
(Hwy 180 W & S Relocation), Acct. No. 5400 5700 5815 00, Project No. 92066.0020 m the
amount of $21,511. A copy of the budget adjustment is attached hereto and made a part hereof.
PASSED AND APPROVED this 17th day of Avynct , 1993.
ATTEST:
By: i u u�� .nvlcv�
Sherry L. Thomas, City Clerk
APPROVED:
BY: 4,414#"--
Fred
Hanna, Mayor
10/
•
•
OWNER:
PROJECT:
Q
City of Fayetteville
113 West Mountain
Fayetteville, AR 72701
Water and Sewer Relocations
6th Street, Hwy 180
Fayetteville, Arkansas
CONTRACTOR: Goodwin & Goodwin
8009 Texas Road
Fort Smith, Arkansas 72901
Change Order No. 2
Date: July 29, 1993
Project No: FY912165
Contract
Date: May 18, 1993
The following changes to the Contract are hereby ordered:
1. The Owner wishes to add a 24 -inch sewer crossing with 36 -inch bored
casing across 6th Street at Gregg Street to serve a planned future
24 -inch gravity relief sewer line.
A. Add Bid Item No. 64 for 90 LF of 36"
Bored Casing at $250/LF
Add $ 22,500.00
B . Add Bid Item No. 65 for 95 LF of
24" PVC, SDR 35 Sewer Pipe at $113/LF
Add
$ 10,735.00
C. Add Bid Item No. 66 for 6 LF External
Drop Pipe for Drop Manhole at $125/LF
Add $ 750.00
D . Increase Bid Item No. 51 by 2 EA Manholes
0' - 8' at $900/EA
Add $ 1,800.00
E . Increase Bid Item No. 52 by 4 EA Manholes
Additional 2' Increments at $200/EA
Add $ 800.00
F. Increase Bid Item No. 2 by 23 LF of 12"
PVC, C-900 Water Line at $21/LF
Add $ 483.00
G . Increase Bid Item No. 31 by 23 LF Flowable
Fill Trench Backfill at $5/LF
Add $ 115.00
•
•
Total Additional cost for 24 -inch
Original Contract Amount
Previouse Change Order Amount
Change Order Will Increase
Contract Amount By
Revised Contract Amount
Contract Time
Increase in Contract Time
Revised Contract Time
CONTRACTOR:
Goodwin & Goodwin
By:
ENGINEER:
McClelland Consulting Engineers, Inc.
By:
OWNER:
OR. Way e es
City of Fayetteville
By:
Fred Hanna, Mayor
•
Sewer Line Crossing
ADD
120
20
140
$ 37,183.00
$371,384.00
$ 25,880.00
$ 37.183.00
$434,447.00
calendar days
calendar days
calendar days
Date
8/7-%3
Date
•
RESOLUTION NO. 86-93
A RESOLUTION AUTHORIZING A CHANGE ORDER IN THE
AMOUNT OF $37,183 TO THE CONSTRUCTION CONTRACT
WITH GOODWIN & GOODWIN CONSTRUCTION COMPANY
FOR THE HIGHWAY 180 WATER AND SEWER
RELOCATION PROJECT AND APPROVAL OF A BUDGET
ADJUSTMENT.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
SecLion1. That the a change order m the amount of $37,183 to the construction
contract with Goodwm & Goodwin Construction Company for the Highway 180 Water and
Sewer Relocation Project. A copy of the change order is attached hereto marked Exhibit "A" and
made a part hereof.
Salim2. The Council hereby approves a budget adjustment decreasing Sewer Manu
Construction (Sewer Rehab), Acct. No. 5400 5700 5815 00 increasing Sewer Mains Construction
(Hwy 180 W & S Relocation), Acct. No. 5400 5700 5815 00, Project No. 92066.0020 in the
amount of $21,511. A copy of the budget adjustment is attached hereto and made a part hereof.
PASSED AND APPROVED this 17th day of 'wrist , 1993.
ATTEST:
BY:
herry L. Thomas, City Clerk
APPROVED: