HomeMy WebLinkAbout99-92 RESOLUTIONRESOLUTION NO. 99-92
A RESOLUTION AUTHORIZING THE MAYOR AND CITY
CLERK TO EXECUTE SUPPLEMENTAL AGREEMENT NO. 1
IN THE AMOUNT OF $37,155 WITH MERIT ELECTRIC,
INC. FOR THE INSTALLATION OF NEW SIGNS AND
RENOVATED SIGNAGE PANELS TO MEET NEW FAA
AIRFIELD SIGN REGULATIONS, PROJECT: RENOVATION
OF RUNWAY AND TAXIWAY LIGHTING SYSTEM, DRAKE
FIELD, FEDERAL GRANT /3-05-0020-16.
BE IT RESOLVED BY THE BOARD OF DIRECTORS OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1. That the Mayor and City Clerk are hereby
authorized and directed to execute Supplemental Agreement No. 1 in
the amount of $37,155 with Merit Electric, Inc. for the
installation of new signs and renovated signage panels to meet new
FAA airfield sign regulations, Project: Renovation of Runway and
Taxiway Lighting System, Drake Field, Federal Grant #3-05-0020-16.
A copy of the agreement authorized for execution hereby is attached
hereto marked Exhibit "A" and made a part hereof.
PASSED AND APPROVED this 7th day of July , 1992.
ATTEST:
By
City C18rk
m:%4 -
•
•
OWNER: City of Fayetteville
113 W. Mountain Street
Fayetteville, Arkansas
PROJECT: Renovation of Runway and
Taxiway Lighting System,
Drake Field
Fayetteville, Arkansas
CONTRACTOR: Merit Electric, Inc.
P.O. Box 150
Morrilton, AR 72110
Supplemental Agreement
AIP 3-05-0020-16
Date: 5-12-92
Project No.FY912127
The Owner wishes to make modifications to
Signs as recommended by the FAA.
The following Changes to the Contract are hereby ordered:
1. The sign renovation consist of the relocation of signs,
new sign legends, new signs and sign extensions. The
following items are added.
the Airport Runway and
No. 1
Taxiway
ITEM
NO• DESCRIPTION UNIT OUANTITY
B-1 L-858 Sign, Size 1 EA 5
Style 2, Class 1
2 Panel Wide
B-2 L-858 Sign, Size
Style 2, Class 1
3 Panel Wide
1 EA 1
B-3 Relocate Existing EA
1 Panel Sign
B-4 L-858 Sign 1 Panel EA
Extension
B-5 L-858 Sign Legends EA
1 Panel Wide
B-6 L-858 Sign Legends EA
3 Panel Wide
4
21
21
1
ADD
Original Contract Amount
Previous Change Order Amount
Supplemental Agreement will Increase
Contract Amount By
Revised Contract Amount
UNIT
PRICE EXTENSION
$1,811.00 $ 9,055.00
$2,635.00 $ 2,635.00
$1,200.00 $ 4,800.00
$ 805.00 $ 16,905.00
$ 160.00 $ 3,360.00
$ 400.00 $ 400.00
$ 37,155.00
$202,942.50
$ 2,067.55
$ 37.155.00
$242,164.80
•
•
•
The delivery for signs will be 4 to 6 weeks after approval of the
submittals therefore, the Contract Time will be increase by A calendar
days.
New Contract Time 165 calendar days.
CONTRACTOR:
Merit Electric, Inc.
By: at1a . �,. dna?
ENGINEER:
McClelland Consulting, E
By:
OWNER:
City of Fayetteville
By
negring, I c
D to
/1474- 25
Date