HomeMy WebLinkAbout124-92 RESOLUTION•
•
RESOLUTION NO.
•1 4-92
A RESOLUTION APPROVING A SETTLEMENT OFFER WITH
MOTOROLA CORP. IN THE AMOUNT OF $40,668.61
REGARDING THE SCADA SYSTEM FOR LIQUIDATION OF
DAMAGES AND APPROVING EXTRA ENGINEERING
SERVICES FOR THE PROJECT WITH ETC ENGINEERS IN
AN AMOUNT NOT TO EXCEED $36,327.92.
BE IT RESOLVED BY THE BOARD OF DIRECTORS OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1. That the Board of Directors hereby authorizes
execution of a settlement offer with Motorola Corp. in the amount
of $40,668.61 regarding the Scads System for liquidation of
damages. A copy of the settlement agreement authorized for
execution hereby is attached hereto marked Exhibit "A" and made a
part hereof.
Section 2. That the Board of Directors hereby approves
extra engineering services for the project with ETC Engineers in an
amount not to exceed $36,327.92.
PASSED AND APPROVED this 18th day of August , 1992.
ATTEST:
By
'
City Clerk ' °
APPROVED:
By: • /'% fr/
Mayor
AGENDA REOUEST
DATE OF BOARD MEETING August 18th. 1992
FROM: Donald R. Bunn
Name
Engineering Public Works
Division Department
BOARD ACTION REQUESTED: Approval of 1) a settlement of liquidated
damages with Motorola Corp in the amount of $40,668.61 in
connection with the SCADA Proiect, and 2) the approval of a "not
to exceed" amount of $36,327.92 for extra engineering services
related to the SCADA Proiect.
COST TO CITY
<S4,340.697
Cost of this Request
% Comp1e ed
560, 0 o. to a
Budgeted Amount
4151! Z4 • 00
Funds used to date
CAPirAL came -
cmonte - sEwe e - 6 o
Account Name
5,4Qo - 5-1/0 - 53:5- C o
54400 -s'oa a 5115:co
Account Number
BUDGET REVIEW:
X
Bu
get Coordinator
Budgeted Item
Budget Adjustment Attached
CONTRACT/LEASE/GRANT APPLICATION,RE,VI
Accou
Assistant City Manager
ordinator
Ci nal Auditor
f f icer
STAFF RECOMMENDATION: Staff recommends a settlement of $40,668.61,
for liquidated damages on the SCADA Proiect and a "not to exceed"
figure of $36,327.92 for extra engineering services.
wS4►,r-_
Departm nt Head
Admin
rvices Director
Julv 30th, 1992
De
3 MCAz
NMeNaMMN
Date
Date
Date
FAYETTEVI I,LE
TIE CITY OF FAYETTEVILLE ARKANSAS
DEPARTMENTAL CORRESPONDENCE
TO: Fayetteville City Board of Directors///
TMRU: Scott Linebaugh, City Manager SCC
Kevin Crosson, Public Works 'rector
FROM: City Engineer
SUBJECT: A) Resolution of Liquidated Damages
SCADA Contract, Motorola Corporation
B) Payment for Extra Engineering Services
ETC Engineers
DATE: July 29, 1992
ITEM A). Motorola Corporation Liquidated Damaaes:
In May of 1990 the City of Fayetteville entered into a
contract with the Motorola Corporation for the installation of a
Supervisory Control and Data Acquisition System (SCADA) in
connection with the City's sewage lift stations, water booster
stations, and water storage tanks. The contract was for a total of
$560,089.00 and had a construction time limit of 130 consecutive
calendar days. Subsequent change orders reduced the contract amount
to $550,506.00.
A Notice to Proceed was given to Motorola on June 22nd, 1990
and the completion date was noted to be October 30th, 1990. The
system was essentially in place on or about October 30, 1990 with
a required 30 day acceptance test scheduled for the middle of
November, 1990. Due to problems in the system, the scheduled 30 day
acceptance date was cancelled.
Subsequently, on December 4th, 1990 the City informed Motorola
that liquidated damages were being charged in accordance with the
contract documents as of October 30, 1990 and would continue until
such time as the system was completed to the satisfaction of the
City. On January 14th, there was a successful walk-through on the
project and a 30 day test period was successfully completed after
that date. In accordance with a previous agreement, the City
stopped charging liquidated damages as of January 14th, 1992.
The time period between October 30th, 1990 through June of
1991 consisted of attempts by the Motorola Corporation to make the
basic system that they had initially installed to work properly and
work 100 percent of the time. During that time period, and up until
January of 1992 the system worked at 60 to 80 percent reliability.
The City was receiving some beneficial use from the system
during that time, however, the system was generally unreliable and
certainly was not meeting all of the specifications all of the
time.
Around June of 1991 the Motorola Corporation suggested some
changes in the system which involved reducing the number of
repeaters in the system from 2 to 1, a change in the location of
the repeater, a re -programming of computers, and other minor
changes designed to improve the reliability of the system. All of
the changes were incorporated in Change Order No. 3 and approved
by ETC Engineers, the City, and the Motorola Corporation. All of
the changes were to be made at no additional cost to the City and
was so indicated in the change order.
The changes as called for in Change Order No. 3 were made and
all work was completed in January of 1992 as indicated earlier in
this memorandum.
The amount of liquidated damages which accumulated from the
original contract completion date (October 30th, 1990) through the
final completion date of January 14th, 1992 was $112,800.00 based
on 376 days at $300.00 per day as recommended by ETC Engineers. In
discussing the matter of liquidated damages with the City Attorney,
it was felt that it was appropriate that the City ask for damages
to the extent that we could document actual monetary damages due
to the delays on completion of the system.
The actual monetary damages incurred by the City were the
expenses by OMI and by City Forces in checking lift stations in the
field during that time (as opposed to being able to get the
required information from the SCADA System) and the cost of extra
engineering inspections and other engineering services performed
by ETC Engineers. A summary of those charges are:
1. Extra Engineering Charges $ 36,327.92
2. OMI Charges 2,989.48
3. Water & Sewer Dept Charges 1.351.21
TOTALS $ 40,668.61
In a letter dated May 7th, 1992 the City made an offer to the
Motorola Corporation to settle the liquidated damages in the amount
of $40,668.61. Motorola has agreed to the settlement offer as
suggested by the City.
It is the recommendation of the Staff that the Board of
Directors approve the settlement offer in the amount of $40,668.61.
B). ETC Enaineers, Payment for Extra Services:
Our engineering contract with ETC Engineers for services
relating to the design of the SCADA System and inspection services
during construction was approved in April of 1989. The amount of
the contract was a "not to exceed" figure of $90,678.60 which
includes an amendment dated June 5th, 1990. We have paid ETC
Engineers for engineering services to the extent allowed in the
engineering contract.
ETC has incurred extra costs associated with the project
during the overrun period of nearly a year and a half. The amount
of $36,327.92 as shown is the amount they are claiming for that
period and that is the amount which served as a basis for our
settlement offer to Motorola. The Staff has not, for the purpose
of this settlement offer, negotiated any kind of fees with ETC for
their extra services. However, we do feel they are entitled to
payment for their services during that time period and the Staff
is hereby recommending that the Board approve a "not to exceed"
amount of $36,327.92 for that purpose. The exact amount of payment
to ETC would depend subsequent negotiations.
The 1992 Water and Sewer Budget has funds specifically for
this project and none of the actions recommended by the Staff will
cause an overrun in those budgeted funds. The liquidated damages
settlement and the extra engineering cost will result in no net
change in the cost of the project.
FAYETTE
THE CITY OF FAYETTEVILLE, ARKANSAS 1.63 [
DEPARTMENTAL CORRESPONDENCE
L'k" . /d?4 _ •
• 3' 19 tia
(f� �r 1 . �# 7' r,Jl o
TO: Scott Linebaugh, City Manager
TURD: Kevin Crosson, Public Works Director
FROM: City Engineer /0'"'"/j i‘:"--'
SUBJECT: Amendment, SCADA Engineering Contract
ETC Engineers, Little Rock, Arkansas
DATE: September 8, 1992
On August 18th, 1992 the Fayetteville Board of Directors
approved a settlement of liquidated damages with the Motorola
Corporation. The settlement involved the payment of $40,668.61 to
the City which would cover, among other items, the cost of extra
engineering incurred by the City of $36,327.92. Attached is an
engineering contract amendment submitted by ETC Engineers which
increases the engineering fee by the approved amount.
I feel that the amount as submitted by ETC is justified and
is representative of the amount of time and effort expended on the
project since the October of 1990. It is my recommendation that the
City execute the contract amendment as submitted.
Attachments:
Resolution 124-92
Board Agenda Item of 8-18-92
ETC Documentation of Charges
Internal Review Sheet
•
AMENDMENT NO. 2
AGREEMENT FOR ENGINEERING SERVICES
FOR
LIFT STATION TELEMETRY
CITY OF FAYEITEVILLE, ARKANSAS
This Amendment No. 2 to the original contract dated April 11, 1989, between the city of
Fayetteville, Arkansas and ETC Engineers, Inc., Little Rock, Arkansas, is for the purpose
of compensating the Engineer for the additional engineenng services from November 1,
1990, (project completion as per contract) until January 21, 1992, (substantial completion
of the project). The following sections of the ongmal contract document is hereby amended
as follows:
SECTION 5: PAYMENT TO ENGINEERS
This is a cost reimbursement type contract. The original budget is increased due to the
expansion of scope as described above. The budget is increased as follows:
1. Lift Station Telemetry $36,327.42
Total Budget Increase: $36,327.42
All other stipulations of the original contract remain unchanged. This Amendment Number
2 is agreed to September 5, 1992.
Attest:
yr sam, aJ
City Clerk
Attest:
CITY OF FAYEI IEVILLE, ARKANSAS
ait
red S. \'orsan
c(4
izan Rahman, President
/Hamid Joodi, P.E.
Project Engineer
•
•
•
•
rN6/NEE2/A/6 Cizr4,9cr /7N6rr/ootr5.
CONTRACT REVIEW
PROJECT: Sc19nn
CitJ6/A/=Ei l.tk; roov"724cr
ENGINEER: C rc f-'K1C;
t
7 -7 -LC ,e&k APieic
nApPROVALS: COMMENTS:
y 4y
ez
Acco i g Supervisor Date 3G gall, 9a, ?
• 10.
Pur��Q, Officer Date
I t rnal Auditor
Date Z top&yziS-36 X27 9L atil
City Attorney
Budg Coordinator
Date
4-Y-42
Date
•
INVOICE FOR ENGINEERING SERVICES
PROJECT: Construction Management DATE: March 12, 1992
SCADA System
CONTRACT NO.: None Dated April 11,1989
TO: Mr. Don Bunn, P.E.
City Engineer
City of Fayettville
113 West Mountain
Fayettville, AR 72701
INVOICE NO.: 92020
PROJECT NO.: 892201
•
In accordance with the Owner Engineer Agreement dated:_Aprii 11,
1989 there is due at this time for Engineering services
including reimbursable items on the above project, for the period
e nding February 29, 1992, the sum of THIRTY SIX THOUSAND THREE
HUNDRED TWENTY SEVEN AND 92/100 DOLLARS($36,327.92).
CATAGORY TIME SPEN HOURS. RATE AMOUNT
Mizan Rahman
6 Hrs. per month for 16
months
128 26.44 $65.00 $8,320.00
H amid Jodi 411.00 $55.00 $22,605.00
N ov. 2, 1990 2
N ov. 6, 1990 4
Nov. 8, 1990 2.50
N ov. 9, 1990 2
N ov. 12, 1990 2
N ov. 14, 1990 3.50
N ov. 22, 1990 11
N ov. 27, 1990 5.50
N ov. 29, 1990 1.50 34.00
Dec. 3, 1990 1
Dec. 11, 1990 2
Dec. 12, 1990 11
Dec. 13, 1990 2
Dec. 14, 1990 3
Dec. 18, 1990 1 20.00
Jan. 1, 1991 4
Jan. 8, 1991 1
Jan. 14, 1991 12
Jan. 21, 1991 12
Jan. 23, 1991 11
Jan. 24, 1991 11 51.00
Feb. 1, 1991 1
Feb. 5, 1991 4
Feb. 6, 1991 12
Feb. 11, 1991 1
Feb. 14, 1991 3
Feb. 15, 1991 2
Feb. 18, 1991 2
•
Feb. 19, 1991 5
Feb. 20, 1991 1
Feb. 21, 1991 2
Feb. 27, 1991 2 35.00
Mar. 1, 1991 9
Mar. 4, 1991 2
Mar. 12, 1991 1
Mar. 20, 1991 3
Mar. 21, 1991 2 17.00
Apr . 5, 1991 12
Apr. 11, 1991 1
Apr. 22, 1991 4
Apr. 24, 1991 1 50 18.50
May 2, 1991 1
May 3, 1991 3
May 7, 1991 1
May 10, 1991 2
May 13, 1991 2
May 14, 1991 4
May 15, 1991 1
May 21, 1991 3
May 29, 1991 2
May 30, 1991 11
Mpy 31, 1991 3 33
Jun. 3, 1991 2
Jun. 4, 1991 2
Jun. 5, 1991 10
Jun. 7, 1991 4
Jun. 11, 1991 1
Jun. 13, 1991 3
Jun. 14, 1991 2
Jun. 19, 1991 1
Jun. 21, 1991 2
Jun. 25, 1991 1
Jun. 8, 1991 3
J un. 17, 1991 10 41.00
Aug. 2, 1991 2
Aug. 16, 1991 1
Aug. 26, 1991 3
Aug. 28, 1991 4
Aug. 29, 1991 1
Aug. 30, 1991 2 13.00
Sep. 13, 1991 8
S ep. 16, 1991 3 8.00
Oct. 1, 1991 1
Oct. 2, 1991 3
Oct. 3, 1991 11
Oct. 4, 1991 2
Oct. 13, 1991 9
Oct. 14, 1991 10
Oct. 16, 1991 6
Oct. 17, 1991 2
Oct. 28, 1991 1
Oct. 30, 1991 2
Oct. 31, 1991 11 58
N ov. 4, 1991 1
N ov. 5, 1991 1
•
•
N ov. 6, 1991 2
Nov. 7, 1991 6
N ov. 8, 1991 1
Nov. 11, 1991 2
Nov. 13, 1991 2 50
Nov. 15, 1991 10 25.50
Dec. 4, 1991 1
Dec. 12. 1991 10
Dec. 20, 1991 2 13
Jan. 21, 1992 4
Jan. 22, 1992 14
Jan. 23, 1992 14 32
Feb. 7, 1992 8
Feb. 12, 1992 1 9
Mark Walter
William Andrew
Clerical
MILLAGE
Nov. 21, 1990
Dec. 12, 1990
N an. 14, 1991
Jan. 21, 1991
Jan. 24, 1991
Feb. 6, 1991
Apr. 5, 1991
May 30, 1991
Jun. 5, 1991
Jul. 17, 1991
Sep. 13, 1991
Oct. 3, 1991
Oct. 13, 1991
Oct. 31, 1991
N ov. 151 1991
Dec. 12, 1991
Jan. 21, 1992
10
25
64
400
400
400
400
400
400
400
400
400
400
400
420
425
415
450
400
420
•
$55.00 $550.00
$55.00 $1,375.00
$15.00 $960.00
6930 @ $0.23/ $1,593.90
PERDIEM & EXPENSES $424.02
N ov. 21, 1990
Dec. 12, 1990
Jan. 14, 1991
Jan. 21, 1991
Jan. 23, 1991
Feb. 6, 1991
Apr. 5, 1991
May 30, 1991
Jun. 5, 1991
Jul. 17, 1991
Sep. 13, 1991
Oct. 3, 1991
Oct. 14, 1991
Oct. 31, 1991
N ov. 15, 1991
$3.50
$5.50
$10.00
$28.44
$63.51
$12.00
$11.81
$10.43
$5.87
$5.50
$12.00
510.55
$46.64
$11.59
$16.06
•
Dec. 12, 1991 $5.55
Jan. 21, 1992 $165.07
OTHER COSTS $500.00
SUBMITTED BY:
TOTAL DUE: $36,327.92
PLEASE MAIL REMITTANCE TO:
ETC Engineers, Inc.
1510 S. Broadway
Little Rock, AR 72202
•
•
RESOLUTION NO. 14_42
A RESOLUTION APPROVING A SETTLEMENT OFFER WITH
MOTOROLA CORP. IN THE AMOUNT OF $40,668.61
REGARDING THE SCADA SYSTEM FOR LIQUIDATION OF
DAMAGES AND APPROVING EXTRA ENGINEERING
SERVICES FOR THE PROJECT WITH ETC ENGINEERS IN
AN AMOUNT NOT TO EXCEED $36,327.92.
BE IT RESOLVED BY THE BOARD OF DIRECTORS OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1. That the Board of Directors hereby authorizes
execution of a settlement offer with Motorola Corp. in the amount
of $40,668.61 regarding the Scada System for liquidation of
damages. A copy of the settlement agreement authorized for
execution hereby is attached hereto marked Exhibit "A" and made a
part hereof.
Section 2. That the Board of Directors hereby approves
extra engineering services for the project with ETC Engineers in an
amount not to exceed $36,327.92.
PASSED AND APPROVED this 18th day of August , 1992.
APPROVED:
By: dfl/1 e rgrN
Mayor
ATTEST:
By
•
•
•
AGENDA REQUEST
DATE OF BOARD MEETING Auaust 18th, 1992
FROM: Donald R. Bunn
Name
Engineering Public Works
Division Department
BOARD ACTION REQUESTED: Anproval of 1) a settlement of liquidated
damages with Motorola Corp in the amount of S40.668.61 in
connection with the SCADA Proiect. and 21 the approval of a "not
to exceed" amount of $36,327.92 for extra engineering services
related to the SCADA Proiect.
COST TO CITY
<$4,340.697
Cost of this Request
% Completed
BUDGET REVIEW:
\i
Bu
lr564 oSo.oa
Budgeted Amount
Afs-fi zee • 0O
Funds used to date
69P,r4c c j r6,e - �a
c,9olrsiC- 'SE4JER • 6CY
Account Name
5400-5900- 53i5.00
64"-,r(oe - S 15:cc
Account Number
_A__ Budgeted Item
Budget Adjustment Attached
get Coordinator
Assistant City Manager
CONTRACT/LEASE/GRANT APPLICATION
Accountin uperyisor
Cit/ Attorn
Purchasing Officer
EVI
A "Al
Bud•e - ordinator
nal Auditor
STAFF RECOMMENDATION: Staff recommends a settlement of S40.668,61
for liauidated damages on the SCADA Proiect and a "not to exceed"
figure of S36.327.92 for extra engineering services.
mimmeekip eilMk
D
Departm
nt Head
Admin'
/f.,
if
OP
M
rvices Director
July 30th. 1992
3 Me
Da
Date
//IDDate
ate
•
•
I�AYETTEV"Iir
THE CITY OF FAYETTEVRIE. ARKANSAS
DEPARTMENTAL CORRESPONDENCE
TO: Fayetteville City Board of Directors/
THRO: Scott Linebaugh, City Manager ,�[C C
Kevin Crosson, Public Works 'recto
FROM: City Engineer
SUBJECT: A) Resolution of Liquidated Damages
SCADA Contract, Motorola Corporation
B) Payment for Extra Engineering Services
ETC Engineers
DATE: July 29, 1992
ITEM M. Motorola Concretion Liquidated Damages:
In May of 1990 the City of Fayetteville entered into a
contract with the Motorola Corporation for the installation of a
Supervisory Control and Data Acquisition System (SCADA) in
connection with the City's sewage lift stations, water booster
stations, and water storage tanks. The contract was for a total of
$560,089.00 and had a construction time limit of 130 consecutive
calendar days. Subsequent change orders reduced the contract amount
to $550,506.00.
A Notice to Proceed was given to Motorola on June 22nd, 1990
and the completion date was noted to be October 30th, 1990. The
system was essentially in place on or about October 30, 1990 with
a required 30 day acceptance test scheduled for the middle of
November, 1990. Due to problems in the system, the scheduled 30 day
acceptance date was cancelled.
Subsequently, on December 4th, 1990 the City informed Motorola
that liquidated damages were being charged in accordance with the
contract documents as of October 30, 1990 and would continue until
such time as the system was completed to the satisfaction of the
City. On January 14th, there was a successful walk-through on the
project and a 30 day test period was successfully completed after
that date. In accordance with a previous agreement, the City
stopped charging liquidated damages as of January 14th, 1992.
The time period between October 30th, 1990 through June of
1991 consisted of attempts by the Motorola Corporation to make the
basic system that they had initially installed to work properly and
work 100 percent of the time. During that time period, and up until
January of 1992 the system worked at 60 to 80 percent reliability.
•
•
•
•
•
The City was receiving some beneficial use from the system
during that time, however, the system was generally unreliable and
certainly was not meeting all of the specifications all of the
time.
Around June
changes in the
repeaters in the
the repeater, a
changes designed
the changes were
by ETC Engineers
the changes were
was so indicated
of 1991 the Motorola Corporation suggested some
system which involved reducing the number of
system from 2 to 1, a change in the location of
re -programming of computers, and other minor
to improve the reliability of the system. All of
incorporated in Change Order No. 3 and approved
, the City, and the Motorola Corporation. All of
to be made at no additional cost to the City and
in the change order.
The changes as called for in Change Order No. 3 were made and
all work was completed in January of 1992 as indicated earlier in
this memorandum.
The amount of liquidated damages which accumulated from the
original contract completion date (October 30th, 1990) through the
final completion date of January 14th, 1992 was $112,800.00 bas$d
on 376 days it $300.00 per day as recommended by ETC Engineers. In
discussing the matter of liquidated damages with the City Attorney,
it was felt that it was appropriate that the City ask for damages
to the extent that we could document actual monetary damages due
to the delays on completion of the system.
The actual monetary damages incurred by the City were the
expenses by OMI and by City Forces in checking lift stations in the
field during that time (as opposed to being able to get the
required information from the SCADA System) and the cost of extra
engineering inspections and other engineering services performed
by ETC Engineers. A summary of those charges are:
1. Extra Engineering Charges $ 36,327.92
2. OMI Charges 2,989.48
3. Water & Sewer Dept Charges 1.351.21
TOTALS $ 40,668.61
In a letter dated May 7th, 1992 the City made an offer to the
Motorola Corporation to settle the liquidated damages in the amount
of $40,668.61. Motorola has agreed to the settlement offer as
suggested by the City.
It is the recommendation of the Staff that the Board of
Directors approve the settlement offer in the amount of $40,668.61.
•
•
•
Hl. ETC Engineers. Payment for Extra Services:
Our engineering contract with ETC Engineers for services
relating to the design of the SCADA System and inspection services
during construction was approved in April of 1989. The amount of
the contract was a "not to exceed" figure of $90,678.60 which
includes an amendment dated June 5th, 1990. We have paid ETC
Engineers for engineering services to the extent allowed in the
engineering contract.
ETC has incurred extra costs associated with the project
during the overrun period of nearly a year and a half. The amount
of $36,327.92 as shown is the amount they are claiming for that
period and that is the amount which served as a basis for our
settlement offer to Motorola. The Staff has not, for the purpose
of this settlement offer, negotiated any kind of fees with ETC for
their extra services. However, we do feel they are entitled to
payment for their services during that time period and the Staff
is hereby recommending that the Board approve a "not to exceed"
amount of $36,327.92 for that purpose. The exact amount of payment
to ETC would depend subsequent negotiations.
The 1992 Water and Sewer Budget has funds specifically f&r
this project and none of the actions recommended by the Staff will
cause an' overrun in those budgeted funds. The liquidated damages
settlement and the extra engineering cost will result in no net
change in the cost of the project.